HomeMy WebLinkAboutWWP273082 (4)=a
MEMORANDUM
TO: City of Renton — Utility Systems Division
John Hobson, PE
FROM: Erik Waligorski, PE�
RE: Stonegate II Lift Station & Conveyance Design
Monthly Progress Report
COPIES: Dave Christensen; Erik Brodahl, PE; File
DATE: December 17, 2009
Roth Hill Engineering Partners, LLC
2600 116"' Avenue NE, Suite 100
Bellevue, Washington 98004
Tel. 425.869.9448
800.835.0292
Fax 425.869.1190
Project No: 0015.00018.001
Page 1 of 1
The services agreement between the City of Renton and Roth Hill for the Stonegate II Lift
Station & Conveyance Design Project was executed on January 11, 2008.
Proiect Status and Tasks Completed
Tasks 3, 4, 7-8 & 10-12 have been completed. Task 7 is shown complete although some
work may be required for the shoring and dewatering design for the lift station project.
Lift Station Design
We are continuing work on the 90% drawings. We will be ready to bid early 2010 as desired.
Outstanding Issues
We are awaiting some responses from the City with regard to electrical questions posed by
Kennedy Jenks.
Project Schedule
The design of both projects is virtually complete and we will be ready to bid the project in
February.
Project Budget Status
Refer to the attached spreadsheet entitled "Monthly Progress Report —Budget" for services for the
month of November 2009. It has been determined that our contract for this project has expired.
As such, we have been asked by the City to generate a new scope of services to complete the
design, including any additional budget required; and also including construction phase services.
That effort will be completed prior to the next billing to the City.
F:`.00 75\00018.0015PrjMgm �Status�.^roni; dy status ; epon_ l 21709.,,Oc
1
City of Renton
Stonegate II Lift Station & Conveyance Design
Monthly Progress Report --Budget Status
For Month of: Nov-09
Task
No.
Phase
No.
Description
Percent
Complete
(+/-)
Percent
Spent
Original
Budget2
Total
Services
Nov 2009'
Total
Invoices
To -Date
Budget
Remaining
1
A060
Project Management'
85%
90%
$ 47,000
$ 1,866.68
$ 42,514.80
$ 4,485.20
2
A080
QA/QC
85%
82%
$ 20,100
$ 16,558.70
$ 3,541.30
3
1 B400
Topographic Survey2
100%
100%
$ 55,800
$ 55,765.94
$ 34.06
4
B103
Facility Evaluation
100%
100%
$ 64,600
$ 64,537.27
$ 62.73
5
C109
Lift Station Design
90%
97%
$ 268,400
$ 22354.85
$ 259,136.26
$ 9,263.74
6
1 C104
Conveyance System Design2,3
95%
100%
$ 112,400
$ 112,538.07
$ (138.07)
7
D171
Geotechnical Services3
100%
99%
$ 77,150
$ 76,512.66
$ 637.34
8
D176
Wetlands/Landscaping
100%
99%
$ 31,000
$ 30:720.07
$ 279.93
9
D500
Public Outreach
75%
27%
S 7,700
$ 2,103.92
$ 5,596.08
10
D190
Acoustics/Noise Study
100%
35%
$ 13,900
$ 4,862.57
$ 9,037.43
11
D004
Easement Exhibits
100%
112%
$ 2,500
$ 2,793.13
$ 293.13)
12
E300
Permitting
100%
95%
$ 15,400
$ 14,653.99
$ 746.01
Totals 94% 95% $ 715,950 $ 4,221.53 $ 682,697.38 $ 33,252.62
Notes:
1) For services completed through the month prior to the billing month (e.g. Nov services billed in Dec).
2) Includes budget transfers of $15,700 from B103 to B400 and $18,500 from B103 to C104
3) Includes budget transfers of $18,000 from D500 to C104 and $4,000 from D500 to D171
4) Includes budget transfer of $15,000 from A060 to C109
Print Date: 12/15/2009 F:\0015\00018.001\PrjMgmt\Status\monthly budget status_nov 2009_121509.xls
Project Titl(2009 Earlington Water & Sewer Improvements
BID DATE: DATE
E Item
IN No.
Description
Unit
Est.
Quantity
1
Mobilization, Demobilization, Site Preparation & Clean-up
Lump Sum
1
2
Traffic Control
Lump Sum
1
3
Trench Excavation Safety Systems
Lump Sum
1
4
Construction Surveying, Staking, and As-Builts
Lump Sum
1
5
Temporary Erosion and Sedimentation Control
Lump Sum
1
6
Re -Establish Existing Monuments
Each
10
7
Furnish and Install 8" PVC Sewer Pipe
Lineal Foot
6,416
8
Furnish and Install 6" PVC Side Sewer Pipe
Lineal Foot
3,850
9
Furnish and Install 48" Diam. Sanitary Sewer Manhole
Each
25
10
Furnish and Install 54" Dia. Sanitary Sewer Saddle Manhole
Each
5
11
Connect New Sanitary Sewer to Existing Manhole
Each
4
12
Abandon Existing Manhole
Each
2
13
Removal and Replacement of Unsuitable Foundation Material
Ton
500
14
Television Inspection of Sanitary Sewers
Lineal Foot
6,416
15
Furnish and Install 8" Cl 52 DI Water Pipe & Fittings w/Polywre
Lineal Foot
7,300
16
Furnish and Install 8" Gate Valve Assembly
Each
44
17
Furnish and Install 12"x8" Wet -Tap Tee&Gate Valve Assembly
Each
2
18
Furnish and Install Fire Hydrant Assembly
Each
15
19
Connection to Existing Water Main
Each
10
20
Concrete for Thrust Blockings, Dead -Man Anchor Blocks
Cubic Yard
33
21
Furnish & Install 3/4" Water Service Connection
Each
130
22
Select Imported Trench Backfill
Ton
24,000
23
Crushed Rocks for Shoulder Restoration
Ton
200
24
H.M.A. Class ''/2" PG 64-22 for Roadway Reconstruction includ
Square -Yard
22,000
25
Temporary Hot Mix Asphalt (HMA) for Trench Patching
Square -Yard
10,000
26
Removal and Replacement of Concrete Curb and Gutter
Lineal Foot
100
27
Replace Traffic Loop Sensor,Pavement Markings &Traffic Butt
Lump Sum
1
28
Concrete Driveway and/or Sidewalk Restoration
Square -Yard
400
29
Property & Landscape Restoration
Lump Sum
1
City of Renton Laser Underground
Engineers Estimate
Unit
Bid
Unit
Bid
Price
Amount
Price
Amount
50,000.00
50,000.00
194,000.00
194,000.00
20,000.00
20,000.00
15,000.00
15,000.00
15, 000.00
15, 000.00
10,000.00
10, 000.00
15, 000.00
15, 000.00
15, 000.00
15, 000.00
5,000.00
5,000.00
5,000.00
5,000.00
1,000.00
10,000.00
500.00
5,000.00
85.00
545,360.00
65.00
417,040.00
70.00
269,500.00
45.00
173,250.00
5,500.00
137,500.00
4,000.00
100,000.00
6,000.00
30,000.00
4,500.00
22,500.00
1,000.00
4,000.00
3,000.00
12,000.00
1,000.00
2,000.00
500.00
1,000.00
20.00
10,000.00
1.00
500.00
2.00
12,832.00
1.00
6,416.00
80.00
584,000.00
35.00
255,500.00
1,000.00
44,000.00
800.00
35,200.00
4,000.00
8,000.00
3,500.00
7,000.00
6,000.00
90,000.00
3,500.00
52,500.00
7,000.00
70,000.00
2,000.00
20,000.00
300.00
9,900.00
250.00
8,250.00
4,000.00
520,000.00
1,200.00
156,000.00
15.00
360,000.00
0.01
240.00
20.00
4,000.00
40.00
8,000.00
15.00
330,000.00
18.00
396,000.00
12.00
120, 000.00
1.00
10, 000.00
20.00
2,000.00
20.00
2,000.00
3,000.00
3,000.00
3,500.00
3,500.00
200.00
80,000.00
35.00
14,000.00
5,000.00
5,000.00
30,000.00
30,000.00
Subtotal
$3,356,092.00
Subtotal
$1,974,896.00
Tax 8.8%
$318,828.74
Tax
$187,615.12
Total
$3,674,920.74
Total
$2,162,511.12
Project Titl(2009 Earlington Water & Sewer Improvements II R.L. Alia Pivetta Brothers
BID DATE: DATE
E Item
� No.
Description
Unit
Est.
Quantity
1
Mobilization, Demobilization, Site Preparation & Clean-up
Lump Sum
1
2
Traffic Control
Lump Sum
1
3
Trench Excavation Safety Systems
Lump Sum
1
4
Construction Surveying, Staking, and As-Builts
Lump Sum
1
5
Temporary Erosion and Sedimentation Control
Lump Sum
1
6
Re -Establish Existing Monuments
Each
10
7
Furnish and Install 8" PVC Sewer Pipe
Lineal Foot
6,416
8
Furnish and Install 6" PVC Side Sewer Pipe
Lineal Foot
3,850
9
Furnish and Install 48" Diam. Sanitary Sewer Manhole
Each
25
10
Furnish and Install 54" Dia. Sanitary Sewer Saddle Manhole
Each
5
11
Connect New Sanitary Sewer to Existing Manhole
Each
4
12
Abandon Existing Manhole
Each
2
13
Removal and Replacement of Unsuitable Foundation Material
Ton
500
14
Television Inspection of Sanitary Sewers
Lineal Foot
6,416
15
Furnish and Install 8" Cl 52 DI Water Pipe & Fittings w/Polywr2
Lineal Foot
7,300
16
Furnish and Install 8" Gate Valve Assembly
Each
44
17
Furnish and Install 12"x8" Wet -Tap Tee&Gate Valve Assembly
Each
2
18
Furnish and Install Fire Hydrant Assembly
Each
15
19
Connection to Existing Water Main
Each
10
20
Concrete for Thrust Blockings, Dead -Man Anchor Blocks
Cubic Yard
33
21
Furnish & Install 3/4" Water Service Connection
Each
130
22
Select Imported Trench Backfill
Ton
24,000
23
Crushed Rocks for Shoulder Restoration
Ton
200
24
H.M.A. Class %' PG 64-22 for Roadway Reconstruction includ
Square -Yard
22,000
25
Temporary Hot Mix Asphalt (HMA) for Trench Patching
Square -Yard
10,000
26
Removal and Replacement of Concrete Curb and Gutter
Lineal Foot
100
27
Replace Traffic Loop Sensor,Pavement Markings &Traffic Butt
Lump Sum
1
28
Concrete Driveway and/or Sidewalk Restoration
Square -Yard
400
29
Property & Landscape Restoration
Lump Sum
1
Unit
Price
Bid
Amount
Unit
Price
Bid
Amount
25, 000.00
125,000.00
182, 300.
00
182, 300.
00
41,000.00
41,000.00
38,000.00
38,000.00
2,000.00
2,000.00
4,600.00
4,600.00
18,000.00
18,000.00
14, 000.00
14,000.00
6,000.00
6,000.00
28,156.00
28,156.00
300.00
3,000.00
325.00
3,250.00
49.00
314,384.00
36.00
230,976.00
47.00
180,950.00
35.00
134,750.00
2,500.00
62,500.00
3,500.00
87,500.00
4,500.00
22,500.00
4,000.00
20,000.00
500.00
2,000.00
5,000.00
20,000.00
500.00
1,000.00
1,600.00
3,200.00
15.00
7,500.00
20.00
10,000.00
1.00
6,416.00
1.80
11,548.80
44.00
321,200.00
36.00
262,800.00
800.00
35,200.00
1,360.00
59,840.00
1,500.00
3,000.00
5,200.00
10,400.00
4,500.00
67,500.00
4,100.00
61,500.00
1,800.00
18,000.00
1,700.00
17,000.00
150.00
4,950.00
105.00
3,465.00
600.00
78,000.00
825.00
107,250.00
0.50
12,000.00
0.50
12,000.00
35.00
7,000.00
22.00
4,400.00
20.50
451,000.00
23.70
521,400.00
16.50
165,000.00
7.25
72,500.00
30.00
3,000.00
30.00
3,000.00
6,000.00
6,000.00
6,200.00
6,200.00
50.00
20,000.00
35.00
14,000.00
10,000.00
10,000.00
54,000.00
54,000.00
Subtotal
$1,994,100.00
Subtotal
$1,998,035.80
Tax
$189,439.50
Tax
$189,813.40
Total $2,183,539.50 Total $2,187,849.20
Project Titl(2009 Earlington Water & Sewer Improvements
BID DATE: DATE
Shoreline Construction Universal Land Construction
E Item
� No.
Description
Unit
Est.
Quantity
Unit
Price
Bid
Amount
Unit
Price
Bid
Amount
1
Mobilization, Demobilization, Site Preparation & Clean-up
Lump Sum
1
180,000.00
180,000.00
135,000.00
135,000.00
2
Traffic Control
Lump Sum
1
28,000.00
28,000.00
67,000.00
67,000.00
3
Trench Excavation Safety Systems
Lump Sum
1
10,000.00
10,000.00
4,000.00
4,000.00
4
Construction Surveying, Staking, and As-Builts
Lump Sum
1
15,000.00
15,000.00
21,000.00
21,000.00
5
Temporary Erosion and Sedimentation Control
Lump Sum
1
5,000.00
5,000.00
10,000.00
10,000.00
6
Re -Establish Existing Monuments
Each
10
600.00
6,000.00
225.00
2,250.00
7
Furnish and Install 8" PVC Sewer Pipe
Lineal Foot
6,416
55.00
352,880.00
90.00
577,440.00
8
Furnish and Install 6" PVC Side Sewer Pipe
Lineal Foot
3,850
45.00
173,250.00
30.00
115,500.00
9
Furnish and Install 48" Diam. Sanitary Sewer Manhole
Each
25
6,500.00
162,500.00
3,200.00
80,000.00
10
Furnish''and Install 54" Dia. Sanitary Sewer Saddle Manhole
Each
5
6,500.00
32,500.00
2,900.00
14,500.00
11
Connect New Sanitary Sewer to Existing Manhole
Each
4
1,300.00
5,200.00
2,000.00
8,000.00
12
Abandon Existing Manhole
Each
2
500.00
1,000.00
500.00
1,000.00
13
Removal and Replacement of Unsuitable Foundation Material
Ton
500
0.01
5.00
25.00
12,500.00
14
Television Inspection of Sanitary Sewers
Lineal Foot
6,416
2.00
12,832.00
2.00
12,832.00
15
Furnish and Install 8" Cl 52 DI Water Pipe & Fittings w/Polywrs
Lineal Foot
7,300
32.00
233,600.00
22.00
160,600.00
16
Furnish and Install 8" Gate Valve Assembly
Each
44
850.00
37,400.00
850.00
37,400.00
17
Furnish and Install 12"x8" Wet -Tap Tee&Gate Valve Assembly
Each
2
5,000.00
10,000.00
3,500.00
7,000.00
18
Furnish and Install Fire Hydrant Assembly
Each
15
3,400.00
51,000.00
3,200.00
48,000.00
19
Connection to Existing Water Main
Each
10
1,000.00
10,000.00
1,000.00
10,000.00
20
Concrete for Thrust Blockings, Dead -Man Anchor Blocks
Cubic Yard
33
150.00
4,950.00
275.00
9,075.00
21
Furnish & Install 3/4" Water Service Connection
Each
130
1,200.00
156,000.00
775.00
100,750.00
22
Select Imported Trench Backfill
Ton
24,000
0.01
240.00
0.01
240.00
23
CrushedlRocks for Shoulder Restoration
Ton
200
40.00
8,000.00
21.00
4,200.00
24
H.M.A. Glass'W' PG 64-22 for Roadway Reconstruction includ
Square -Yard
22,000
22.00
484,000.00
23.00
506,000.00
25
Temporary Hot Mix Asphalt (HMA) for Trench Patching
Square -Yard
10,000
0.01
100.00
4.00
40,000.00
26
Removal' and Replacement of Concrete Curb and Gutter
Lineal Foot
100
20.00
2,000.00
21.00
2,100.00
27
Replace Traffic Loop Sensor,Pavement Markings &Traffic Butt
Lump Sum
1
2,500.00
2,500.00
5,900.00
5,900.00
28
Concrete Driveway and/or Sidewalk Restoration
Square -Yard
400
32.00
12,800.00
33.00
13,200.00
29
Property & Landscape Restoration
Lump Sum
1
10,000.00
10,000.00
5,000.00
5,000.00
Subtotal
$2,006,757.00
Subtotal
$2,010,487.00
Tax
$190,641.92
Tax
$190,996.27
Total $2,197,398.92 Total $2,201,483.27
Project TitIE 2009 Earl ington Water & Sewer Improvements
BID DATE: DATE
E Item
No.
Description
Unit
Est.
Quantity
1
Mobilization, Demobilization, Site Preparation & Clean-up
Lump Sum
1
2
Traffic Control
Lump Sum
1
3
Trench Excavation Safety Systems
Lump Sum
1
4
Construction Surveying, Staking, and As-Builts
Lump Sum
1
5
Temporary Erosion and Sedimentation Control
Lump Sum
1
6
Re -Establish Existing Monuments
Each
10
7
Furnish and Install 8" PVC Sewer Pipe
Lineal Foot
6,416
8
Furnish and Install 6" PVC Side Sewer Pipe
Lineal Foot
3,850
9
Furnish and Install 48" Diam. Sanitary Sewer Manhole
Each
25
10
Furnish iand Install 54" Dia. Sanitary Sewer Saddle Manhole
Each
5
11
Connect New Sanitary Sewer to Existing Manhole
Each
4
12
Abandon Existing Manhole
Each
2
13
Removal and Replacement of Unsuitable Foundation Material
Ton
500
14
Television Inspection of Sanitary Sewers
Lineal Foot
6,416
15
Furnish and Install 8" Cl 52 DI Water Pipe & Fittings w/Polywre
Lineal Foot
7,300
16
Furnish and Install 8" Gate Valve Assembly
Each
44
17
Furnish and Install 12"x8" Wet -Tap Tee&Gate Valve Assembly
Each
2
18
Furnish and Install Fire Hydrant Assembly
Each
15
19
Connection to Existing Water Main
Each
10
20
Concrete for Thrust Blockings, Dead -Man Anchor Blocks
Cubic Yard
33
21
Furnish & Install 3/4" Water Service Connection
Each
130
22
Select Imported Trench Backfill
Ton
24,000
23
Crushed Rocks for Shoulder Restoration
Ton
200
24
H.M.A. Class''/2' PG 64-22 for Roadway Reconstruction includ
Square -Yard
22,000
25
Temporary Hot Mix Asphalt (HMA) for Trench Patching
Square -Yard
10,000
26
Removal and Replacement of Concrete Curb and Gutter
Lineal Foot
100
27
Replace Traffic Loop Sensor,Pavement Markings &Traffic Butt
Lump Sum
1
28
Concrete Driveway and/or Sidewalk Restoration
Square -Yard
400
29
Property & Landscape Restoration
Lump Sum
1
Buno Construction Rodarte Construction
Unit
Bid
Unit
Bid
Price
Amount
Price
Amount
75,000.00
75,000.00
200,000.00
200,000.00
30,000.00
30,000.00
100,000.00
100,000.00
25,000.00
25.000.00
100.00
100.00
20,000.00
20,000.00
10,000.00
10,000.00
10,000.00
10,000.00
8,000.00
8,000.00
800.00
8,000.00
250.00
2,500.00
73.00
468,368.00
40.00
256,640.00
50.00
192,500.00
28.00
107,800.00
3,200.00
80,000.00
2,500.00
62,500.00
3,300.00
16,500.00
2,900.00
14,500.00
5,000.00
20,000.00
2,000.00
8,000.00
500.00
1,000.00
200.00
400.00
1.00
500.00
14.00
7,000.00
1.00
6,416.00
4.00
25,664.00
32.00
233,600.00
38.00
277,400.00
900.00
39,600.00
1,000.00
44,000.00
3,500.00
7,000.00
3,500.00
7,000.00
3,500.00
52,500.00
3,500.00
52,500.00
2,000.00
20,000.00
1,250.00
12,500.00
100.00
3,300.00
200.00
6,600.00
1,000.00
130,000.00
750.00
97,500.00
9.00
216,000.00
8.00
192,000.00
18.00
3,600.00
20.00
4,000.00
15.00
330,000.00
18.00
396,000.00
0.01
100.00
10.00
100, 000.00
20.00
2,000.00
30.00
3,000.00
5,000.00
5,000.00
5,000.00
5,000.00
40.00
16,000.00
45.00
18,000.00
15, 000.00
15, 000.00
15, 000.00
15, 000.00
Subtotal
$2,026,984.00
Subtotal
$2,033,604.00
Tax
$192,563.48
Tax
$193,192.38
Total $2,219,547.48 Total $2,226,796.38
Project Titl(2009 Earlington Water & Sewer Improvements
BID DATE: DATE
E Item
� No. Description
1 Mobilization, Demobilization, Site Preparation & Clean-up
2 Traffic Control
3 Trench Excavation Safety Systems
4 Construction Surveying, Staking, and As-Builts
5 Temporary Erosion and Sedimentation Control
6 Re -Establish Existing Monuments
7 Furnish and Install 8" PVC Sewer Pipe
8 Furnish and Install 6" PVC Side Sewer Pipe
9 Furnish and Install 48" Diam. Sanitary Sewer Manhole
10 Furnish and Install 54" Dia. Sanitary Sewer Saddle Manhole
11 Connect New Sanitary Sewer to Existing Manhole
12 Abandon Existing Manhole
13 Removal and Replacement of Unsuitable Foundation Material
14 Television Inspection of Sanitary Sewers
15 Furnish and Install 8" Cl 52 DI Water Pipe & Fittings w/Polywrz
16 Furnish and Install 8" Gate Valve Assembly
17 Furnish and Install 12"x8" Wet -Tap Tee&Gate Valve Assembly
18 Furnish and Install Fire Hydrant Assembly
19 Connection to Existing Water Main
20 Concrete for Thrust Blockings, Dead -Man Anchor Blocks
21 Furnish & Install 3/4" Water Service Connection
22 Select Imported Trench Backfill
23 Crushed Rocks for Shoulder Restoration
24 H.M.A. Class'/2" PG 64-22 for Roadway Reconstruction includ
25 Temporary Hot Mix Asphalt (HMA) for Trench Patching
26 Removal and Replacement of Concrete Curb and Gutter
27 Replace Traffic Loop Sensor,Pavement Markings &Traffic Butt
28 Concrete Driveway and/or Sidewalk Restoration
29 Property '& Landscape Restoration
Unit
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Each
Lineal Foot
Lineal Foot
Each
Each
Each
Each
Ton
Lineal Foot
Lineal Foot
Each
Each
Each
Each
Cubic Yard
Each
Ton
Ton
Square -Yard
Square -Yard
Lineal Foot
Lump Sum
Square -Yard
Lump Sum
Est.
Quanti
10
6,416
3,850
25
5
4
2
500
6,416
7,300
44
2
15
10
33
130
24,000
200
22,000
10,000
100
400
Kar-Vel Construction Plats Plus
Unit
Bid
Unit
Bid
Price
Amount
Price
Amount
210,000.00
210,000.00
155,000.00
155,000.00
15, 000.00
15,000.00
19,000.00
19,000.00
8,000.00
8,000.00
100.00
100.00
24,000.00
24,000.00
11,000.00
11,000.00
8,000.00
8,000.00
7,500.00
7,500.00
1,200.00
12,000.00
300.00
3,000.00
59.00
378,544.00
36.00
230,976.00
54.00
207,900.00
35.00
134,750.00
4,000.00
100,000.00
3,400.00
85,000.00
5,000.00
25,000.00
4,200.00
21,000.00
2,500.00
10,000.00
2,100.00
8,400.00
3,500.00
7,000.00
450.00
900.00
8.00
4,000.00
12.00
6,000.00
2.00
12,832.00
0.75
4,812.00
38.00
277,400.00
37.00
270,100.00
950.00
41,800.00
850.00
37,400.00
5,200.00
10,400.00
3,100.00
6,200.00
4,600.00
69,000.00
3,200.00
48,000.00
3,000.00
30,000.00
1,200.00
12,000.00
75.00
2,475.00
180.00
5,940.00
1,000.00
130,000.00
690.00
89,700.00
1.00
24,000.00
13.00
312,000.00
16.00
3,200.00
22.00
4,400.00
21.00
462,000.00
22.00
484,000.00
1.00
10, 000.00
15.00
150, 000.00
35.00
3,500.00
28.00
2,800.00
8,000.00 8,000.00
48.00 19, 200.00
20,000.00 20,000.00
Subtotal $2,133,251.00
Tax $202,658.85
Total $2,335,909.85
5,600.00 5,600.00
45.00 18,000.00
30,000.00 30,000.00
Subtotal $2,163,578.00
Tax $205,539.91
Total $2,369,117.91
Project Titl(2009 Earlington Water & Sewer Improvements I Archer Construction Johansen Excavating
BID DATE: DATE
E Item
� No.
Description
Unit
1
Mobilization, Demobilization, Site Preparation & Clean-up
Lump Sum
2
Traffic Control
Lump Sum
3
Trench Excavation Safety Systems
Lump Sum
4
Construction Surveying, Staking, and As-Builts
Lump Sum
5
Temporary Erosion and Sedimentation Control
Lump Sum
6
Re -Establish Existing Monuments
Each
7
Furnish and Install 8" PVC Sewer Pipe
Lineal Foot
8
Furnish and Install 6" PVC Side Sewer Pipe
Lineal Foot
9
Furnish and Install 48" Diam. Sanitary Sewer Manhole
Each
10
Furnish and Install 54" Dia. Sanitary Sewer Saddle Manhole
Each
11
Connect New Sanitary Sewer to Existing Manhole
Each
12
Abandon Existing Manhole
Each
13
Removal and Replacement of Unsuitable Foundation Material
Ton
14
Television Inspection of Sanitary Sewers
Lineal Foot
15
Furnish and Install 8" Cl 52 DI Water Pipe & Fittings w/Polywrz
Lineal Foot
16
Furnish and Install 8" Gate Valve Assembly
Each
17
Furnish and Install 12"x8" Wet -Tap Tee&Gate Valve Assembly
Each
18
Furnish and Install Fire Hydrant Assembly
Each
19
Connection to Existing Water Main
Each
20
Concrete for Thrust Blockings, Dead -Man Anchor Blocks
Cubic Yard
21
Furnish & Install 3/4" Water Service Connection
Each
22
Select Imported Trench Backfill
Ton
23
Crushed Rocks for Shoulder Restoration
Ton
24
H.M.A. Class Yz' PG 64-22 for Roadway Reconstruction includ
Square -Yard
25
Temporary Hot Mix Asphalt (HMA) for Trench Patching
Square -Yard
26
Removal and Replacement of Concrete Curb and Gutter
Lineal Foot
27
Replace Traffic Loop Sensor,Pavement Markings &Traffic Butt
Lump Sum
28
Concrete Driveway and/or Sidewalk Restoration
Square -Yard
29
Property & Landscape Restoration
Lump Sum
Est.
Quantity
1
1
1
1
1
10
6,416
3,850
25
5
4
2
500
6,416
7,300
44
2
15
10
33
130
24,000
200
22,000
10,000
100
1
400
1
Unit
Bid
Price
Amount
218,000.00
218,000.00
130,000.00
130,000.00
5,000.00
5,000.00
12,000.00
12,000.00
15,000.00
15,000.00
250.00
2,500.00
70.00
449,120.00
50.00
192,500.00
2,400.00
60,000.00
3,000.00
15,000.00
2,0010.00
8,000.00
500.00
1,000.00
1.00
500.00
3.00
19,248.00
40.00
292,000.00
900.00
39,600.00
3,800.00
7,600.00
3,600.00
54,000.00
1,000.00
10,000.00
110.00
3,630.00
850.00
110,500.00
1.00
24,000.00
25.00
5,000.00
21.00
462,000.00
1.00
10,000.00
30.00
3,000.00
6,000.00
6,000.00
55.00
22,000.00
10,000.00
10,000.00
Subtotal $2,187,198.00
Tax $207,783.81
Total $2,394,981.81
Unit
Price
86,400.00
153,900.00
21,250.00
12, 350.00
10,875.00
320.00
37.35
40.65
3,300.00
5,000.00
1,370.00
335.00
24.00
1.00
29.00
985.00
3,450.00
3,600.00
1,200.00
155.00
725.00
13.35
17.00
21.95
10.85
31.00
6,000.00
14, 350.00
43, 500.00
•
EET=
86,400.00
153,900.00
21,250.00
12,350.00
10,875.00
3,200.00
239,637.60
156,502.50
82,500.00
25,000.00
5,480.00
670.00
12, 000.00
6,416.00
211, 700.00
43,340.00
6,900.00
54,000.00
12,000.00
5,115.00
94,250.00
320,400.00
3,400.00
482,900.00
108,500.00
3,100.00
6,000.00
5,740,000.00
43,500.00
Subtotal $7,951,286.10
Tax $755,372.18
Total $8,706,658.28
Project Titl( 2009,Earlington Water & Sewer Improvements
BID DATE: DATE
_E Item
No.
Description
Unit
Est.
Quantity
1
Mobilization, Demobilization, Site Preparation & Clean-up
Lump Sum
1
2
Traffic Control
Lump Sum
1
3
Trench Excavation Safety Systems
Lump Sum
1
4
Construction Surveying, Staking, and As-Builts
Lump Sum
1
5
Temporary Erosion and Sedimentation Control
Lump Sum
1
6
Re -Establish Existing Monuments
Each
10
7
Furnish and Install 8" PVC Sewer Pipe
Lineal Foot
6,416
8
Furnish and Install 6" PVC Side Sewer Pipe
Lineal Foot
3,850
9
Furnish and Install 48" Diam. Sanitary Sewer Manhole
Each
25
10
Furnish and Install 54" Dia. Sanitary Sewer Saddle Manhole
Each
5
11
Connect New Sanitary Sewer to Existing Manhole
Each
4
12
Abandon Existing Manhole
Each
2
13
Removal and Replacement of Unsuitable Foundation Material
Ton
500
14
Television Inspection of Sanitary Sewers
Lineal Foot
6,416
15
Furnish and Install 8" Cl 52 DI Water Pipe & Fittings w/Polywre
Lineal Foot
7,300
16
Furnish and Install 8" Gate Valve Assembly
Each
44
17
Furnish and Install 12"x8" Wet -Tap Tee&Gate Valve Assembly
Each
2
18
Furnish and Install Fire Hydrant Assembly
Each
15
19
Connection to Existing Water Main
Each
10
20
Concrete for Thrust Blockings, Dead -Man Anchor Blocks
Cubic Yard
33
21
Furnish & Install 3/4" Water Service Connection
Each
130
22
Select Imported Trench Backfill
Ton
24,000
23
Crushed 'Rocks for Shoulder Restoration
Ton
200
24
H.M.A. Class''/i" PG 64-22 for Roadway Reconstruction includ
Square -Yard
22,000
25
Temporary Hot Mix Asphalt (HMA) for Trench Patching
Square -Yard
10,000
26
Removal and Replacement of Concrete Curb and Gutter
Lineal Foot
100
27
Replace Traffic Loop Sensor,Pavement Markings &Traffic Butt
Lump Sum
1
28
Concrete Driveway and/or Sidewalk Restoration
Square -Yard
400
29
Property & Landscape Restoration
Lump Sum
1
Hoffman Construction Construct Company
Unit
Bid
Unit
Bid
Price
Amount
Price
Amount
150,000.00
150, 000.00
160, 000.00
160,000.00
40,000.00
40,000.00
57,000.00
57,000.00
10,000.00
10,000.00
8,000.00
8,000.00
19, 000.00
19, 000.00
12, 000.00
12, 000.00
5,400.00
5,400.00
9,000.00
9,000.00
500.00
5,000.00
4.50
45.00
62.00
397,792.00
95.00
609,520.00
67.50
259,875.00
60.00
231,000.00
3,175.00
79,375.00
2,800.00
70,000.00
3,450.00
17,250.00
3,300.00
16,500.00
2,300.00
9,200.00
600.00
2,400.00
1,000.00
2,000.00
2,000.00
4,000.00
0.01
5.00
1.00
500.00
1.00
6,416.00
1.50
9,624.00
33.00
240,900.00
45.00
328,500.00
925.00
40,700.00
930.00
40,920.00
2,800.00
5,600.00
2,800.00
5,600.00
3,560.00
53,400.00
3,900.00
58,500.00
1,000.00
10,000.00
2,300.00
23,000.00
105.00
3,465.00
180.00
5,940.00
975.00
126,750.00
935.00
121,550.00
12.15
291,600.00
0.01
240.00
22.50
4,500.00
35.00
7,000.00
19.50
429,000.00
20.00
440,000.00
0.01
100.00
1.00
10, 000.00
26.00
2,600.00
27.00
2,700.00
2,500.00
2,500.00
5,100.00
5,100.00
36.50
14,600.00
43.00
17,200.00
33,600.00
33,600.00
6,000.00
6,000.00
Subtotal $2,260,628.00
Tax $214,759.66
Total $2,475,387.66
Subtotal $2,261,839.00
Tax $214,874.71
Total $2,476,713.71
Project Titl(2009 Earlington Water & Sewer Improvements
BID DATE: DATE
E Item
� No.
Description
Unit
Est.
Quantity
1
Mobilization, Demobilization, Site Preparation & Clean-up
Lump Sum
1
2
Traffic Control
Lump Sum
1
3
Trench Excavation Safety Systems
Lump Sum
1
4
Construction Surveying, Staking, and As-Builts
Lump Sum
1
5
Temporary Erosion and Sedimentation Control
Lump Sum
1
6
Re -Establish Existing Monuments
Each
10
7
Furnish and Install 8" PVC Sewer Pipe
Lineal Foot
6,416
8
Furnish and Install 6" PVC Side Sewer Pipe
Lineal Foot
3,850
9
Furnish and Install 48" Diam. Sanitary Sewer Manhole
Each
25
10
Furnish and Install 54" Dia. Sanitary Sewer Saddle Manhole
Each
5
11
Connect New Sanitary Sewer to Existing Manhole
Each
4
12
Abandon Existing Manhole
Each
2
13
Removal and Replacement of Unsuitable Foundation Material
Ton
500
14
Television Inspection of Sanitary Sewers
Lineal Foot
6,416
15
Furnish and Install 8" Cl 52 DI Water Pipe & Fittings w/Polywr2
Lineal Foot
7,300
16
Furnish and Install 8" Gate Valve Assembly
Each
44
17
Furnish and Install 12"x8" Wet -Tap Tee&Gate Valve Assembly
Each
2
18
Furnish and Install Fire Hydrant Assembly
Each
15
19
Connection to Existing Water Main
Each
10
20
Concrete for Thrust Blockings, Dead -Man Anchor Blocks
Cubic Yard
33
21
Furnish & Install 3/4" Water Service Connection
Each
130
22
Select Imported Trench Backfill
Ton
24,000
23
Crushed Rocks for Shoulder Restoration
Ton
200
24
H.M.A. Class W' PG 64-22 for Roadway Reconstruction includ
Square -Yard
22,000
25
Temporary Hot Mix Asphalt (HMA) for Trench Patching
Square -Yard
10,000
26
Removal and Replacement of Concrete Curb and Gutter
Lineal Foot
100
27
Replace Traffic Loop Sensor,Pavement Markings &Traffic Butt
Lump Sum
1
28
Concrete Driveway and/or Sidewalk Restoration
Square -Yard
400
29
Property & Landscape Restoration
Lump Sum
1
DPK Construction Olson Brothers
Unit
Bid
Unit
Bid
Price
Amount
Price
Amount
193,000.00
193,000.00
50,000.00
50,000.00
86,000.00
86,000.00
75,000.00
75,000.00
1,000.00
1,000.00
2,600.00
2,600.00
19,000.00
19,000.00
12,000.00
12,000.00
15,000.00
15,000.00
12,000.00
12, 000.00
600.00
6,000.00
250.00
2,500.00
72.00
461,952.00
60.00
384,960.00
60.00
231,000.00
50.00
192,500.00
1,800.00
45,000.00
1,810.00
45,250.00
3,400.00
17,000.00
2,300.00
11,500.00
2,000.00
8,000.00
1,050.00
4,200.00
650.00
1,300.00
500.00
1,000.00
10.00
5,000.00
25.00
12,500.00
1.00
6,416.00
1.00
6,416.00
45.00
328,500.00
47.00
343,100.00
1,000.00
44,000.00
1,000.00
44,000.00
4,100.00
8,200.00
2,800.00
5,600.00
3,200.00
48,000.00
3,400.00
51,000.00
3,200.00
32,000.00
1,400.00
14,000.00
275.00
9,075.00
120.00
3,960.00
950.00
123,500.00
610.00
79,300.00
0.01
240.00
15.00
360,000.00
30.00
6,000.00
26.00
5,200.00
25.00
550,000.00
23.00
506,000.00
0.01
100.00
15.00
150, 000.00
25.00
2,500.00
31.00
3,100.00
7,500.00
7,500.00
5,500.00
5,500.00
33.00
13,200.00
68.00
27,200.00
72,000.00
72,000.00
6,500.00
6,500.00
Subtotal $2,340,483.00
Tax $222,345.89
Total $2,562,828.89
Subtotal $2,416,886.00
Tax $229,604.17
Total $2,646,490.17
Project Tit1E 2009 Earlington Water & Sewer Improvements
BID DATE: DATE
Marshbank Construction
E Item
Unit
Est.
Unit
Bid
� No.
Description
Quantity I
Price
Amount
1
Mobilization, Demobilization, Site Preparation & Clean-up
Lump Sum
1
86,300.00
86,300.00
2
Traffic Control
Lump Sum
1
135,000.00
135,000.00
3
Trench Excavation Safety Systems
Lump Sum
1
26,100.00
26,100.00
4
Construction Surveying, Staking, and As-Builts
Lump Sum
1
18,800.00
18,800.00
5
Temporary Erosion and Sedimentation Control
Lump Sum
1
27,100.00
27,100.00
6
Re -Establish Existing Monuments
Each
10
329.00
3,290.00
7
Furnish and Install 8" PVC Sewer Pipe
Lineal Foot
6,416
56.00
359,296.00
8
Furnish and Install 6" PVC Side Sewer Pipe
Lineal Foot
3,850
28.00
107,800.00
9
Furnish and Install 48" Diam. Sanitary Sewer Manhole
Each
25
2,530.00
63,250.00
10
Furnish and Install 54" Dia. Sanitary Sewer Saddle Manhole
Each
5
3,000.00
15,000.00
11
Connect New Sanitary Sewer to Existing Manhole
Each
4
938.00
3,752.00
12
Abandon Existing Manhole
Each
2
436.00
872.00
13
Removal and Replacement of Unsuitable Foundation Material
Ton
500
24.00
12,000.00
14
Television Inspection of Sanitary Sewers
Lineal Foot
6,416
1.35
8,661.60
15
Furnish and Install 8" Cl 52 DI Water Pipe & Fittings w/Polywr2
Lineal Foot
7,300
40.00
292,000.00
16
Furnish and Install 8" Gate Valve Assembly
Each
44
868.00
38,192.00
17
Furnish and Install 12"x8" Wet -Tap Tee&Gate Valve Assembly
Each
2
2,890.00
5,780.00
18
Furnish and Install Fire Hydrant Assembly
Each
15
3,333.00
49,995.00
19
Connection to Existing Water Main
Each
10
1,524.00
15,240.00
20
Concrete for Thrust Blockings, Dead -Man Anchor Blocks
Cubic Yard
33
168.00
5,544.00
21
Furnish & Install 3/4" Water Service Connection
Each
130
773.00
100,490.00
22
Select Imported Trench Backfill
Ton
24,000
11.00
264,000.00
23
Crushed Rocks for Shoulder Restoration
Ton
200
17.00
3,400.00
24
H.M.A. Class 1/2' PG 64-22 for Roadway Reconstruction includ
Square -Yard
22,000
29.00
638,000.00
25
Temporary Hot Mix Asphalt (HMA) for Trench Patching
Square -Yard
10,000
21.00
210,000.00
26
Removal and Replacement of Concrete Curb and Gutter
Lineal Foot
100
46.00
4,600.00
27
Replace Traffic Loop Sensor,Pavement Markings &Traffic Butt
Lump Sum
1
7,800.00
7,800.00
28
Concrete Driveway and/or Sidewalk Restoration
Square -Yard
400
42.00
16,800.00
29
Property & Landscape Restoration
Lump Sum
1
29,300.00
29,300.00
Subtotal
$2,548,362.60
Tax
$242,094.45
Total $2,790,457.05
Denis Law
Mayor .
December 15, 2009
d
itv of
Public Works Department - Gregg Zimmerman P. E., Administrator
Bret Lane, President
Laser Underground & Earthworks, Inc.
20417 87th Ave. SE
Snohomish, WA 98296
SUBJECT: Award of Contract for the 2009 Earlington Water and. Sanitary Sewer
Improvements Project (CAG-09-171)
Dear Mr. Lane:'
At the Renton City Council meeting on December 14, 2009, Council accepted Laser
Underground's bid of $2,162,511.12.for the 2009 Earlington Water and Sewer Improvements
.Project. You should be receiving a letter from the City Clerk with the official bid award.
For execution -of the contract, please submit the, following information as soon as possible so
we can prepare the contract documents for review and signature by the Mayor:
❑ A list of'names, addresses, phone numbers, and emergency phone numbers for:
Responsible Officer, Job Foreman, and'Bonding Agent.
o Corporation letter or Resolution giving names of those authorized to sign the contract
and samples of their signatures.
❑ Photocopy of,your current State Contractor's License (not master license).
❑ Photocopy of your current City of Renton Business License.
(To activate your City. Business license, please contact Linda Weldon 425-430-6851)..
❑ Two signed contract bonds on City of Renton forms (enclosed), UNDATED..
-.-The date will'be filled in when signed by the Mayor.
❑ One City.of Renton Fair Practices Affidavit of Compliance (enclosed).
❑ Two signed contracts, also UNDATED (enclosed).
❑ One..lnsura.nce Information form and one Endorsement form (enclosed).
❑ One Certificate of Insurance for 2010. Please add the City of Renton as additional
insured.
In the Cancellation section.of the standard ACORD Certificate of Insurance form, the
language should specify "4S" days written'notice and the language shall.have the words
"ENDEAVOR TO" and "BUT FAILURE TO. MAIL SUCH NOTICE SHALL IMPOSE NO
OBLIGATIONOR LIABILITY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
REPRESENTATIVES'.' struck (see attached example).
❑ The insurance policy declaration.pages of all required insurance policies obtained.from
the insurance carrier.:
Renton City Hall • 1055 South Grady Way • Renton, Washington 98057 • rentonwa.gov
Mr. Lane, President of Laser Underground
December 15, 2009
Page 2 of 2
After you submit the contract information, we will need the following information to review
and approve before construction may start. We would like to have most of it before we
schedule a pre -construction conference. If you intend to use private property for material
storage or staging you will need the approval of our Development Services Department. In
some instances this may include the need for a Temporary Use Permit. This does not apply to
storage and staging areas within City rights -of -way.
1. Provide material submittals as required for the work involved with this job. This will
include, but not be limited to, information on the proposed source and specifications of all
materials that will be used in the project. Show that the proposed materials meet the
project specifications, per Standard Specifications and Special Provisions. Provide any shop
drawings and submittals needed for the project per Standard Specifications and Special
Provisions Section.
2. Work Plan. Include the following items:
1. Proposed construction sequencing and schedule for the project.
2. Mobilization Plan.
3. Temporary Erosion and Sediment Control Plan.
4. Traffic Control Plan.
5. Street Cleaning and Sweeping Plan.
6. Trench Excavation Safety Systems Plan.
7. Disposal Site.
Construction Surveying. Identify the surveying firm/surveyor and a letter showing that the
surveyor is licensed in the State of Washington.
4. Traffic Control Plan. The plan will be reviewed and final adjustments made at the pre -
construction conference. Please refer to the project specifications
Please let me know when you would like to have the pre -construction conference. We will
need to notify the private utilities and City inspector, so there should be a lead-time of at least
one week before the conference. If you have any questions or need additional information,
please call me at 425-430-7208.
Sincerely,
Andrew Weygandt,, P.E.
Water Utility Civil Engineer
Enclosures
cc: Abdoul Gafour, Water Utility Supervisor
David Christensen, Wastewater Utility Supervisor
John Hobson, Wastewater Utility
H:\File Sys\WTR - Drinking Water Utility\WTR-27 - Water Project Files\WTR-27-3082- 2009 Earlington Water and Sewer
I m prove ments\Construction\WTR-27-3179_Award-aw.doc\AWtp
PUBLIC WORKS DEPARTMENT D City ot
M E M O R A N D U M
DATE: December 9, 2009
TO: Bonnie Walton, City Clerk
FROM: Abdoul Gafour, Water Utility Supervisor (ext. 7210)I�
Andrew Weygandt, Water Utility Engineer (ext. 7208)
SUBJECT: Bid Opening for 2009 Earlington Water and Sewer
Improvements Project (CAG-09-171)
On December 9, 2009, at 2:30 p.m., the City received sixteen bids for the 2009
Earlington Water and Sewer Improvements. The City Clerk opened and publicly read all
bids at 2:45 p.m. Laser Underground and Earthworks, Inc. of Snohomish, WA submitted
the low bid, in the total amount $2,162,511.12.
We have checked all bids for completeness, mathematical correctness, and inclusion of
all required forms, and found no irregularities or mathematical errors in the low bid
submitted by Laser Underground and Earthworks, Inc. The engineer's estimate for this
project is $3,656,305.74.
In accordance with Council procedure, the low bid meets all three conditions for award:
1. The low bid must be within the total project budget.
2. There must be more than one bidder.
3. The lowest responsive, responsible bid contains no significant irregularities.
The Water Utility recommends that Council award the contract to Laser Underground
and Earthworks, Inc., in the total amount of $2,162,511.12, at its meeting of
December 14, 2009.
The total project budget is $2,700,000. The Water Utility share is $1,200,000 from the
Water Utility Capital Improvement budget and the Wastewater Utility share is
$1,500,000 from the Wastewater Utility Capital Improvement budget.
If you have any questions, please call me. Thank you for your assistance.
Attachments: Bid tabulation
cc: Lys Hornsby, Utility Systems Director
David Christensen, Wastewater Utility Supervisor
h:\file sys\wtr - drinking water utility\wtr-27 - water project files\wtr-27-3082- 2009 earlington water and sewer
improve ments\construction\wtr-27-3082_memo-to-city-clerk-contract-award.doc\AWtp
SUMMARY OF ESTIMATED PROJECT COSTS
Description
Amount
Construction Contract including 9.5% sales tax
(from low bid submitted by Laser Underground and
Earthworks, Inc. on 12/8/09)
$2,162,511.12
Construction Engineering & Administration (estimated)
$150,000
Special Inspection & Testing (estimated)
$10,000
Contingencies (estimated)
$367,488.88
Total Contract Cost (estimated)
$2,700,000
Total Project Budget
$2,700,000
h:\file_sys\wtr - drinking water utility\wtr-27 - water project files\wtr-27-3082- 2009 earlington water and sewer
i m prove me nts\co nstruction\wtr-27-3082 memo-to-city-clerk-contract-award.doc\AWtp
Project Title: 2009 Earlington Water & Sewer Improvements
BID DATE: December 08, 2009
Item
No.
Description
Unit
Est.
Quantity
1
Mobilization, Demobilization, Site Preparation & Clean-up
Lump Sum
1
2
Traffic Control
Lump Sum
1
3
Trench Excavation Safety Systems
Lump Sum
1
4
Construction Surveying, Staking, and As-Builts
Lump Sum
1
5
Temporary Erosion and Sedimentation Control
Lump Sum
1
6
Re -Establish Existing Monuments
Each
10
7
Furnish. and Install 8" PVC Sewer Pipe
Lineal Foot
6,416
8
Furnish and Install 6" PVC Side Sewer Pipe
Lineal Foot
3,850
9
Furnish and Install 48" Diam. Sanitary Sewer Manhole
Each
25
10
Furnish and Install 54" Dia. Sanitary Sewer Saddle Manhole
Each
5
11
Connect New Sanitary Sewer to Existing Manhole
Each
4
12
Abandon Existing Manhole
Each
2
13
Removal and Replacement of Unsuitable Foundation Material
Ton
500
14
Television Inspection of Sanitary Sewers
Lineal Foot
6,416
15
Furnish and Install 8" Cl 52 DI Water Pipe & Fittings w/Polywra
Lineal Foot
7,300
16
Furnish and Install 8" Gate Valve Assembly
Each
44
17
Furnish.and Install 12"x8" Wet -Tap Tee&Gate Valve Assembly
Each
2
18
Furnish and Install Fire Hydrant Assembly
Each
15
19
Connection to Existing Water Main
Each
10
20
Concrete for Thrust Blockings, Dead -Man Anchor Blocks
Cubic Yard
33
21
Furnish & Install 3/4" Water Service Connection
Each
130
22
Select Imported Trench Backfill
Ton
24,000
23
Crushed Rocks for Shoulder Restoration
Ton
200
24
H.M.A. Class'/2' PG 64-22 for Roadway Reconstruction includi
Square -Yard
22,000
25
Temporary Hot Mix Asphalt (HMA) for Trench Patching
Square -Yard
10,000
26
Removal and Replacement of Concrete Curb and Gutter
Lineal Foot
100
27
Replace Traffic Loop Sensor,Pavement Markings &Traffic Butt
Lump Sum
1
28
Concrete Driveway and/or Sidewalk Restoration
Square -Yard
400
29
Property & Landscape Restoration
Lump Sum
1
R.L. Alia
Pivetta Brothers
Shoreline Construction
Universal Land Construction
Buno Construction
Unit
Bid
Unit
Bid
Unit
Bid
Unit
Bid
Unit
Bid
Price
Amount
Price
Amount
Price
Amount
Price
Amount
Price
Amount
125,000.00
125,000.00
182,300.00
182,300.00
180,000.00
180,000.00
135,000.00
135,000.00
75,000.00
75,000.00
41,000.00
41,000.00
38,000.00
38,000.00
28,000.00
28,000.00
67,000.00
67,000.00
30,000.00
30,000.00
2,000.00
2,000.00
4,600.00
4,600.00
10,000.00
10,000.00
4,000.00
4,000.00
25,000.00
25,000.00
18,000.00
18,000.00
14,000.00
14,000.00
15,000.00
15,000.00
21,000.00
21,000.00
20,000.00
20,000.00
6,000.00
6,000.00
28,156.00
28,156.00
5,000.00
5,000.00
10,000.00
10,000.00
10,000.00
10,000.00
300.00
3,000.00
325.00
3,250.00
600.00
6,000.00
225.00
2,250.00
800.00
8,000.00
49.00
31-4,384.00
36.00
230,976.00
55.00
352,880.00
90.00
577,440.00
73.00
468,368.00
47.00
180,950.00
35.00
134,750.00
45.00
173,250.00
30.00
115,500.00
50.00
192,500.00
2,500.00
62,500.00
3,500.00
87,500.00
6,500.00
162,500.00
3,200.00
80,000.00
3,200.00
80,000.00
4,500.00
22,500.00
4,000.00
20,000.00
6,500.00
32,500.00
2,900.00
14,500.00
3,300.00
16,500.00
500.00
2,000.00
5,000.00
20,000.00
1,300.00
5,200.00
2,000.00
8.000.00
5,000.00
20,000.00
500.00
1,000.00
1,600.00
3,200.00
500.00
1,000.00
500.00
1,000.00
500.00
1,000.00
15.00
7,500.00
20.00
10,000.00
0.01
5.00
25.00
12,500.00
1.00
500.00
1.00
6,416.00
1.80
11,548.80
2.00
12,832.00
2.00
12,832.00
1.00
6,416.00
44.00
321,200.00
36.00
262,800.00
32.00
233,600.00
22.00
160,600.00
32.00
233,600.00
800.00
35,200.00
1,360.00
59,840.00
850.00
37,400.00
850.00
37,400.00
900.00
39,600.00
1,500.00
3,000.00
5,200.00
10,400.00
5,000.00
10,000.00
3,500.00
7,000.00
3,500.00
7,000.00
4,500.00
67,500.00
4,100.00
61,500.00
3,400.00
51,000.00
3,200.00
48,000.00
3,500.00
52,500.00
1,800.00
18,000.00
1,700.00
17,000.00
1,000.00
10,000.00
1,000.00
10,000.00
2,000.00
20,000.00
150.00
4,950.00
105.00
3,465.00
150.00
4,950.00
275.00
9,075.00
100.00
3,300.00
600.00
78,000.00
825.00
107,250.00
1,200.00
156,000.00
775.00
100,750.00
1,000.00
130,000.00
0.50
12,000.00
0.50
12,000.00
0.01
240.00
0.01
240.00
9.00
216,000.00
35.00
7,000.00
22.00
4,400.00
40.00
8,000.00
21.00
4,200.00
18.00
3,600.00
20.50
451,000.00
23.70
521,400.00
22.00
484,000.00
23.00
506,000.00
15.00
330,000.00
16.50
165,000.00
7.25
72,500.00
0.01
100.00
4.00
40,000.00
0.01
100.00
30.00
3,000.00
30.00
3,000.00
20.00
2,000.00
21.00
2,100.00
20.00
2,000.00
6,000.00
6,000.00
6,200.00
6,200.00
2,500.00
2,500.00
5,900.00
5,900.00
5,000.00
5,000.00
50.00
20,000.00
35.00
14,000.00
32.00
12,800.00
33.00
13,200.00
40.00
16,000.00
10,000.00
10,000.00
54,000.00
54,000.00
10,000.00
10,000.00
5,000.00
5,000.00
15,000.00
15,000.00
Subtotal $1,994,100.00
Tax $189:439.50
Subtotal $1,998,035.80
Tax $189,813.40
Subtotal $2,006,757.00
Tax $190,641.92
Total $2,183,539.50 Total $2,187,849.20 Total $2,197,398.92
Subtotal $2,010,487.00
Tax $190,996.27
Total $2,201,483.27
Subtotal $2,026,984.00
Tax $192,563.48
Total $2,219,547.48
Rodarte Construction
Kar-Vel Construction
Plats Plus
Archer Construction
Johansen Excavating
Unit
Bid
Unit
Bid
Unit
Bid
Unit
Bid
Unit
Bid
Price
Amount
Price
Amount
Price
Amount
Price
Amount
Price
Amount
200,000.00
200,000.00
210,000.00
210,000.00
155,000.00
155,000.00
218,000.00
218,000.00
86,400.00
86,400.00
100,000.00
100,000.00
15,000.00
15,000.00
19,000.00
19,000.00
130,000.00
130,000.00
153,900.00
153, 900.00
100.00
100.00
8,000.00
8,000.00
100.00
100.00
5,000.00
5,000.00
21,250.00
21,250.00
10,000.00
10,000.00
24,000.00
24,000.00
11,000.00
11,000.00
12,000.00
12,000.00
12,350.00
12,350.00
8,000.00
8,000.00
8,000.00
8,000.00
7,500.00
7,500.00
15,000.00
15,000.00
10,875.00
10,875.00
250.00
2,500.00
1,200.00
12,000.00
300.00
3,000.00
250.00
2,500.00
320.00
3,200.00
40.00
256,640.00
59.00
378,544.00
36.00
230,976.00
70.00
449,120.00
37.35
239,637.60
28.00
107,800.00
54.00
207,900.00
35.00
134,750.00
50.00
192,500.00
40.65
156,502.50
2,500.00
62,500.00
4,000.00
100,000.00
3,400.00
85,000.00
2,400.00
60,000.00
3,300.00
82,500.00
2,900.00
14,500.00
5,000.00
25,000.00
4,200.00
21,000.00
3,000.00
15,000.00
5,000.00
25,000.00
2,000.00
8,000.00
2,500.00
10,000.00
2,100.00
8,400.00
2,000.00
8,000.00
1,370.00
5,480.00
200.00
400.00
3,500.00
7,000.00
450.00
900.00
500.00
1,000.00
335.00
670.00
14.00
7,000.00
8.00
4,000.00
12.00
6,000.00
1.00
500.00
24.00
12,000.00
4.00
25,664.00
2.00
12,832.00
0.75
4,812.00
3.00
19,248.00
1.00
6,416.00
38.00
277,400.00
38.00
277,400.00
37.00
270,100.00
40.00
292,000.00
29.00
211,700.00
1,000.00
44,000.00
950.00
41,800.00
850.00
37,400.00
900.00
39,600.00
985.00
43,340.00
3,500.00
7,000.00
5,200,00
10,400.00
3,100.00
6,200.00
3,800.00
7,600.00
3,450.00
6,900.00
3,500.00
52,500.00
4,600.00
69,000.00
3,200.00
48,000.00
3,600.00
54,000.00
3,600.00
54,000.00
1.250.00
12,500.00
3,000.00
30,000.00
1,200.00
12,000.00
1,000.00
10,000.00
1,200.00
12,000.00
200.00
6,600.00
75.00
2,475.00
180.00
5,940.00
110.00
3,630.00
155.00
5,115.00
750.00
97,500.00
1,000.00
130,000.00
690.00
89,700.00
850.00
110,500.00
725.00
94,250.00
8.00
192,000.00
1.00
24,000.00
13.00
312,000.00
1.00
24,000.00
13.35
320,400.00
20.00
4„000.00
16.00
3,200.00
22.00
4,400.00
25.00
5,000.00
17.00
3,400.00
18.00
396,000.00
21.00
462,000.00
22.00
484,000.00
21.00
462,000.00
21.95
482,900.00
10.00
100, 000.00
1.00
10,000.00
15.00
150,000.00
1.00
10,000.00
10.85
108,500.00
30.00
3',000.00
35.00
3,500.00
28.00
2,800.00
30.00
3,000.00
31.00
3,100.00
5,000.00
5,000.00
8,000.00
8,000.00
5,600.00
5,600.00
6,000.00
6,000.00
6,000.00
6,000.00
45.00
18,000.00
48.00
19,200.00
45.00
18,000.00
55.00
22,000.00
14,350.00
5,740,000.00 ..
15,000.00
15,000.00
20,000.00
20,000.00
30,000.00
30,000.00
10,000.00
10,000.00
43,500.00
43,500.00
Subtotal
$2,033,604.00
Subtotal
$2,133,251.00
Subtotal
$2,163,578.00
Subtotal
$2,187,198.00
Subtotal
$7,951,286.10
Tax
$193,192.38
Tax
$202,658.85
Tax
$205,539.91
Tax
$207,783.81
Tax
$755,372.18
Total
$2,226,796.38
Total
$2,335,909.85
Total
$2,369,117.91
Total
$2,394,981.81
Total
$8,706,658.28
Hoffman Construction
Construct Company
DPK Construction
Olson Brothers
Marshbank Construction
Unit
Bid
Unit
Bid
Unit
Bid
Unit
Bid
Unit
Bid
Price
Amount
Price
Amount
Price
Amount
Price
Amount
Price
Amount
150,000.00
150,000.00
160,000.00
160,000.00
193,000.00
193,000.00
50,000.00
50,000.00
86,300.00
86,300.00
40,000.00
40,000.00
57,000.00
57,000.00
86,000.00
86,000.00
75,000.00
75,000.00
135,000.00
135,000.00
10,000.00
10,000.00
8,000.00
8,000.00
1,000.00
1,000.00
2,600.00
2,600.00
26,100.00
26,100.00
19,000.00
19,000.00
12,000.00
12,000.00
19,000.00
19,000.00
12,000.00
12,000.00
18,800.00
18, 800.00
5,400.00
5,400.00
9,000.00
9,000.00
15,000.00
15,000.00
12,000.00
12,000.00
27,100.00
27,100.00
500.00
5,000.00
4.50
45.00
600.00
6,000.00
250.00
2,500.00
329.00
3,290.00
62.00
397,792.00
95.00
609,520.00
72.00
461,952.00
60.00
384,960.00
56.00
359,296.00
67.50
259,875.00
60.00
231,000.00
60.00
231,000.00
50.00
192,500.00
28.00
107,800.00
3,175.00
79,375.00
2,800.00
70,000.00
1,800.00
45,000.00
1,810.00
45,250.00
2,530.00
63,250.00
3,450.00
17,250.00
3,300.00
16,500.00
3,400.00
17,000.00
2,300.00
11,500.00
3,000.00
15,000.00
2,300.00
9,200.00
600.00
2,400.00
2,000.00
8,000.00
1,050.00
4,200.00
938.00
3,752.00
1,000.00
2,000.00
2,000.00
4,000.00
650.00
1,300.00
500.00
1,000.00
436.00
872.00
0.01
5.00
1.00
500.00
10.00
5,000.00
25.00
12,500.00
24.00
12,000.00
1.00
6.416.00
1.50
9,624.00
1.00
6,416.00
1.00
6,416.00
1.35
8,661.60
33.00
240.900.00
45.00
328,500.00
45.00
328,500.00
47.00
343,100.00
40.00
292,000.00
925.00
40,700.00
930.00
40,920.00
1,000.00
44,000.00
1,000.00
44,000.00
868.00
38,192.00
2,800.00
5,600.00
2,800.00
5,600.00
4,100.00
8,200.00
2,800.00
5,600.00
2,890.00
5,780.00
3,560.00
53,400.00
3,900.00
58,500.00
3,200.00
48,000.00
3,400.00
51,000.00
3,333.00
49,995.00
1,000.00
10.000.00
2,300.00
23,000.00
3,200.00
32,000.00
1,400.00
14,000.00
1,524.00
15,240.00
105.00
3,465.00
180.00
5,940.00
275.00
9,075.00
120.00
3,960.00
168.00
5,544.00
975.00
126,750.00
935.00
121,550.00
950.00
123,500.00
610.00
79,300.00
773.00
100,490.00
12.15
291,600.00
0.01
240.00
0.01
240.00
15.00
360,000.00
11.00
264,000.00
22.50
4,500.00
35.00
7,000.00
30.00
6,000.00
26.00
5,200.00
17.00
3,400.00
19.50
429,000.00
20.00
440,000.00
25.00
550,000.00
23.00
506,000.00
29.00
638,000.00
0.01
100.00
1.00
10,000.00
0.01
100.00
15.00
150,000.00
21.00
210,000.00
26.00
2,600.00
27.00
2,700.00
25.00
2,500.00
31.00
3,100.00
46.00
4,600.00
2,500.00
2,500.00
5,100.00
5,100.00
7,500.00
7,500.00
5,500.00
5,500.00
7,800.00
7,800.00
36.50
14,600.00
43.00
17,200.00
33.00
13,200.00
68.00
27,200.00
42.00
16,800.00
33,600.00
33,600.00
6,000.00
6,000.00
72,000.00
72,000.00
6,500.00
6,500.00
29,300.00
29,300.00
Subtotal
$2,260,628.00
Subtotal
$2,261,839.00
Subtotal
$2,340,483.00
Subtotal
$2,416,886.00
Subtotal
$2,548,362.60
Tax
$214,759.66
Tax
$214,874.71
Tax
$222,345.89
Tax
$229,604.17
Tax
$242,094.45
Total
$2,475,387.66
Total
$2,476,713.71
Total
$2,562,828.89
Total
$2,646,490.17
Total
$2,790,457.05
PUBLIC WORKS DEPARTMENT p
M E M O R A N D U M
DATE: November 3, 2009
TO: Bonnie Walton, City Clerk
FROM: Abdoul Gafour, Water Utility Supervisor (ext. 7210)
Andrew Weygandt, Water Utility Project Engineer (ext. 7208)
SUBJECT: Bid Opening for Earlington Water and Sewer Improvements
Project
On October 27, 2009, at 2:30 p.m., the City received twenty-six (26) bids for the 2009
Earlington Water and Sewer Improvements project. The City Clerk opened and publicly
read all bids at 2:45 p.m.
In accordance with Section 1-03.1 Consideration of Bids of the standard specifications in
the bid documents, the Utility Systems Division recommends that all bids be rejected.
We will revise the bid documents and project plans and we anticipate re -publishing the
call for bids for this project in December 2009.
If you have any questions, please call me. Thank you for your assistance.
Attachments: Originals of 26 submitted bids
cc: Lys Hornsby, Utility Systems Director
Dave Christensen, Wastewater Utility Engineer
h:\file sys\wtr - drinking water utility\wtr-27 - water project files\wtr-27-3082- 2009 earlington water and sewer
improvements\bid info & specs\memo-to-city-clerk-reject-bids.doc\AGtp