HomeMy WebLinkAbout20180398E003_Renton_ES_16_2022-11-14_TESC_029Temporary Erosion and
Sediment Control Monitoring
DATE PROJECT NAME AESI PROJECT NO. TESC REPORT NO.
11/14/2022 Renton ES 16 20180398E003 029
LOCATION CITY MUNICIPALITY CSWGP
1075 Duvall Ave NE Renton Renton WAR310781
PREVIOUS SITE VISIT CLIENT/OWNER WEATHER 24 HOUR RAINFALL PAST WEEK RAINFALL
11/07/2022 Renton School District 403 Clear 30F 0 0.14
AESI FIELD REP Bruce Guenzler AESI PROJECT MANAGER Bruce Guenzler
QUALITY/CONDITION (SEE SWPPP FOR BMP LOCATIONS)
CONSTRUCTION ENTRANCE SITE RESTRICTED ACCESS
Gravel, quarry spalls Locked chain link fences
WHEEL WASH SEDIMENT TRACK OUT
N/A City construction in right of way, not under this permit
ROADWAY SURFACE CATCH BASIN
Crushed rock, quarry spalls Silt socks installed in catch basins
LIMITS BUFFER AREA STABILIZATION
Marked by chain link fences N/A
SILT FENCING CONCRETE WORK (Sidewalks, curbing, foundation)
Installed along site perimeter None observed
COVER MEARSURES OVERALL STRAW
Good, actively using stockpiles Covering exposed soils and slopes
PLASTIC SHEETING HYDROSEED
N/A Hydroseed covering exposed soils on N and W end of site
CONVEYENCE CHANNEL CHECK DAMS
Temporary channels on north and south end of site
directing water to catch basin
Temporary check dams and swale on NE end of site
STOCKPILE COVER PIPE SLOPE DRAINS
Actively using stockpiles N/A
LEVEL SPREADER LANDSCAPE/MULCH
N/A N/A
SEDIMENT POND TRAP SEDIMENT POND INLET/OUTLET
Temporary sediment ponds on NE and W end of site N/A
SEDIMENT POND SIDE SLOPES SURFACE WATER OBSERVATION
(Creek, Wetland, or Lake) (Clear, Turbid, Sheen)
Covered with hydroseed and quarry spalls Clear puddles
WATER QUALITY SAMPLE TURBIDITY (NTU) pH OVERALL
No discharge N/A N/A BMP's adequate
SAMPLE LOCATION AREAS OF CONCERN
Temporary swale in NE corner of site Silt fence
CORRECTIVE ACTIONS
PAST CORRECTIVE ACTIONS
Is this site in compliance with the terms and conditions of the SWPP and CSWGP discharge Permit? Yes
www.aesgeo.com
This document is considered DRAFT until reviewed and initialed by an AESI Project Manager
TESC REPORT
DATE CSWGP PROJECT NO. TESC REPORT NO.
11/14/2022 WAR310781 20180398E003 029
Sample Location Approximate Flow Turbidity NTU/Transparency pH Compliance
ADDITIONAL COMMENTS:
The contractor is using temporary check dams and swales onsite to impound the water. The swale has adequate water
storage for now and will work as a temporary short term solution. The contractor has acquired a Baker tank and notified
AESI that a permit from King County is pending to allow storm water discharge to the sanitary sewer system with higher
turbidity limits.