January 24, 2023
Ian Dahl
Encompass Engineering & Surveying
165 NE Juniper St, Ste 201
Issaquah WA 98027
SUBJECT: "On Hold" Notice
PR22-000352 Sierra Homes Short Plat / LUA22-000427
Dear Mr. Dahl,
The Planning Division of the City of Renton accepted the above master application for review on January 4, 2023.
During review of the submitted project documents, staff has determined issues with the Technical Information
Report (dated November 2, 2022) that need to be addressed in order to proceed further with the review. Please
see the attached memorandum prepared by Nathan Janders, Development Engineer, dated January 20, 2023 for
a description of items needing to be addressed before review may continue. In addition to the issues noted in the
memo, the applicant shall address the following items:
At this time, your project has been placed “on hold” pending receipt of the updated project documents identified
above and in the attached memo. The maximum time for resubmittal shall be within ninety (90) days of this notice,
unless an extension is approved by the Current Planning Project Manager. Please contact me at (425) 430-7219 if
you have any questions.
Sincerely,
Alex Morganroth
Senior Planner
cc: Awesome Yah Church/ Owner(s)
Dan Finkbeiner/Applicant
Parties of Record
Attachment: Memorandum prepared by Nathan Janders and dated January 20, 2023
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: January 20, 2023
TO: Alex Morganroth, Senior Planner
FROM: Nathan Janders, Development Engineer
SUBJECT: Sierra Homes Short Plat
702 Nile Ave NE
LUA22-000427
I have reviewed the application for the Sierra Homes Short Plat project located at 702 Nile Ave NE and have the
following comments:
The following comments represent additional information or corrections that are required to be made:
1. In the TIR a flow control facility exemption is claimed for core requirement #3. However, the modeling
used to support the claim must be revised for the following items:
a. The WWHM model used an hourly timestep, a 15 minute timestep shall be used.
b. The WWHM model has a target surface area of 0.195 AC which is equal to the new impervious
surface only. However, per section 1.2.3.1.B – Target Surfaces – 2 the new pervious surface shall
be assumed to be the entire lot area. The total lot area is 0.735 AC and thus both the predeveloped
and developed conditions should have an area equal to 0.735 AC.
c. The WWHM model appears to use flow control facility sizing credits, however, per table 1.2.9.A
privately maintained BMP’s are not allowed to receive facility sizing credits unless using f ull
dispersion or full infiltration (neither of which are indicated as feasible).
d. If a flow control facility is found to be required, then the applicant shall demonstrate that there is
no downstream drainage problem to the wetland; See section 1.2.2.1.1 – Potential Impacts to
Wetlands Hydrology Problem of the RSWDM for further information.
2. The TIR appears to be based on the 2022 Renton Surface Water Design Manual (RSWDM) however there
are references to the 2017 RSWDM. The report shall be updated for compliance with the 2022 RSWDM.
The following comments represent additional information or corrections that should be made when considering
site layout:
1. All existing and proposed utility lines along the property frontage must be relocated underground per
RMC 4-6-090. There is an existing utility pole along the properties Nile Ave NE frontage that shall be
removed and those services spanning to the north and south shall be installed underground to the next
utility pole. Those utilities that service houses on the west side of Nile Ave NE from this span may remain
overhead, however, only up to the serviced properties connection with the ROW; a new service pole may
be installed to retain overhead service and that portion of the service within the ROW shall be installed
underground. Further the subject utility pole contains an existing streetlight, a new streetlight conforming
to COR std. plan 117.1 shall be provided.