FIELD REPORT
Project No. 0895.06 Page 1 of 3 Report ID 0895.06 S 12282022
Date Wed 12/28/2022 Weather 50°F, Cloudy
Arrival/Departure Time(s) 12:00pm-12:45pm Travel Time (hr) 1.00
Project Name Weatherly Inn
Location 4500 Talbot Road S., Renton
ESNW Rep., CESCL No.,
Phone No. & Report Statement
Christopher Halter, ECO-3-2072210, (206)-602-9915
“This report is true, accurate, and complete to the best of my knowledge and belief.”
Client Info/Contact RJ Development | Jeff Bennett
Permit No(s). WAR-307963
Reviewed By MLP
Initials/Date
N/A
Initials/Date Field Supervisor Project Manager
Limitations: The presence of our field representative at the site is to provide our client with a source of professional advice, opinions, and recommendations based upon the field representative’s observations and testing of the contractor’s work. Our services do not include supervision or direction of the contractor, their employees, or agents. Recommendations for obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible for complying with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations, is the sole
responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager.
Type of visit: Weekly Monthly Post–Storm Event
Precipitation since last inspection (approximate): 3.91 inches
Precipitation in last 24 hours (approximate): 0.00 inches
Phase of active construction (check all that apply):
Pre-construction Clearing, demolition, or grading Infrastructure or roads
Concrete pours Vertical construction Utilities
Off-site improvements Site temporarily stabilized Final stabilization
Was water quality sampling part of this inspection? Yes No
If “Yes”:
• Record results in the table below.
• Hanna Turbidity Meter No. 32
Monitoring
Point Monitoring Location Turbidity
(NTU) pH Description of
Discharge Notes
MP-1 Stormwater Vault
Report ID 0895.06 S 12282022 Page 2 of 3
Earth Solutions NW, LLC
Erosion Control BMPs
(13 Elements)
Overall
Condition
(Good; Fair; Poor)
Needs
Repair?
(Yes; No)
Comments
1. Preserve Vegetation; Mark Clearing Limits
• Buffer Zones around Sensitive Areas
• Silt Fence G N - Chain link fence installed along site perimeter.
2. Establish Construction Access • Fabric; Quarry Spalls
• Wheel Wash
• Sweeper Truck
F N - Site entrance is paved.
3. Control Flow Rates
• Stormwater Vault or Facility • Straw Wattles
• Check Dams
G N - Onsite stormwater vault is plugged.
4. Install Sediment Controls
• Silt Fence
• Straw Bale Barriers • Vegetation
• Straw
• Sediment Ponds, Traps & Filters
• Treatment • Water Truck
F N
- Silt fence installed around majority of site perimeter. Partly down on SW corner.
- Straw wattles placed along side of small slope
near Talbot Rd S.
5. Stabilize Soils
• Nets & Blankets
• Mulch, Bark & Rock • Hydroseeding; Grass
• Plastic Sheeting
• Stockpiles
F N - Much of site is paved, including entrance and
parking areas.
6. Protect Slopes
• Benching; Track-Walking • Pipe Slope Drains
• Plastic Sheeting; Anchors
- - N/A
7. Protect Drain Inlets
• Catch Basin Inserts G N - CB inserts installed in offsite catch basins.
8. Stabilize Channels and Outlets • Channel Lining
• Check Dam
• Outlet Protection
• Nets and Blankets
- - N/A
9. Control Pollutants
• Chemical Storage Area Covered • Concrete Handling G N -Chemical/material storage onsite.
-Concrete washout is present onsite.
10. Control Dewatering G N - Via KC Sewer Discharge Permit as needed.
11. Maintain BMPs F N -Maintain BMP’s.
12. Maintain SWPPP & Site Logbook G N - Available upon request.
13. Protect Low-Impact Development (LID BMPs) • Bioretention Rain Garden Facilities
• Permeable Pavement - - N/A
Do existing BMPs need to be modified or removed, or do other BMPs need to be installed? Yes No
List the action items in the table below:
Element
# Description and Location Action Required Completion
Date
Report ID 0895.06 S 12282022 Page 3 of 3
Earth Solutions NW, LLC
BMP LEGEND
STORMWATER VAULT
SILT FENCE
CONSTRUCTION ENTRANCE
CHEMICAL/MATERIAL STORAGE
CATCH BASIN INSERT
CONCRETE WASHOUT