Loading...
HomeMy WebLinkAboutWH MM KC Streetlighting Pre-ConCITY OF RENTON PRECONSTRUCTION MEETING – STREETLIGHTING 10/4/16 Weston Heights Plat, Monterey Meadows Plat, Kinkade Crossing Plat PROJECT PERSONNEL: Ian Fitz-James, City Project Manager 425-430-7288 Justin Johnson, Public Works Inspector – Weston Heights 425-430-7291 Brad Stocco, Public Works Inspector – Monterey Meadows 425-430-6582 Tom Main, Public Works Inspector – Kinkade Crossing 425-430-7430 Ryan Puddy, Electrical Inspector 206-999-1821 Jack Oxford, Electrical Inspector 206-999-1822 Eric Cutshall, Transportation Maintenance Supervisor 425-430-7423 GENERAL: 1. Contractors shall use only sets of drawings stamped and signed by the City of Renton for constructing streetlighting improvements. Keep a set of approved drawings on-site at all times. 2. CONSTRUCTION HOURS: 7:00 AM to 8:00 PM Monday thru Friday and 9:00 AM to 8:00 PM on Saturdays by permission only. No work allowed on Sundays. 3. Streets shall be kept clean at all times. Truck washing and other measures as approved are required for the duration of the project. Provide whatever measures necessary for cleanup and dust control during job and at night. 4. Field changes: If minor, submit a shop drawing or schematic through the Public Works Inspector or by FAX 425-430-7300. If major, the project engineer should submit drawings and complete justification, information and calculations as applicable to the City Project Manager. City staff will respond by memo or schedule a meeting within two days. The Public Works Inspector cannot give approval in the field for major construction changes. 5. Street Restoration is required to conform to the City of Renton Trench Restoration and Street Overlay Standards. A copy has been provided. All street repairs shall be complete and in place within 14 days, or as directed by the Public Works Inspector. 6. If the materials shown on the approved plans differ from those shown on the City standard details, material submittals shall be reviewed and approved by the City prior to installation. ELECTRICAL: 1. After calling in the inspection request through the Inspection Request Line, contact Ryan Puddy (206-999-1821) or Jack Oxford (206-999-1822) at 7:30 a.m. the morning of the inspection to provide a contact name and phone number for arranging the electrical inspection with your representative. 2. Have in your possession the electrical permit and streetlight luminaire checklist. Insert both in a clear plastic document protector and attach it to a conduit stubbed up. If the signal control box is installed, for underground conduit inspection approval, place the documents in the signal control box. 3. Service inspection for signal or lighting control pedestals requires access for electrical inspection. If approved, a service approval sticker will be attached by the meter opening for the serving utility. The serving utility will not and shall not connect power unless the approval sticker is in place. 4. All grounding is to meet Standard Plan -119, dated March 20, 2012. 5. Provide Megger Test Report of all wiring to identify any undergrounded conductor that is grounded or open not completing circuit. 6. When calling in a request for final electrical inspection, provide access to all handholes and access openings to light poles. Some bolts require special sockets or wrenches, which are not available to or provided by the Electrical Inspector. 7. Electrical cabinets (Millbank service cabinets) do not meet the minimum City code standards, therefore shall not be considered allowable.