HomeMy WebLinkAbout2023-04-24 Seattle Sounders FC HQ CSWPPP Construction Stormwater General Permit Stormwater Pollution Prevention Plan (SWPPP) for Seattle Sounders FC Headquarters & Training Center Prepared for: The Washington State Department of Ecology Northwest Regional Office (Bellevue, WA) Permittee / Owner Developer Operator / Contractor Seattle Sounders FC Seattle Sounders FC Venture General Contracting LLC Certified Erosion and Sediment Control Lead (CESCL) Name Organization Contact Phone Number TBD TBD TBD SWPPP Prepared By Name Organization Contact Phone Number William Andres Coughlin Porter Lundeen 206-343-0460 SWPPP Preparation Date 4/24/2023 Project Construction Dates Activity / Phase Start Date End Date Construction 5/2023 12/2023 P a g e | 1 Table of Contents 1 Project Information .............................................................................................................. 6 1.1 Existing Conditions ...................................................................................................... 6 1.2 Proposed Construction Activities .................................................................................. 7 2 Construction Stormwater Best Management Practices (BMPs) ........................................... 8 2.1 The 13 Elements .......................................................................................................... 8 2.1.1 Element 1: Preserve Vegetation / Mark Clearing Limits ........................................ 8 2.1.2 Element 2: Establish Construction Access ............................................................ 9 2.1.3 Element 3: Control Flow Rates ............................................................................10 2.1.4 Element 4: Install Sediment Controls ...................................................................11 2.1.5 Element 5: Stabilize Soils ....................................................................................12 2.1.6 Element 6: Protect Slopes....................................................................................13 2.1.7 Element 7: Protect Drain Inlets ............................................................................14 2.1.8 Element 8: Stabilize Channels and Outlets ..........................................................15 2.1.9 Element 9: Control Pollutants ...............................................................................16 2.1.10 Element 10: Control Dewatering ..........................................................................20 2.1.11 Element 11: Maintain BMPs .................................................................................21 2.1.12 Element 12: Manage the Project ..........................................................................22 2.1.13 Element 13: Protect Low Impact Development (LID) BMPs .................................25 3 Pollution Prevention Team .................................................................................................26 4 Monitoring and Sampling Requirements ............................................................................27 4.1 Site Inspection ............................................................................................................27 4.2 Stormwater Quality Sampling ......................................................................................27 4.2.1 Turbidity Sampling ...............................................................................................27 4.2.2 pH Sampling ........................................................................................................29 5 Discharges to 303(d) or Total Maximum Daily Load (TMDL) Waterbodies .........................30 5.1 303(d) Listed Waterbodies ..........................................................................................30 5.2 TMDL Waterbodies .....................................................................................................30 6 Reporting and Record Keeping ..........................................................................................31 6.1 Record Keeping ..........................................................................................................31 6.1.1 Site Log Book ......................................................................................................31 6.1.2 Records Retention ...............................................................................................31 6.1.3 Updating the SWPPP ...........................................................................................31 6.2 Reporting ....................................................................................................................32 6.2.1 Discharge Monitoring Reports ..............................................................................32 6.2.2 Notification of Noncompliance ..............................................................................32 P a g e | 2 List of Tables Table 2 – Pollutants ..................................................................................................................16 Table 3 – pH-Modifying Sources ...............................................................................................18 Table 5 – Management .............................................................................................................22 Table 6 – BMP Implementation Schedule .................................................................................24 Table 7 – Team Information ......................................................................................................26 Table 8 – Turbidity Sampling Method ........................................................................................27 List of Appendices Appendix/Glossary A. Site Map B. BMP Detail C. BMP C101: Preserving Natural Vegetation · BMP C103: High Visibility Fence · BMP C105/COR STD 215.00: Stabilized Construction Entrance/Exit · BMP C106/COR STD 215.00: Wheel Wash · BMP C120: Temporary and Permanent Seeding · BMP C123: Plastic Covering · BMP C140: Dust Control · BMP C150: Materials on Hand · BMP C151: Concrete Handling · BMP C152: Sawcutting and Surfacing Pollution Prevention · BMP C153: Material Delivery, Storage, and Containment · BMP C160: Certified Erosion and Sediment Control Lead · BMP C162: Scheduling · BMP C220/COR STD 216.30: Storm Drain Inlet Protection · BMP C233/COR STD 214.00: Silt Fence · BMP C235/COR STD 213.40: Straw Wattles · BMP C252: High pH Neutralization Using CO2 P a g e | 3 Correspondence D. Department of Ecology – Northwest Regional Office 3190 160th Avenue SE Bellevue, WA 98008 425-649-7000 City of Renton – Public Works 11055 S Grandy Way Renton, WA 98057 425-430-7400 P a g e | 4 Site Inspection Form E. Construction Stormwater General Permit (CSWGP) F. 303(d) List Waterbodies / TMDL Waterbodies Information G. Contaminated Site Information P a g e | 5 List of Acronyms and Abbreviations Acronym / Abbreviation Explanation 303(d) Section of the Clean Water Act pertaining to Impaired Waterbodies BFO Bellingham Field Office of the Department of Ecology BMP(s) Best Management Practice(s) CESCL Certified Erosion and Sediment Control Lead CO2 Carbon Dioxide CRO Central Regional Office of the Department of Ecology CSWGP Construction Stormwater General Permit CWA Clean Water Act DMR Discharge Monitoring Report DO Dissolved Oxygen Ecology Washington State Department of Ecology EPA United States Environmental Protection Agency ERO Eastern Regional Office of the Department of Ecology ERTS Environmental Report Tracking System ESC Erosion and Sediment Control GULD General Use Level Designation NPDES National Pollutant Discharge Elimination System NTU Nephelometric Turbidity Units NWRO Northwest Regional Office of the Department of Ecology pH Power of Hydrogen RCW Revised Code of Washington SPCC Spill Prevention, Control, and Countermeasure su Standard Units SWMMEW Stormwater Management Manual for Eastern Washington SWMMWW Stormwater Management Manual for Western Washington SWPPP Stormwater Pollution Prevention Plan TESC Temporary Erosion and Sediment Control SWRO Southwest Regional Office of the Department of Ecology TMDL Total Maximum Daily Load VFO Vancouver Field Office of the Department of Ecology WAC Washington Administrative Code WSDOT Washington Department of Transportation WWHM Western Washington Hydrology Model P a g e | 6 1 Project Information Project/Site Name: Seattle Sounders FC Headquarters & Training Center Street/Location: 1901 Oakesdale Ave SW City: Renton State: WA Zip code: 98057 Receiving waterbody: Puget Sound 1.1 Existing Conditions Total acreage (including support activities such as off-site equipment staging yards, material storage areas, borrow areas). Total acreage: 13.15 Disturbed acreage: 13.15 Existing structures: 1.37 (existing office building) Topography: The site slopes generally south-southeast to north-northwest with about a 3-foot elevation change throughout most of the area. Larger grade differences exist in localized areas within that plane, especially along the western edge of the project site which is adjacent to Pond B’s side-slope. Drainage patterns: Runoff from the site will be conveyed to a new water quality vault, then into South Pond B. The site discharges to the managed stormwater system within the Longacres property which was sized and constructed in anticipation of receiving undetained and untreated runoff from this site. That system drains to Springbrook Creek in accordance with the Development Agreement and associated Master Drainage Plan for the Longacres Office Park that was previously permitted by the City and State. Springbrook Creek, in turn, drains to the Black River and, ultimately, the Duwamish River and Puget Sound. Existing Vegetation: There are trees and landscaping throughout the site surrounding the asphalt parking lots and concrete walkways. Critical Areas (wetlands, streams, high erosion risk, steep or difficult to stabilize slopes): Wetland A is located northwest of the project limits. List of known impairments for 303(d) listed or Total Maximum Daily Load (TMDL) for the receiving waterbody: Puget Sound · Bacteria – Assessment Unit ID: 47122F4I00101 There are no suspected and/or known contaminants associated with the project site. P a g e | 7 1.2 Proposed Construction Activities Description of site development: The Seattle Sounders FC Headquarters & Training Center Project proposes to build (4) sports fields by eveloped upon existing open grass fields, portions of a parking lot, and a decommissioned helicopter pad. Existing swales and ponds located on the site will not be encroached upon for this project Description of construction activities: Site development will include asphalt paving, landscaping, concrete sidewalk and installation, excavation for 584,020 fubic feet of floodplain mitigation, and the construction of the (4) sport fields and associated infrastructure. Description of site drainage including flow from and onto adjacent properties. Must be consistent with Site Map in Appendix A: This project proposes to construct a drainage system with a new network of underground pipes and catch basins to collect surface water runoff throughout the site and direct it to a water quality treatment facility that will be constructed adjacent to an existing detention pond (Pond B) which exists on the property. Treated water from that facility will flow into Pond B, along with higher storm events that are not subject to the requirements for water quality treatment. Pond B was designed for the Boeing Master Plan and was constructed to accommodate the full detention requirements for the overall Longacres Campus, of which this Sounders Field Complex site is a part. From Pond B, the storm runoff flows into the North Pond (Pond A) via a flow control facility which in turn flows out to Springbrook Creek and ultimately the Duwamish River. This system is consistent with the conditions of the original Longacres Development Agreement with the City which was the basis for the existing development on the property. Additionally, a series of underground storage chambers (StormTech or Eq) is proposed to provide the flood plain fill mitigation volume. Description of final stabilization: Native landscape shrubs and trees are being retained where feasible. All areas on-site will be stabilized with either paving or landscape areas. Contaminated Site Information: There are no contaminated areas on-site. Proposed activities regarding contaminated soils or groundwater: Not applicable. P a g e | 8 2 Construction Stormwater Best Management Practices (BMPs) The SWPPP is a living document reflecting current conditions and changes throughout the life of the project. These changes may be informal (i.e., hand-written notes and deletions). Update the SWPPP when the CESCL has noted a deficiency in BMPs or deviation from original design. 2.1 The 13 Elements 2.1.1 Element 1: Preserve Vegetation / Mark Clearing Limits To protect adjacent properties and to reduce the area of soil exposed to construction, the limits of construction will be clearly marked before land-disturbing activities begin. Trees that are to be preserved shall be clearly delineated, both in the field and on the plans. In general, natural vegetation and native topsoil shall be retained in an undisturbed state to the maximum extent possible. The BMPs relevant to marking the clearing limits that will be applied for this project include: · BMP C101: Preserving Natural Vegatation · BMP C103: High-Visability Fence · BMP C233/COR STD 214.00: Silt Fence Installation Schedules: The high visibility fencing, silt fencing, and natural vegetation protection shall be installed at the beginning of construction to ensure that the above listed areas are preserved to the maximum extent possible through the duration of construction activities. Inspection and Maintenance plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL P a g e | 9 2.1.2 Element 2: Establish Construction Access Construction access or activities occurring on unpaved areas shall be minimized, yet where necessary, access points shall be stabilized to minimize the tracking of sediment onto public roads. Wheel washing, street sweeping, and street cleaning shall be employed as necessary to prevent sediment from entering state waters. All wash wastewater shall be controlled on site. The specific BMPs related to establishing construction access that will be used on this project include: · BMP C105/COR STD 215.00: Stabilized Construction Access · BMP C106/COR STD 215.00: Wheel Wash Installation Schedules: The project will utilize the existing paved access driveways, onsite hardscape, and asphalt parking areas for access and staging. Quarry spall access roads are not recommended or necessary. The stabilized construction access shall be available via the existing site driveways at the start of construction and will be utilized to the maximum extent possible through the duration of construction activities. Inspection and Maintenance Plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL P a g e | 10 2.1.3 Element 3: Control Flow Rates Will you construct stormwater retention and/or detention facilities? Yes No Will you use permanent infiltration ponds or other low impact development (example: rain gardens, bio-retention, porous pavement) to control flow during construction? Yes No In order to protect the properties and waterways downstream of the project site, stormwater discharge from the site will be controlled. In general, discharge rates of stormwater from the site will be controlled where increases in impervious area or soil compaction during construction could lead to downstream erosion, or where necessary to meet local agency stormwater discharge requirements. The specific BMPs for flow control that shall be used on this project include: · BMP C235/COR STD 213.40: Straw Wattles See Appendix B – Construction BMPs for BMP details. Installation Schedules: Wattles shall be installed at the beginning of construction activities to ensure the protection of onsite areas downstream of the clearing area to the maximum extent possible. Inspection and Maintenance Plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL P a g e | 11 2.1.4 Element 4: Install Sediment Controls All stormwater runoff from disturbed areas shall pass through appropriate sediment removal BMPs before leaving the construction site or prior to being discharged to an infiltration facility. The specific BMPs to be used for controlling sediment on this project include: · BMP C233/COR STD 214.00: Silt Fence · BMP C235/COR STD 213.40: Straw Wattles See Appendix B – Construction BMPs for BMP details. In addition, sediment will be removed from paved areas in and adjacent to construction work areas manually or using mechanical sweepers, as needed, to minimize tracking of sediments on vehicle tires away from the site and to minimize wash off of sediments from adjacent streets in runoff. Installation Schedules: Silt fence and straw wattles shall be installed at the beginning of construction activities to ensure onsite areas downstream of the clearing area are protected to the maximum extent possible. Inspection and Maintenance Plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL P a g e | 12 2.1.5 Element 5: Stabilize Soils West of the Cascade Mountains Crest Season Dates Number of Days Soils Can be Left Exposed During the Dry Season May 1 – September 30 7 days During the Wet Season October 1 – April 30 2 days Soils must be stabilized at the end of the shift before a holiday or weekend if needed based on the weather forecast. Anticipated project dates: Start date: 4/2023 End date: 12/2023 Will you construct during the wet season? Yes No Exposed and unworked soils shall be stabilized with the application of effective BMPs to prevent erosion throughout the life of the project. The specific BMPs for soil stabilization that shall be used on this project include: · BMP C120: Temporary and Permanent Seeding · BMP C123: Plastic Covering · BMP C140: Dust Control See Appendix B – Construction BMPs for BMP details. In general, exposed soils will be stabilized as soon as possible, and soil stockpiles will be temporarily covered with plastic sheeting. All stockpiled soils shall be stabilized from erosion, protected with sediment trapping measures, and where possible, be located away from storm drain inlets, waterways, and drainage channels. Construction activities shall be scheduled in a way that limits the amount of time soil is exposed throughout the duration of the project. Installation Schedules: Soil stabilization BMPs shall be installed and maintained starting at the beginning of construction as soon as soils are exposed, and throughout construction activities for as long as they are exposed during the designated time frames listed above to ensure they are utilized to the maximum extent possible through the duration of construction activities. Inspection and Maintenance Plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL P a g e | 13 2.1.6 Element 6: Protect Slopes Will steep slopes be present at the site during construction? Yes No All temporary stockpile slopes will be designed, constructed, and protected in a manner that minimizes erosion. The following BMPs will be used to protect slopes for this project: · BMP C120: Temporary and Permanent Seeding · BMP C123: Plastic Covering See Appendix B – Construction BMPs for BMP details. Installation Schedules: Slope protection BMPs shall be installed and maintained starting at the beginning of construction as soon as soils are exposed, and throughout construction activities for as long as they are exposed during the designated time frames listed above to ensure they are utilized to the maximum extent possible through the duration of construction activities. Inspection and Maintenance Plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL P a g e | 14 2.1.7 Element 7: Protect Drain Inlets All storm drain inlets made operable during construction shall be protected to prevent unfiltered or untreated water from entering the drainage conveyance system. The following inlet protection measures will be applied on this project:  BMP C220/COR STD 216.30: Storm Drain Inlet Protection See Appendix B – Construction BMPs for BMP details. Installation Schedules: Storm drain inlet protection shall be installed at the beginning of construction, as no grading or construction is required prior to their installation. Inspection and Maintenance plan: Inlet protection will be cleaned (or removed and replaced) when sediment has filled the device by one third (1/3) or as specified by the manufacturer. Inlets will be inspected weekly at a minimum and daily during storm events. Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL P a g e | 15 2.1.8 Element 8: Stabilize Channels and Outlets There will be no temporary on-site conveyance channels for the civil scope of this project. No onsite channels exist within the project site nor the immediately surrounding areas. Installation Schedules: N/A Inspection and Maintenance plan: N/A Responsible Staff: CESCL P a g e | 16 2.1.9 Element 9: Control Pollutants The following pollutants are anticipated to be present on-site: Table 2 – Pollutants Pollutant (List pollutants and source, if applicable) Vehicle, Construction Equipment, and Petroleum Storage/Dispensing: Petroleum Chemical Storage: Agricultural Chemicals, Fertilizer, Pesticides Demolition: Dust, Soil, Debris Concrete and Grout Vehicles, construction equipment, and/or petroleum product storage/dispensing:  All vehicles, equipment, and petroleum product storage/dispensing areas will be inspected regularly to detect any leaks or spills, and to identify maintenance needs to prevent leaks or spills.  On-site fueling tanks and petroleum product storage containers shall include secondary containment.  Spill prevention measures, such as drip pans, will be used when conducting maintenance and repair of vehicles or equipment.  In order to perform emergency repairs on site, temporary plastic will be placed beneath and, if raining, over the vehicle.  Contaminated surfaces shall be cleaned immediately following any discharge or spill incident. Chemical storage:  BMP C153: Material Delivery, Storage and Containment  Any chemicals stored in the construction areas will conform to the appropriate source control BMPs listed in Volume IV of the Ecology stormwater manual. In Western WA, all chemicals shall have cover, containment, and protection provided on site.  Application of agricultural chemicals, including fertilizers and pesticides, shall be conducted in a manner and at application rates that will not result in loss of chemical to stormwater runoff. Manufacturers’ recommendations for application procedures and rates shall be followed. Demolition:  BMP C140: Dust Control:  Dust released from demolished sidewalks, buildings, or structures will be controlled using Dust Control measures.  BMP C220/COR STD 216.30: Storm Drain Inlet Protection  Storm drain inlets vulnerable to stormwater discharge carrying dust, soil, or debris will be protected using Storm Drain Inlet Protection.  BMP C152: Sawcutting and Surfacing Pollution Prevention  Process water and slurry resulting from saw cutting and surfacing operations will be prevented from entering the waters of the State by implementing Sawcutting and Surfacing Pollution Prevention measures. P a g e | 17 Concrete and grout:  BMP C151: Concrete Handling  Process water and slurry resulting from concrete work will be prevented from entering the waters of the state by implementing Concrete Handling measures. Other:  Other BMPs will be administered as necessary to address any additional pollutant sources on site. The specific BMPs for control pollutants to be used on-site shall be implemented as needed and include:  BMP C140: Dust Control  BMP C151: Concrete Handling  BMP C152: Sawcutting and Surfacing Pollution Prevention  BMP C153: Material Delivery, Storage, and Containment  BMP C220/COR STD 216.30: Storm Drain Inlet Protection See Appendix B – Construction BMPs for BMP details. Installation Schedules: The above listed BMPs shall be implemented as the need arises, depending on the pollutant they will mitigate, so as to reduce the possibility of pollutants off and on-site. Inspection and Maintenance plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL Will maintenance, fueling, and/or repair of heavy equipment and vehicles occur on-site? Yes No Will wheel wash or tire bath system BMPs be used during construction? Yes No Wheel washing, street sweeping, and street cleaning shall be employed as necessary to prevent sediment from entering state waters. All wash wastewater shall be controlled on site. The specific BMPs related to establishing construction access that will be used on this project include: · BMP C106/COR STD 215.00: Wheel Wash P a g e | 18 Installation Schedules: The project will utilize the existing paved access driveways, onsite hardscape, and asphalt parking areas for access and staging. Quarry spall access roads are not recommended or necessary. The stabilized construction access shall be available via the existing site driveways at the start of construction and will be utilized to the maximum extent possible through the duration of construction activities. Inspection and Maintenance Plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL Will pH-modifying sources be present on-site? Yes No If yes, check the source(s). Table 3 – pH-Modifying Sources None Bulk cement Cement kiln dust Fly ash Other cementitious materials New concrete washing or curing waters Waste streams generated from concrete grinding and sawing Exposed aggregate processes Dewatering concrete vaults Concrete pumping and mixer washout waters Recycled concrete Recycled concrete stockpiles Other (i.e., calcium lignosulfate) [please describe: ] Where pH-modifying sources may be encountered, steps must be taken to prevent pollutants from contaminating stormwater and raising the pH level above 8.5. The acceptable pH range for stormwater is between 6.5 and 8.5, beyond that, pH neutralization must occur. The specific BMPs for pH modification that shall be used on this project include: · BMP C252: High pH Neutralization Using CO2 See Appendix B – Construction BMPs for BMP details. Installation Schedules: The above listed BMP shall be implemented as soon as a stormwater pH reaches higher than 8.5, which typically occurs when the aforementioned pH-modifying sources come into contact with stormwater. P a g e | 19 Inspection and Maintenance plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL Concrete trucks must not be washed out onto the ground, or into storm drains, open ditches, streets, or streams. Excess concrete must not be dumped on-site, except in designated concrete washout areas with appropriate BMPs installed. Will uncontaminated water from water-only based shaft drilling for construction of building, road, and bridge foundations be infiltrated provided the wastewater is managed in a way that prohibits discharge to surface waters? Yes No P a g e | 20 2.1.10 Element 10: Control Dewatering No dewatering is anticipated for civil scope of this project. Installation Schedules: N/A Inspection and Maintenance plan: N/A Responsible Staff: CESCL P a g e | 21 2.1.11 Element 11: Maintain BMPs All temporary and permanent Erosion and Sediment Control (ESC) BMPs shall be maintained and repaired as needed to ensure continued performance of their intended function. Maintenance and repair shall be conducted in accordance with each particular BMP specification (see Volume II of the SWMMWW or Chapter 7 of the SWMMEW). Visual monitoring of all BMPs installed at the site will be conducted at least once every calendar week and within 24 hours of any stormwater or non-stormwater discharge from the site. If the site becomes inactive and is temporarily stabilized, the inspection frequency may be reduced to once every calendar month. All temporary ESC BMPs shall be removed within 30 days after final site stabilization is achieved or after the temporary BMPs are no longer needed. Trapped sediment shall be stabilized on-site or removed. Disturbed soil resulting from removal of either BMPs or vegetation shall be permanently stabilized. Additionally, protection must be provided for all BMPs installed for the permanent control of stormwater from sediment and compaction. BMPs that are to remain in place following completion of construction shall be examined and restored to full operating condition. If sediment enters these BMPs during construction, the sediment shall be removed and the facility shall be returned to conditions specified in the construction documents. List and describe BMPs:  BMP C150: Materials on Hand  BMP C160: Certified Erosion and Sediment Control Lead See Appendix B – Construction BMPs for BMP details. Installation Schedules: Establish BMP at the start of construction. Inspection and Maintenance plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL P a g e | 22 2.1.12 Element 12: Manage the Project The project will be managed based on the following principles: · Projects will be phased to the maximum extent practicable and seasonal work limitations will be taken into account. · Inspection and monitoring: o Inspection, maintenance and repair of all BMPs will occur as needed to ensure performance of their intended function. o Site inspections and monitoring will be conducted in accordance with Special Condition S4 of the CSWGP. Sampling locations are indicated on the Site Map. Sampling station(s) are located in accordance with applicable requirements of the CSWGP. · Maintain an updated SWPPP. o The SWPPP will be updated, maintained, and implemented in accordance with Special Conditions S3, S4, and S9 of the CSWGP. As site work progresses the SWPPP will be modified routinely to reflect changing site conditions. The SWPPP will be reviewed monthly to ensure the content is current. Table 5 – Management Design the project to fit the existing topography, soils, and drainage patterns Emphasize erosion control rather than sediment control Minimize the extent and duration of the area exposed Keep runoff velocities low Retain sediment on-site Thoroughly monitor site and maintain all ESC measures Schedule major earthwork during the dry season Other (please describe) In addition, project management will incorporate the key components listed below: As this project site is located west of the Cascade Mountain Crest, the project will be managed according to the following key project components: Phasing of Construction  The construction project is being phased to the extent practicable in order to prevent soil erosion, and, to the maximum extent possible, the transport of sediment from the site during construction.  Revegetation of exposed areas and maintenance of that vegetation shall be an integral part of the clearing activities during each phase of construction, per the Scheduling BMP (BMP C162). P a g e | 23 Coordination with Utilities and Other Jurisdictions  Care has been taken to coordinate with utilities, other construction projects, and the local jurisdiction in preparing this SWPPP and scheduling the construction work. Inspection and Monitoring  All BMPs shall be inspected, maintained, and repaired as needed to assure continued performance of their intended function. Site inspections shall be conducted by a person who is knowledgeable in the principles and practices of erosion and sediment control. This person has the necessary skills to:  Assess the site conditions and construction activities that could impact the quality of stormwater, and  Assess the effectiveness of erosion and sediment control measures used to control the quality of stormwater discharges.  A Certified Erosion and Sediment Control Lead shall be on-site or on-call at all times.  Whenever inspection and/or monitoring reveals that the BMPs identified in this SWPPP are inadequate, due to the actual discharge of or potential to discharge a significant amount of any pollutant, appropriate BMPs or design changes shall be implemented as soon as possible. P a g e | 24 Table 6 – BMP Implementation Schedule Phase of Construction Project Stormwater BMPs Date Wet/Dry Season Start of Construction C101 04/2023 Wet Start of Construction C103 04/2023 Wet Start of Construction C105/COR STD 215.00 04/2023 Wet Start of Construction C106/COR STD 215.00 04/2023 Wet Start of Construction C120 04/2023 Wet Start of Construction C123 04/2023 Wet As Needed C140 N/A Dry As Needed C150 N/A Dry As Needed C151 N/A Dry As Needed C152 N/A Dry As Needed C153 N/A Dry Start of Construction C160 04/2023 Wet Start of Construction C162 04/2023 Wet Start of Construction C220/COR STD 216.30 04/2023 Wet Start of Construction C233/COR STD 214.00 04/2023 Wet Start of Construction C235/COR STD 213.40 04/2023 Wet Start of Construction C252 04/2023 Wet P a g e | 25 2.1.13 Element 13: Protect Low Impact Development (LID) BMPs No proposed LID BMP measures are located on site. Installation Schedules: N/A Inspection and Maintenance plan: N/A Responsible Staff: CESCL P a g e | 26 3 Pollution Prevention Team Table 7 – Team Information Title Name(s) Phone Number Certified Erosion and Sediment Control Lead (CESCL) TBD TBD Resident Engineer Tim Brockway, P.E. 206-343-0460 Emergency Ecology Contact TBD TBD Emergency Permittee/ Owner Contact Tom Chiado 206-550-8363 Non-Emergency Owner Contact TBD TBD Monitoring Personnel TBD TBD Ecology Regional Office Northwest Regional Office 425-649-7000 P a g e | 27 4 Monitoring and Sampling Requirements Monitoring includes visual inspection, sampling for water quality parameters of concern, and documentation of the inspection and sampling findings in a site log book. A site log book will be maintained for all on-site construction activities and will include: · A record of the implementation of the SWPPP and other permit requirements · Site inspections · Stormwater sampling data The site log book must be maintained on-site within reasonable access to the site and be made available upon request to Ecology or the local jurisdiction. Numeric effluent limits may be required for certain discharges to 303(d) listed waterbodies. See CSWGP Special Condition S8 and Section 5 of this template. 4.1 Site Inspection Site inspections will be conducted at least once every calendar week and within 24 hours following any discharge from the site. For sites that are temporarily stabilized and inactive, the required frequency is reduced to once per calendar month. The discharge point(s) are indicated on the Site Map (see Appendix A) and in accordance with the applicable requirements of the CSWGP. 4.2 Stormwater Quality Sampling 4.2.1 Turbidity Sampling Requirements include calibrated turbidity meter or transparency tube to sample site discharges for compliance with the CSWGP. Sampling will be conducted at all discharge points at least once per calendar week. Method for sampling turbidity: Table 8 – Turbidity Sampling Method Turbidity Meter/Turbidimeter (required for disturbances 5 acres or greater in size) Transparency Tube (option for disturbances less than 1 acre and up to 5 acres in size) The benchmark for turbidity value is 25 nephelometric turbidity units (NTU) and a transparency less than 33 centimeters. If the discharge’s turbidity is 26 to 249 NTU or the transparency is less than 33 cm but equal to or greater than 6 cm, the following steps will be conducted: 1. Review the SWPPP for compliance with Special Condition S9. Make appropriate revisions within 7 days of the date the discharge exceeded the benchmark. P a g e | 28 2. Immediately begin the process to fully implement and maintain appropriate source control and/or treatment BMPs as soon as possible. Address the problems within 10 days of the date the discharge exceeded the benchmark. If installation of necessary treatment BMPs is not feasible within 10 days, Ecology may approve additional time when the Permittee requests an extension within the initial 10-day response period. 3. Document BMP implementation and maintenance in the site log book. If the turbidity exceeds 250 NTU or the transparency is 6 cm or less at any time, the following steps will be conducted: 1. Telephone or submit an electronic report to the applicable Ecology Region’s Environmental Report Tracking System (ERTS) within 24 hours. · Central Region (Benton, Chelan, Douglas, Kittitas, Klickitat, Okanogan, Yakima): (509) 575-2490 or http://www.ecy.wa.gov/programs/spills/forms/nerts_online/CRO_nerts_online.html · Eastern Region (Adams, Asotin, Columbia, Ferry, Franklin, Garfield, Grant, Lincoln, Pend Oreille, Spokane, Stevens, Walla Walla, Whitman): (509) 329-3400 or http://www.ecy.wa.gov/programs/spills/forms/nerts_online/ERO_nerts_online.html · Northwest Region (King, Kitsap, Island, San Juan, Skagit, Snohomish, Whatcom): (425) 649-7000 or http://www.ecy.wa.gov/programs/spills/forms/nerts_online/NWRO_nerts_online.html · Southwest Region (Clallam, Clark, Cowlitz, Grays Harbor, Jefferson, Lewis, Mason, Pacific, Pierce, Skamania, Thurston, Wahkiakum,): (360) 407-6300 or http://www.ecy.wa.gov/programs/spills/forms/nerts_online/SWRO_nerts_online.html 2. Immediately begin the process to fully implement and maintain appropriate source control and/or treatment BMPs as soon as possible. Address the problems within 10 days of the date the discharge exceeded the benchmark. If installation of necessary treatment BMPs is not feasible within 10 days, Ecology may approve additional time when the Permittee requests an extension within the initial 10-day response period 3. Document BMP implementation and maintenance in the site log book. 4. Continue to sample discharges daily until one of the following is true: · Turbidity is 25 NTU (or lower). · Transparency is 33 cm (or greater). · Compliance with the water quality limit for turbidity is achieved. o 1 - 5 NTU over background turbidity, if background is less than 50 NTU o 1% - 10% over background turbidity, if background is 50 NTU or greater · The discharge stops or is eliminated. P a g e | 29 4.2.2 pH Sampling pH monitoring is not required since this project does not involve “significant concrete work” (less than 1000 cubic yards poured concrete over the life of the project). P a g e | 30 5 Discharges to 303(d) or Total Maximum Daily Load (TMDL) Waterbodies 5.1 303(d) Listed Waterbodies Is the receiving water 303(d) (Category 5) listed for turbidity, fine sediment, phosphorus, or pH? Yes No List the impairment(s): · Bacteria – Assessment Unit ID: 47122F4I00101 5.2 TMDL Waterbodies In order to protect the properties and waterways downstream of the project site and remain TMDL compliant, stormwater discharges from the site will be controlled. In general, discharge rates of stormwater from the site will be controlled where increases in impervious area or soil compaction during construction could lead to downstream erosion, or where necessary to meet local agency stormwater discharge requirements (e.g., discharge to combined sewer systems). Installation Schedules: Existing detention facilities shall be inspected to ensure they are functioning properly before constructing site improvements. Inspection and Maintenance plan: Inspection and Maintenance Plan to be prepared by contractor in accordance with the BMP details (appendix B) from Volume II of the State of Washington Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. Responsible Staff: CESCL Discharges to TMDL receiving waterbodies will meet in-stream water quality criteria at the point of discharge. P a g e | 31 6 Reporting and Record Keeping 6.1 Record Keeping 6.1.1 Site Log Book A site log book will be maintained for all on-site construction activities and will include: · A record of the implementation of the SWPPP and other permit requirements · Site inspections · Sample logs 6.1.2 Records Retention Records will be retained during the life of the project and for a minimum of three (3) years following the termination of permit coverage in accordance with Special Condition S5.C of the CSWGP. Permit documentation to be retained on-site: · CSWGP · Permit Coverage Letter · SWPPP · Site Log Book Permit documentation will be provided within 14 days of receipt of a written request from Ecology. A copy of the SWPPP or access to the SWPPP will be provided to the public when requested in writing in accordance with Special Condition S5.G.2.b of the CSWGP. 6.1.3 Updating the SWPPP The SWPPP will be modified if: · Found ineffective in eliminating or significantly minimizing pollutants in stormwater discharges from the site. · There is a change in design, construction, operation, or maintenance at the construction site that has, or could have, a significant effect on the discharge of pollutants to waters of the State. · The SWPPP will be modified within seven (7) days if inspection(s) or investigation(s) determine additional or modified BMPs are necessary for compliance. An updated timeline for BMP implementation will be prepared. P a g e | 32 6.2 Reporting 6.2.1 Discharge Monitoring Reports Cumulative soil disturbance is one (1) acre or larger; therefore, Discharge Monitoring Reports (DMRs) will be submitted to Ecology monthly. If there was no discharge during a given monitoring period the DMR will be submitted as required, reporting “No Discharge”. The DMR due date is fifteen (15) days following the end of each calendar month. DMRs will be reported online through Ecology’s WQWebDMR System. 6.2.2 Notification of Noncompliance If any of the terms and conditions of the permit is not met, and the resulting noncompliance may cause a threat to human health or the environment, the following actions will be taken: 1. Ecology will be notified within 24-hours of the failure to comply by calling the applicable Regional office ERTS phone number (Regional office numbers listed below). 2. Immediate action will be taken to prevent the discharge/pollution or otherwise stop or correct the noncompliance. If applicable, sampling and analysis of any noncompliance will be repeated immediately and the results submitted to Ecology within five (5) days of becoming aware of the violation. 3. A detailed written report describing the noncompliance will be submitted to Ecology within five (5) days, unless requested earlier by Ecology. Anytime turbidity sampling indicates turbidity is 250 NTUs or greater, or water transparency is 6 cm or less, the Ecology Regional office will be notified by phone within 24 hours of analysis as required by Special Condition S5.A of the CSWGP. · Northwest Region at (425) 649-7000 for Island, King, Kitsap, San Juan, Skagit, Snohomish, or Whatcom County Include the following information: 1. Your name and / Phone number 2. Permit number 3. City / County of project 4. Sample results 5. Date / Time of call 6. Date / Time of sample 7. Project name In accordance with Special Condition S4.D.5.b of the CSWGP, the Ecology Regional office will be notified if chemical treatment other than CO2 sparging is planned for adjustment of high pH water. P a g e | 33 Appendix/Glossary A. Site Map LegendPROPERTY LINELIMITS OF CONSTRUCTIONINTERCEPTOR SWALEFILTER FABRIC FENCINGWEIGHTED PLASTIC Do not use BlockEdit, Use LEGEND to editTEMPORARY STORM PIPETEMPORARY SWALETREE PROTECTIONINLET PROTECTIONSTRAW WATTLESWETLANDPOTENTIAL STOCKPILELAYDOWN AREACONSTRUCTIONENTRANCE TEMPORARYTEMPORARYCONSTRUCTION GATECONSTRUCTIONFENCING TEMPORARY7C2.206C2.208C2.205C2.2012C2.201C2.20OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPxXΔSSxSSxSSxSSx SSx SSx SSx SSx SSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSx SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx SDx SDxSDxSDx SDx SDx SDxSDx SDx SDxSDx SDx SDx SDxSDx SDxSDxSDx SDxSDxSDx SDx SDxSDx SDxSSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx WxWxWxWxWxWxWx Wx Wx Wx Wx Wx Wx Wx Wx Wx WxWxWxWxWxWxWxWxWxWxSDxSDxSDxSDxSDxSDxSDx SDxSDx SDx SDx SDx SDx SDx SDx SDx S D x SDxSDxSDxSDxSDxSDxSDx SDxSDxSDxSDx S D x SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx S D x S D x SD x WxWxSDxSDxSDxSDxSDxSDxSDxWxWxWxWxWxS D x SDx010203040506070809101112OAKESDALE AVE SW (NOT INCLUDED)(NOT INCLUDED)100 FT POND"A" WETLANDBUFFERWETLAND APOND BLOT LINEADJUSTMENTFOR SOUNDERSHEADQUARTERSOHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPxXΔSSxSSxSSxSSx SSx SSx SSx SSx SSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSx SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx SDx SDxSDxSDx SDx SDx SDxSDx SDx SDxSDx SDx SDx SDxSDx SDxSDxSDx SDxSDxSDx SDx SDxSDx SDxSSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx WxWxWxWxWxWxWx Wx Wx Wx Wx Wx Wx Wx Wx Wx WxWxWxWxWxWxWxWxWxWxSDxSDxSDxSDxSDxSDxSDx SDxSDx SDx SDx SDx SDx SDx SDx SDx S D x SDxSDxSDxSDxSDxSDxSDx SDxSDxSDxSDx S D x SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx S D x S D x SD x WxWxSDxSDxSDxSDxSDxSDxSDxWxWxWxWxWxS D x SDxOHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPxXΔSSxSSxSSxSSx SSx SSx SSx SSx SSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSx SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx SDx SDxSDxSDx SDx SDx SDxSDx SDx SDxSDx SDx SDx SDxSDx SDxSDxSDx SDxSDxSDx SDx SDxSDx SDxSSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx WxWxWxWxWxWxWx Wx Wx Wx Wx Wx Wx Wx Wx Wx WxWxWxWxWxWxWxWxWxWxSDxSDxSDxSDxSDxSDxSDx SDxSDx SDx SDx SDx SDx SDx SDx SDx S D x SDxSDxSDxSDxSDxSDxSDx SDxSDxSDxSDx S D x SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx S D x S D x SD x WxWxSDxSDxSDxSDxSDxSDxSDxWxWxWxWxWxS D x SDxOHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPxXΔSSxSSxSSxSSx SSx SSx SSx SSx SSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSx SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx SDx SDxSDxSDx SDx SDx SDxSDx SDx SDxSDx SDx SDx SDxSDx SDxSDxSDx SDxSDxSDx SDx SDxSDx SDxSSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSxSSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx WxWxWxWxWxWxWx Wx Wx Wx Wx Wx Wx Wx Wx Wx WxWxWxWxWxWxWxWxWxWxSDxSDxSDxSDxSDxSDxSDx SDxSDx SDx SDx SDx SDx SDx SDx SDx S D x SDxSDxSDxSDxSDxSDxSDx SDxSDxSDxSDx S D x SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx S D x S D x SD x WxWxSDxSDxSDxSDxSDxSDxSDxWxWxWxWxWxS D x SDx(NOT INCLUDED)100 YEAR FLOODPLAINELEVATIONBFE=20.0100 YEAR FLOODPLAINELEVATIONBFE=20.0100 YEAR FLOODPLAINELEVATIONBFE=20.0040801601"=80'801 SECOND AVENUE, SUITE 900 (206) 343-0460 SEATTLE, WA 98104 www.cplinc.com COUGHLIN LUNDEEN PORTER E N G I N E E R I N G S E I S M I C C I V I L S T R U C T U R A L 33708STATE OF WASHINGTONREGISTERED PROFESSIONALENGINEER CORB.BYHTOMITYAWK A PORTION OF THE NW 1/4 OF SECTION 8, TOWNSHIP 23N, RANGE 5E, W.M.Call Before You Dig. 8-1-1 or 1-800-424-5555 Underground Service (USA)TED-40-4238 SEATTLE SOUNDERS FC HEADQUARTERS& TRAINING CENTERRENTON, WASHINGTONSEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER LUA22-000357 C22005747SEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER -4238PR22-000301CITY OFRENTON13ROVERALL TESC PLAN LegendPROPERTY LINELIMITS OF CONSTRUCTIONINTERCEPTOR SWALEFILTER FABRIC FENCINGDo not use BlockEdit, Use LEGEND to editTEMPORARY STORM PIPETEMPORARY SWALETREE PROTECTIONINLET PROTECTIONSTRAW WATTLESWETLANDPOTENTIAL STOCKPILELAYDOWN AREACONSTRUCTIONENTRANCE TEMPOARYTEMPORARYCONSTRUCTION GATECONSTRUCTIONFENCING TEMPORARYWEIGHTED PLASTICSHEETING7C2.2012C2.208C2.206C2.205C2.201C2.20TREEPROTECTION(TYP)TREEPROTECTION(TYP)TREEPROTECTION(TYP)100 FT POND "A"WETLANDBUFFERWETLAND AΔZONEAESDxSDxSDxSDxΔZONEAESDxSDxSDxSDx801 SECOND AVENUE, SUITE 900 (206) 343-0460 SEATTLE, WA 98104 www.cplinc.com COUGHLIN LUNDEEN PORTER E N G I N E E R I N G S E I S M I C C I V I L S T R U C T U R A L 33708STATE OF WASHINGTONREGISTEREDPROFESSIONALENGINEER CORB.BYHTOMITYAWK A PORTION OF THE NW 1/4 OF SECTION 8, TOWNSHIP 23N, RANGE 5E, W.M.Call Before You Dig. 8-1-1 or 1-800-424-5555 Underground Service (USA)TED-40-4238 SEATTLE SOUNDERS FC HEADQUARTERS& TRAINING CENTERRENTON, WASHINGTONSEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER LUA22-000357 C22005747SEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER -4238PR22-000301CITY OFRENTON01020401"=20'TESC PLAN14RCONTINUED - SEE SHEET C2.04CONTINUED - SEE SHEET C2.02 LegendPROPERTY LINELIMITS OF CONSTRUCTIONINTERCEPTOR SWALEFILTER FABRIC FENCINGDo not use BlockEdit, Use LEGEND to editTEMPORARY STORM PIPETEMPORARY SWALETREE PROTECTIONINLET PROTECTIONSTRAW WATTLESWETLANDPOTENTIAL STOCKPILELAYDOWN AREACONSTRUCTIONENTRANCE TEMPOARYTEMPORARYCONSTRUCTION GATECONSTRUCTIONFENCING TEMPORARYWEIGHTED PLASTICSHEETING7C2.2012C2.208C2.206C2.205C2.201C2.20INLETPROTECTION(TYP)TREEPROTECTION(TYP)TREEPROTECTION(TYP)SSx SSx SSx SSx SSx SSx SSx SSx SSx SSxSSxSSxSSxSSxSDxSDxSDxSDxSDxSDxWx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx WxWxWxWxWxWxWxWxWxWx WxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDxSDxSDxSDxSDxSDxSDxSDx SDx SDx SDx SDxSDxSDxSDxSDxSDxSDx SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx S D x S D x WxWxWxWxWxWxWxWxWxSDx SDx SDx SDx SDxSDxSDxSDxSDxSSx SSx SSx SSx SSx SSx SSx SSx SSx SSxSSxSSxSSxSSxSDxSDxSDxSDxSDxSDxWx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx WxWxWxWxWxWxWxWxWxWx WxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDxSDxSDxSDxSDxSDxSDxSDx SDx SDx SDx SDxSDxSDxSDxSDxSDxSDx SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx S D x S D x WxWxWxWxWxWxWxWxWxSDx SDx SDx SDx SDxSDxSDxSDxSDx100 FT POND "A"WETLANDBUFFER801 SECOND AVENUE, SUITE 900 (206) 343-0460 SEATTLE, WA 98104 www.cplinc.com COUGHLIN LUNDEEN PORTER E N G I N E E R I N G S E I S M I C C I V I L S T R U C T U R A L 33708STATE OF WASHINGTONREGISTEREDPROFESSIONALENGINEER CORB.BYHTOMITYAWK A PORTION OF THE NW 1/4 OF SECTION 8, TOWNSHIP 23N, RANGE 5E, W.M.Call Before You Dig. 8-1-1 or 1-800-424-5555 Underground Service (USA)TED-40-4238 SEATTLE SOUNDERS FC HEADQUARTERS& TRAINING CENTERRENTON, WASHINGTONSEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER LUA22-000357 C22005747SEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER -4238PR22-000301CITY OFRENTON01020401"=20'TESC PLAN15RCONTINUED - SEE SHEET C2.05CONTINUED - SEE SHEET C2.03 CONTINUED - SEE SHEET C2.01 1901 OAKESDALE AVE SW LegendPROPERTY LINELIMITS OF CONSTRUCTIONINTERCEPTOR SWALEFILTER FABRIC FENCINGDo not use BlockEdit, Use LEGEND to editTEMPORARY STORM PIPETEMPORARY SWALETREE PROTECTIONINLET PROTECTIONSTRAW WATTLESWETLANDPOTENTIAL STOCKPILELAYDOWN AREACONSTRUCTIONENTRANCE TEMPOARYTEMPORARYCONSTRUCTION GATECONSTRUCTIONFENCING TEMPORARYWEIGHTED PLASTICSHEETING7C2.2012C2.208C2.206C2.205C2.201C2.20TREEPROTECTION(TYP)100 FT POND"A" WETLANDBUFFERPOND BXXXXXXSDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDxSDxSDxXXXXXXSDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDxSDxSDx801 SECOND AVENUE, SUITE 900 (206) 343-0460 SEATTLE, WA 98104 www.cplinc.com COUGHLIN LUNDEEN PORTER E N G I N E E R I N G S E I S M I C C I V I L S T R U C T U R A L 33708STATE OF WASHINGTONREGISTEREDPROFESSIONALENGINEER CORB.BYHTOMITYAWK A PORTION OF THE NW 1/4 OF SECTION 8, TOWNSHIP 23N, RANGE 5E, W.M.Call Before You Dig. 8-1-1 or 1-800-424-5555 Underground Service (USA)TED-40-4238 SEATTLE SOUNDERS FC HEADQUARTERS& TRAINING CENTERRENTON, WASHINGTONSEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER LUA22-000357 C22005747SEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER -4238PR22-000301CITY OFRENTON01020401"=20'TESC PLAN16RCONTINUED - SEE SHEET C2.07CONTINUED - SEE SHEET C2.05 CONTINUED - SEE SHEET C2.01 LegendPROPERTY LINELIMITS OF CONSTRUCTIONINTERCEPTOR SWALEFILTER FABRIC FENCINGDo not use BlockEdit, Use LEGEND to editTEMPORARY STORM PIPETEMPORARY SWALETREE PROTECTIONINLET PROTECTIONSTRAW WATTLESWETLANDPOTENTIAL STOCKPILELAYDOWN AREACONSTRUCTIONENTRANCE TEMPOARYTEMPORARYCONSTRUCTION GATECONSTRUCTIONFENCING TEMPORARYWEIGHTED PLASTICSHEETING7C2.2012C2.208C2.206C2.205C2.201C2.20INLETPROTECTION(TYP)WHEEL WASHCONSTRUCTIONENTRANCESEE DETAILPOTENTIALSTOCKPILE/LAYDOWN AREACONSTRUCTIONENTRANCE AND GATESEE DETAIL1C2.201C2.20SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxWxWxWxWxWxWxWxWxWxWxWxWxWxWxWxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxWxWxWxWxWxWxWxWxWxWxWxWxWxWxWx801 SECOND AVENUE, SUITE 900 (206) 343-0460 SEATTLE, WA 98104 www.cplinc.com COUGHLIN LUNDEEN PORTER E N G I N E E R I N G S E I S M I C C I V I L S T R U C T U R A L 33708STATE OF WASHINGTONREGISTEREDPROFESSIONALENGINEER CORB.BYHTOMITYAWK A PORTION OF THE NW 1/4 OF SECTION 8, TOWNSHIP 23N, RANGE 5E, W.M.Call Before You Dig. 8-1-1 or 1-800-424-5555 Underground Service (USA)TED-40-4238 SEATTLE SOUNDERS FC HEADQUARTERS& TRAINING CENTERRENTON, WASHINGTONSEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER LUA22-000357 C22005747SEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER -4238PR22-000301CITY OFRENTON01020401"=20'TESC PLAN17RCONTINUED - SEE SHEET C2.08CONTINUED - SEE SHEET C2.06 CONTINUED - SEE SHEET C2.04 CONTINUED - SEE SHEET C2.021901 OAKESDALE AVE SW LegendPROPERTY LINELIMITS OF CONSTRUCTIONINTERCEPTOR SWALEFILTER FABRIC FENCINGDo not use BlockEdit, Use LEGEND to editTEMPORARY STORM PIPETEMPORARY SWALETREE PROTECTIONINLET PROTECTIONSTRAW WATTLESWETLANDPOTENTIAL STOCKPILELAYDOWN AREACONSTRUCTIONENTRANCE TEMPOARYTEMPORARYCONSTRUCTION GATECONSTRUCTIONFENCING TEMPORARYWEIGHTED PLASTICSHEETING7C2.2012C2.208C2.206C2.205C2.201C2.20PROTECTEXISTING PONDINSTALL WEIGHTED PLASTICSHEETING UP TO WATER LINE.ADJUST LIMITS AS NEEDEDFOR WALL CONSTRUCTIONFILTER AND FABRIC FENCE TO BEINSTALLED AROUND THE EXISTINGWATER FEATURESTREEPROTECTION(TYP)POND BSDxSDxSDx SDx SDxSDx SDx SDx SDx SDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDx SDxSDx SDx SDx SDx SDxSDxSDxSDxSDxSDxSDx801 SECOND AVENUE, SUITE 900 (206) 343-0460 SEATTLE, WA 98104 www.cplinc.com COUGHLIN LUNDEEN PORTER E N G I N E E R I N G S E I S M I C C I V I L S T R U C T U R A L 33708STATE OF WASHINGTONREGISTEREDPROFESSIONALENGINEER CORB.BYHTOMITYAWK A PORTION OF THE NW 1/4 OF SECTION 8, TOWNSHIP 23N, RANGE 5E, W.M.Call Before You Dig. 8-1-1 or 1-800-424-5555 Underground Service (USA)TED-40-4238 SEATTLE SOUNDERS FC HEADQUARTERS& TRAINING CENTERRENTON, WASHINGTONSEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER LUA22-000357 C22005747SEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER -4238PR22-000301CITY OFRENTON01020401"=20'TESC PLAN18RCONTINUED - SEE SHEET C2.10CONTINUED - SEE SHEET C2.08 CONTINUED - SEE SHEET C2.04 LegendPROPERTY LINELIMITS OF CONSTRUCTIONINTERCEPTOR SWALEFILTER FABRIC FENCINGDo not use BlockEdit, Use LEGEND to editTEMPORARY STORM PIPETEMPORARY SWALETREE PROTECTIONINLET PROTECTIONSTRAW WATTLESWETLANDPOTENTIAL STOCKPILELAYDOWN AREACONSTRUCTIONENTRANCE TEMPOARYTEMPORARYCONSTRUCTION GATECONSTRUCTIONFENCING TEMPORARYWEIGHTED PLASTICSHEETING7C2.2012C2.208C2.206C2.205C2.201C2.20INLETPROTECTION(TYP)POTENTIALSTOCKPILE/LAYDOWN AREAWHEEL WASHCONSTRUCTIONENTRANCESEE DETAILCONSTRUCTIONENTRANCEAND GATE1C2.20SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSD x S D x SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSD x S D x SDxSDx801 SECOND AVENUE, SUITE 900 (206) 343-0460 SEATTLE, WA 98104 www.cplinc.com COUGHLIN LUNDEEN PORTER E N G I N E E R I N G S E I S M I C C I V I L S T R U C T U R A L 33708STATE OF WASHINGTONREGISTEREDPROFESSIONALENGINEER CORB.BYHTOMITYAWK A PORTION OF THE NW 1/4 OF SECTION 8, TOWNSHIP 23N, RANGE 5E, W.M.Call Before You Dig. 8-1-1 or 1-800-424-5555 Underground Service (USA)TED-40-4238 SEATTLE SOUNDERS FC HEADQUARTERS& TRAINING CENTERRENTON, WASHINGTONSEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER LUA22-000357 C22005747SEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER -4238PR22-000301CITY OFRENTON01020401"=20'TESC PLAN19RCONTINUED - SEE SHEET C2.11CONTINUED - SEE SHEET C2.07 CONTINUED - SEE SHEET C2.05CONTINUED - SEE SHEET C2.09 LegendPROPERTY LINELIMITS OF CONSTRUCTIONINTERCEPTOR SWALEFILTER FABRIC FENCINGDo not use BlockEdit, Use LEGEND to editTEMPORARY STORM PIPETEMPORARY SWALETREE PROTECTIONINLET PROTECTIONSTRAW WATTLESWETLANDPOTENTIAL STOCKPILELAYDOWN AREACONSTRUCTIONENTRANCE TEMPOARYTEMPORARYCONSTRUCTION GATECONSTRUCTIONFENCING TEMPORARYWEIGHTED PLASTICSHEETING7C2.2012C2.208C2.206C2.205C2.201C2.20OAKESDALE AVE SWINLETPROTECTION(TYP)OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDxSDx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPx OHPxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDxSDx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx SSx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx Wx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx SDx801 SECOND AVENUE, SUITE 900 (206) 343-0460 SEATTLE, WA 98104 www.cplinc.com COUGHLIN LUNDEEN PORTER E N G I N E E R I N G S E I S M I C C I V I L S T R U C T U R A L 33708STATE OF WASHINGTONREGISTEREDPROFESSIONALENGINEER CORB.BYHTOMITYAWK A PORTION OF THE NW 1/4 OF SECTION 8, TOWNSHIP 23N, RANGE 5E, W.M.Call Before You Dig. 8-1-1 or 1-800-424-5555 Underground Service (USA)TED-40-4238 SEATTLE SOUNDERS FC HEADQUARTERS& TRAINING CENTERRENTON, WASHINGTONSEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER LUA22-000357 C22005747SEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER -4238PR22-000301CITY OFRENTON01020401"=20'TESC PLAN20RCONTINUED - SEE SHEET C2.08 CONTINUED - SEE SHEET C2.06 LegendPROPERTY LINELIMITS OF CONSTRUCTIONINTERCEPTOR SWALEFILTER FABRIC FENCINGDo not use BlockEdit, Use LEGEND to editTEMPORARY STORM PIPETEMPORARY SWALETREE PROTECTIONINLET PROTECTIONSTRAW WATTLESWETLANDPOTENTIAL STOCKPILELAYDOWN AREACONSTRUCTIONENTRANCE TEMPOARYTEMPORARYCONSTRUCTION GATECONSTRUCTIONFENCING TEMPORARYWEIGHTED PLASTICSHEETING7C2.2012C2.208C2.206C2.205C2.201C2.20PROTECTEXISTING PONDPROTECTEXISTING PONDINSTALL WEIGHTED PLASTICSHEETING UP TO WATER LINE.ADJUST LIMITS AS NEEDEDFOR WALL CONSTRUCTIONFILTER AND FABRIC FENCE TO BEINSTALLED AROUND THE EXISTINGWATER FEATURES. ONCE GRADINGHAS COMPLETED, TESC FENCINGSHALL MATCH SHOWN LIMITS.INSTALL WEIGHTED PLASTICSHEETING UP TO WATER LINE.ADJUST LIMITS AS NEEDEDFOR WALL CONSTRUCTIONFILTER AND FABRIC FENCE TO BEINSTALLED AROUND THE EXISTINGWATER FEATURES. ONCE GRADINGHAS COMPLETED, TESC FENCINGSHALL MATCH SHOWN LIMITS.POND B100 YEARFLOODPLAINELEVATIONLOT LINE ADJUSTMENTFOR SOUNDERSHEADQUARTERSSDxSDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDxSDxSDxSDxSDxSDxSDx SDx SDx SDx SDx SDx SDx SDx SDxSDxSDxSDxSDx801 SECOND AVENUE, SUITE 900 (206) 343-0460 SEATTLE, WA 98104 www.cplinc.com COUGHLIN LUNDEEN PORTER E N G I N E E R I N G S E I S M I C C I V I L S T R U C T U R A L 33708STATE OF WASHINGTONREGISTEREDPROFESSIONALENGINEER CORB.BYHTOMITYAWK A PORTION OF THE NW 1/4 OF SECTION 8, TOWNSHIP 23N, RANGE 5E, W.M.Call Before You Dig. 8-1-1 or 1-800-424-5555 Underground Service (USA)TED-40-4238 SEATTLE SOUNDERS FC HEADQUARTERS& TRAINING CENTERRENTON, WASHINGTONSEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER LUA22-000357 C22005747SEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER -4238PR22-000301CITY OFRENTON01020401"=20'TESC PLAN21RCONTINUED - SEE SHEET C2.11 CONTINUED - SEE SHEET C2.07 LegendPROPERTY LINELIMITS OF CONSTRUCTIONINTERCEPTOR SWALEFILTER FABRIC FENCINGDo not use BlockEdit, Use LEGEND to editTEMPORARY STORM PIPETEMPORARY SWALETREE PROTECTIONINLET PROTECTIONSTRAW WATTLESWETLANDPOTENTIAL STOCKPILELAYDOWN AREACONSTRUCTIONENTRANCE TEMPOARYTEMPORARYCONSTRUCTION GATECONSTRUCTIONFENCING TEMPORARYWEIGHTED PLASTICSHEETING7C2.2012C2.208C2.206C2.205C2.201C2.20100 YEARFLOODPLAINELEVATIONZONE XZONE X801 SECOND AVENUE, SUITE 900 (206) 343-0460 SEATTLE, WA 98104 www.cplinc.com COUGHLIN LUNDEEN PORTER E N G I N E E R I N G S E I S M I C C I V I L S T R U C T U R A L 33708STATE OF WASHINGTONREGISTEREDPROFESSIONALENGINEER CORB.BYHTOMITYAWK A PORTION OF THE NW 1/4 OF SECTION 8, TOWNSHIP 23N, RANGE 5E, W.M.Call Before You Dig. 8-1-1 or 1-800-424-5555 Underground Service (USA)TED-40-4238 SEATTLE SOUNDERS FC HEADQUARTERS& TRAINING CENTERRENTON, WASHINGTONSEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER LUA22-000357 C22005747SEATTLE SOUNDERS FC HEADQUARTERS & TRAINING CENTER -4238PR22-000301CITY OFRENTON01020401"=20'TESC PLAN22RCONTINUED - SEE SHEET C2.10 CONTINUED - SEE SHEET C2.08CONTINUED - SEE SHEET C2.12 P a g e | 34 B. BMP Detail · BMP C101: Preserving Natural Vegetation · BMP C103: High Visibility Fence · BMP C105/COR STD 215.00: Stabilized Construction Entrance/Exit · BMP C106/COR STD 215.00: Wheel Wash · BMP C120: Temporary and Permanent Seeding · BMP C123: Plastic Covering · BMP C140: Dust Control · BMP C150: Materials on Hand · BMP C151: Concrete Handling · BMP C152: Sawcutting and Surfacing Pollution Prevention · BMP C153: Material Delivery, Storage, and Containment · BMP C160: Certified Erosion and Sediment Control Lead · BMP C162: Scheduling · BMP C220/COR STD 216.30: Storm Drain Inlet Protection · BMP C233/COR STD 214.00: Silt Fence · BMP C235/COR STD 213.40: Straw Wattles · BMP C252: High pH Neutralization Using CO2 BMP C101: Preserving Natural Vegetation Purpose The purpose of preserving natural vegetation is to reduce erosion wherever practicable. Limiting site  disturbance is the single most effective method for reducing erosion. For example, conifers can hold  up to about 50 percent of all rain that falls during a storm. Up to 20-30 percent of this rain may never  reach the ground but is taken up by the tree or evaporates. Another benefit is that the rain held in the  tree can be released slowly to the ground after the storm. Conditions of Use Natural vegetation should be preserved on steep slopes, near perennial and intermittent water- courses or swales, and on building sites in wooded areas.  l As required by local governments.  l Phase construction to preserve natural vegetation on the project site for as long as possible  during the construction period. Design and Installation Specifications Natural vegetation can be preserved in natural clumps or as individual trees, shrubs and vines. The preservation of individual plants is more difficult because heavy equipment is generally used to  remove unwanted vegetation. The points to remember when attempting to save individual plants  are:  l Is the plant worth saving? Consider the location, species, size, age, vigor, and the work  involved. Local governments may also have ordinances to save natural vegetation and trees.  l Fence or clearly mark areas around trees that are to be saved. It is preferable to keep ground  disturbance away from the trees at least as far out as the dripline. Plants need protection from three kinds of injuries:  l Construction Equipment - This injury can be above or below the ground level. Damage results  from scarring, cutting of roots, and compaction of the soil. Placing a fenced buffer zone around  plants to be saved prior to construction can prevent construction equipment injuries.  l Grade Changes - Changing the natural ground level will alter grades, which affects the plant's  ability to obtain the necessary air, water, and minerals. Minor fills usually do not cause prob- lems although sensitivity between species does vary and should be checked. Trees can typ- ically tolerate fill of 6 inches or less. For shrubs and other plants, the fill should be less. When there are major changes in grade, it may become necessary to supply air to the roots of  plants. This can be done by placing a layer of gravel and a tile system over the roots before the  fill is made. The tile system should be laid out on the original grade leading from a dry well  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 271 around the tree trunk. The system should then be covered with small stones to allow air to cir- culate over the root area. Lowering the natural ground level can seriously damage trees and shrubs. The highest per- centage of the plant roots are in the upper 12 inches of the soil and cuts of only 2-3 inches can  cause serious injury. To protect the roots it may be necessary to terrace the immediate area  around the plants to be saved. If roots are exposed, construction of retaining walls may be  needed to keep the soil in place. Plants can also be preserved by leaving them on an undis- turbed, gently sloping mound. To increase the chances for survival, it is best to limit grade  changes and other soil disturbances to areas outside the dripline of the plant.  l Excavations - Protect trees and other plants when excavating for drainfields, power, water,  and sewer lines. Where possible, the trenches should be routed around trees and large  shrubs. When this is not possible, it is best to tunnel under them. This can be done with hand  tools or with power augers. If it is not possible to route the trench around plants to be saved,  then the following should be observed:  o Cut as few roots as possible. When you have to cut, cut clean. Paint cut root ends with a  wood dressing like asphalt base paint if roots will be exposed for more than 24-hours.  o Backfill the trench as soon as possible.  o Tunnel beneath root systems as close to the center of the main trunk to preserve most  of the important feeder roots. Some problems that can be encountered with a few specific trees are:  l Maple, Dogwood, Red alder, Western hemlock, Western red cedar, and Douglas fir do not  readily adjust to changes in environment and special care should be taken to protect these  trees.  l The windthrow hazard of Pacific silver fir and madrona is high, while that of Western hemlock  is moderate. The danger of windthrow increases where dense stands have been thinned.  Other species (unless they are on shallow, wet soils less than 20 inches deep) have a low  windthrow hazard.  l Cottonwoods, maples, and willows have water-seeking roots. These can cause trouble in  sewer lines and infiltration fields. On the other hand, they thrive in high moisture conditions  that other trees would not.  l Thinning operations in pure or mixed stands of Grand fir, Pacific silver fir, Noble fir, Sitka  spruce, Western red cedar, Western hemlock, Pacific dogwood, and Red alder can cause ser- ious disease problems. Disease can become established through damaged limbs, trunks,  roots, and freshly cut stumps. Diseased and weakened trees are also susceptible to insect  attack. Maintenance Standards Inspect flagged and/or fenced areas regularly to make sure flagging or fencing has not been  removed or damaged. If the flagging or fencing has been damaged or visibility reduced, it shall be  repaired or replaced immediately and visibility restored. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 272 If tree roots have been exposed or injured, “prune” cleanly with an appropriate pruning saw or lop- pers directly above the damaged roots and recover with native soils. Treatment of sap flowing trees  (fir, hemlock, pine, soft maples) is not advised as sap forms a natural healing barrier. BMP C102: Buffer Zones Purpose Creation of an undisturbed area or strip of natural vegetation or an established suitable planting that  will provide a living filter to reduce soil erosion and stormwater runoff velocities. Conditions of Use Buffer zones are used along streams, wetlands and other bodies of water that need protection from  erosion and sedimentation. Contractors can use vegetative buffer zone BMPs to protect natural  swales and they can incorporate them into the natural landscaping of an area. Do not use critical-areas buffer zones as sediment treatment areas. These areas shall remain com- pletely undisturbed. The local permitting authority may expand the buffer widths temporarily to allow  the use of the expanded area for removal of sediment. The types of buffer zones can change the level of protection required as shown below: Designated Critical Area Buffers - buffers that protect Critical Areas, as defined by the Washington  State Growth Management Act, and are established and managed by the local permitting authority.  These should not be disturbed and must protected with sediment control BMPs to prevent impacts.  The local permitting authority may expand the buffer widths temporarily to allow the use of the expan- ded area for removal of sediment. Vegetative Buffer Zones - areas that may be identified in undisturbed vegetation areas or managed  vegetation areas that are outside any Designated Critical Area Buffer. They may be utilized to  provide an additional sediment control area and/or reduce runoff velocities. If being used for pre- servation of natural vegetation, they should be arranged in clumps or strips. They can be used to pro- tect natural swales and incorporated into the natural landscaping area. Design and Installation Specifications  l Preserving natural vegetation or plantings in clumps, blocks, or strips is generally the easiest  and most successful method.  l Leave all unstable steep slopes in natural vegetation.  l Mark clearing limits and keep all equipment and construction debris out of the natural areas  and buffer zones. Steel construction fencing is the most effective method to protect sensitive  areas and buffers. Alternatively, wire-backed silt fence on steel posts is marginally effective.  Flagging alone is typically not effective.  l Keep all excavations outside the dripline of trees and shrubs.  l Do not push debris or extra soil into the buffer zone area because it will cause damage by  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 273 burying and smothering vegetation.  l Vegetative buffer zones for streams, lakes or other waterways shall be established by the  local permitting authority or other state or federal permits or approvals. Maintenance Standards Inspect the area frequently to make sure flagging remains in place and the area remains undis- turbed. Replace all damaged flagging immediately. Remove all materials located in the buffer area  that may impede the ability of the vegetation to act as a filter. BMP C103: High-Visibility Fence Purpose High-visibility fencing is intended to:  l Restrict clearing to approved limits.  l Prevent disturbance of sensitive areas, their buffers, and other areas required to be left undis- turbed.  l Limit construction traffic to designated construction entrances, exits, or internal roads.  l Protect areas where marking with survey tape may not provide adequate protection. Conditions of Use To establish clearing limits plastic, fabric, or metal fence may be used:  l At the boundary of sensitive areas, their buffers, and other areas required to be left uncleared.  l As necessary to control vehicle access to and on the site. Design and Installation Specifications High-visibility plastic fence shall be composed of a high-density polyethylene material and shall be at  least four feet in height. Posts for the fencing shall be steel or wood and placed every 6 feet on center  (maximum) or as needed to ensure rigidity. The fencing shall be fastened to the post every six inches  with a polyethylene tie. On long continuous lengths of fencing, a tension wire or rope shall be used as  a top stringer to prevent sagging between posts. The fence color shall be high-visibility orange. The  fence tensile strength shall be 360 lbs/ft using the ASTM D4595 testing method. If appropriate install fabric silt fence in accordance with BMP C233:  Silt Fence to act as high-visibility  fence. Silt fence shall be at least 3 feet high and must be highly visible to meet the requirements of  this BMP. Metal fences shall be designed and installed according to the manufacturer's specifications. Metal fences shall be at least 3 feet high and must be highly visible. Fences shall not be wired or stapled to trees. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 274 Maintenance Standards If the fence has been damaged or visibility reduced, it shall be repaired or replaced immediately and  visibility restored. BMP C105: Stabilized Construction Access Purpose Stabilized construction accesses are established to reduce the amount of sediment transported onto  paved roads outside the project site by vehicles or equipment. This is done by constructing a sta- bilized pad of quarry spalls at entrances and exits for project sites. Conditions of Use Construction accesses shall be stabilized wherever traffic will be entering or leaving a construction  site if paved roads or other paved areas are within 1,000 feet of the site. For residential subdivision construction sites, provide a stabilized construction access for each res- idence, rather than only at the main subdivision entrance. Stabilized surfaces shall be of sufficient  length/width to provide vehicle access/parking, based on lot size and configuration. On large commercial, highway, and road projects, the designer should include enough extra mater- ials in the contract to allow for additional stabilized accesses not shown in the initial Construction  SWPPP. It is difficult to determine exactly where access to these projects will take place; additional  materials will enable the contractor to install them where needed. Design and Installation Specifications See Figure II-3.1: Stabilized Construction Access for details. Note: the 100’ minimum length of the  access shall be reduced to the maximum practicable size when the size or configuration of the site  does not allow the full length (100’). Construct stabilized construction accesses with a 12-inch thick pad of 4-inch to 8-inch quarry spalls,  a 4-inch course of asphalt treated base (ATB), or use existing pavement. Do not use crushed con- crete, cement, or calcium chloride for construction access stabilization because these products raise  pH levels in stormwater and concrete discharge to waters of the State is prohibited. A separation geotextile shall be placed under the spalls to prevent fine sediment from pumping up  into the rock pad. The geotextile shall meet the standards listed in Table II-3.2: Stabilized Con- struction Access Geotextile Standards. Geotextile Property Required Value Grab Tensile  Strength (ASTM D4751)200  psi min. Table II-3.2: Stabilized Construction Access Geotextile Standards 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 275 Geotextile Property Required Value Grab Tensile  Elongation (ASTM D4632)30%  max. Mullen Burst  Strength (ASTM D3786-80a)400  psi min. AOS (ASTM D4751)20-45  (U.S. standard sieve size) Table II-3.2: Stabilized Construction Access Geotextile Standards (continued)  l Consider early installation of the first lift of asphalt in areas that will be paved; this can be used  as a stabilized access. Also consider the installation of excess concrete as a stabilized access.  During large concrete pours, excess concrete is often available for this purpose.  l Fencing (see BMP C103:  High-Visibility Fence) shall be installed as necessary to restrict  traffic to the construction access.  l Whenever possible, the access shall be constructed on a firm, compacted subgrade. This can  substantially increase the effectiveness of the pad and reduce the need for maintenance.  l Construction accesses should avoid crossing existing sidewalks and back of walk drains if at  all possible. If a construction access must cross a sidewalk or back of walk drain, the full length  of the sidewalk and back of walk drain must be covered and protected from sediment leaving  the site. Alternative Material Specification WSDOT has raised safety concerns about the Quarry Spall rock specified above. WSDOT observes  that the 4-inch to 8-inch rock sizes can become trapped between Dually truck tires, and then  released off-site at highway speeds. WSDOT has chosen to use a modified specification for the rock  while continuously verifying that the Stabilized Construction Access remains effective. To remain  effective, the BMP must prevent sediment from migrating off site. To date, there has been no per- formance testing to verify operation of this new specification. Jurisdictions may use the alternative  specification, but must perform increased off-site inspection if they use, or allow others to use, it. Stabilized Construction Accesses may use material that meets the requirements of WSDOT's Stand- ard Specifications for Road, Bridge, and Municipal Construction Section 9-03.9(1) (WSDOT, 2016)  for ballast except for the following special requirements. The grading and quality requirements are listed in Table II-3.3: Stabilized Construction Access  Alternative Material Requirements. Sieve Size Percent Passing 2½″99-100 Table II-3.3: Stabilized Construction Access Alternative Material Requirements 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 276 Sieve Size Percent Passing 2″65-100 ¾″40-80 No. 4 5 max. No. 100 0-2 % Fracture 75 min. Table II-3.3: Stabilized Construction Access Alternative Material Requirements (continued)  l All percentages are by weight.  l The sand equivalent value and dust ratio requirements do not apply.  l The fracture requirement shall be at least one fractured face and will apply the combined  aggregate retained on the No. 4 sieve in accordance with FOP for AASHTO T 335. Maintenance Standards Quarry spalls shall be added if the pad is no longer in accordance with the specifications.  l If the access is not preventing sediment from being tracked onto pavement, then alternative  measures to keep the streets free of sediment shall be used. This may include replace- ment/cleaning of the existing quarry spalls, street sweeping, an increase in the dimensions of  the access, or the installation of BMP C106: Wheel Wash.  l Any sediment that is tracked onto pavement shall be removed by shoveling or street sweep- ing. The sediment collected by sweeping shall be removed or stabilized on site. The pavement  shall not be cleaned by washing down the street, except when high efficiency sweeping is inef- fective and there is a threat to public safety. If it is necessary to wash the streets, the con- struction of a small sump to contain the wash water shall be considered. The sediment would  then be washed into the sump where it can be controlled.  l Perform street sweeping by hand or with a high efficiency sweeper. Do not use a non-high effi- ciency mechanical sweeper because this creates dust and throws soils into storm systems or  conveyance ditches.  l Any quarry spalls that are loosened from the pad, which end up on the roadway shall be  removed immediately.  l If vehicles are entering or exiting the site at points other than the construction access(es),  BMP C103:  High-Visibility Fence shall be installed to control traffic. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 277  l Upon project completion and site stabilization, all construction accesses intended as per- manent access for maintenance shall be permanently stabilized. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 278 Figure II-3.1: Stabilized Construction Access 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 279 Approved as Functionally Equivalent Ecology has approved products as able to meet the requirements of this BMP. The products did not  pass through the Technology Assessment Protocol – Ecology (TAPE) process. Local jurisdictions  may choose not to accept these products, or may require additional testing prior to consideration for  local use. Products that Ecology has approved as functionally equivalent are available for review on  Ecology’s website at:  https://ecology.wa.gov/Regulations-Permits/Guidance-technical-assistance/Stormwater-per- mittee-guidance-resources/Emerging-stormwater-treatment-technologies BMP C106: Wheel Wash Purpose Wheel washes reduce the amount of sediment transported onto paved roads by washing dirt from  the wheels of motor vehicles prior to the motor vehicles leaving the construction site. Conditions of Use  l Use a wheel wash when BMP C105:  Stabilized Construction Access is not preventing sed- iment from being tracked off site.  l Wheel washing is generally an effective BMP when installed with careful attention to topo- graphy. For example, a wheel wash can be detrimental if installed at the top of a slope abut- ting a right-of-way where the water from the dripping truck can run unimpeded into the street.  l Pressure washing combined with an adequately sized and surfaced pad with direct drainage  to a large 10-foot x 10-foot sump can be very effective.  l Wheel wash wastewater is not stormwater. It is commonly called process water, and must be  discharged to a separate on-site treatment system that prevents discharge to waters of the  State, or to the sanitary sewer with local sewer district approval.  l Wheel washes may use closed-loop recirculation systems to conserve water use.  l Wheel wash wastewater shall not include wastewater from concrete washout areas.  l When practical, the wheel wash should be placed in sequence with BMP C105:  Stabilized  Construction Access. Locate the wheel wash such that vehicles exiting the wheel wash will  enter directly onto BMP C105:  Stabilized Construction Access. In order to achieve this, BMP  C105:  Stabilized Construction Access may need to be extended beyond the standard install- ation to meet the exit of the wheel wash. Design and Installation Specifications Suggested details are shown in Figure II-3.2: Wheel Wash. The Local Permitting Authority may  allow other designs. A minimum of 6 inches of asphalt treated base (ATB) over crushed base mater- ial or 8 inches over a good subgrade is recommended to pave the wheel wash. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 280 Use a low clearance truck to test the wheel wash before paving. Either a belly dump or lowboy will  work well to test clearance. Keep the water level from 12 to 14 inches deep to avoid damage to truck hubs and filling the truck  tongues with water. Midpoint spray nozzles are only needed in extremely muddy conditions. Wheel wash systems should be designed with a small grade change, 6- to 12-inches for a 10-foot- wide pond, to allow sediment to flow to the low side of pond to help prevent re-suspension of sed- iment. A drainpipe with a 2- to 3-foot riser should be installed on the low side of the pond to allow for  easy cleaning and refilling. Polymers may be used to promote coagulation and flocculation in a  closed-loop system. Polyacrylamide (PAM) added to the wheel wash water at a rate of 0.25 - 0.5  pounds per 1,000 gallons of water increases effectiveness and reduces cleanup time. If PAM is  already being used for dust or erosion control and is being applied by a water truck, the same truck  can be used to change the wash water. Maintenance Standards The wheel wash should start out each day with fresh water. The wheel wash water should be changed a minimum of once per day. On large earthwork jobs  where more than 10-20 trucks per hour are expected, the wheel wash water will need to be changed  more often. Approved as Functionally Equivalent Ecology has approved products as able to meet the requirements of this BMP. The products did not  pass through the Technology Assessment Protocol – Ecology (TAPE) process. Local jurisdictions  may choose not to accept these products, or may require additional testing prior to consideration for  local use. Products that Ecology has approved as functionally equivalent are available for review on  Ecology’s website at:  https://ecology.wa.gov/Regulations-Permits/Guidance-technical-assistance/Stormwater-per- mittee-guidance-resources/Emerging-stormwater-treatment-technologies 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 281 Figure II-3.2: Wheel Wash 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 282 BMP C107: Construction Road / Parking Area Stabilization Purpose Stabilizing roads, parking areas, and other on-site vehicle transportation routes immediately after  grading reduces erosion caused by construction traffic or stormwater runoff. Conditions of Use Roads and parking areas shall be stabilized wherever they are constructed, whether permanent or  temporary, for use by construction traffic. BMP C103:  High-Visibility Fence shall be installed, if necessary, to limit the access of vehicles to only  those roads and parking areas that are stabilized. Design and Installation Specifications  l On areas that will receive asphalt as part of the project, install the first lift as soon as possible.  l A 6-inch depth of 2- to 4-inch crushed rock, gravel base, or crushed surfacing base course  shall be applied immediately after grading or utility installation. A 4-inch course of asphalt  treated base (ATB) may also be used, or the road/parking area may be paved. It may also be  possible to use cement or calcium chloride for soil stabilization. If cement or cement kiln dust is  used for roadbase stabilization, pH monitoring and BMP C252:  Treating and Disposing of  High pH Water is necessary to evaluate and minimize the effects on stormwater. If the area  will not be used for permanent roads, parking areas, or structures, a 6-inch depth of hog fuel  may also be used, but this is likely to require more maintenance. Whenever possible, con- struction roads and parking areas shall be placed on a firm, compacted subgrade.  l Temporary road gradients shall not exceed 15 percent. Roadways shall be carefully graded to  drain. Drainage ditches shall be provided on each side of the roadway in the case of a  crowned section, or on one side in the case of a super-elevated section. Drainage ditches  shall be directed to a sediment control BMP.  l Rather than relying on ditches, it may also be possible to grade the road so that runoff sheet- flows into a heavily vegetated area with a well-developed topsoil. Landscaped areas are not  adequate. If this area has at least 50 feet of vegetation that water can flow through, then it is  generally preferable to use the vegetation to treat runoff, rather than a sediment pond or trap.  The 50 feet shall not include wetlands or their buffers. If runoff is allowed to sheetflow through  adjacent vegetated areas, it is vital to design the roadways and parking areas so that no con- centrated runoff is created.  l Storm drain inlets shall be protected to prevent sediment-laden water entering the drainage  system (see BMP C220:  Inlet Protection). Maintenance Standards Inspect stabilized areas regularly, especially after large storm events. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 283 Crushed rock, gravel base, etc., shall be added as required to maintain a stable driving surface and  to stabilize any areas that have eroded. Following construction, these areas shall be restored to pre-construction condition or better to pre- vent future erosion. Perform street cleaning at the end of each day or more often if necessary. BMP C120: Temporary and Permanent Seeding Purpose Seeding reduces erosion by stabilizing exposed soils. A well-established vegetative cover is one of  the most effective methods of reducing erosion. Conditions of Use Use seeding throughout the project on disturbed areas that have reached final grade or that will  remain unworked for more than 30 days. The optimum seeding windows for western Washington are April 1 through June 30 and September  1 through October 1. Between July 1 and August 30 seeding requires irrigation until 75 percent grass cover is established. Between October 1 and March 30 seeding requires a cover of mulch or an erosion control blanket  until 75 percent grass cover is established. Review all disturbed areas in late August to early September and complete all seeding by the end of  September. Otherwise, vegetation will not establish itself enough to provide more than average pro- tection. Mulch is required at all times for seeding because it protects seeds from heat, moisture loss, and  transport due to runoff. Mulch can be applied on top of the seed or simultaneously by hydroseeding.  See BMP C121: Mulching for specifications. Seed and mulch all disturbed areas not otherwise vegetated at final site stabilization. Final sta- bilization means the completion of all soil disturbing activities at the site and the establishment of a  permanent vegetative cover, or equivalent permanent stabilization measures (such as pavement,  riprap, gabions, or geotextiles) which will prevent erosion. See BMP T5.13: Post-Construction Soil  Quality and Depth. Design and Installation Specifications General  l Install channels intended for vegetation before starting major earthwork and hydroseed with a  Bonded Fiber Matrix. For vegetated channels that will have high flows, install erosion control  blankets over the top of hydroseed. Before allowing water to flow in vegetated channels,  establish 75 percent vegetation cover. If vegetated channels cannot be established by seed  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 284 before water flow; install sod in the channel bottom — over top of hydromulch and erosion con- trol blankets.  l Confirm the installation of all required surface water control measures to prevent seed from  washing away.  l Hydroseed applications shall include a minimum of 1,500 pounds per acre of mulch with 3 per- cent tackifier. See BMP C121: Mulching for specifications.  l Areas that will have seeding only and not landscaping may need compost or meal-based  mulch included in the hydroseed in order to establish vegetation. Re-install native topsoil on  the disturbed soil surface before application. See BMP T5.13: Post-Construction Soil Quality  and Depth.  l When installing seed via hydroseeding operations, only about 1/3 of the seed actually ends up  in contact with the soil surface. This reduces the ability to establish a good stand of grass  quickly. To overcome this, consider increasing seed quantities by up to 50 percent.  l Enhance vegetation establishment by dividing the hydromulch operation into two phases:  o Phase 1- Install all seed and fertilizer with 25-30 percent mulch and tackifier onto soil in  the first lift.  o Phase 2- Install the rest of the mulch and tackifier over the first lift. Or, enhance vegetation by:  o Installing the mulch, seed, fertilizer, and tackifier in one lift.  o Spread or blow straw over the top of the hydromulch at a rate of 800-1000 pounds per  acre.  o Hold straw in place with a standard tackifier. Both of these approaches will increase cost moderately but will greatly improve and enhance  vegetative establishment. The increased cost may be offset by the reduced need for:  o Irrigation.  o Reapplication of mulch.  o Repair of failed slope surfaces. This technique works with standard hydromulch (1,500 pounds per acre minimum) and Bon- ded Fiber Matrix/ Mechanically Bonded Fiber Matrix (BFM/MBFMs) (3,000 pounds per acre  minimum).  l Seed may be installed by hand if:  o Temporary and covered by straw, mulch, or topsoil.  o Permanent in small areas (usually less than 1 acre) and covered with mulch, topsoil, or  erosion blankets.  l The seed mixes listed in Table II-3.4: Temporary and Permanent Seed Mixes include  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 285 recommended mixes for both temporary and permanent seeding.  l Apply these mixes, with the exception of the wet area seed mix, at a rate of 120 pounds per  acre. This rate can be reduced if soil amendments or slow-release fertilizers are used. Apply  the wet area seed mix at a rate of 60 pounds per acre.  l Consult the local suppliers or the local conservation district for their recommendations. The  appropriate mix depends on a variety of factors, including location, exposure, soil type, slope,  and expected foot traffic. Alternative seed mixes approved by the local authority may be used,  depending on the soil type and hydrology of the area. Common Name Latin Name % Weight % Purity % Germination Temporary Erosion Control Seed Mix A standard mix for areas requiring a temporary vegetative cover. Chewings or   annual blue grass Festuca rubra var. commutata or Poa anna 40 98 90 Perennial rye  Lolium perenne 50 98 90 Redtop or colonial  bentgrass  Agrostis alba or  Agrostis tenuis 5 92 85 White dutch clover Trifolium repens 5 98 90 Landscaping Seed Mix A recommended mix for landscaping seed. Perennial rye blend Lolium perenne 70 98 90 Chewings and red  fescue blend Festuca rubra var. commutata or Fes- tuca rubra 30 98 90 Low-Growing Turf Seed Mix A turf seed mix for dry situations where there is no need for watering. This mix requires very little main- tenance. Dwarf tall fescue  (several  varieties) Festuca arundin- acea var. 45 98 90 Dwarf perennial  rye (Barclay) Lolium perenne var. barclay 30 98 90 Red fescue Festuca rubra 20 98 90 Colonial bentgrass Agrostis tenuis 5 98 90 Bioswale Seed Mix A seed mix for bioswales and other intermittently wet areas. Tall or meadow fes-Festuca arundin-75-80 98 90 Table II-3.4: Temporary and Permanent Seed Mixes 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 286 Common Name Latin Name % Weight % Purity % Germination cue acea or   Festuca elatior Seaside/Creeping  bentgrass Agrostis palustris 10-15 92 85 Redtop bentgrass Agrostis alba or  Agrostis gigantea 5-10 90 80 Wet Area Seed Mix A low-growing, relatively non-invasive seed mix appropriate for very wet areas that are not regulated wet- lands. Consult Hydraulic Permit Authority (HPA) for seed mixes if applicable. Tall or meadow fes- cue Festuca arundin- acea or Festuca elatior 60-70 98 90 Seaside/Creeping  bentgrass Agrostis palustris 10-15 98 85 Meadow foxtail Alepocurus praten- sis 10-15 90 80 Alsike clover Trifolium hybridum 1-6 98 90 Redtop bentgrass Agrostis alba 1-6 92 85 Meadow Seed Mix A recommended meadow seed mix for infrequently maintained areas or non-maintained areas where col- onization by native plants is desirable. Likely applications include rural road and utility right-of-way. Seed- ing should take place in September or very early October in order to obtain adequate establishment prior to  the winter months. Consider the appropriateness of clover, a fairly invasive species, in the mix. Amending  the soil can reduce the need for clover. Redtop or Oregon  bentgrass Agrostis alba or  Agrostis ore- gonensis 20 92 85 Red fescue Festuca rubra 70 98 90 White dutch clover Trifolium repens 10 98 90 Table II-3.4: Temporary and Permanent Seed Mixes (continued) Roughening and Rototilling  l The seedbed should be firm and rough. Roughen all soil no matter what the slope. Track walk  slopes before seeding if engineering purposes require compaction. Backblading or smoothing  of slopes greater than 4H:1V is not allowed if they are to be seeded.  l Restoration-based landscape practices require deeper incorporation than that provided by a  simple single-pass rototilling treatment. Wherever practical, initially rip the subgrade to  improve long-term permeability, infiltration, and water inflow qualities. At a minimum,  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 287 permanent areas shall use soil amendments to achieve organic matter and permeability per- formance defined in engineered soil/landscape systems. For systems that are deeper than 8  inches complete the rototilling process in multiple lifts, or prepare the engineered soil system  per specifications and place to achieve the specified depth. Fertilizers  l Conducting soil tests to determine the exact type and quantity of fertilizer is recommended.  This will prevent the over-application of fertilizer.  l Organic matter is the most appropriate form of fertilizer because it provides nutrients (includ- ing nitrogen, phosphorus, and potassium) in the least water-soluble form.  l In general, use 10-4-6 N-P-K (nitrogen-phosphorus-potassium) fertilizer at a rate of 90  pounds per acre. Always use slow-release fertilizers because they are more efficient and  have fewer environmental impacts. Do not add fertilizer to the hydromulch machine, or agit- ate, more than 20 minutes before use. Too much agitation destroys the slow-release coating.  l There are numerous products available that take the place of chemical fertilizers. These  include several with seaweed extracts that are beneficial to soil microbes and organisms. If  100 percent cottonseed meal is used as the mulch in hydroseed, chemical fertilizer may not be  necessary. Cottonseed meal provides a good source of long-term, slow-release, available  nitrogen. Bonded Fiber Matrix and Mechanically Bonded Fiber Matrix  l On steep slopes use Bonded Fiber Matrix (BFM) or Mechanically Bonded Fiber Matrix  (MBFM) products. Apply BFM/MBFM products at a minimum rate of 3,000 pounds per acre  with approximately 10 percent tackifier. Achieve a minimum of 95 percent soil coverage during  application. Numerous products are available commercially. Most products require 24-36  hours to cure before rainfall and cannot be installed on wet or saturated soils. Generally,  products come in 40-50 pound bags and include all necessary ingredients except for seed and  fertilizer.  l Install products per manufacturer's instructions.  l BFMs and MBFMs provide good alternatives to blankets in most areas requiring vegetation  establishment. Advantages over blankets include:  o BFM and MBFMs do not require surface preparation.  o Helicopters can assist in installing BFM and MBFMs in remote areas.  o On slopes steeper than 2.5H:1V, blanket installers may require ropes and harnesses  for safety.  o Installing BFM and MBFMs can save at least $1,000 per acre compared to blankets. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 288 Maintenance Standards Reseed any seeded areas that fail to establish at least 75 percent cover (100 percent cover for areas  that receive sheet or concentrated flows). If reseeding is ineffective, use an alternate method such  as sodding, mulching, nets, or blankets.  l Reseed and protect by mulch any areas that experience erosion after achieving adequate  cover. Reseed and protect by mulch any eroded area.  l Supply seeded areas with adequate moisture, but do not water to the extent that it causes run- off. Approved as Functionally Equivalent Ecology has approved products as able to meet the requirements of this BMP. The products did not  pass through the Technology Assessment Protocol – Ecology (TAPE) process. Local jurisdictions  may choose not to accept these products, or may require additional testing prior to consideration for  local use. Products that Ecology has approved as functionally equivalent are available for review on  Ecology’s website at:  https://ecology.wa.gov/Regulations-Permits/Guidance-technical-assistance/Stormwater-per- mittee-guidance-resources/Emerging-stormwater-treatment-technologies BMP C121: Mulching Purpose Mulching soils provides immediate temporary protection from erosion. Mulch also enhances plant  establishment by conserving moisture, holding fertilizer, seed, and topsoil in place, and moderating  soil temperatures. There are a variety of mulches that can be used. This section discusses only the  most common types of mulch. Conditions of Use As a temporary cover measure, mulch should be used:  l For less than 30 days on disturbed areas that require cover.  l At all times for seeded areas, especially during the wet season and during the hot summer  months.  l During the wet season on slopes steeper than 3H:1V with more than 10 feet of vertical relief. Mulch may be applied at any time of the year and must be refreshed periodically. For seeded areas, mulch may be made up of 100 percent:   l cottonseed meal;   l fibers made of wood, recycled cellulose, hemp, or kenaf;  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 289 BMP C123: Plastic Covering Purpose Plastic covering provides immediate, short-term erosion protection to slopes and disturbed areas. Conditions of Use Plastic covering may be used on disturbed areas that require cover measures for less than 30 days,  except as stated below.  l Plastic is particularly useful for protecting cut and fill slopes and stockpiles. However, the rel- atively rapid breakdown of most polyethylene sheeting makes it unsuitable for applications  greater than six months.  l Due to rapid runoff caused by plastic covering, do not use this method upslope of areas that  might be adversely impacted by concentrated runoff. Such areas include steep and/or  unstable slopes.  l Plastic sheeting may result in increased runoff volumes and velocities, requiring additional on- site measures to counteract the increases. Creating a trough with wattles or other material  can convey clean water away from these areas.  l To prevent undercutting, trench and backfill rolled plastic covering products.  l Although the plastic material is inexpensive to purchase, the cost of installation, maintenance,  removal, and disposal add to the total costs of this BMP.  l Whenever plastic is used to protect slopes, install water collection measures at the base of the  slope. These measures include plastic-covered berms, channels, and pipes used to convey  clean rainwater away from bare soil and disturbed areas. Do not mix clean runoff from a  plastic covered slope with dirty runoff from a project.  l Other uses for plastic include:  o Temporary ditch liner.  o Pond liner in temporary sediment pond.  o Liner for bermed temporary fuel storage area if plastic is not reactive to the type of fuel  being stored.  o Emergency slope protection during heavy rains.  o Temporary drainpipe (“elephant trunk”) used to direct water. Design and Installation Specifications  l Plastic slope cover must be installed as follows:  1. Run plastic up and down the slope, not across the slope.  2. Plastic may be installed perpendicular to a slope if the slope length is less than 10 feet. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 298  3. Provide a minimum of 8-inch overlap at the seams.  4. On long or wide slopes, or slopes subject to wind, tape all seams.  5. Place plastic into a small (12-inch wide by 6-inch deep) slot trench at the top of the slope  and backfill with soil to keep water from flowing underneath.  6. Place sand filled burlap or geotextile bags every 3 to 6 feet along seams and tie them  together with twine to hold them in place.  7. Inspect plastic for rips, tears, and open seams regularly and repair immediately. This  prevents high velocity runoff from contacting bare soil, which causes extreme erosion.  8. Sandbags may be lowered into place tied to ropes. However, all sandbags must be  staked in place.  l Plastic sheeting shall have a minimum thickness of 0.06 millimeters.  l If erosion at the toe of a slope is likely, a gravel berm, riprap, or other suitable protection shall  be installed at the toe of the slope in order to reduce the velocity of runoff. Maintenance Standards  l Torn sheets must be replaced and open seams repaired.  l Completely remove and replace the plastic if it begins to deteriorate due to ultraviolet radi- ation.  l Completely remove plastic when no longer needed.  l Dispose of old tires used to weight down plastic sheeting appropriately. Approved as Functionally Equivalent Ecology has approved products as able to meet the requirements of this BMP. The products did not  pass through the Technology Assessment Protocol – Ecology (TAPE) process. Local jurisdictions  may choose not to accept these products, or may require additional testing prior to consideration for  local use. Products that Ecology has approved as functionally equivalent are available for review on  Ecology’s website at:  https://ecology.wa.gov/Regulations-Permits/Guidance-technical-assistance/Stormwater-per- mittee-guidance-resources/Emerging-stormwater-treatment-technologies BMP C124: Sodding Purpose The purpose of sodding is to establish turf for immediate erosion protection and to stabilize drainage  paths where concentrated overland flow will occur. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 299 BMP C140: Dust Control Purpose Dust control prevents wind transport of dust from disturbed soil surfaces onto roadways, drainage  ways, and surface waters. Conditions of Use Use dust control in areas (including roadways) subject to surface and air movement of dust where  on-site or off-site impacts to roadways, drainage ways, or surface waters are likely. Design and Installation Specifications  l Vegetate or mulch areas that will not receive vehicle traffic. In areas where planting, mulching,  or paving is impractical, apply gravel or landscaping rock.  l Limit dust generation by clearing only those areas where immediate activity will take place,  leaving the remaining area(s) in the original condition. Maintain the original ground cover as  long as practical.  l Construct natural or artificial windbreaks or windscreens. These may be designed as enclos- ures for small dust sources.  l Sprinkle the site with water until the surface is wet. Repeat as needed. To prevent carryout of  mud onto the street, refer to BMP C105:  Stabilized Construction Access and BMP C106:  Wheel Wash.  l Irrigation water can be used for dust control. Irrigation systems should be installed as a first  step on sites where dust control is a concern.  l Spray exposed soil areas with a dust palliative, following the manufacturer’s instructions and  cautions regarding handling and application. Used oil is prohibited from use as a dust sup- pressant. Local governments may approve other dust palliatives such as calcium chloride or  PAM.  l PAM (BMP C126:  Polyacrylamide (PAM) for Soil Erosion Protection) added to water at a rate  of 0.5 pounds per 1,000 gallons of water per acre and applied from a water truck is more effect- ive than water alone. This is due to increased infiltration of water into the soil and reduced  evaporation. In addition, small soil particles are bonded together and are not as easily trans- ported by wind. Adding PAM may reduce the quantity of water needed for dust control. Note  that the application rate specified here applies to this BMP, and is not the same application  rate that is specified in BMP C126:  Polyacrylamide (PAM) for Soil Erosion Protection, but the  downstream protections still apply. Refer to BMP C126:  Polyacrylamide (PAM) for Soil Erosion Protection for conditions of use.  PAM shall not be directly applied to water or allowed to enter a water body.  l Contact your local Air Pollution Control Authority for guidance and training on other dust con- trol measures. Compliance with the local Air Pollution Control Authority constitutes  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 313 compliance with this BMP.  l Use vacuum street sweepers.  l Remove mud and other dirt promptly so it does not dry and then turn into dust.  l Techniques that can be used for unpaved roads and lots include:  o Lower speed limits. High vehicle speed increases the amount of dust stirred up from  unpaved roads and lots.  o Upgrade the road surface strength by improving particle size, shape, and mineral types  that make up the surface and base materials.  o Add surface gravel to reduce the source of dust emission. Limit the amount of fine  particles (those smaller than .075 mm) to 10 to 20 percent.  o Use geotextile fabrics to increase the strength of new roads or roads undergoing recon- struction.  o Encourage the use of alternate, paved routes, if available.  o Apply chemical dust suppressants using the admix method, blending the product with  the top few inches of surface material. Suppressants may also be applied as surface  treatments.  o Limit dust-causing work on windy days.  o Pave unpaved permanent roads and other trafficked areas. Maintenance Standards Respray area as necessary to keep dust to a minimum. BMP C150: Materials on Hand Purpose Keep quantities of erosion prevention and sediment control materials on the project site at all times  to be used for regular maintenance and emergency situations such as unexpected heavy rains. Hav- ing these materials on-site reduces the time needed to replace existing or implement new BMPs  when inspections indicate that existing BMPs are not meeting the Construction SWPPP require- ments. In addition, contractors can save money by buying some materials in bulk and storing them at  their office or yard. Conditions of Use  l Construction projects of any size or type can benefit from having materials on hand. A small  commercial development project could have a roll of plastic and some gravel available for  immediate protection of bare soil and temporary berm construction. A large earthwork project,  such as highway construction, might have several tons of straw, several rolls of plastic, flexible  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 314 pipe, sandbags, geotextile fabric and steel “T” posts.  l Materials should be stockpiled and readily available before any site clearing, grubbing, or  earthwork begins. A large contractor or project proponent could keep a stockpile of materials  that are available for use on several projects.  l If storage space at the project site is at a premium, the contractor could maintain the materials  at their office or yard. The office or yard must be less than an hour from the project site. Design and Installation Specifications Depending on project type, size, complexity, and length, materials and quantities will vary. A good  minimum list of items that will cover numerous situations includes:  l Clear Plastic, 6 mil  l Drainpipe, 6 or 8 inch diameter  l Sandbags, filled  l Straw Bales for mulching  l Quarry Spalls  l Washed Gravel  l Geotextile Fabric  l Catch Basin Inserts  l Steel "T" Posts  l Silt fence material  l Straw Wattles Maintenance Standards  l All materials with the exception of the quarry spalls, steel “T” posts, and gravel should be kept  covered and out of both sun and rain.  l Re-stock materials as needed. BMP C151: Concrete Handling Purpose Concrete work can generate process water and slurry that contain fine particles and high pH, both of  which can violate water quality standards in the receiving water. Concrete spillage or concrete dis- charge to waters of the State is prohibited. Use this BMP to minimize and eliminate concrete, con- crete process water, and concrete slurry from entering waters of the State. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 315 Conditions of Use Any time concrete is used, utilize these management practices. Concrete construction project com- ponents include, but are not limited to:  l Curbs  l Sidewalks  l Roads  l Bridges  l Foundations  l Floors  l Runways Disposal options for concrete, in order of preference are:  1. Off-site disposal  2. Concrete wash-out areas (see BMP C154: Concrete Washout Area)  3. De minimus washout to formed areas awaiting concrete Design and Installation Specifications  l Wash concrete truck drums at an approved off-site location or in designated concrete  washout areas only. Do not wash out  concrete trucks onto the ground (including formed areas  awaiting concrete), or into storm drains, open ditches, streets, or streams. Refer to BMP  C154: Concrete Washout Area for information on concrete washout areas.  o Return unused concrete remaining in the truck and pump to the originating batch plant  for recycling. Do not dump excess concrete on site, except in designated concrete  washout areas as allowed in BMP C154: Concrete Washout Area.  l Wash small concrete handling equipment (e.g. hand tools, screeds, shovels, rakes, floats,  trowels, and wheelbarrows) into designated concrete washout areas or into formed areas  awaiting concrete pour.  l At no time shall concrete be washed off into the footprint of an area where an infiltration fea- ture will be installed.  l Wash equipment difficult to move, such as concrete paving machines, in areas that do not dir- ectly drain to natural or constructed stormwater conveyance or potential infiltration areas.  l Do not allow washwater from areas, such as concrete aggregate driveways, to drain directly  (without detention or treatment) to natural or constructed stormwater conveyances.  l Contain washwater and leftover product in a lined container when no  designated concrete  washout areas (or formed areas, allowed as described above) are available. Dispose of con- tained concrete and concrete washwater (process water) properly. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 316  l Always use forms or solid barriers for concrete pours, such as pilings, within 15-feet of surface  waters.  l Refer to BMP C252:  Treating and Disposing of High pH Water for pH adjustment require- ments.  l Refer to the Construction Stormwater General Permit (CSWGP) for pH monitoring require- ments if the project involves one of the following activities:  o Significant concrete work (as defined in the CSWGP).  o The use of soils amended with (but not limited to) Portland cement-treated base,  cement kiln dust or fly ash.  o Discharging stormwater to segments of water bodies on the 303(d) list (Category 5) for  high pH. Maintenance Standards Check containers for holes in the liner daily during concrete pours and repair the same day. BMP C152: Sawcutting and Surfacing Pollution Prevention Purpose Sawcutting and surfacing operations generate slurry and process water that contains fine particles  and high pH (concrete cutting), both of which can violate the water quality standards in the receiving  water. Concrete spillage or concrete discharge to waters of the State is prohibited. Use this BMP to  minimize and eliminate process water and slurry created through sawcutting or surfacing from enter- ing waters of the State. Conditions of Use Utilize these management practices anytime sawcutting or surfacing operations take place. Saw- cutting and surfacing operations include, but are not limited to:  l Sawing  l Coring  l Grinding  l Roughening  l Hydro-demolition  l Bridge and road surfacing 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 317 Design and Installation Specifications  l Vacuum slurry and cuttings during cutting and surfacing operations.  l Slurry and cuttings shall not remain on permanent concrete or asphalt pavement overnight.  l Slurry and cuttings shall not drain to any natural or constructed drainage conveyance includ- ing stormwater systems. This may require temporarily blocking catch basins.  l Dispose of collected slurry and cuttings in a manner that does not violate ground water or sur- face water quality standards.  l Do not allow process water generated during hydro-demolition, surface roughening or similar  operations to drain to any natural or constructed drainage conveyance including stormwater  systems. Dispose of process water in a manner that does not violate ground water or surface  water quality standards.  l Handle and dispose of cleaning waste material and demolition debris in a manner that does  not cause contamination of water. Dispose of sweeping material from a pick-up sweeper at an  appropriate disposal site. Maintenance Standards Continually monitor operations to determine whether slurry, cuttings, or process water could enter  waters of the state. If inspections show that a violation of water quality standards could occur, stop  operations and immediately implement preventive measures such as berms, barriers, secondary  containment, and/or vacuum trucks. BMP C153: Material Delivery, Storage, and Containment Purpose Prevent, reduce, or eliminate the discharge of pollutants to the stormwater system or watercourses  from material delivery and storage. Minimize the storage of hazardous materials on-site, store mater- ials in a designated area, and install secondary containment. Conditions of Use Use at construction sites with delivery and storage of the following materials:  l Petroleum products such as fuel, oil and grease  l Soil stabilizers and binders (e.g., Polyacrylamide)  l Fertilizers, pesticides and herbicides  l Detergents  l Asphalt and concrete compounds 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 318  l Hazardous chemicals such as acids, lime, adhesives, paints, solvents, and curing compounds  l Any other material that may be detrimental if released to the environment Design and Installation Specifications  l The temporary storage area should be located away from vehicular traffic, near the con- struction entrance(s), and away from waterways or storm drains.  l Safety Data Sheets (SDS) should be supplied for all materials stored. Chemicals should be  kept in their original labeled containers.  l Hazardous material storage on-site should be minimized.  l Hazardous materials should be handled as infrequently as possible.  l During the wet weather season (Oct 1 – April 30), consider storing materials in a covered  area.  l Materials should be stored in secondary containments, such as an earthen dike, horse trough,  or even a children’s wading pool for non-reactive materials such as detergents, oil, grease,  and paints. Small amounts of material may be secondarily contained in “bus boy” trays or con- crete mixing trays.  l Do not store chemicals, drums, or bagged materials directly on the ground. Place these items  on a pallet and, when possible, within secondary containment.  l If drums must be kept uncovered, store them at a slight angle to reduce ponding of rainwater  on the lids to reduce corrosion. Domed plastic covers are inexpensive and snap to the top of  drums, preventing water from collecting.  l Liquids, petroleum products, and substances listed in 40 CFR Parts 110, 117, or 302 shall be  stored in approved containers and drums and shall not be overfilled. Containers and drums  shall be stored in temporary secondary containment facilities.  l Temporary secondary containment facilities shall provide for a spill containment volume able  to contain 10% of the total enclosed container volume of all containers, or 110% of the capa- city of the largest container within its boundary, whichever is greater.  l Secondary containment facilities shall be impervious to the materials stored therein for a min- imum contact time of 72 hours.  l Sufficient separation should be provided between stored containers to allow for spill cleanup  and emergency response access.  l During the wet weather season (Oct 1 – April 30), each secondary containment facility shall  be covered during non-working days, prior to and during rain events.  l Keep material storage areas clean, organized and equipped with an ample supply of appro- priate spill clean-up material (spill kit).  l The spill kit should include, at a minimum: 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 319  o 1-Water Resistant Nylon Bag  o 3-Oil Absorbent Socks 3”x 4’  o 2-Oil Absorbent Socks 3”x 10’  o 12-Oil Absorbent Pads 17”x19”  o 1-Pair Splash Resistant Goggles  o 3-Pair Nitrile Gloves  o 10-Disposable Bags with Ties  o Instructions Maintenance Standards  l Secondary containment facilities shall be maintained free of accumulated rainwater and spills.  In the event of spills or leaks, accumulated rainwater and spills shall be collected and placed  into drums. These liquids shall be handled as hazardous waste unless testing determines  them to be non-hazardous.  l Re-stock spill kit materials as needed. BMP C154: Concrete Washout Area Purpose Prevent or reduce the discharge of pollutants from concrete waste to stormwater by conducting  washout off-site, or performing on-site washout in a designated area. Conditions of Use Concrete washout areas are implemented on construction projects where:  l Concrete is used as a construction material  l It is not possible to dispose of all concrete wastewater and washout off-site (ready mix plant,  etc.).  l Concrete truck drums are washed on-site. Note that auxiliary concrete truck components (e.g. chutes and hoses) and small concrete  handling equipment (e.g. hand tools, screeds, shovels, rakes, floats, trowels, and wheel- barrows) may be washed into formed areas awaiting concrete pour. At no time shall concrete be washed off into the footprint of an area where an infiltration feature will  be installed. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 320 BMP C160: Certified Erosion and Sediment Control Lead Purpose The project proponent designates at least one person as the responsible representative in charge of  erosion and sediment control (ESC), and water quality protection. The designated person shall be  responsible for ensuring compliance with all local, state, and federal erosion and sediment control  and water quality requirements. Construction sites one acre or larger that discharge to waters of the  State must designate a Certified Erosion and Sediment Control Lead (CESCL) as the responsible  representative. Conditions of Use A CESCL shall be made available on projects one acre or larger that discharge stormwater to sur- face waters of the state. Sites less than one acre may have a person without CESCL certification  conduct inspections. The CESCL shall:  l Have a current certificate proving attendance in an erosion and sediment control training  course that meets the minimum ESC training and certification requirements established by  Ecology. Ecology has provided the minimum requirements for CESCL course training, as well as a list  of ESC training and certification providers at:  https://ecology.wa.gov/Regulations-Permits/Permits-certifications/Certified-erosion-sed- iment-control  OR  l Be a Certified Professional in Erosion and Sediment Control (CPESC). For additional inform- ation go to:  http://www.envirocertintl.org/cpesc/ Specifications  l CESCL certification shall remain valid for three years.  l The CESCL shall have authority to act on behalf of the contractor or project proponent and  shall be available, or on-call, 24 hours per day throughout the period of construction.  l The Construction SWPPP shall include the name, telephone number, fax number, and  address of the designated CESCL. See II-2 Construction Stormwater Pollution Prevention  Plans (Construction SWPPPs).  l A CESCL may provide inspection and compliance services for multiple construction projects  in the same geographic region, but must be on site whenever earthwork activities are  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 327 occurring that could generate release of turbid water.  l Duties and responsibilities of the CESCL shall include, but are not limited to the following:  o Maintaining a permit file on site at all times which includes the Construction SWPPP  and any associated permits and plans.  o Directing BMP installation, inspection, maintenance, modification, and removal.  o Updating all project drawings and the Construction SWPPP with changes made.  o Completing any sampling requirements including reporting results using electronic Dis- charge Monitoring Reports (WebDMR).  o Facilitate, participate in, and take corrective actions resulting from inspections per- formed by outside agencies or the owner.  o Keeping daily logs, and inspection reports. Inspection reports should include:  n Inspection date/time.  n Weather information; general conditions during inspection and approximate  amount of precipitation since the last inspection.  n Visual monitoring results, including a description of discharged stormwater. The  presence of suspended sediment, turbid water, discoloration, and oil sheen shall  be noted, as applicable.  n Any water quality monitoring performed during inspection.  n General comments and notes, including a brief description of any BMP repairs,  maintenance or installations made as a result of the inspection.  n A summary or list of all BMPs implemented, including observations of all  erosion/sediment control structures or practices. The following shall be noted:  1. Locations of BMPs inspected.  2. Locations of BMPs that need maintenance.  3. Locations of BMPs that failed to operate as designed or intended.  4. Locations of where additional or different BMPs are required. BMP C162: Scheduling Purpose Sequencing a construction project reduces the amount and duration of soil exposed to erosion by  wind, rain, runoff, and vehicle tracking. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 328 Conditions of Use The construction sequence schedule is an orderly listing of all major land-disturbing activities  together with the necessary erosion and sedimentation control measures planned for the project.  This type of schedule guides the contractor on work to be done before other work is started so that  serious erosion and sedimentation problems can be avoided. Following a specified work schedule that coordinates the timing of land-disturbing activities and the  installation of control measures is perhaps the most cost-effective way of controlling erosion during  construction. The removal of ground cover leaves a site vulnerable to erosion. Construction sequen- cing that limits land clearing, provides timely installation of erosion and sedimentation controls, and  restores protective cover quickly can significantly reduce the erosion potential of a site. Design Considerations  l Minimize construction during rainy periods.  l Schedule projects to disturb only small portions of the site at any one time. Complete grading  as soon as possible. Immediately stabilize the disturbed portion before grading the next por- tion. Practice staged seeding in order to revegetate cut and fill slopes as the work progresses. II-3.3 Construction Runoff BMPs BMP C200: Interceptor Dike and Swale Purpose Provide a dike of compacted soil or a swale at the top or base of a disturbed slope or along the peri- meter of a disturbed construction area to convey stormwater. Use the dike and/or swale to intercept  the runoff from unprotected areas and direct it to areas where erosion can be controlled. This can  prevent storm runoff from entering the work area or sediment-laden runoff from leaving the con- struction site. Conditions of Use Use an interceptor dike or swale where runoff from an exposed site or disturbed slope must be con- veyed to an erosion control BMP which can safely convey the stormwater.  l Locate upslope of a construction site to prevent runoff from entering the disturbed area.  l When placed horizontally across a disturbed slope, it reduces the amount and velocity of run- off flowing down the slope.  l Locate downslope to collect runoff from a disturbed area and direct it to a sediment  BMP (e.g.  BMP C240:  Sediment Trap or BMP C241:  Sediment Pond (Temporary)). 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 329 thickness is 2 feet.  o For outlets at the base of steep slope pipes (pipe slope greater than 10 percent), use an  engineered energy dissipator.  o Filter fabric or erosion control blankets should always be used under riprap to prevent  scour and channel erosion. See BMP C122:  Nets and Blankets.  l Bank stabilization, bioengineering, and habitat features may be required for disturbed areas.  This work may require a Hydraulic Project Approval (HPA) from the Washington State Depart- ment of Fish and Wildlife. See I-2.11 Hydraulic Project Approvals. Maintenance Standards  l Inspect and repair as needed.  l Add rock as needed to maintain the intended function.  l Clean energy dissipator if sediment builds up. BMP C220: Inlet Protection Purpose Inlet protection prevents coarse sediment from entering drainage systems prior to permanent sta- bilization of the disturbed area. Conditions of Use Use inlet protection at inlets that are operational before permanent stabilization of the disturbed  areas that contribute runoff to the inlet. Provide protection for all storm drain inlets downslope and  within 500 feet of a disturbed or construction area, unless  those inlets are preceded by a sediment  trapping BMP. Also consider inlet protection for lawn and yard drains on new home construction. These small and  numerous drains coupled with lack of gutters can add significant amounts of sediment into the roof  drain system. If possible, delay installing lawn and yard drains until just before landscaping, or cap  these drains to prevent sediment from entering the system until completion of landscaping. Provide  18-inches of sod around each finished lawn and yard drain. Table II-3.10: Storm Drain Inlet Protection lists several options for inlet protection. All of the methods  for inlet protection tend to plug and require a high frequency of maintenance. Limit contributing drain- age areas for an individual inlet to one acre or less. If possible, provide emergency overflows with  additional end-of-pipe treatment where stormwater ponding would cause a hazard. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 356 Type of Inlet Pro- tection Emergency Overflow Applicable for Paved/ Earthen Sur- faces Conditions of Use Drop Inlet Protection Excavated  drop  inlet protection Yes, temporary  flooding may   occur Earthen Applicable for heavy flows. Easy   to maintain. Large area requirement:   30'x30'/acre Block  and gravel  drop inlet pro- tection Yes Paved or Earthen Applicable for heavy  concentrated flows.  Will not pond. Gravel and wire  drop inlet pro- tection No Paved or Earthen Applicable for  heavy concentrated flows.  Will pond. Can withstand traffic. Catch  basin filters Yes Paved or Earthen Frequent maintenance  required. Curb Inlet Protection Curb  inlet pro- tection with  wooden weir Small capacity  overflow Paved Used for sturdy, more compact  install- ation. Block and gravel  curb inlet pro- tection Yes Paved Sturdy, but  limited filtration. Culvert Inlet Protection Culvert  inlet sed- iment trap N/A N/A 18 month expected life. Table II-3.10: Storm Drain Inlet Protection Design and Installation Specifications Excavated Drop Inlet Protection Excavated drop inlet protection consists of an excavated impoundment around the storm drain inlet.  Sediment settles out of the stormwater prior to entering the storm drain. Design and installation spe- cifications for excavated drop inlet protection include:  l Provide a depth of 1-2 ft as measured from the crest of the inlet structure.  l Slope sides of excavation should be no steeper than 2H:1V.  l Minimum volume of excavation is 35 cubic yards.  l Shape the excavation to fit the site, with the longest dimension oriented toward the longest  inflow area.  l Install provisions for draining to prevent standing water.  l Clear the area of all debris. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 357  l Grade the approach to the inlet uniformly.  l Drill weep holes into the side of the inlet.  l Protect weep holes with screen wire and washed aggregate.  l Seal weep holes when removing structure and stabilizing area.  l Build a temporary dike, if necessary, to the down slope side of the structure to prevent bypass  flow. Block and Gravel Filter A block and gravel filter is a barrier formed around the inlet with standard concrete blocks and gravel.  See Figure II-3.17: Block and Gravel Filter. Design and installation specifications for block gravel fil- ters include:  l Provide a height of 1 to 2 feet above the inlet.  l Recess the first row of blocks 2-inches into the ground for stability.  l Support subsequent courses by placing a pressure treated wood 2x4 through the block open- ing.  l Do not use mortar.  l Lay some blocks in the bottom row on their side to allow for dewatering the pool.  l Place hardware cloth or comparable wire mesh with ½-inch openings over all block openings.  l Place gravel to just below the top of blocks on slopes of 2H:1V or flatter.  l An alternative design is a gravel berm surrounding the inlet, as follows:  o Provide a slope of 3H:1V on the upstream side of the berm.  o Provide a slope of 2H:1V on the downstream side of the berm.  o Provide a 1-foot wide level stone area between the gravel berm and the inlet.  o Use stones 3 inches in diameter or larger on the upstream slope of the berm.  o Use gravel ½- to ¾-inch at a minimum thickness of 1-foot on the downstream slope of  the berm. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 358 Figure II-3.17: Block and Gravel Filter   2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 359 Gravel and Wire Mesh Filter Gravel and wire mesh filters are gravel barriers placed over the top of the inlet. This method does not  provide an overflow. Design and installation specifications for gravel and wire mesh filters include:  l Use a hardware cloth or comparable wire mesh with ½-inch openings.  o Place wire mesh over the drop inlet so that the wire extends a minimum of 1-foot bey- ond each side of the inlet structure.  o Overlap the strips if more than one strip of mesh is necessary.  l Place coarse aggregate over the wire mesh.  o Provide at least a 12-inch depth of aggregate over the entire inlet opening and extend at  least 18-inches on all sides. Catch Basin Filters Catch  basin filters are designed by manufacturers for construction sites. The limited sediment stor- age capacity increases the amount of inspection and maintenance required, which may be daily for  heavy sediment loads. To reduce maintenance requirements, combine a catch  basin filter with  another type of inlet protection. This type of inlet protection provides flow bypass without overflow  and therefore may be a better method for inlets located along active rights-of-way. Design and install- ation specifications for catch basin filters include:  l Provides 5 cubic feet of storage.  l Requires dewatering provisions.  l Provides a high-flow bypass that will not clog under normal use at a construction site.  l Insert the catch  basin filter in the catch  basin just below the grating. Curb Inlet Protection with Wooden Weir Curb inlet protection with wooden weir is an option that consists of a barrier formed around a curb  inlet with a wooden frame and gravel. Design and installation specifications for curb inlet protection  with wooden weirs include:  l Use wire mesh with ½-inch openings.  l Use extra strength filter cloth.  l Construct a frame.  l Attach the wire and filter fabric to the frame.  l Pile coarse washed aggregate against the wire and fabric.  l Place weight on the frame anchors. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 360 Block and Gravel Curb Inlet Protection Block and gravel curb inlet protection is a barrier formed around a curb inlet with concrete blocks and  gravel. See Figure II-3.18: Block and Gravel Curb Inlet Protection. Design and installation spe- cifications for block and gravel curb inlet protection include:  l Use wire mesh with ½-inch openings.  l Place two concrete blocks on their sides abutting the curb at either side of the inlet opening.  These are spacer blocks.  l Place a 2x4 stud through the outer holes of each spacer block to align the front blocks.  l Place blocks on their sides across the front of the inlet and abutting the spacer blocks.  l Place wire mesh over the outside vertical face.  l Pile coarse aggregate against the wire to the top of the barrier. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 361 Figure II-3.18: Block and Gravel Curb Inlet Protection   2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 362 Curb and Gutter Sediment Barrier Curb and gutter sediment barrier is a sandbag or rock berm (riprap and aggregate) 3 feet high and 3  feet wide in a horseshoe shape. See Figure II-3.19: Curb and Gutter Barrier. Design and installation  specifications for curb and gutter sediment barrier include:  l Construct a horseshoe shaped berm, faced with coarse aggregate if using riprap, 3 feet high  and 3 feet wide, at least 2 feet from the inlet.  l Construct a horseshoe shaped sedimentation trap on the upstream side of the berm. Size the  trap to sediment trap standards for protecting a culvert inlet. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 363 Figure II-3.19: Curb and Gutter Barrier 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 364 Maintenance Standards  l Inspect all forms of inlet protection frequently, especially after storm events. Clean and  replace clogged catch basin filters. For rock and gravel filters, pull away the rocks from the  inlet and clean or replace. An alternative approach would be to use the clogged rock as fill and  put fresh rock around the inlet.  l Do not wash sediment into storm drains while cleaning. Spread all excavated material evenly  over the surrounding land area or stockpile and stabilize as appropriate. Approved as Functionally Equivalent Ecology has approved products as able to meet the requirements of this BMP. The products did not  pass through the Technology Assessment Protocol – Ecology (TAPE) process. Local jurisdictions  may choose not to accept these products, or may require additional testing prior to consideration for  local use. Products that Ecology has approved as functionally equivalent are available for review on  Ecology’s website at:  https://ecology.wa.gov/Regulations-Permits/Guidance-technical-assistance/Stormwater-per- mittee-guidance-resources/Emerging-stormwater-treatment-technologies BMP C231: Brush Barrier Purpose The purpose of brush barriers is to reduce the transport of coarse sediment from a construction site  by providing a temporary physical barrier to sediment and reducing the runoff velocities of overland  flow. Conditions of Use  l Brush barriers may be used downslope of disturbed areas that are less than one-quarter acre.  l Brush barriers are not intended to treat concentrated flows, nor are they intended to treat sub- stantial amounts of overland flow. Any concentrated flows must be directed to a sediment trap- ping BMP. The only circumstance in which overland flow can be treated solely by a brush  barrier, rather than by a sediment trapping BMP, is when the area draining to the barrier is  small.  l Brush barriers should only be installed on contours. Design and Installation Specifications  l Height: 2 feet (minimum) to 5 feet (maximum).  l Width: 5 feet at base (minimum) to 15 feet (maximum).  l Filter fabric (geotextile) may be anchored over the brush berm to enhance the filtration ability  of the barrier. Ten-ounce burlap is an adequate alternative to filter fabric. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 365 BMP C233: Silt Fence Purpose Silt fence reduces the transport of coarse sediment from a construction site by providing a temporary  physical barrier to sediment and reducing the runoff velocities of overland flow. Conditions of Use Silt fence may be used downslope of all disturbed areas.  l Silt fence shall prevent sediment carried by runoff from going beneath, through, or over the  top of the silt fence, but shall allow the water to pass through the fence.  l Silt fence is not intended to treat concentrated flows, nor is it intended to treat substantial  amounts of overland flow. Convey any concentrated flows through the drainage system to a  sediment trapping BMP.  l Do not construct silt fences in streams or use in V-shaped ditches. Silt fences do not provide  an adequate method of silt control for anything deeper than sheet or overland flow. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 370 Figure II-3.22: Silt Fence 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 371 Design and Installation Specifications  l Use in combination with other construction stormwater BMPs.  l Maximum slope steepness (perpendicular to the silt fence line) 1H:1V.  l Maximum sheet or overland flow path length to the silt fence of 100 feet.  l Do not allow flows greater than 0.5 cfs.  l Use geotextile fabric that meets the following standards. All geotextile properties listed below  are minimum average roll values (i.e., the test result for any sampled roll in a lot shall meet or  exceed the values shown in Table II-3.11: Geotextile Fabric Standards for Silt Fence): Geotextile Property Minimum Average Roll Value Polymeric  Mesh AOS  (ASTM D4751) 0.60 mm maximum for slit film  woven (#30 sieve).  0.30 mm  maximum for all other geotextile types (#50 sieve).  0.15 mm minimum for all fabric types (#100 sieve). Water  Permittivity  (ASTM D4491) 0.02 sec-1 minimum Grab  Tensile Strength  (ASTM D4632) 180 lbs. Minimum for extra  strength fabric.  100 lbs  minimum for standard strength fabric. Grab Tensile Strength  (ASTM D4632) 30% maximum Ultraviolet  Resistance  (ASTM D4355) 70%  minimum Table II-3.11: Geotextile Fabric Standards for Silt Fence  l Support standard strength geotextiles with wire mesh, chicken wire, 2-inch x 2-inch wire,  safety fence, or jute mesh to increase the strength of the geotextile. Silt fence materials are  available that have synthetic mesh backing attached.  l Silt fence material shall contain ultraviolet ray inhibitors and stabilizers to provide a minimum  of six months of expected usable construction life at a temperature range of 0°F to 120°F.  l One-hundred percent biodegradable silt fence is available that is strong, long lasting, and can  be left in place after the project is completed, if permitted by the local jurisdiction.  l Refer to Figure II-3.22: Silt Fence for standard silt fence details. Include the following Stand- ard Notes for silt fence on construction plans and specifications:  1. The Contractor shall install and maintain temporary silt fences at the locations shown in  the Plans.  2. Construct silt fences in areas of clearing, grading, or drainage prior to starting those  activities. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 372  3. The silt fence shall have a 2-feet min. and a 2½-feet max. height above the original  ground surface.  4. The geotextile fabric shall be sewn together at the point of manufacture to form fabric  lengths as required. Locate all sewn seams at support posts. Alternatively, two sections  of silt fence can be overlapped, provided  that the overlap is long enough and that the  adjacent silt fence sections are close enough together to prevent silt laden water from  escaping through the fence at the overlap.  5. Attach the geotextile fabric on the up-slope side of the posts and secure with staples,  wire, or in accordance with the manufacturer's recommendations. Attach the geotextile  fabric to the posts in a manner that reduces the potential for tearing.  6. Support the geotextile fabric with wire or plastic mesh, dependent on the properties of  the geotextile selected for use. If wire or plastic mesh is used, fasten the mesh securely  to the up-slope side of the posts with the geotextile fabric up-slope of the mesh.  7. Mesh support, if used, shall consist of steel wire with a maximum mesh spacing of 2- inches, or a prefabricated polymeric mesh. The strength of the wire or polymeric mesh  shall be equivalent to or greater than 180 lbs. grab tensile strength. The polymeric mesh  must be as resistant to the same level of ultraviolet radiation as the geotextile fabric it  supports.  8. Bury the bottom of the geotextile fabric 4-inches min. below the ground surface. Backfill  and tamp soil in place over the buried portion of the geotextile fabric, so that no flow can  pass beneath the silt fence and scouring cannot occur. When wire or polymeric back-up  support mesh is used, the wire or polymeric mesh shall extend into the ground 3-inches  min.  9. Drive or place the silt fence posts into the ground 18-inches min. A 12–inch min. depth  is allowed if topsoil or other soft subgrade soil is not present and 18-inches cannot be  reached. Increase fence post min. depths by 6 inches if the fence is located on slopes of  3H:1V or steeper and the slope is perpendicular to the fence. If required post depths  cannot be obtained, the posts shall be adequately secured by bracing or guying to pre- vent overturning of the fence due to sediment loading.  10. Use wood, steel or equivalent posts. The spacing of the support posts shall be a max- imum of 6-feet. Posts shall consist of either:  l Wood with minimum dimensions of 2 inches by 2 inches by 3 feet. Wood shall be  free of defects such as knots, splits, or gouges.  l No. 6 steel rebar or larger.  l ASTM A 120 steel pipe with a minimum diameter of 1-inch.  l U, T, L, or C shape steel posts with a minimum weight of 1.35 lbs./ft.  l Other steel posts having equivalent strength and bending resistance to the post  sizes listed above.  11. Locate silt fences on contour as much as possible, except at the ends of the fence,  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 373 where the fence shall be turned uphill such that the silt fence captures the runoff water  and prevents water from flowing around the end of the fence.  12. If the fence must cross contours, with the exception of the ends of the fence, place  check dams perpendicular to the back of the fence to minimize concentrated flow and  erosion. The slope of the fence line where contours must be crossed shall not be  steeper than 3H:1V.  l Check dams shall be approximately 1-foot deep at the back of the fence. Check  dams shall be continued perpendicular to the fence at the same elevation until  the top of the check dam intercepts the ground surface behind the fence.  l Check dams shall consist of crushed surfacing base course, gravel backfill for  walls, or shoulder ballast. Check dams shall be located every 10 feet along the  fence where the fence must cross contours.  l Refer to Figure II-3.23: Silt Fence Installation by Slicing Method for slicing method details. The  following are specifications for silt fence installation using the slicing method:  1. The base of both end posts must be at least 2- to 4-inches above the top of the geo- textile fabric on the middle posts for ditch checks to drain properly. Use a hand level or  string level, if necessary, to mark base points before installation.  2. Install posts 3- to 4-feet apart in critical retention areas and 6- to 7-feet apart in standard  applications.  3. Install posts 24-inches deep on the downstream side of the silt fence, and as close as  possible to the geotextile fabric, enabling posts to support the geotextile fabric from  upstream water pressure.  4. Install posts with the nipples facing away from the geotextile fabric.  5. Attach the geotextile fabric to each post with three ties, all spaced within the top 8- inches of the fabric. Attach each tie diagonally 45 degrees through the fabric, with each  puncture at least 1-inch vertically apart. Each tie should be positioned to hang on a post  nipple when tightening to prevent sagging.  6. Wrap approximately 6-inches of the geotextile fabric around the end posts and secure  with 3 ties.  7. No more than 24-inches of a 36-inch geotextile fabric is allowed above ground level.  8. Compact the soil immediately next to the geotextile fabric with the front wheel of the  tractor, skid steer, or roller exerting at least 60 pounds per square inch. Compact the  upstream side first and then each side twice for a total of four trips. Check and correct  the silt fence installation for any deviation before compaction. Use a flat-bladed shovel  to tuck the fabric deeper into the ground if necessary. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 374 Figure II-3.23: Silt Fence Installation by Slicing Method 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 375 Maintenance Standards  l Repair any damage immediately.  l Intercept and convey all evident concentrated flows uphill of the silt fence to a sediment trap- ping BMP.  l Check the uphill side of the silt fence for signs of the fence clogging and acting as a barrier to  flow and then causing channelization of flows parallel to the fence. If this occurs, replace the  fence and remove the trapped sediment.  l Remove sediment deposits when the deposit reaches approximately one-third the height of  the silt fence, or install a second silt fence.  l Replace geotextile fabric that has deteriorated due to ultraviolet breakdown. BMP C234: Vegetated Strip Purpose Vegetated strips reduce the transport of coarse sediment from a construction site by providing a  physical barrier to sediment and reducing the runoff velocities of overland flow. Conditions of Use  l Vegetated strips may be used downslope of all disturbed areas.  l Vegetated strips are not intended to treat concentrated flows, nor are they intended to treat  substantial amounts of overland flow. Any concentrated flows must be conveyed through the  drainage system to BMP C241:  Sediment Pond (Temporary) or other sediment trapping  BMP. The only circumstance in which overland flow can be treated solely by a vegetated strip,  rather than by a sediment trapping BMP, is when the following criteria are met (see Table II- 3.12: Contributing Drainage Area for Vegetated Strips): Average Contributing Area Slope Average Contributing Area Per- cent Slope Max Contributing area Flowpath Length 1.5H : 1V or flatter 67% or flatter 100 feet 2H : 1V or  flatter 50% or flatter 115 feet 4H : 1V or  flatter 25% or flatter 150  feet 6H : 1V or  flatter 16.7% or flatter 200  feet 10H : 1V or  flatter 10% or flatter 250  feet Table II-3.12: Contributing Drainage Area for Vegetated Strips 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 376 Design and Installation Specifications  l The vegetated strip shall consist of a continuous strip of dense vegetation with topsoil for a min- imum of a 25-foot length along the flowpath. Grass-covered, landscaped areas are generally  not adequate because the volume of sediment overwhelms the grass. Ideally, vegetated strips  shall consist of undisturbed native growth with a well-developed soil that allows for infiltration  of runoff.  l The slope within the vegetated strip shall not exceed 4H:1V.  l The uphill boundary of the vegetated strip shall be delineated with clearing limits. Maintenance Standards  l Any areas damaged by erosion or construction activity shall be seeded immediately and pro- tected by mulch.  l If more than 5 feet of the original vegetated strip width has had vegetation removed or is being  eroded, sod must be installed.  l If there are indications that concentrated flows are traveling across the vegetated strip, storm- water runoff controls must be installed to reduce the flows entering the vegetated strip, or addi- tional perimeter protection must be installed. BMP C235: Wattles Purpose Wattles are temporary erosion and sediment control barriers consisting of straw, compost, or other  material that is wrapped in netting made of natural plant fiber or similar encasing material. They  reduce the velocity and can spread the flow of rill and sheet runoff, and can capture and retain sed- iment. Conditions of Use  l Wattles shall consist of cylinders of plant material such as weed-free straw, coir, wood chips,  excelsior, or wood fiber or shavings encased within netting made of natural plant fibers  unaltered by synthetic materials.  l Use wattles:  o In disturbed areas that require immediate erosion protection.  o On exposed soils during the period of short construction delays, or over winter months.  o On slopes requiring stabilization until permanent vegetation can be established.  l The material used dictates the effectiveness period of the wattle. Generally, wattles are effect- ive for one to two seasons. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 377  l Prevent rilling beneath wattles by entrenching and overlapping wattles to prevent water from  passing between them. Design Criteria  l See Figure II-3.24: Wattles for typical construction details.  l Wattles are typically 8 to 10 inches in diameter and 25 to 30 feet in length.   l Install wattles perpendicular to the flow direction and parallel to the slope contour.  l Place wattles in shallow trenches, staked along the contour of disturbed or newly constructed  slopes. Dig narrow trenches across the slope (on contour) to a depth of 3- to 5-inches on clay  soils and soils with gradual slopes. On loose soils, steep slopes, and areas with high rainfall,  the trenches should be dug to a depth of 5- to 7- inches, or 1/2 to 2/3 of the thickness of the  wattle.  l Start building trenches and installing wattles from the base of the slope and work up. Spread  excavated material evenly along the uphill slope and compact it using hand tamping or other  methods.  l Construct trenches at intervals of 10- to 25-feet depending on the steepness of the slope, soil  type, and rainfall. The steeper the slope the closer together the trenches.  l Install the wattles snugly into the trenches and overlap the ends of adjacent wattles 12 inches  behind one another.  l Install stakes at each end of the wattle, and at 4-foot centers along entire length of wattle.  l If required, install pilot holes for the stakes using a straight bar to drive holes through the wattle  and into the soil.  l Wooden stakes should be approximately 0.75 x 0.75 x 24 inches min. Willow cuttings or 3/8- inch rebar can also be used for stakes.  l Stakes should be driven through the middle of the wattle, leaving 2 to 3 inches of the stake pro- truding above the wattle. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 378 Figure II-3.24: Wattles 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 379 Maintenance Standards  l Wattles may require maintenance to ensure they are in contact with soil and thoroughly  entrenched, especially after significant rainfall on steep sandy soils.  l Inspect the slope after significant storms and repair any areas where wattles are not tightly  abutted or water has scoured beneath the wattles. Approved as Functionally Equivalent Ecology has approved products as able to meet the requirements of this BMP. The products did not  pass through the Technology Assessment Protocol – Ecology (TAPE) process. Local jurisdictions  may choose not to accept these products, or may require additional testing prior to consideration for  local use. Products that Ecology has approved as functionally equivalent are available for review on  Ecology’s website at:  https://ecology.wa.gov/Regulations-Permits/Guidance-technical-assistance/Stormwater-per- mittee-guidance-resources/Emerging-stormwater-treatment-technologies BMP C236: Vegetative Filtration Purpose Vegetative filtration as a BMP is used in conjunction with detention storage in the form of portable  tanks or BMP C241:  Sediment Pond (Temporary), BMP C206:  Level Spreader, and a pumping sys- tem with surface intake. Vegetative filtration improves turbidity levels of stormwater discharges by fil- tering runoff through existing vegetation where undisturbed forest floor duff layer or established lawn  with thatch layer are present.  Vegetative filtration can also be used to infiltrate dewatering waste  from foundations, vaults, and trenches as long as runoff does not occur. Conditions of Use  l For every five acres of disturbed soil use one acre of grass field, farm pasture, or wooded  area. Reduce or increase this area depending on project size, ground water table height, and  other site conditions.  l Wetlands shall not be used for vegetative filtration.  l Do not use this BMP in areas with a high ground water table, or in areas that will have a high  seasonal ground water table during the use of this BMP.  l This BMP may be less effective on soils that prevent the infiltration of the water, such as hard  till.  l Using other effective source control measures throughout a construction site will prevent the  generation of additional highly turbid water and may reduce the time period or area need for  this BMP.  l Stop distributing water into the vegetated filtration area if standing water or erosion results. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 380 system) will be directed into the permanent Flow Control BMP. If site constraints make locating the  untreated stormwater storage pond difficult, the permanent Flow Control BMP may be divided to  serve as the untreated stormwater storage pond and the post-treatment temporary flow control  pond. A berm or barrier must be used in this case so the untreated water does not mix with the  treated water. Both untreated stormwater storage requirements, and adequate post-treatment flow  control must be achieved. The designer must document in the Construction SWPPP how the per- manent Flow Control BMP is able to attenuate the discharge from the site to meet the requirements  of Element 3: Control Flow Rates. If the design of the permanent Flow Control BMP was modified  for temporary construction flow control purposes, the construction of the permanent Flow Control  BMP must be finalized, as designed for its permanent function, at project completion. Maintenance Standards  l Rapid sand filters typically have automatic backwash systems that are triggered by a pre-set  pressure drop across the filter. If the backwash water volume is not large or substantially more  turbid than the untreated stormwater stored in the holding pond or tank, backwash return to  the untreated stormwater pond or tank may be appropriate. However, other means of treat- ment and disposal may be necessary.  l Screen, bag, and fiber filters must be cleaned and/or replaced when they become clogged.  l Sediment shall be removed from the storage and/or treatment ponds as necessary. Typically,  sediment removal is required once or twice during a wet season and at the decommissioning  of the ponds.  l Disposal of filtration equipment must comply with applicable local, state, and federal reg- ulations. BMP C252: Treating and Disposing of High pH Water Purpose When pH levels in stormwater rise above 8.5, it is necessary to lower the pH levels to the acceptable  range of 6.5 to 8.5 prior to discharge to surface or ground water. A pH level range of 6.5 to 8.5 is typ- ical for most natural watercourses, and this neutral pH range is required for the survival of aquatic  organisms. Should the pH rise or drop out of this range, fish and other aquatic organisms may  become stressed and may die. Conditions of Use  l The water quality standard for pH in Washington State is in the range of 6.5 to 8.5. Storm- water with pH levels exceeding water quality standards may be either neutralized on site or  disposed of  to a sanitary sewer or concrete batch plant with pH neutralization capabilities.  l Neutralized stormwater may be discharged to surface waters under the Construction Storm- water General permit.  l Neutralized process water such as concrete truck wash-out, hydro-demolition, or saw-cutting  slurry must be managed to prevent discharge to surface waters. Any stormwater  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 406 contaminated during concrete work is considered process wastewater and must not be dis- charged to waters of the State or stormwater collection systems.  l The process used for neutralizing and/or disposing of high pH stormwater from the site must  be documented in the Construction Stormwater Pollution Prevention Plan. Causes of High pH High pH at construction sites is most commonly caused by the contact of stormwater with poured or  recycled concrete, cement, mortars, and other Portland cement or lime containing construction  materials. (See BMP C151: Concrete Handling for more information on concrete handling pro- cedures). The principal caustic agent in cement is calcium hydroxide (free lime). Calcium hardness can contribute to high pH values and cause toxicity that is associated with high pH  conditions. A high level of calcium hardness in waters of the state is not allowed. Ground water stand- ard for calcium and other dissolved solids in Washington State is less than 500 mg/l. Treating High pH Stormwater by Carbon Dioxide Sparging Advantages of Carbon Dioxide Sparging  l Rapidly neutralizes high pH water.  l Cost effective and safer to handle than acid compounds.  l CO2 is self-buffering. It is difficult to overdose and create harmfully low pH levels.  l Material is readily available. The Chemical Process of Carbon Dioxide Sparging When carbon dioxide (CO2) is added to water (H2O), carbonic acid (H2CO3) is formed which can  further dissociate into a proton (H+) and a bicarbonate anion (HCO3-) as shown below: CO2 + H2O ↔ H2CO3 ↔ H+ + HCO3- The free proton is a weak acid that can lower the pH. Water temperature has an effect on the reac- tion as well. The colder the water temperature is, the slower the reaction occurs. The warmer the  water temperature is, the quicker the reaction occurs. Most construction applications in Washington  State have water temperatures in the 50°F or higher range so the reaction is almost simultaneous. The Treatment Process of Carbon Dioxide Sparging High pH water may be treated using continuous treatment, continuous discharge systems. These  manufactured systems continuously monitor influent and effluent pH to ensure that pH values are  within an acceptable range before being discharged. All systems must have fail safe automatic shut  off switches in the event that pH is not within the acceptable discharge range. Only trained operators  may operate manufactured systems. System manufacturers often provide trained operators or train- ing on their devices. The following procedure may be used when not using a continuous discharge system: 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 407  1. Prior to treatment, the appropriate jurisdiction should be notified in accordance with the reg- ulations set by the jurisdiction.  2. Every effort should be made to isolate the potential high pH water in order to treat it separately  from other stormwater on-site.  3. Water should be stored in an acceptable storage facility, detention pond, or containment cell  prior to pH treatment.  4. Transfer water to be treated for pH to the pH treatment structure. Ensure that the pH treat- ment structure size is sufficient to hold the amount of water that is to be treated. Do not fill the  pH treatment structure completely, allow at least 2 feet of freeboard.  5. The operator samples the water within the pH treatment structure for pH and notes the clarity  of the water. As a rule of thumb, less CO2 is necessary for clearer water. The results of the  samples and water clarity observations should be recorded.  6. In the pH treatment structure, add CO2 until the pH falls into the range of 6.9-7.1. Adjusting  pH to within 0.2 pH units of receiving water (background pH) is recommended. It is unlikely  that pH can be adjusted to within 0.2 pH units using dry ice. Compressed carbon dioxide gas  should be introduced to the water using a carbon dioxide diffuser located near the bottom of  the pH treatment structure, this will allow carbon dioxide to bubble up through the water and  diffuse more evenly.  7. Slowly discharge the water, making sure water does not get stirred up in the process. Release  about 80% of the water from the pH treatment structure leaving any sludge behind. If turbidity  remains above the maximum allowable, consider adding filtration to the treatment train. See  BMP C251:  Construction Stormwater Filtration.  8. Discharge treated water through a pond or drainage system.  9. Excess sludge needs to be disposed of properly as concrete waste. If several batches of  water are undergoing pH treatment, sludge can be left in the treatment structure for the next  batch treatment. Dispose of sludge when it fills 50% of the treatment structure volume.  10. Disposal must comply with applicable local, state, and federal regulations. Treating High pH Stormwater by Food Grade Vinegar Food grade vinegar that meets FDA standards may be used to neutralize high pH water. Food  grade vinegar is only 4% to 18% acetic acid with the remainder being water.  Food grade vinegar  may be used if dosed just enough to lower pH sufficiently. Use a treatment process as described  above for CO2 sparging, but add food grade vinegar instead of CO2. This treatment option for high pH stormwater does not apply to anything but food grade vinegar.  Acetic acid does not equal vinegar. Any other product or waste containing acetic acid must go  through the evaluation process in Appendix G of Whole Effluent Toxicity Testing Guidance and Test Review Criteria (Marshall, 2016).  2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 408 Disposal of High pH Stormwater Sanitary Sewer Disposal Local sewer authority approval is required prior to disposal via the sanitary sewer. Concrete Batch Plant Disposal  l Only permitted facilities may accept high pH water.  l Contact the facility to ensure they can accept the high pH water. Maintenance Standards Safety and materials handling:  l All equipment should be handled in accordance with OSHA rules and regulations.  l Follow manufacturer guidelines for materials handling. Each operator should provide:  l A diagram of the monitoring and treatment equipment.  l A description of the pumping rates and capacity the treatment equipment is capable of treat- ing. Each operator should keep a written record of the following:  l Client name and phone number.  l Date of treatment.  l Weather conditions.  l Project name and location.  l Volume of water treated.  l pH of untreated water.  l Amount of CO2 or food grade vinegar needed to adjust water to a pH range of 6.9-7.1.  l pH of treated water.  l Discharge point location and description. A copy of this record should be given to the client/contractor who should retain the record for three  years. 2019 Stormwater Management Manual for Western Washington Volume II -Chapter 3 -Page 409 P a g e | 35 C. Correspondence Department of Ecology – Northwest Regional Office 3190 160th Avenue SE Bellevue, WA 98008 425-649-7000 City of Renton – Public Works 11055 S Grandy Way Renton, WA 98057 425-430-7400 P a g e | 36 D. Site Inspection Form Construction Stormwater Site Inspection Form Page 1 Project Name MSCR-SBB Permit # 307268 Inspection Date Time Name of Certified Erosion Sediment Control Lead (CESCL) or qualified inspector if less than one acre Print Name: Approximate rainfall amount since the last inspection (in inches): Approximate rainfall amount in the last 24 hours (in inches): Current Weather Clear Cloudy Mist Rain Wind Fog A. Type of inspection: Weekly Post Storm Event Other B. Phase of Active Construction (check all that apply): Pre Construction/installation of erosion/sediment controls Clearing/Demo/Grading Infrastructure/storm/roads Concrete pours Vertical Construction/buildings Utilities Offsite improvements Site temporary stabilized Final stabilization C. Questions: 1. Were all areas of construction and discharge points inspected? Yes No 2. Did you observe the presence of suspended sediment, turbidity, discoloration, or oil sheen Yes No 3. Was a water quality sample taken during inspection? (refer to permit conditions S4 & S5) Yes No 4. Was there a turbid discharge 250 NTU or greater, or Transparency 6 cm or less? * Yes No 5. If yes to #4 was it reported to Ecology? Yes No 6. Is pH sampling required? pH range required is 6.5 to 8.5. Yes No If answering yes to a discharge, describe the event. Include when, where, and why it happened; what action was taken, and when. *If answering yes to # 4 record NTU/Transparency with continual sampling daily until turbidity is 25 NTU or less/ transparency is 33 cm or greater. Sampling Results: Date: 6/20/19 Parameter Method (circle one) Result Other/Note NTU cm pH Turbidity tube, meter, laboratory pH Paper, kit, meter Construction Stormwater Site Inspection Form Page 2 D. Check the observed status of all items. Provide “Action Required “details and dates. Element # Inspection BMPs Status Good/Ok/Bad BMP Commentary BMP failed Action required (describe in section F) G Ok B 1 Clearing Limits Before beginning land disturbing activities are all clearing limits, natural resource areas (streams, wetlands, buffers, trees) protected with barriers or similar BMPs? (high visibility recommended) 2 Construction Access Construction access is stabilized with quarry spalls or equivalent BMP to prevent sediment from being tracked onto roads? Sediment tracked onto the roadway was cleaned thoroughly at the end of the day or more frequent as necessary. 3 Control Flow Rates Are flow control measures installed to control stormwater volumes and velocity during construction and do they protect downstream properties and waterways from erosion? If permanent infiltration ponds are used for flow control during construction, are they protected from siltation? 4 Sediment Controls All perimeter sediment controls (e.g. silt fence, wattles, compost socks, berms, etc.) installed, and maintained in accordance with the Stormwater Pollution Prevention Plan (SWPPP). Sediment control BMPs (sediment ponds, traps, filters etc.) have been constructed and functional as the first step of grading. Stormwater runoff from disturbed areas is directed to sediment removal BMP. 5 Stabilize Soils Have exposed un-worked soils been stabilized with effective BMP to prevent erosion and sediment deposition? Construction Stormwater Site Inspection Form Page 3 Element # Inspection BMPs Status Good/Ok/Bad BMP needs maintenance BMP failed Action required (describe in section F) G Ok B 5 Stabilize Soils Cont. Are stockpiles stabilized from erosion, protected with sediment trapping measures and located away from drain inlet, waterways, and drainage channels? Have soils been stabilized at the end of the shift, before a holiday or weekend if needed based on the weather forecast? 6 Protect Slopes Has stormwater and ground water been diverted away from slopes and disturbed areas with interceptor dikes, pipes and or swales? Is off-site storm water managed separately from stormwater generated on the site? Is excavated material placed on uphill side of trenches consistent with safety and space considerations? Have check dams been placed at regular intervals within constructed channels that are cut down a slope? 7 Drain Inlets Storm drain inlets made operable during construction and are protected. Are existing storm drains within the influence of the project protected? 8 Stabilize Channel and Outlets Have all on-site conveyance channels been designed, constructed and stabilized to prevent erosion from expected peak flows? Is stabilization, including armoring material, adequate to prevent erosion of outlets, adjacent stream banks, slopes and downstream conveyance systems? 9 Control Pollutants Are waste materials and demolition debris handled and disposed of to prevent contamination of stormwater? Has cover been provided for all chemicals, liquid products, petroleum products, and other material? Has secondary containment been provided capable of containing 110% of the volume? Were contaminated surfaces cleaned immediately after a spill incident? Were BMPs used to prevent contamination of stormwater by a pH modifying sources? Construction Stormwater Site Inspection Form Page 4 Element # Inspection BMPs Status Good/Ok/Bad BMP needs maintenance BMP failed Action required (describe in section F) G Ok B 9 Cont. Wheel wash wastewater is handled and disposed of properly. 10 Control Dewatering Concrete washout in designated areas. No washout or excess concrete on the ground. Dewatering has been done to an approved source and in compliance with the SWPPP. Were there any clean non turbid dewatering discharges? 11 Maintain BMP Are all temporary and permanent erosion and sediment control BMPs maintained to perform as intended? 12 Manage the Project Has the project been phased to the maximum degree practicable? Has regular inspection, monitoring and maintenance been performed as required by the permit? Has the SWPPP been updated, implemented and records maintained? 13 Protect LID Is all Bioretention and Rain Garden Facilities protected from sedimentation with appropriate BMPs? Is the Bioretention and Rain Garden protected against over compaction of construction equipment and foot traffic to retain its infiltration capabilities? Permeable pavements are clean and free of sediment and sediment laden- water runoff. Muddy construction equipment has not been on the base material or pavement. Have soiled permeable pavements been cleaned of sediments and pass infiltration test as required by stormwater manual methodology? Heavy equipment has been kept off existing soils under LID facilities to retain infiltration rate. Construction Stormwater Site Inspection Form Page 5 E. Check all areas that have been inspected. All in place BMPs All disturbed soils All concrete wash out area All material storage areas All discharge locations All equipment storage areas All construction entrances/exits F. Elements checked “Action Required” (section D) describe corrective action to be taken. List the element number; be specific on location and work needed. Document, initial, and date when the corrective action has been completed and inspected. Element # Description and Location Action Required Completion Date Initials Sign the following certification: “I certify that this report is true, accurate, and complete, to the best of my knowledge and belief” Inspected by: (print) (Signature) Date: Title/Qualification of Inspector: Construction Stormwater Site Inspection Form Page 6 Corrective Action Figures: P a g e | 37 E. Construction Stormwater General Permit (CSWGP) To be provided upon receipt of approved. P a g e | 38 F. 303(d) List Waterbodies / TMDL Waterbodies Information N/A P a g e | 39 G. Contaminated Site Information There are no suspected and/or known contaminants associated with the project site.