HomeMy WebLinkAboutConditionsDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Conditions for Permit B22006218
Building
1 Instructions for Issued permits:
1. Print full~sized plan sheets in color for field inspector, plans must have text at 1/8" or larger for inspector, print
conditions of approval and attach them to the approved set of plans for the inspector.
2. Hard copies of permit, approved plans, site plans, and conditions must remain on the job site for the inspector.
Inspections will not take place if printed plans are not on site.
2 Authorized hours of construction/activity: 7:00 a.m. - 8:00 p.m. Monday Through Friday; 9:00 a.m. - 8:00 p.m.
Saturday; No work allowed on Sunday. Per Ordinance 4703, 2-2-1998
3 TREE PROTECTION MEASURES FOR ALL TREES IN THE CONSTRUCTION AREA OF A DEVELOPMENT
SITE. THESE MEASURES INCLUDE: 1. 6 foot high chain link fences around the trees out to and including the
drip line of the tree. 2. All the area within the fenced area needs a minimum of 3" of bark mulch. 3. Warning signs
must also be included on the fence. 4. Construction activity, parking, and storage of materials and equipment is
not allowed within the drip line (and therefore fenced) area of any tree. 5. The only new impervious surfaces
allowed within the drip line of existing trees are those shown on approved building or construction plans, which
typically should be limited to the new buildings, new driveways, new parking lots, new streets and new sidewalks.
4 Approval for building permit only-separate approval and permits required for any mechanical, plumbing, electrical,
fire suppression, or hazardous materials system.
5 All construction, demolition and land clearing waste must be recycled at a King County licensed or approved
facility, or taken to Regional Disposal Facilities.
6 Ground Electrode System (either 1 or 2 are approved methods): 1. An electrode of at least 20 ft long bare copper,
sized in accordance with NEC. 2. An electrode of 20 ft long #4 rebar (not less than 1/2 inch in diameter) and
sized per NEC; either one shall be encased by at least 2 inches of concrete, located within and near the bottom
of a concrete footing that is in direct contact with the Earth, and shall be installed in all new residential and
commercial construction.
7 For all new Photovoltaic Systems a rough in electrical inspection on the associated electrical permit is required
prior to installation of PV panels to verify equipment grounding and installation of mounting hardware.