Loading...
HomeMy WebLinkAboutSubmittal Transmittal-005 - Baseline CPM ScheduleIDTask ModeTask NameDuration Start FinishPredecessorsSuccessors1Project Planning12 daysWed 6/7/23Thu 6/22/232Project Start0 daysWed 6/7/23Wed 6/7/2333Project Award1 dayWed 6/7/23Wed 6/7/23244Submittals7 daysThu 6/8/23Fri 6/16/23355Preconstruction Meeting1 dayMon 6/19/23Mon 6/19/2346FS+1 day6Site Survey2 daysWed 6/21/23Thu 6/22/235FS+1 day8FS-1 day,7FS-5 days7PCMS Boards 1 dayFri 6/16/23Fri 6/16/236FS-5 days118Notice-to-Proceed1 dayThu 6/22/23Thu 6/22/236FS-1 day10FS+0.5 days,119Construction42 daysFri 6/23/23Mon 8/21/2310Construction Start0 daysFri 6/23/23Fri 6/23/238FS+0.5 days11Mobilization / TESC Setup7 daysFri 6/23/23Mon 7/3/238,712FS-6 days12Arrow Board / Traffic Control Setup 2 daysMon 6/26/23Tue 6/27/2311FS-6 days13FS-1 day13Sawcutting /Asphalt/ Conc Removal 5 daysTue 6/27/23Mon 7/3/2312FS-1 day14FS-2 days14Curb Removal / Salvage Signs 5 daysFri 6/30/23Thu 7/6/2313FS-2 days1515Electrical Trenching 4 daysFri 7/7/23Wed 7/12/231416FS-3 days16Electrical Conduit (By Others) 10 daysMon 7/10/23Fri 7/21/2315FS-3 days17FS-4 days17Push Button Upgrade 5 daysTue 7/18/23Mon 7/24/2316FS-4 days1818Grade Curb & Gutter / ADA / Sidewalk5 daysTue 7/25/23Mon 7/31/23171919Pour Curb & Gutter / ADA / Sidewalk3 daysTue 8/1/23Thu 8/3/23182020Asphalt Patching / Grind & Overlay 2 daysFri 8/4/23Mon 8/7/23192121Adjust Utilities 1 dayTue 8/8/23Tue 8/8/23202222Striping 2 daysWed 8/9/23Thu 8/10/23212323Landscape Restoration / Tree Grates 2 daysFri 8/11/23Mon 8/14/23222424Take Down Traffic Control / TESC 2 daysTue 8/15/23Wed 8/16/23232525Clean Up / Demobilization3 daysThu 8/17/23Mon 8/21/23242726Project Closeout6 daysTue 8/22/23Tue 8/29/2327Substantial Completion0 daysMon 8/21/23Mon 8/21/23252828Punch List6 daysTue 8/22/23Tue 8/29/23272929Physical Completion0 daysTue 8/29/23Tue 8/29/23286/76/238/218/29TWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWJun 4, '23Jun 11, '23Jun 18, '23Jun 25, '23Jul 2, '23Jul 9, '23Jul 16, '23Jul 23, '23Jul 30, '23Aug 6, '23Aug 13, '23Aug 20, '23Aug 27, '23Sep 3, '23TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineCriticalCritical SplitProgressManual ProgressRenton School Dist Sartori Elem School Underground Power CPM Schedule - BaselineNorthwest Cascade, Inc.Page 1Project: 4413 CPM SchDate: Tue 6/13/23