April 25, 2018
Brianne Bannwarth
Development Engineering Manager
1055 S Grady Way, Renton, WA, 98033
Phone: (425)-430-7299
email: BBannwarth@Rentonwa.com
RE: Boun Short Plat, 1024 Duvall Ave NE, Renton
Dear Brianne,
Please find attached revised Site Development Plans and Technical Information Report, which
reflect the changes as requested in your review dated April 23, 2018. Our response to each
comment is shown below in bold.
Sheet C1
1. Spelling error.
Fixed.
2. Submit postmaster approval for mailbox location to the City prior to construction permit
approval.
Waiting for approval.
Sheet C2
1. Remove drafting line.
Removed.
2. Adjust sawcut line to reflect asphalt overlay.
Fixed.
Sheet C4
1. Adjust leader.
Fixed.
2. Update/revise elevations and contours in the easement plan and profile.
The surface error has been fixed. The contours and elevations for this sheet
and C7 are now correct.
Page 2 of 3
Sheet C5
1. Add line work for existing 10” City of Renton water line.
The existing water line has been extended across the street.
2. Remove mailbox location note reference.
Removed.
3. Remove note and provide mailbox approval prior to permit approval.
The note has been removed, and the new mail box note is included on C1.
4. Remove grate and note.
Removed.
5. Show solid locking lid and ladder on the east side of structure as noted in the site plan.
Revise dimensions.
The lid and ladder were moved to the proper location, and the dimensions were
updated.
6. Show access lid and ladder on east side of the structure as shown in the site plan.
The lid and ladder were moved to the proper location.
Sheet C6
1. Adjust dimension labels to show 6’.
Fixed.
Sheet C7
1. Adjust Leader.
Fixed.
2. Show and label footing drain connection points as referenced on the structural plans.
The footing drains cannot daylight or gravity to a storm system. The structural
design of the vault will be modified to work properly with these site
constraints. The structural plans will be changed before being submitted for the
vault’s separate permit.
Page 3 of 3
Technical Information Report
1. Edit bond quantity worksheet values.
All numbers gave been changed or moved accordingly.
Thank you for your time and assistance in the review of this project. Should you need any
additional information to help facilitate your review and subsequent approval of this project,
please do not hesitate to contact me at 253-301-4157 or via email at
dbudsberg@beylerconsulting.com.
Sincerely,
Beyler Consulting
Dan Budsberg, P.E.