Duvall Schedule 20170120
IDTask Mode Task Name Duration Start Finish Predecessors % Complete Resource Names1Notice to Proceed0 daysMon 6/27/16Mon 6/27/160%2PROJECT MANAGEMENT289 daysTue 5/24/16Fri 6/30/1751%3Contract Set Up5 daysMon 6/27/16Fri 7/1/161100%4Subconsultant Coordination10 daysMon 6/27/16Fri 7/8/161100%5Conference Calls265 daysMon 6/27/16Fri 6/30/17150%6Progress Meetings (8)265 daysTue 5/24/16Thu 6/1/17150%7Schedule Preparation & Updates265 daysMon 6/27/16Fri 6/30/17150%8Misc. Corrrespondence265 daysMon 6/27/16Fri 6/30/17150%9Kickoff/Walkthough0 daysWed 6/29/16Wed 6/29/161FS+2 days100%10Draft Cost Estimate10 daysWed 6/29/16Tue 7/12/169100%11Progress Report(12)265 daysMon 6/27/16Fri 6/30/17150%12SURVEYING AND BASE MAPPING45 daysMon 6/27/16Fri 8/26/16100%13Records Research10 daysMon 6/27/16Fri 7/8/161100%14APS Coordination10 daysMon 7/4/16Fri 7/15/161FS+5 days100%15Field Work15 daysMon 7/18/16Fri 8/5/1614100%16Basemap Preparation15 daysMon 8/8/16Fri 8/26/1615100%17GEOTECHNICAL ANALYSIS20 daysMon 7/18/16Fri 8/12/1690%18See Subconsultant Cost (Below)20 daysMon 7/18/16Fri 8/12/161FS+15 days90%19PUBLIC OUTREACH10 daysThu 2/9/17Wed 2/22/170%20One-on-One Meetings (3)5 daysThu 2/9/17Wed 2/15/17540%21Meeting notes5 daysThu 2/16/17Wed 2/22/17200%22DESIGN REPORT30 daysMon 8/29/16Fri 10/7/1633%23Draft Memo10 daysMon 8/29/16Fri 9/9/1616100%24Final Memo20 daysMon 9/12/16Fri 10/7/16230%25STORMWATER ANALYSIS123 daysMon 8/29/16Wed 2/15/1788%26Gather Info5 daysMon 8/29/16Fri 9/2/1616100%27Offsite Analysis5 daysMon 9/5/16Fri 9/9/1626100%28Downstream Analysis5 daysMon 9/5/16Fri 9/9/1626100%29Meeting with City0 daysFri 9/9/16Fri 9/9/1628100%30Prepare Draft TIR20 daysMon 9/12/16Fri 12/30/1652FF100%31Prepare Final TIR5 daysThu 2/9/17Wed 2/15/17540%32PRELIMINARY DESIGN118 daysMon 8/29/16Wed 2/8/1795%33Preliminary Plan & Profile10 daysMon 8/29/16Fri 9/9/1616100%34Worskshop Meeting w/City0 daysFri 9/9/16Fri 9/9/1633100%35Refine Design based on Workshop25 daysMon 9/12/16Fri 10/14/1634100%36Second Workshop Mtg w/City0 daysFri 10/21/16Fri 10/21/1635FS+5 days100%37Cover Sheet30 daysMon 10/24/16Fri 12/2/1636100%38Legend30 daysMon 10/24/16Fri 12/2/1636100%6/276/299/99/910/21SMTWTFSSMTWTFSSMTWApr 3, '16Jun 5, '16Aug 7, '16Oct 9, '16Dec 11, '16Feb 12, '17Apr 16, '17Jun 18, '17Aug TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 1Project: Duvall Schedule 201701Date: Sat 1/21/17 IDTask Mode Task Name Duration Start Finish Predecessors % Complete Resource Names39Typical Sections30 daysMon 10/24/16Fri 12/2/1636100%40Demo30 daysMon 10/24/16Fri 12/2/1636100%41Plan & Profile Sheets30 daysMon 10/24/16Fri 12/2/1636100%42Storm Drainage Plans30 daysMon 10/24/16Fri 12/2/1636100%43Storm Drainage Details30 daysMon 10/24/16Fri 12/2/1636100%44Wall Plan30 daysMon 10/24/16Fri 12/2/1636100%45Wall Profiles30 daysMon 10/24/16Fri 12/2/1636100%46Channelization, Signing & Illumination30 daysMon 10/24/16Fri 12/2/1636100%47Utility Conflict Plans20 daysMon 12/5/16Fri 12/30/1643100%48Planting Plans & Details30 daysMon 10/24/16Fri 12/2/1636100%49Draft Specifications10 daysMon 12/5/16Fri 12/16/1648100%50Preliminary Opinion of Cost10 daysMon 12/5/16Fri 12/16/1648100%51Utility Coordination Meeting0 daysFri 1/20/17Fri 1/20/1747FS+10 days100%52Submit Preliminary Plans0 daysFri 12/30/16Fri 12/30/1650FS+10 days100%53City Review25 daysMon 1/2/17Fri 2/3/175220%54Review Meeting with City0 daysWed 2/8/17Wed 2/8/1753FS+3 days0%55ENVIRONMENTAL ASSISTANCE265 daysMon 6/27/16Fri 6/30/170%56Coordinate with Widener & Assoc.265 daysMon 6/27/16Fri 6/30/1710%57BID DOCUMENTS115 daysThu 2/9/17Wed 7/19/170%58Incorporate Prelim Comments40 daysThu 2/9/17Wed 4/5/17540%59Submit 30% final plans0 daysWed 4/5/17Wed 4/5/17580%60Update Plan Sheets20 daysThu 4/6/17Wed 5/3/17580%61Update Specs20 daysThu 4/6/17Wed 5/3/17580%62Update Estimate20 daysThu 4/6/17Wed 5/3/17580%63Submit 90% PS&E0 daysWed 5/17/17Wed 5/17/1762FS+10 days0%64Review Meeting with City0 daysWed 5/31/17Wed 5/31/1763FS+10 days0%65Update PS&E15 daysThu 6/1/17Wed 6/21/17640%66Submit Final PS&E0 daysWed 6/21/17Wed 6/21/17650%67 Post to Builders Exchange0 daysWed 6/21/17Wed 6/21/17650%68Bidding Assistance20 daysThu 6/22/17Wed 7/19/17670%1/2012/302/84/55/175/316/216/21SMTWTFSSMTWTFSSMTWApr 3, '16Jun 5, '16Aug 7, '16Oct 9, '16Dec 11, '16Feb 12, '17Apr 16, '17Jun 18, '17Aug TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 2Project: Duvall Schedule 201701Date: Sat 1/21/17