HomeMy WebLinkAbout7945.04 S 2023 0515Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
esnw.com
FIELD REPORT
Project No. 7945.04 Page 1 of 3 Report ID 7945.04 S 2023 0515
Date Mon 5/15/2023 Weather 77°F, Sunny
Arrival/Departure Time(s) 9:45-10:10 Travel Time (hr)0.25
Project Name Canopy Property
Location 4130 Lincoln Ave NE, Renton
ESNW Rep., CESCL No.,
Phone No. & Report Statement
Jeannie Bratulina, ECO-3-6272223, (206) 376-4906
“This report is true, accurate, and complete to the best of my knowledge and belief.”
Client Info/Contact Century Communities | Stacia Bloom
Permit No(s). WAR311273
Reviewed By JLG
Initials/Date
N/A
Asst Field Supervisor Project Manager Initials/Date
Limitations: The presence of our field representative at the site is to provide our client with a source of professional advice, opinions, and recommendations based upon the field representative’s observations and testing of the contractor’s work. Our services do not include supervision or direction of the contractor, their employees, or agents. Recommendations for obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible for complying with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations, is the sole
responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager.
Type of visit: Weekly Monthly Post–Storm Event
Precipitation since last inspection (approximate): 0.00 inches
Precipitation in last 24 hours (approximate): 0.00 inches
Phase of active construction (check all that apply):
Pre-construction Clearing, demolition, or grading Infrastructure or roads
Concrete pours Vertical construction Utilities
Off-site improvements Site temporarily stabilized Final stabilization
Was water quality sampling part of this inspection? Yes No
If “Yes”:
•Record results in the table below.
•Hanna Turbidity Meter No. 16
Monitoring
Point Monitoring Location Turbidity
(NTU) pH Description of
Discharge Notes
MP-1 Beehive on Lincoln Ave NE - - N/A
Water moved from the vault
to the Water Tectonics
treatment system on-site then
piped to beehive
Report ID 7945.04 S 2023 0515 Page 2 of 3
Earth Solutions NW, LLC
Erosion Control BMPs
(13 Elements)
Overall
Condition
(Good; Fair; Poor)
Needs
Repair?
(Yes; No)
Comments
1. Preserve Vegetation; Mark Clearing Limits
• Buffer Zones around Sensitive Areas
• Silt Fence G N
- Site perimeter marked by silt fence and chainlink
fence
- Concrete barrier blocks and high visibility fence
utilized along perimeter of NW vault excavation
2. Establish Construction Access
• Fabric; Quarry Spalls • Wheel Wash
• Sweeper Truck
G N
- Stabilized construction entrance off of Lincoln Ave
NE using quarry spalls
- Sweeper truck on-site; continue to utilize along NE 40th and Lincoln Ave NE as needed
3. Control Flow Rates • Stormwater Vault or Facility
• Straw Wattles
• Check Dams
G N - Stormwater vault at NW corner of site
- Sandbag berm utilized before slope
4. Install Sediment Controls
• Silt Fence
• Straw Bale Barriers • Vegetation
• Straw
• Sediment Ponds, Traps & Filters
• Treatment • Water Truck
F N
- Silt fence installed where needed for sediment
control
- Curb installation underway
- Majority of on-site road is freshly paved; gravel
base applied to unpaved road sections - Construction of second vault at NW corner of site
underway; quarry spalls added in various points to
control flows
5. Stabilize Soils
• Nets & Blankets
• Mulch, Bark & Rock
• Hydroseeding; Grass • Plastic Sheeting
• Stockpiles
F N
- Exposed soils are covered in plastic and anchored
down with sandbags, hydroseeded or actively
worked
- Cover any stockpiles with plastic sheeting if
unworked 7+ days
6. Protect Slopes
• Benching; Track-Walking • Pipe Slope Drains
• Plastic Sheeting; Anchors
G N - Plastic sheeting on slopes
- Upper slopes hydroseeded and covered in grass;
straw placed throughout slope where needed
7. Protect Drain Inlets
• Catch Basin Inserts G N - Inserts removed while catch basins are being
worked on; replace inserts once work is completed
8. Stabilize Channels and Outlets
• Channel Lining
• Check Dam • Outlet Protection
• Nets and Blankets
F N
- Rock-lined swales throughout site direct water from
East to West towards vault; quarry spalls scarce in a
few areas of the swale on the East side of the site,
still working as intended
9. Control Pollutants
• Chemical Storage Area Covered
• Concrete Handling G N - Storage shack on-site
- Plastic-lined concrete washout constructed at SW
corner of site
10. Control Dewatering G N - Water moved from the vault to the Water Tectonics
treatment system on-site then piped to beehive on
Lincoln Ave NE when needed
11. Maintain BMPs F N - See details below
12. Maintain SWPPP & Site Logbook G N - Available upon request
13. Protect Low-Impact Development (LID BMPs) • Bioretention Rain Garden Facilities
• Permeable Pavement - - N/A
Do existing BMPs need to be modified or removed, or do other BMPs need to be installed? Yes No
List the action items in the table below:
Element
# Description and Location Action Required Completion
Date
Report ID 7945.04 S 2023 0515 Page 3 of 3
Earth Solutions NW, LLC
BMP LEGEND
CONSTRUCTION ENTRANCE
CHAINLINK FENCE
SWALE
STORMWATER VAULT
HYDROSEEDED LOTS
PLASTIC SHEETING
STRAW
MONITORING POINT
STOCKPILE
CONCRETE WASHOUT
SILT FENCE
HIGH VISIBILITY FENCE
SANDBAG