Day Short Plat
7-Lot Development - SFR
18600 116th Ave SE, Renton, WA
CONSTRUCTION
MITIGATION
Proposed Construction Dates (begin and end dates): Start of construction is proposed
for the Spring of 2023. Completion of construction improvements is proposed for Fall of
2023.
Hours and days of operation: 8:00 am to 5:30 pm, Monday through Friday or as
otherwise allowed by City of Renton.
Proposed Hauling/ Transportation routes: Materials and labor will be brought to
the site from 116th Ave SE and 120th Ave SE. On-site parking and material storage
will be within the proposed SE 186th St extension and Tract A at the SE 160th Ave
entrance to the short plat. Access to the east end of the project site will be via 120th
Ave SE.
Measures to minimize construction activities: The construction activity in and
adjacent to the existing ROWs will be necessary to provide the required public and
private improvements for this project. City requires 9.5’ of ROW dedication (10’ is
being proposed) and frontage improvements along 116th Ave SE, per PRE19-000033
including providing a bike lane and installing new curb, gutter, planter strip, sidewalk
and storm drain where a paved shoulder, road ditch and driveway culverts presently
exist. It is planned to minimize public disturbance and as much as is feasible, provide
adequate pedestrian access during the new construction. Measures will be implemented
per the required DOE Construction Storm Water General Permit to minimize dust,
traffic and transportation impacts, erosion, mud, noise, and other noxious
characteristics.
Special hours: No special hours are necessary to complete construction. Weekend work
may be necessary to complete the project on schedule; this will be determined by owner,
contractor, and City of Renton.
Preliminary Traffic Control Plan: Coordination with the City of Renton staff will
be necessary to minimize disruption to vehicle and pedestrian traffic on 116th and
120th Ave SE. Once a contractor is selected, a traffic control plan will be submitted
and approved prior to the pre-construction meeting with the City of Renton. This plan
will be implemented prior to any construction activities.