HomeMy WebLinkAboutC_NCR#001_Footing Concrete Pour_20180409Title:
CIP Retaining Wall Footing
NCR No.:
001
City assigned # only
Origination Date:
04/04/2018
Project:
Allura @ Tiffany Park (Permit #C17004253)
Contractor:
Rino Construction
Contractor / Fabricator related to this NCR: Apeland Concrete, Inc.
I. Description of Defect or Nonconformance (list any supporting documentation, pictures, etc) and name of plant representative providing the description:
12:00 pm arrived on-site and noticed that the third party inspector had not tested any of the concrete. The contractor had placed approximately 50 cubic yards of concrete into the footing
starting on the south side moving to the north.
Notified the third party inspector that this project is a WSDOT job and they are required to follow the testing requirements as specified per WSDOT Standard specifications. Third party
inspector was unaware that this project was a WSDOT job and immediately began to test the concrete.
Joe Olivieri from Rino Construction was notified that the concrete tester on-site was unaware of the testing requirements. City Inspector notified Joe Olivieri (Rino Construction) that
the concrete for the wall has not been tested.
Signature:
Printed Name:
Date:
Description confirmed by:
(Print and sign name)
Date:
II. Description of Proposed Repair:
Contractor:
Date:
Proposed Repair Acceptance:
Engineer of Record: (Print and sign name)
Date:
Comments:
II. Description of Proposed Repair:
Contractor:
Date:
Proposed Repair Acceptance:
Engineer of Record: (Print and sign name)
Date:
Comments:
III. Acceptance of Repair:
Acceptance of Repair as per Section II
(Print and sign name)
Date:
Comments: