HomeMy WebLinkAboutFINAL - Street Lighting Inspection ProcessCITY OF RENTON STREET LIGHTING INSPECTION PROCESS Street Lighting Pre-Construction Meeting Separate pre-Construction meeting will be held for the street lighting construction. City Representatives: CED Project Manager (plan reviewer) Construction Inspector Transportation Maintenance Inspector Electrical Inspector Applicant’s Representatives: Applicant or General Contractor Electrical Contractor Inspection Items 1-3 Electrical Contractor will call the City of Renton Construction Inspection phone number provided on the permit to request and schedule first inspection of street lighting. Construction Inspector will: Inspect Items 1-3 on the Street Light-Luminaire Checklist. Any punch list items will be given directly to the electrical contractor. Date and initial Street Light-Luminaire Checklist when the items are acceptable and sign off the Construction Inspection Street Lighting Inspection in Energov. Leave permit/checklist with applicant. Inspection Item 4 1. Electrical Contractor will call the City of Renton Electrical Inspection phone number provided on the permit to request and schedule Item 4 on the Street Light-Luminaire Checklist. Electrical Inspector will: Inspect Item 4 on the Street Light-Luminaire Checklist. Any code corrections items will be given directly to the electrical contractor. Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and sign off the inspection in Energov. Leave permit/checklist with applicant. Inspection Item 5 Electrical Contractor will call the City of Renton Transportation Maintenance Inspection phone number provided on the permit to request and schedule Item 5 on the Street Light-Luminaire Checklist. Transportation Maintenance Inspector will: Inspect Item 5 on the Street Light-Luminaire Checklist. Any punch list items will be given directly to the electrical contractor. Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and sign off the inspection in Energov. Leave permit/checklist in service cabinet and notify applicant that inspection has been completed. Inspection Item 6 Electrical Contractor will call the City of Renton Electrical Inspection phone number provided on the permit to request and schedule Item 6 on the Street Light-Luminaire Checklist. Electrical Inspector will: Inspect Item 6 on the Street Light-Luminaire Checklist. Any code corrections items will be given directly to the electrical contractor. Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and sign off the inspection in Energov. Leave permit/checklist with applicant, notify contractor that they can now submit application (201E) to PSE to energize street lighting, and place service approval sticker in meter base. Inspection Item 7 Electrical Contractor will: Submit PSE Application (201E) to energize lights to PSE. Call the City of Renton Electrical Inspection phone number provided on the permit to request and schedule Item 7 on the Street Light-Luminaire Checklist once lights have been energized. Electrical Inspector will: Inspect Item 7 on the Street Light-Luminaire Checklist. Any code corrections items will be given directly to the electrical contractor. Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and finalize the electrical permit in Energov. Give one copy of permit/checklist to applicant and one copy or email to Development Engineering Secretary for Energov construction permit close-out. Automated Energov email will be sent to signal Shop of street lighting completion.