HomeMy WebLinkAbout7945.04 S 12082022Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
esnw.com
FIELD REPORT
Project No. 7945.04 Page 1 of 3 Report ID 7945.04 S 12082022
Date Thu 12/8/2022 Weather 39°F, Overcast
Arrival/Departure Time(s) 10:00AM/10:30AM Travel Time (hr) 1.0
Project Name Canopy Property
Location 4130 Lincoln Ave NE, Renton
ESNW Rep., CESCL No., Phone No. & Report Statement
Jessie Gilbert, ECO-3-6132204, (206) 468-0991
“This report is true, accurate, and complete to the best of my knowledge and belief.”
Client Info/Contact Century Communities | Stacia Bloom
Permit No(s). WAR311273
Reviewed By MLP
Initials/Date
N/A
Field Supervisor Project Manager Initials/Date
Limitations: The presence of our field representative at the site is to provide our client with a source of professional advice, opinions, and recommendations based upon the field representative’s observations and testing of the contractor’s work. Our services do not include supervision or direction of the contractor, their employees, or agents. Recommendations for obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible for complying
with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations, is the sole
responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager.
Type of visit: Weekly Monthly Post–Storm Event
Precipitation since last inspection (approximate): 1.86 inches
Precipitation in last 24 hours (approximate): 0.24 inches
Phase of active construction (check all that apply):
Pre-construction Clearing, demolition, or grading Infrastructure or roads
Concrete pours Vertical construction Utilities
Off-site improvements Site temporarily stabilized Final stabilization
Was water quality sampling part of this inspection? Yes No
If “Yes”:
• Record results in the table below.
• Hanna Turbidity Meter No. 35
Monitoring
Point Monitoring Location Turbidity
(NTU) pH Description of
Discharge Notes
MP-1 Beehive on Lincoln Ave NE 4.47 7 Clear
Discharge cleaned with
Water Tectonics treatment
system on-site before
entering beehive.
Report ID 7945.04 S 12082022 Page 2 of 3
Earth Solutions NW, LLC
Erosion Control BMPs
(13 Elements)
Overall
Condition
(Good; Fair; Poor)
Needs
Repair?
(Yes; No)
Comments
1. Preserve Vegetation; Mark Clearing Limits
• Buffer Zones around Sensitive Areas
• Silt Fence G N -Site perimeter marked by silt fence and chain-link
fence.
-Silt fence around wetland areas.
2. Establish Construction Access
• Fabric; Quarry Spalls • Wheel Wash
• Sweeper Truck
G N
-Stabilized construction entrance with quarry spalls
coming off of Lincoln Ave NE.
-Continue to utilize sweeper often to prevent track-
out.
3. Control Flow Rates
• Stormwater Vault or Facility
• Straw Wattles • Check Dams
G N -Stormwater vault at NW corner of site.
4. Install Sediment Controls
• Silt Fence
• Straw Bale Barriers
• Vegetation • Straw
• Sediment Ponds, Traps & Filters
• Treatment
• Water Truck
G N
-Silt fence installed where needed for sediment control.
-Water-truck on-site; Continue to use as needed to
prevent dust buildup.
5. Stabilize Soils
• Nets & Blankets
• Mulch, Bark & Rock • Hydroseeding; Grass
• Plastic Sheeting
• Stockpiles
G N
-Topsoil throughout site.
-Construction road covered in rocks throughout site.
-Cover any stockpiles if unworked 2+ days;
Stockpiles actively worked at time of visit.
6. Protect Slopes
• Benching; Track-Walking
• Pipe Slope Drains • Plastic Sheeting; Anchors
G N
-Lower slopes covered with plastic, anchored down
with sandbags.
-Upper slopes covered in hydroseed and properly track-walked; Vegetation beginning to grow.
7. Protect Drain Inlets
• Catch Basin Inserts G N -Catch basin inserts have been installed throughout the swales on-site; Silt socks installed in most CB’s.
8. Stabilize Channels and Outlets
• Channel Lining
• Check Dam • Outlet Protection • Nets and Blankets
G N -Rock-lined swales throughout entire site directing
water from East to West towards vault.
9. Control Pollutants • Chemical Storage Area Covered
• Concrete Handling
G N -Storage shack on-site.
10. Control Dewatering G N -Water moved from the vault to the Water Tectonics
treatment system on-site then piped to beehive on
Lincoln Ave NE when needed.
11. Maintain BMPs G N -Maintain BMPs.
12. Maintain SWPPP & Site Logbook G N -Available upon request.
13. Protect Low-Impact Development (LID BMPs)
• Bioretention Rain Garden Facilities • Permeable Pavement - - N/A
Do existing BMPs need to be modified or removed, or do other BMPs need to be installed? Yes No
List the action items in the table below:
Element
# Description and Location Action Required Completion
Date
Report ID 7945.04 S 12082022 Page 3 of 3
Earth Solutions NW, LLC
BMP LEGEND
CONSTRUCTION ENTRANCE
CHAINLINK FENCE
SWALE
STORMWATER VAULT
HYDROSEEDED LOTS
PLASTIC
MONITORING POINT
SILT FENCE