HomeMy WebLinkAbout32 00 00-1-0 - Directional Drill Procedures_SKANSKA REVIEWEDSkanska USA Building
221 Yale Avenue North
Suite 400
Seattle, Washington 98109
P: (206) 726-8000
F: (206) 328-9235
Project: 4222030 Amazon SWA2 - Sub Same Day
FC
1905 Raymond Ave. Renton, WA 98054-2621
Renton, Washington 98054
Submittal #31 00 00-1.0 - Directional Drill Procedures
31 00 00 - Earthwork
Revision 0 Submittal Manager Peyton Yamamoto (Skanska USA Building Inc.
(WA))
Status Open Date Created Feb 15, 2023
Issue Date Feb 15, 2023 Spec Section 31 00 00 - Earthwork
Responsible
Contractor
Ceccanti Inc.Received From Bill Parsons (Ceccanti Inc.)
Received Date Submit By
Final Due Date Mar 7, 2023 Lead Time
Location Type Procedure
Approvers Peyton Yamamoto (Skanska USA Building Inc. (WA)), John Karnowski (NV5), Mark Marquez (NV5), James Miller (NV5), Shane
Walker (Amazon.com Services, Inc.), Greg Wegner (Amazon.com Services, Inc.), Brian Wiese (NV5), Michael Sippo (City of
Renton)
Ball in Court Michael Sippo (City of Renton)
Distribution
Description Please see the attached submittal for the directional drill procedures.
ADDITIONAL SUBMITTAL DETAILS
Delivered Via Priority
LEED No Tracking Number
Track for Expediting No
Submittal Workflow
Name Sent Date Due Date Returned Date Response Attachments
General Information
Attachments
32 00 00-1-0 - Directional Drill
Procedures.pdf
Bill Parsons Mar 7, 2023 Feb 15, 2023 Submitted 32 00 00-1-0 - Directional Drill
Procedures.pdf
Comment Please see the attached submittal for the directional drill procedures.
Peyton Yamamoto Feb 15, 2023 Mar 7, 2023 Feb 15, 2023 For Record Only 32 00 00-1-0 - Directional Drill
Procedures_SKANSKA REVIEWED.pdf
John Karnowski Feb 15, 2023 Mar 7, 2023 Feb 15, 2023 For Record Only
Comment The procedures for conducting directional boring is not a material submittal and not subject to EOR approval. The
procedures should be discussed with the City's inspector.
Mark Marquez Feb 15, 2023 Mar 7, 2023 Pending
Skanska USA Building Page 1 of 2 Printed On: Feb 15, 2023 01:25 PM PST
Name Sent Date Due Date Returned Date Response Attachments
James Miller Feb 15, 2023 Mar 7, 2023 Pending
Shane Walker Feb 15, 2023 Mar 7, 2023 Pending
Greg Wegner Feb 15, 2023 Mar 7, 2023 Pending
Brian Wiese Feb 15, 2023 Mar 7, 2023 Pending
Michael Sippo Mar 7, 2023 Pending
Submittal #31 00 00-1.0 - Directional Drill Procedures Project: 4222030 Amazon SWA2 - Sub Same Day FC
Skanska USA Building Page 2 of 2 Printed On: Feb 15, 2023 01:25 PM PST
MATERIAL TRANSMITTAL
To: Skanska Transmittal No.: 017
Attn: Paul Tosello Date: 2-15-22
Project: SWA2 Amazon Project No.:
Owner: Amazon Location: Renton, WA
Previous Transmittal No. (if resubmitted)
Bid
Item
Spec.
Paragraph
Number Item Description and Use Manufacturer
Dwg.
No(s).
Approval
Status
(Engineer)
Directional Drill Procedures Trenchless
Construction
By this submittal, the Contractor represents that he has determined and verified all field measurements, field construction criteria,
materials, catalog numbers and similar data, or will do so, and that he has checked and coordinated each Shop Drawing with the
project requirements and the Contract Documents. Deviations from the Contract Documents are noted below.
COMMENTS:
Contractor Ceccanti, Inc. Signature Brandon McDonald
(THIS SPACE FOR REVIEW ENGINEER)
To: Date:
Approval status as noted above is in accordance with the following legend:
A. No Exceptions Taken
B. Make Corrections Noted
C. Revise and Resubmit
D. Submit Specified Item By:
E. Rejected cc:
F. See attached Review Comment Sheet dated
Request for Approval of Material
Contract Number
221110
FA Number SR
Date
12/19/2022
Section / Title of Project
Fiber/ITS Lind Ave SW & SW 19th ST to SW 16th ST
County
King
Contractor
Ceccanti
Subcontractor
West Coast Signal
This form shall be completed prior to submittal. If this form is not complete at time of submittal it may be returned for information that was omitted. For assistance in completing, see Instructions and Example
Project Engineer Distribution State Materials Engineer Distribution
Contractor Region Materials General File Signing Inspection
Region Operations Engineer
Fabrication Inspection
DOT Form 350-071 EF Revised 12/2012
State Materials Lab M/S 47365 Other
For WSDOT Use Only
RAM #
Bid
Item No.
Material or
Product/Type
Name and Location of Fabricator,
Manufacturer or Pit Number
Specification
Reference
PE/QPL
Code
Hdqtr./QPL
Code
4 Directional Bore Procedure Trenchless Construction
Project Engineer Date State Materials Engineer Date
Acceptance Action Codes for use by Project Engineer and State Materials Laboratory
1. Acceptance Criteria: Acceptance based upon 'Satisfactory' Test Report for samples of materials to be incorporated into project.
2. Acceptance Criteria: Mfg. Cert. of Compliance for 'Acceptance' prior to use of material.
3. Acceptance Criteria: Catalog Cuts for 'Acceptance' prior to use of material. Catalog Cut Approved Yes No
4. Acceptance Criteria: Submit Shop Drawings for 'Approval' prior to fabrication of material.
5. Acceptance Criteria: Only 'Approved for Shipment', 'WSDOT Inspected' or 'Fabrication Approved Decal' material shall be used.
6. Acceptance Criteria: Submit Certificate of Materials Origin to Project Engineer Office.
7. Acceptance Criteria: Request Transmitted to State Materials Laboratory for Approval Action.
8. Source Approved: 9. Approval Withheld: Submit samples for preliminary evaluation.
10. Approval Withheld:
11. Miscellaneous Acceptance Criteria.
Remarks:
RE: Horizontal Directional Drilling Procedures
SET-UP:
The drill machine, mud truck, tool truck, and vacuum trailer will be mobilized to the site.
POTHOLING EXISTING UTILITIES:
All existing utilities in the bore path will be potholed to determine their location and depth. This is
accomplished by using a vacuum trailer to excavate to find the utility. After determining the depths of
existing utilities, a safe bore path will be planned.
DRILLING PROCEDURES:
Once the machine is set up, the drill head is calibrated, and the mud supply is hooked up. Directly in front
of the machine, a small receiving pit (3’ deep X 5’ long X 3’ wide) is dug. As the drilling progresses, a
mixture of bentonite clay will be pumped into the bore hole. Along the way the depth and pitches of the
drill head are monitored and recorded. The drilling will then proceed to the exit point. Once the pilot bore
is constructed, the pull back process will begin. The exit pit will be 3’ deep X 5’ long X 3’ wide to “feed”
the pipe as the drill pulls it back toward the machine. The fluid used in the drilling process is then
vacuumed into a trailer and hauled to a dump site.
TRACKING EQUIPMENT:
In order to accurately monitor slope and depth, a transmitter capable of reading percent grade and depth
is used. These are of the walk-over variety; the person locating the drill head receives information while
walking over the drill head’s location along the path. The locating system can also be set up at a fixed
location allowing the drill head to steer to the locating box if walking along the bore path is not allowed.
PIPE PULL:
After drilling the pilot hole, the drill head will be removed, and a swivel/reamer attached in order to pull
back the product pipe. As the drill rods are pulled back and removed, the pipe is pulled into the bore
hole. When the pipe is completely pulled in, the pull head is removed from the pipe and the pipe is ready
for tie-in.
If you have questions or need additional information regarding the directional drilling process, please
contact me at 360.474.0123 or on my cellular at 206.396.5554.
Sincerely,
Steve Torgerson
Project Manager
Trenchless Construction Services, L.L.C.