ADVISORY NOTES TO APPLICANT
The following notes are supplemental information provided in conjunction with the administrative land use
action. Because these notes are provided as information only, they are not subject to the appeal process for
the land use action.
Planning:
(Contact: Jill Ding, 425-430-6598, jding@rentonwa.gov)
1. RMC section 4-4-030.C.2 limits haul hours between 8:30 am to 3:30 pm, Monday through Friday unless
otherwise approved by the Development Services Division.
2. Commercial, multi-family, new single family and other nonresidential construction activities shall be
restricted to the hours between seven o’clock (7:00) a.m. and eight o’clock (8:00) p.m., Monday through
Friday. Work on Saturdays shall be restricted to the hours between nine o’clock (9:00) a.m. and eight
o’clock (8:00) p.m. No work shall be permitted on Sundays.
3. Within thirty (30) days of completion of grading work, the applicant shall hydroseed or plant an
appropriate ground cover over any portion of the site that is graded or cleared of vegetation and wh ere
no further construction work will occur within ninety (90) days. Alternative measures such as mulch,
sodding, or plastic covering as specified in the current King County Surface Water Management Design
Manual as adopted by the City of Renton may be proposed between the dates of November 1st and
March 31st of each year. The Development Services Division’s approval of this work is required prior to
final inspection and approval of the permit.
4. A National Permit Discharge Elimination System (NPDES) permit is required when more than one acre is
being cleared.
5. The applicant may not fill, excavate, stack or store any equipment, dispose of any materials, supplies or
fluids, operate any equipment, install impervious surfaces, or compact the earth in any way with in the
area defined by the drip line of any tree to be retained.
6. The applicant shall erect and maintain six foot (6') high chain link temporary construction fencing around
the drip lines of all retained trees, or along the perimeter of a stand of retained trees. Placards shall be
placed on fencing every fifty feet (50') indicating the words, “NO TRESPASSING – Protected Trees” or on
each side of the fencing if less than fifty feet (50'). Site access to individually protected trees or groups
of trees shall be fenced and signed. Individual trees shall be fenced on four (4) sides. In addition, the
applicant shall provide supervision whenever equipment or trucks are moving near trees.
Development Engineering:
(Contact: Michael Sippo, 425-430-7298, msippo@rentonwa.gov)
1. See Attached Development Engineering Memo dated January 18, 2023
Fire Authority:
(Contact: Corey Thomas, 425-276-9582, cthomas@rentonrfa.org)
1. Fire impact fees are applicable at the rate of $0.26 per square foot of commercial bank/offi ce space
and $1.25 per square foot of retail space. No charge for gas station canopy. This fee is paid at time of
building permit issuance. Credit will be granted for the area of total buildings removed.
2. The preliminary fire flow is 2,000 gpm. A minimum of one hydrant is required within 150 -feet of each
structure and one additional hydrant is required within 300-feet of each structure. A water availability
certificate is required from Soos Creek Water District. The water availability certificate that has been
EXHIBIT 15
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
ADVISORY NOTES TO APPLICANT
Page 2 of 2 LUA22-000424
provided is not sufficient as it only shows 1,000 gpm available. Existing fire hydrants that meet these
criteria can be used to satisfy the requirements.
3. Approved fire alarm systems are required throughout all buildings of 3,000 square feet or more.
Separate plans and permits required by the fire department. Fully addressable and full detection is
required for the fire alarm system. Fire sprinklers are not required in the proposed buildings.
4. Fire department apparatus access roadways are required within 150 -feet of all points on the building.
Fire lane signage required for the on-site roadways. Required turning radiuses are 25-feet inside and
45-feet outside. Roadways shall be a minimum of 20-feet wide. Roadways shall support a minimum of
a 30-ton vehicle and 75-psi point loading.
5. Separate plans and permits are required to be submitted to and obtained from the Renton Regional
Fire Authority for all new underground gasoline tanks and tank monitoring systems.
Technical Services:
(Contact: Amanda Askren, 425-430-7369, aaskren@rentonwa.gov)
1. None
Community Services:
(Contact: Erica Schmitz, 425-430-6614, eschmitz@rentonwa.gov)
1. None
Police:
(Contact: Cyndie Parks, 425-430-7521, cparks@rentonwa.gov)
1. See attached memo.
Building:
(Contact: Rob Shuey, 425-430-7235, rshuey@rentonwa.gov)
1. None
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
DEPARTMENT OF COMMUNITY
& ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: 01/18/2023
TO: Jill Ding, Senior Planner
FROM: Michael Sippo, Civil Engineer III, Plan Review
SUBJECT: Benson & 176th Commercial Redevelopment
17426 108th Ave SE & 10810, 10828 SE Petrovitsky Rd
LUA22-000424
I have reviewed for the Benson & 176th (Petrovitsky) project located at parcel(s) 292305-9017,
9095, and 9110. The following comments are based on the land-use application submittal made
to the City of Renton by the applicant.
EXISTING CONDITIONS
The site is approximately 1.67 acres in size and is rectangular in shape with two lots fronting SE
Petrovitsky Rd extending approximately 300 feet to the north with the parcel fronting both 108th
Ave SE (Benson) and SE Petrovitsky Rd extending approximately 140 feet to the north. The site
is relatively flat and contains a vacant gas-station and vehicle service building at the corner of the
intersection and vacant buildings on the longer rectangular parcels. There is also an active cell-
tower array located on one of the vacant parcels. As mentioned previously, the existing vacant
commercial sites contain multiple buildings and is covered approximately 900 percent by
impervious areas such as parking, buildings and service areas with the remainder grass and a treed
areas located within the interior of the site’s existing lot lines. The site generally slopes from the
east to west and runoff is collected by an existing onsite conveyance system and routed to the
public conveyance systems on 108th Ave SE and SE Petrovitsky Rd.
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
Benson Petrovitsky Redevelopment– LUA22-000424
1/18/2023
Page 2 of 10
WATER
1. The subject development is within the water service area of Soos Creek Water and Sewer
District.
2. The site is located outside of an Aquifer Protection Area.
SEWER
1. The subject development is within the water service area of Soos Creek Water and Sewer
District.
STORM
1. The site is located within the Black River – Panther Creek Drainage Basin and contains
only minor regulated slopes along the north side of the property. The site topography
slopes from the east to west. There is an existing unmapped conveyance system located
on the 3 parcels that connect to the City’s conveyance system in SE Petrovitsky Rd and
108th Ave SE. There is an existing 12-inch stormwater main in SE Petrovitsky Rd south of
the subject property frontage located along the north flowline of the existing roadway
that flows from east to west into the intersection and continues north along 108th Ave SE.
TRANSPORTATION
1. The proposed development fronts SE Petrovitsky Road (176th St SE) along the southern
property lines of the development for a length of approximately 290 feet. SE Petrovitsky
Road is a five lane Principal Arterial. Per the King County Assessor map, the existing half
street ROW width on the site frontage is approximately 30 feet and contains flush 8’
sidewalks on both sides.
2. The proposed development fronts 108th Ave SE (Benson Road/ SR 515) along the western
property line of the development for a length of approximately 140 feet. 108th Ave SE is
a six lane Principal Arterial. Per the King County Assessor map, the existing half street
ROW width on the site frontage is approximately 45 feet and contains flush 8’ sidewalks
on both sides
CODE REQUIREMENTS
WATER
1. A water availability certificate from Soos Creek Water and Sewer District is required as
part of the Land-Use Application.
a. A Certificate of Water Availability dated 8/8/2022 was provided with the Land-
Use Application.
b. The Certificate of Water Availability notes that the “Water service will require and
improvement to the water system of: Water main fronting south side of property
along SE Petrovitsky Rd. Final water requirements and layout will be based on
the final site development plan, road, storm, grading and fire marshal
requirements.”
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
Benson Petrovitsky Redevelopment– LUA22-000424
1/18/2023
Page 3 of 10
c. The Certificate of Water Availability notes that “Service is subject to the following:
Other: Will require oil and water separator.”
d. Renton Regional Fire Authority commented on January 6, 2023 that: “The
preliminary fire flow is 2,000 gpm…The water availability certificate that has been
provided is not sufficient as it only shows 1,000 gmp available”. Accommodation
shall be made to ensure that the site contains the required fire flow prior to civil
construction permit approval.
2. A copy of the approved water plan Error! Reference source not found. shall be provided
to the City prior to approval of the Civil Construction Permit.
a. The number and locations of fire hydrants shall be determined by the Renton
Regional Fire Authority as part of the review of the project plans.
3. The site is located outside of an Aquifer Protection Area.
SEWER
1. A sewer availability certificate from Soos Creek Water and Sewer District is required as a
part of the Land-Use Application.
a. A Certificate of Sewer Availability dated 8/9/2022 was provided with the Land-
Use Application
2. A copy of the approved sewer plans from Error! Reference source not found. shall be
provided to the City prior to approval of the Civil Construction Permit.
a. The covered fuel pump dispensary areas shall be connected to an oil/water
separator that drains to the sanitary sewer.
b. A grease interceptor is required if there is a commercial kitchen. The grease
interceptor shall be sized based on drainage fixture units in accordance with
standards found in the latest edition of the Uniform Plumbing Code (UPC). The
grease interceptor shall drain by gravity to the sewer main.
c. The dedicated garbage/recycling area shall be covered and will be required to
drain to an approved oil/water separator that drains to the sanitary sewer.
3. If any of the existing buildings on the site are served by private on-site septic systems, the
septic systems shall be abandoned in accordance with King County Department of Health
regulations and Renton Municipal Code.
SURFACE WATER
1. The development is subject to a system development charge (SDC) for stormwater. The
2023 SDC for stormwater is $0.92 per square foot of new impervious surface area, but
not less than $2,300.00. The fee that is current will be charged at the time of
construction permit issuance.
2. A preliminary Drainage Plan and Technical Information Report (TIR), dated August, 2022,
was submitted by Contour Engineering, LLC with the Land Use Application. Based on the
City of Renton’s flow control map, the site falls under Flow Control Duration Standards
(Forested Site Conditions) and is located within the Black River drainage basin. The
development is subject to a Full Drainage Review in accordance with the 2022 Renton
Surface Water Design Manual (RSWDM). All nine core requirements and the six special
requirements have been discussed in the Technical Information Report. The detention,
water quality and conveyance shall be designed in accordance with the RSWDM that is
current at the time of the civil construction permit application. The applicant has
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
Benson Petrovitsky Redevelopment– LUA22-000424
1/18/2023
Page 4 of 10
proposed to connect to the City of Renton’s storm drainage system located within 108th
Ave SE.
a. The development currently is showing a 27,000 cubic foot detention vault to meet
the flow control requirement. During the review of the final TIR the applicant will
need to ensure that flow control standards are being met as outlined in the 2022
RSWDM.
b. The applicant is proposing to use the modular wetland in order for the project to
meet the enhanced water quality requirements. The modular wetland is located
within the parking lot downstream of the detention system prior to connecting
into the City of Renton system located within 108th Ave SE.
c. On-site BMPs satisfying Core Requirement #9 will be required for the site. On-site
BMPs shall be evaluated in order of preference by feasibility as described in
Section C.1.3 of the 2022 RSWDM. All targeted impervious area to the maximum
extent feasible shall be conveyed to an On-site BMP.
i. The applicant is not currently proposing any mitigation for the site based
on the infeasibility criteria within the 2022 RSWDM. Final review of onsite
BMP feasibility will be reviewed during the civil construction permit
approval process.
d. The following stormwater improvements are required and shall be discussed or
revised within the TIR:
i. All Core Requirements and Special Requirements must be evaluated within
the TIR. The technical information report did not address Core
Requirement #6 and shall be evaluated during the civil construction permit
approval process.
ii. The technical information report noted that “oil control is not required for
this project, but an oil-water separator is provided for the runoff from the
fuel pumps.” Per Special Requirement #5 of the 2022 RSWDM notes that if
the proposed project develops a site that will have high-use characteristics
then oil control must be met. Additionally, high-use road intersections are
required to provide oil control. Since the site has an expected average
daily traffic count equal to or greater than 100 vehicles per 1,000 square
feet of gross building are and is subject to petroleum storage or transfer in
excess of 1,500 gallons per year, oil control for the entire site is applicable.
Also, City traffic studies from 2009 note that the ADT for the Benson-
Petrovitsky intersection is 29,000 trips which exceeds the minimum of
25,000 trips meeting the definition of high-use intersection. The applicant
shall evaluate utilizing oil controls per Special Requirement #5 during the
civil construction permit approval process. These oil control facilities will
be in addition to the oil control requirements of the covered fuel islands
and garbage/recycling areas.
3. Storm drainage improvements along all public street frontages are required to conform
to the City’s street and stormwater conveyance standards. Any new storm drain
installed on or off-site shall be designed and sized in accordance with standards found in
Chapter 4 of the 2022 RSWDM and shall account for the total upstream tributary area,
assuming developed conditions for onsite tributary areas and existing conditions for any
offsite tributary areas.
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
Benson Petrovitsky Redevelopment– LUA22-000424
1/18/2023
Page 5 of 10
4. Effective June 22, 2022, the City of Renton has adopted the 2022 RSWDM, which is
based on the 2021 King County SWDM. Under the new 2022 RSWDM stormwater
requirements, on-site BMP sizing credits for modeling credits can no longer be used for
privately maintained on-site BMPs, with the exception of full dispersion and full
infiltration BMPs.”
5. A geotechnical report for the site was prepared by PanGEO, Inc. dated May 2019 and
was provided with the land-use submittal. The report includes information concerning
the soils, geology, drainage patterns, vegetation present, water table and soil
permeability, with recommendations of appropriate on-site BMP options with typical
designs for the site from the geotechnical engineer.
a. The geotech report should indicates that the site contains a fill layer consisting of
a few inches of gravel over sandy silt ranging from 2-1/2 to 4-1/2 feet. Below the
fill layer is a highly impermeable weathered Vashon till and Renton formation of
hard sandy silt with gravel below the till. Groundwater seepage was encountered
in portions of the test pits and indicative of perched locations of water due to the
perched till.
i. Due to the native soils underlying the site consisting of Vashon till, a
medium to very dense deposit comprised of clay, silt, sand, gravel, and
perched groundwater, the report determines that infiltration is infeasible
and non-infiltration alternatives should be considered to manage the
surface runoff at the site. Staff concurs with this recommendation and will
provide final review of infiltration options during the civil construction
permit process.
ii. Due to the presence of perched groundwater, the report recommends
where seepage is encountered, the base of the excavation should be
sloped to one or more shallow sump pits. Where loose soils are
encountered in conjunction with groundwater seepage, remedial measure
such as overexcavation of soft soils or tamping quarry spall into the base
of the excavation may be required.
6. Erosion control measures and construction stormwater pollution prevention measures
to meet the City requirements shall be proved for during the civil construction permit
process.
7. A Construction Stormwater General Permit from Department of Ecology will be required
since grading and clearing of the site exceeds one acre. A Stormwater Pollution
Prevention Plan (SWPPP) is required for this site.
8. The current Surface Water Standard Plans shall be used in all drainage plan
submittals. The current City of Renton Standard Details is available online in the City
of Renton website.
TRANSPORTATION
1. Street and frontage requirements: The proposed development site has frontage on SE
Petrovitsky Road (176th St SE) and on 108th Ave SE ( Benson Road/ SR 515).
a. SE Petrovitsky Road (176th St SE) is a five lane Principal Arterial. Per the King
County Assessor map, the existing half street ROW width on the site frontage is
approximately 30 feet. Per Renton Municipal Code (RMC) 4-6-060, the minimum
ROW width required on a five lane principal arterial is 103 feet.
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
Benson Petrovitsky Redevelopment– LUA22-000424
1/18/2023
Page 6 of 10
i. In 2013, the City’s Transportation Division prepared a preliminary corridor
safety project to provide intersection improvements at the intersection of
SE Petrovitsky Rd and S Benson Dr (SR 515). The safety plans require
street frontage improvements that include an additional 11-feet wide
right-turn only lane, a 0.5-foot wide curb, an 8-foot wide landscaped
planter, a 12-foot wide ped/ bike path, 2-foot clear area from back of the
path to the new ROW line and a pedestrian safety refuge island. The
street and frontage section requires varying ROW dedication along the
frontage of the 3 parcels. The ROW dedication width of approximately
33.5 feet (subject to final survey) in front of parcel 10810 SE Petrovitsky
Road and varying ROW dedication of the frontages of parcels 17426 108th
Ave SE and 10828 SE Petrovitsky Road are required to be provided by the
developer.
ii. The applicant has provided a street section showing and labelling the
existing ROW line, centerline of ROW, ROW dedication, centerline of
pavement, pavement width, showing and labelling all the street frontage
elements and widths with the land use application. Staff concurs that this
street section generally meets the intention of the corridor safety project
and will review in detail during the civil construction permit process.
iii. The applicant shall provide detailed design and survey information for the
taper lane transition beyond the project’s eastern extent incoming to the
right-turn lane. The design information shall include connections and
rebuilding of the existing sidewalks to provide safe transitions and
reconstruction of neighboring driveways meeting ADA requirements to the
extent that the taper lane matches to existing improvements.
iv. The City of Renton 2023-2028 Transportation Improvement Program,
adopted October 3, 2022 identifies the Carr Rd Improvements as TIP
candidate project #22-29 and extends through the intersection of Carr
Rd/Petrovitsky and Benson Rd (https://cdn5-
hosted.civiclive.com/UserFiles/Servers/Server_7922657/File/City%20Hall/
Public%20Works/Transportation%20Systems/Planning%20and%20Progra
mming/Transportation%20Improvement%20Program%20(TIP)%202018-
2023/2023-
2028%20Transportation%20Improvement%20Program%20(TIP).pdf). The
purpose of the project is to provide “improvements are necessary to
enhance vehicle traffic capacity and safety for vehicles, bicycles, and
pedestrians on this major east-west transportation corridor.” As such, the
frontage improvements, or a portion thereof, may be eligible for credits to
the transportation impact fees levied for the project. These credits will be
determined prior to the issuance of the civil construction and building
permits for the project based on cost estimates provided by the applicant
and reviewed by the City Administrator. RMC 4-1-190 (J) outlines the
criteria for awarding of credits for dedications, construction of
improvements, and past tax payment.
v. The access from SE Petrovitsky Rd will be restricted to right-in right-out
only access (no left turns). C-curbing will be required to be provided on SE
Petrovitsky Road to prevent left turns to and from the site access. Signage
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
Benson Petrovitsky Redevelopment– LUA22-000424
1/18/2023
Page 7 of 10
shall be provided interior to the site and on the driveway approach across
the street to the south indicating right-turn out only.
vi. A minimum intersection radius of 35 feet is required at the intersection SE
Petrovitsky Road (176th St SE) and on 108th Ave SE (Benson Road/ SR 515),
however, the applicant shall provide detailed auto-turn analysis during the
civil construction permit approval process demonstrating clearly that large
trucks can negotiate the turn without driving onto the curb, crossing
ramps and landscape strip. If the review shows deficiency, the radius shall
be increased to accommodate the large vehicles and the site plan adjusted
accordingly.
vii. The Washington State Department of Transportation (WSDOT) provided
comments during the land-use approval process. Primarily, the
intersection of SE Petrovitsky Rd and Benson Rd/SR 515) lies within
WSDOT’s jurisdiction for channelization and intersection control
operations. An Intersection Control Evaluation shall be reviewed and
approved by WSDOT prior to issuance of the civil construction permit. Any
changes resulting from WSDOT’s review shall be implemented in the final
civil construction design. A reduction in lane additions or elimination of
the right-turn and acceleration lanes shall not preclude the need for the
full right-of-way dedication as required in the sections above and below
for the programmed implementation of the corridor safety project in the
future.
b. 108th Ave SE (Benson Road/ SR 515) - is a Principal Arterial. Per King County
Assessor map, the existing half street ROW width on the site frontage is
approximately 45 feet. Per Renton Municipal Code (RMC) 4-6-060, the minimum
ROW width required on a six lane principal arterial is 113 feet.
i. In 2013, the City’s Transportation Division prepared a preliminary corridor
safety project to provide intersection improvements at the intersection of
SE Petrovitsky Rd and S Benson Dr (SR 515). The safety plans require
street frontage improvements that include an additional 11-feet wide
acceleration lane, a 0.5-foot wide curb, an 8-foot wide landscaped planter,
a 12-foot wide ped/ bike path, 2-foot clear area from back of the path to
the new ROW line, and a pedestrian refuge safety island. ROW
dedication of varying width is be required in front of parcel 2923059110 to
accommodate these frontage improvements. The Transportation Division
plan also includes driveway access for this parcel. ROW dedication and
street frontage improvements are required to be provided by the
developer.
ii. The applicant has provided a street section showing and labelling the
existing ROW line, centerline of ROW, ROW dedication, centerline of
pavement, pavement width, showing and labelling all the street frontage
elements and widths with the land use application. Staff concurs that this
street section generally meets the intention of the corridor safety project
and will review in detail during the civil construction permit process.
iii. The applicant shall provide detailed design and survey information for the
taper lane transition beyond the project’s northern extent past the
acceleration lane. The design information shall include connections and
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
Benson Petrovitsky Redevelopment– LUA22-000424
1/18/2023
Page 8 of 10
rebuilding of the existing sidewalks to provide safe transitions and
reconstruction of neighboring driveways meeting ADA requirements to the
extent that the taper lane matches to existing improvements.
iv. The access from 108th Ave SE will be restricted to right-in right-out only
access (no left turns). Signage shall be provided interior to the site
indicating right-turn out only.
v. The Washington State Department of Transportation (WSDOT) provided
comments during the land-use approval process. Primarily, the
intersection of SE Petrovitsky Rd and Benson Rd/SR 515) lies within
WSDOT’s jurisdiction for channelization and intersection control
operations. An Intersection Control Evaluation shall be reviewed and
approved by WSDOT prior to issuance of the civil construction permit. Any
changes resulting from WSDOT’s review shall be implemented in the final
civil construction design. A reduction in lane additions or elimination of
the right-turn and acceleration lanes shall not preclude the need for the
full right-of-way dedication as required in the sections above and below
for the programmed implementation of the corridor safety project in the
future.
2. The proposed intersection corridor safety improvements shall, at a minimum, require
the relocation of the traffic signal at the northeast corner of the SE Petrovitsky Rd/108th
Ave SE intersection.
a. The relocation will require that crosswalk striping and ADA upgrades be made to
the opposing intersections, including, but not limited to receiving ramps, push
button signals, underground conduits, utilities and junction boxes.
b. A pedestrian actuated signal to cross the exclusive right-turn lane shall be
installed between the sidewalk and pedestrian refuge island.
3. The applicant has requested a street modification in order to modify the ROW width
and/or street cross sections for 108th Ave SE and SE Petrovitsky Rd.
a. The City’s transportation group has determined and will support an alternative
standard to match the established standard street sections for 108th Ave SE, SE
Petrovitsky Rd and the intersection thereof as described in sections 1 & 2 above.
b. Therefore, staff is in support of the requested modification. The following are
conditions of the modification approval:
i. Alternative cross-sections as noted in sections 1 & 2 above shall be
implemented for the project pending final review and approval by City
Development Engineering, Transportation Department and WSDOT during
the civil construction permit approval process.
ii. In the event that, at this time, the WSDOT review and approval process
does not allow for the addition of the right-turn and acceleration lanes,
the project shall dedicate right-of-way as described in section 1 above for
the future programmed implementation of TIP Project #22-29. The traffic
signal shall be moved to a location conducive to accommodating the
addition of the right-turn and acceleration lanes.
4. On and off-site ADA (including the street frontages), curbing, sidewalk and parking
lot/drive-aisle improvements will be reviewed in conjunction with the civil construction
permit for the project and will require a grading plan consisting of spot elevations and
slopes showing that ADA and City specifications are being met.
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
Benson Petrovitsky Redevelopment– LUA22-000424
1/18/2023
Page 9 of 10
5. Property corner dedication meeting City code shall be provided.
6. Street lighting and street trees are required to meet current city standards. Final
lighting plans are required to be submitted with the civil construction permit application
and will be reviewed during the construction utility permit review.
7. Undergrounding of all existing and proposed utilities is required on all frontages per
RMC 4-6-090.
8. Paving and trench restoration will comply with the City’s Trench Restoration and
Overlay Requirements.
9. Refer to City code 4-4-080 regarding driveway regulations. Driveways shall be designed
in accordance with City standard plans 104.4 and 104.5.
a. The maximum width of any driveway shall not exceed 30-feet.
i. The driveways as shown on the preliminary engineering plans consisting of
curved radii entrances and exits do not meet City standard driveway
requirements. Final driveway configuration shall meet City standards and
will be reviewed and approved during the civil construction permit approval
process.
b. Driveways shall be located a minimum of 5-feet from property lines.
c. Maximum driveway slope is 8%
10. Parking lot construction shall be in accordance with City code 4-4-80 (G).
11. A traffic impact analysis dated October 4, 2022 was provided by TENW. The site
generated traffic volumes were calculated using data from the Institute of
Transportation Engineers (ITE) Trip Generation Manual, 11th Edition, (2021). The
analysis determined vehicular traffic generated from a proposed development exceeds
20 vehicles per hour in either the AM (6:00 – 9:00) or PM (3:00 – 6:00) peak periods and
provided a discussion on traffic circulation to and from the site and onsite traffic
circulation.
a. Based on the calculations provided, the proposed development would average
1,085 new daily vehicle trips. Weekday peak hour AM trips would generate 71
new vehicle trips, with 34 vehicles leaving and 37 vehicles entering the site.
Weekday peak hour PM trips would generate 104 new vehicle trips, with 52
vehicles entering and 52 vehicles exiting the site. As detailed in the report the
proposed project is not expected to lower the levels of service of the surrounding
intersections included in the traffic study.
i. Increased traffic created by the development will be mitigated by payment
of transportation impact fees, frontage and intersection improvements as
noted in sections 1 & 2 above, and access improvements as noted in
section 1 above.
b. Washington State Department of Transportation (WSDOT) provided comments on
the traffic impact analysis on January 5, 2023.
i. A revised traffic impact analysis addressing the WSDOT comments shall be
submitted to the City and WSDOT at the civil construction permit
application for review and approval. Additional mitigation may be
warranted as a result of the revised analysis.
ii. An Intersection Control Evaluation to be reviewed and approved by
WSDOT is required prior to issuance of the civil construction permit.
iii. WSDOT approval of all channelization and intersection improvements is
required prior to issuance of the civil construction permit.
DocuSign Envelope ID: AA4FA6BA-AA72-4A92-A78C-D1916105F712
Benson Petrovitsky Redevelopment– LUA22-000424
1/18/2023
Page 10 of 10
GENERAL COMMENTS
1. All existing and proposed utility lines and poles (i.e. power, electrical, phone, and cable
services, etc.) along property frontage and within the site must be underground. The
construction of these franchise utilities must be inspected and approved by a City of
Renton inspector.
2. Maximum exposed retaining wall height is 6-ft and shall be setback a minimum of 3-ft
from the right-of-way as outlined in RMC 4-4-040 – Fences, Hedges and Retaining Walls.
3. Adequate separation between utilities as well as other features shall be provided in
accordance with code requirements.
a. 7-ft minimum horizontal and 1-ft vertical separation between storm and other
utilities is required with the exception of water lines which require 10-ft horizontal
and 1.5-ft vertical.
b. The stormwater line should be minimum 5 feet away from any other structure or
wall or building.
c. Trench of any utility should not be in the zone of influence of the retaining wall or
of the building.
4. All civil construction permits for utility and street improvements will require separate plan
submittals. All utility plans shall confirm to the Renton Drafting Standards. A licensed Civil
Engineer shall prepare the civil plans. Please visit the Development Engineering Forms
page for the most up-to-date plan submittal requirements:
http://rentonwa.gov/business/default.aspx?id=42473
5. A landscaping plan shall be included with the civil plan submittal. Each plan shall be on
separate sheets.
6. Fees quoted in this document reflect the fees applicable in the year 2023 only and will be
assessed based on the fee that is current at the time of the permit application or issuance,
as applicable to the permit type. Please visit www.rentonwa.gov for the current
development fee schedule.
7. A demo permit is required for the demolition of the existing buildings. The demo permit
shall be acquired through the building department.