HomeMy WebLinkAboutEX_03_Compton_Lumber_DNS-M_AddendumDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
ADDENDUM TO ENVIRONMENTAL (SEPA) DETERMINATION OF NON-
SIGNIFICANCE (DNS-M) - MITIGATED
Pursuant to WAC 197-11-600(4)(c) and WAC 197-11-625
Addendum to the BMC Renton DNS-M for Compton Lumber
Determination of Non-Significance - Mitigated (DNS-M)
Date of Addendum: April 1, 2019
Date of Initial Threshold Determination: February 6, 2018
Applicant: TorJan Rohhovde, Ronhovde Architects, 14900
Interurban Ave S, Suite 138, Tukwila, WA 98168
File Numbers: LUA17-000445, ECF, SA-A, MOD and LUA19-
000050
Project Name: BMC Renton and Compton Lumber
Location: 2940, 2960, 2980, and 2990 East Valley Road,
Renton, WA 98057
Lead Agency: City of Renton, Department of Community and
Economic Development
Review Process: Addendum to previously issued Determination
of Non-Significance – Mitigated (DNS-M)
Proposal / Purpose of Addendum: The original SEPA threshold determination for the BMC
Renton Site Plan and Modification application was issued on February 7, 2018. The original
application included a proposal for a 24,000 square foot retail/office/storage building, two
4,000 square foot lumber sales buildings, an asphalt lumber yard, 55 surface parking spaces,
and landscaping improvements. The project site is located within the Employment Area land
use designation and the Commercial Arterial (CA) zoning designation. A Category III wetland
with a standard 75-foot buffer has been identified and delineated along the east and south
property boundaries. The applicant is requested a 25 percent buffer reduction with
enhancement, which would reduce the buffer to 56.25 feet. BMC Renton decided not to pursue
their proposal on the project site. Compton Lumber has filed a Site Plan review application
(LUA19-000050) with the City for the construction of a 50,000 square foot lumber and
hardware sales building with outdoor lumber sales and 99 surface parking spaces. Compton
Lumber’s project is similar in scope and scale to the BMC proposal, for which the DNS-M SEPA
DocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD
Addendum to Environmental (SEPA) Review
Page 2 of 3
April 1, 2019
threshold determination was issued. Due to the projects similarities staff has determined that
the existing DNS-M would be appropriate to mitigate the impacts of the Compton Lumber
proposal.
The original SEPA determination included the following mitigation measures all of which should
apply to the Compton Lumber project (LUA19-000050):
1. Project construction shall comply with the recommendations found in the submitted
Geotechnical report prepared by Terra Associates, Inc., dated January 24, 2017.
2. The applicant’s geotechnical engineer shall review the project’s construction and building
permit plans to verify compliance with the submitted geotechnical report. The geotechnical
engineer shall submit a sealed letter stating that he/she has reviewed the construction and
building permit plans and in their opinion the plans and specifications meet the intent of the
report.
3. Prior to the issuance of a construction or building permit for this site, the applicant shall
provide an opinion letter from either the voluntary cleanup program of the Washington
Department of Ecology (WDOE) or from the Washington State Pollution Liability Insurance
Agency (PLIA) that states that soil cleanup and planned groundwater monitoring are likely to
receive a No Further Action (NFA) or that the project progress and proposed groundwater
monitoring is in Partial Sufficiency (PS) of the cleanup and is in substantive compliance with the
Model Toxics Control Act.
4. Prior to any occupancy of this site and prior to the issuance of a Temporary or Final
Certificate of Occupancy for this site, the applicant shall provide documentation from the
Department of Ecology evidencing that the cleanup on the site has been completed (less any
required ongoing monitoring) to bring the site in compliance with the Model Toxics Control Act
and any other applicable cleanup law.
The City’s Environmental Review Committee issued a Determination of Non-Significance -
Mitigated (DNS-M) for the BMC Renton Site Plan and Street Modification. The DNS-M included
four mitigation measures. A 14-day appeal period commenced on February 6, 2018 and ended
on February 23, 2018.
Analysis: It has been determined that the environmental impacts of the proposal were
adequately addressed under the analysis contained within the project’s issued DNS-M. Based
on WAC 197-11-600(4)c, the addendum process may be used if analysis or information is added
that does not substantially change the analysis of significant impacts and alternatives in the
existing environmental document.
This Addendum is appropriate because it contains only minor information not includ ed in the
DNS-M and there are no environmental impacts related to inclusion of the new information.
The proposed site plan modification would not change the analysis or impacts in the initial SEPA
Review, therefore an Addendum to the DNS-M may be issued pursuant to WAC 197-11-625.
DocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD
Addendum to Environmental (SEPA) Review
Page 3 of 3
April 1, 2019
DECISION: The City of Renton is hereby issuing a SEPA Addendum pursuant to WAC 197-11-600
to addend the Weatherly Inn project to provide seven (7) additional assisted living units, three
(3) additional memory care beds and associated parking.
Additional Information: If you would like additional information, please contact Matt Herrera,
Senior Planner, City of Renton Planning Division, Department of Community & Economic
Development at (425) 430-6593. There is no comment period for this Addendum, dated April 1,
2019 issued by the City of Renton Environmental Review Committee
Exhibits
Exhibit 1 DNS-M Addendum
Exhibit 2 BMC Renton SEPA DNS-M (LUA17-000445, SA-A, ECF, MOD), dated February 6,
2018
Exhibit 3 Compton Lumber Architectural Plan Set
ENVIRONMENTAL REVIEW COMMITTEE SIGNATURES:
Gregg Zimmerman, Administrator
Public Works Department
Date
Kelly Beymer, Administrator
Community Services Department
Date
Rick M. Marshall, Administrator
Fire & Emergency Services Department
Date
C.E. “Chip” Vincent, Administrator
Department of Community & Economic Development
Date
DocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD
4/1/2019 | 2:54 PM PDT
4/1/2019 | 5:49 PM PDT
4/1/2019 | 4:17 PM PDT
4/1/2019 | 2:50 PM PDT
C.DEPARTMENTOFCOMMUNITY—‘“Renton.ANDECONOMICDEVELOPMENTMEMORANDUMDATE:February6,2018TO:EnvironmentalReviewCommittee(ERC)FROM:JillDing,SeniorPlannerSUBJECT:BMCRenton(LUA17-000445)SEPARequestforReconsiderationTheEnvironmentalReviewCommittee(ERC)reviewedtheabovementionedSitePlanReviewapplicationandissuedaSEPADeterminationofNon-SignificanceMitigated(DNS-M)onJanuary8,2018withthreemitigationmeasures:1.ProjectconstructionshallcomplywiththerecommendationsfoundinthesubmittedGeotechnicalreportpreparedbyTerraAssociates,Inc.,datedJanuary24,2017.2.Theapplicant’sgeotechnicalengineershallreviewtheproject’sconstructionandbuildingpermitplanstoverifycompliancewiththesubmittedgeotechnicalreport.Thegeotechnicalengineershallsubmitasealedletterstatingthathe/shehasreviewedtheconstructionandbuildingpermitplansandintheiropiniontheplansandspecificationsmeettheintentofthereport.3.Cleanupand/orremediationofthecontaminatedsoilsonsiteshallcomplywiththerequirementsasoutlinedbytheDepartmentofEcology.TheapplicantshallberequiredtosubmitacopyofaNoFurtherActionletterorcomparablefromtheDepartmentofEcologypriortotheissuanceofanyConstructionorBuildingPermitsontheprojectsite.TheDNS-MwaspublishedonJanuary12,2018withanappealperiodthatendedonJanuary26,2018.ArequestforreconsiderationoftheSEPAdeterminationwasreceivedonJanuary25,2018fromMichaelDaDaltoofBMC.TherequestforreconsiderationrequeststhatMitigationMeasure#3bereplacedwiththefollowinglanguage:“TheapplicantwillprovideanopinionletterfromeitherthevoluntarycleanupprogramoftheWDOEorfromtheWashingtonStatePollutionLiabilityInsuranceAgency(PLIA)thatstatesthesoilcleanupandplannedgroundwatermonitoringarelikelytoreceiveanNFAorthattheprojectprogressandproposedgroundwatermonitoringisinPartialSufficiency(PS)ofthecleanupandisinsubstantivecompliancewiththeModelToxicscontrolactpriortotheissuanceofaconstructionorbuildingpermitforthissite.”TherequestforreconsiderationstatesthatduetotheexistingbacklogatDOEregardingtheEXHIBIT 2DocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD
EnvironmentalReviewCommitteePage2of3February6,2018cleanupofcontaminatedsites,constructionshouldbepermittedtocommenceprovidedtheapplicantcandemonstratethattheyareworkingwiththenecessaryregulatoryagenciesregardingthecleanupofcontaminantsonthesite.StaffComment:Theapplicant’srequesttoallowpermitstobeissuedprovidedcleanupworkhasbeeninitiatedincompliancewithstaterequirementsisreasonable,howevertoensurethatthecleanupiscompletedinatimelymanner,theapplicantshouldberequiredtocompletecleanuppriortoanyoccupancyoftheproposedbuildingbeingissued.Recommendation:Inlightoftheadditionalinformationprovidedbytheapplicant,staffrecommendsthattheERCmodifyMitigationMeasure#3andaddonenewmitigationmeasuresuchthatthemitigationmeasuresreadintheirentiretyasfollows:1.ProjectconstructionshallcomplywiththerecommendationsfoundinthesubmittedGeotechnicalreportpreparedbyTerraAssociates,Inc.,datedJanuary24,2017.2.Theapplicant’sgeotechnicalengineershallreviewtheproject’sconstructionandbuildingpermitplanstoverifycompliancewiththesubmittedgeotechnicalreport.Thegeotechnicalengineershallsubmitasealedletterstatingthathe/shehasreviewedtheconstructionandbuildingpermitplansandintheiropiniontheplansandspecificationsmeettheintentofthereport.3.Priortotheissuanceofaconstructionorbuildingpermitforthissite,theapplicantshallprovideanopinionletterfromeitherthevoluntarycleanupprogramoftheWashingtonDepartmentofEcology(WDOE)orfromtheWashingtonStatePollutionLiabilityInsuranceAgency(PLIA)thatstatesthatsoilcleanupandplannedgroundwatermonitoringarelikelytoreceiveaNoFurtherAction(NFA)orthattheprojectprogressandproposedgroundwatermonitoringisinPartialSufficiency(PS)ofthecleanupandisinsubstantivecompliancewiththeModelToxicsControlAct.4.PriortoanyoccupancyofthissiteandpriortotheissuanceofaTemporaryorFinalCertificateofOccupancyforthissite,theapplicantshallprovidedocumentationfromtheDepartmentofEcologyevidencingthatthecleanuponthesitehasbeencompleted(lessanyrequiredongoingmonitoring)tobringthesiteincompliancewiththeModelToxicsControlActandanyotherapplicablecleanuplaw.Appealsoftheenvironmentaldeterminationmustbefiledinwritingonorbefore5:00p.m.onFebruary23,2018.Appealsmustbefiledinwritingtogetherwiththerequiredfeewith:HearingExaminer,CityofRenton,1055SouthGradyWay,Renton,WA98057.AppealstotheExamineraregovernedbyRMC4-8-110andmoreinformationmaybeobtainedfromtheRentonCityClerk’sOffice,(425)430-6510.DocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD
EnvironmentalReviewCommitteePage3of3February6,2018DATEOFDECISION:SIGNATURES:FEBRUARY6,2018GreggZimmermjatorPublicWorksDdprtmentKellyBeWA(1DateCommunityServicesDepartment1RickM.Marshall,AdministratorDateDateRentonRegionalFireAuthorityYsI1—C.E.“Chip”Vincent,AdministratorDepartmentofCommunity&EconomicDevelopmentDateDocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD
PARCEL NO.
3023059099
PARCEL NO.
3023059091
PARCEL NO.
3023059098 PARCEL NO.
3023059096
PARCEL NO.
3023059085 PARCEL NO.
30230591036,000 SFTWO STORYOFFICE SPACE11,000 SF
COVERED
LUMBER SALES
REMOVE EXISTING ACCESS
EXISTING DRIVEWAY
TO REMAIN. INSTALL
ONE-WAY SPIKE STRIP.
EXISTING DRIVEWAY
TO REMAIN
ASPHALT LUMBER
SALES AREA
15' BUILDING
SETBACK
24'x12' OVERHEAD DOOR
20'x12'
OVERHEAD
DOOR
10,000 SF RETAIL
SALES AREA
DUMPSTER AND
RECYCLING
423 SF (MIN)S89° 39' 04"E452.25'S9° 28' 54"E
628.23'S89° 45' 25"E321.19'S1° 49' 52"W
658.54'S89° 45' 25"E406.80'S89° 45' 25"E361.01'S89° 39' 04"E167.06'S1° 49' 52"W
108.04'
S1° 49' 52"W
1216.80'
S1° 49' 52"W
1216.80'
EXISTING STRUCTURE
TO BE REMOVED
EXISTING STRUCTURE
TO BE REMOVED
EXISTING STRUCTURE
TO BE REMOVED
EXISTING STRUCTURE
TO BE REMOVED
EXISTING STRUCTURE
TO BE REMOVED
PARCEL BOUNDARY LINE
PARCEL BOUNDARY LINE
PARCEL BOUNDARY LINE
PARCEL BOUNDARY
LINE
71' ROW
EXISTING WETLAND
BOUNDARY
CONTRACTOR SHALL CUT
AND PATCH ASPHALT WHERE
STORM DRAINAGE SYSTEM CONNECTS
TO EXISTING.
NEW 6' BLACK
VINYL COATED
CHAINLINK
FENCE.
ACCESS
GATE
GUARD SHACK
EXISTING STRUCTURE
TO BE REMOVED
36'
INSTALL NEW
DRIVEWAY ACCESS
MATCH EXISTING SIDEWALK
100'
40'
30'
40'
15' SETBACK
EXISTING STRUCTURES
TO BE REMOVED
56.25' REDUCED WETLAND BUFFER
15'
100'
14'
TRUCK SCALE
15'
ROOF
OVERHANG
15' BUILDING SETBACK
10' BUILDING SETBACK
40'
4,000 SF COVERED
LUMBER SALES
FFE= 19.5
4,000 SF COVERED
LUMBER SALES
FFE= 19.5
CONTRACTOR SHALL CUT
AND PATCH ASPHALT WHERE
STORM DRAINAGE SYSTEM CONNECTS
TO EXISTING.
WASHINGTON
S
R
1
6
7
30'
24'
R20'R20'
R20'
R20'R5'
R5'
R6'
R4'
FLAG POLE RESTING AREA
1
2
3
4
TEL FAX www.ahbl.comWEBTELFAXwww.ahbl.comWEBTELFAXwww.ahbl.comWEB
2215 North 30th Street, Suite 300 Tacoma, WA 98403
253.383.2422TEL 253.383.2572FAX www.ahbl.comWEB
TACOMA SEATTLE SPOKANE TRI-CITIES
Know what's below.
before you dig.Call
R
3
TCSDJHDJH/LDJ
11.01.2017
PERMIT SET
2160915.10
PO BOX 817
AUBURN, WA 98071-0817
CONTACT: MR. DARRELL DONOVAN
LATITUDE
DEVELOPMENT, LLC
BMC RENTON
A PORTION OF THE SW 1/4 OF THE NE 1/4 OF SEC. 30, TWN. 23 N., RGE. 05 E. W.M.
CITY OF RENTON, KING COUNTY, WASHINGTON.
BMC RENTON
DATE: November 22, 2017 FILENAME: Q:\2016\2160915\10_CIV\CAD\2160915-SITE.dwg
C1.0
2
SITE PLANNGRAPHIC SCALE
0 30 60
1" = 30 FEET
15
SITE ADDRESS
2940, 2960, 2980, AND 2990 EAST VALLEY ROAD
RENTON, WA 98057
PARKING NOTES:
MINIMUM REQUIRED:
15520 SF LARGE ITEMS SALES AREA - 20 SPACES
6,000 SF GENERAL OFFICES - 10 SPACES
10,000 SF RETAIL - 25 SPACES
TOTAL: 55 PARKING SPACES REQUIRED
PROVIDED PARKING:
57 SPACES INCLUDING 3 ADA PARKING SPACES
FLAG POLE
EXHIBIT 3
RECEIVED
12/07/2017 jding
PLANNING DIVISION
DocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD
14900 INTERURBAN AVE SOUTHSUITE 138TUKWILA, WASHINGTON 98168(206)859-5500 | FAX (206)859-5501ronhovdearchitects.comARCHITECTURAL RENDERINGSSTACEY HOLDINGS SHOWROOM AND LUMBER YARDRENTON, WA 98168 JOB NO: 2018.60DRAWN BY: LWSCHECK'D BY:TJRDATE: 03/11/19 AR1.1EXHIBIT 4RECEIVED03/18/2019 jdingPLANNING DIVISIONDocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD
DocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD
DocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD
DocuSign Envelope ID: E78DFD02-DC51-4714-9306-1CF3E407ACCD