Construction Mitigation Description:
Project Name
Swanson Gardner Meyers Office Addition
King County Parcel #:312305-9069
Site Address: 4512 Talbot Road Renton WA
Proposed Construction Dates
Up to two months dependent upon permit approval date.
Hours and days of operation
Monday – Friday 7am-5pm
Proposed hauling / transportation routes
Excavation, demolition and construction waste shall be transport directly from the job site on Talbot Road to
appropriate site designated by the subcontractors. All construction shall be through Benjamin Asphalt .
Measures to be implemented to minimize dust, traffic and transportation impacts, erosion, mud, noise and other
noxious characteristics.
A silt fence shall be established to aid in erosion control of the site along with straw on disturbed soil areas. See
Environmental Check List for additional information. Carpooling shall be proposed to minimize traffic impact during
construction per jurisdictional requirements. Noise generation shall be limited to the hours of construction operation.
Preliminary Traffic Control Plan
Per conversation & emails with Ann Fowler (City of Renton Civil Engineer), a traffic study shall not be required for
this project.
Cranes and FAA approval
The use of a crane shall not be required for this project.
Respectfully,
Edward Pozniak, Project Manager
Architectural Innovations, P.S.