HomeMy WebLinkAboutKPI Schedule 3-22-23.pdfID Task Mode Task Name Duration Start Finish Predecessors 1 Sector 3 27 days Mon 3/13/23Tue 4/18/23 2 EWF play chips 4 days Mon 3/20/23Thu 3/23/23 3 Portland Loo Plumbing 3 days Fri 3/24/23 Tue 3/28/23 4 Light Pole Bases - final conduit 2 days Tue 3/28/23 Wed 3/29/23 5 Concrete Entry Ramp and Wall 7 days Thu 3/23/23 Fri 3/31/23 6 Decorative Fence 3 days Wed 3/29/23Fri 3/31/23 7 PSE - wiring install 1 day Mon 4/3/23 Mon 4/3/23 8 Portland Loo foundation 10 days Mon 3/27/23Fri 4/7/23 9 Compost and Soil incorporation 20 days Mon 3/13/23Fri 4/7/23 10 School ADA Ramp - Spring Break 5 days Mon 4/10/23Fri 4/14/23 11 Final Sod Installation 5 days Mon 4/10/23Fri 4/14/23 12 Portland Loo Install 5 days Mon 4/10/23Fri 4/14/23 13 Site Furnishings - Tables, Benches, Trash Cans, Bleachers, Drinking fountains 12 days Mon 4/3/23 Tue 4/18/23 14 Sector 2 35 days Mon 3/20/23Fri 5/5/23 15 Sewer work for ASI 9 7 days Mon 3/20/23Tue 3/28/23 16 Electrical pole bases and bench footings3 days Mon 4/3/23 Wed 4/5/23 17 Field Backstop Lumber 3 days Mon 4/3/23 Wed 4/5/23 18 Trench Drain - backstop area 3 days Tue 4/4/23 Thu 4/6/23 19 Dug out Concrete work 7 days Thu 4/6/23 Fri 4/14/23 20 Dug out installtion 5 days Mon 4/17/23Fri 4/21/23 21 Sector 3 21 days Mon 4/3/23 Mon 5/1/23 22 parking lot demo 3 days Mon 4/17/23Wed 4/19/23 23 parking lots curbs 5 days Wed 4/19/23Tue 4/25/23 24 Parking Lot Fencing 5 days Wed 4/26/23Tue 5/2/23 25 asphlat lay 2 days Wed 5/3/23 Thu 5/4/23 26 striping 1 day Fri 5/5/23 Fri 5/5/23 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: KPI Schedule 3-22-23 Date: Wed 3/22/23