Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutWWP273555ENGINEERING . PLANNING . ENVIRONMENTAL SCIENCES
1019 39th AVE SE, SUITE 100
PUYALLUP, WA 98374
T.253.604.6600 F.253.604.6799
www.parametrixxom
TECHNICAL MEMORANDUM
Date: June 21, 2011
To: Dave Christensen
John Hobson
Ron Straka
Allen Quynn
From: Jeff Coop, P.E.
Subject: Upper Failure Site Options
cc: Jenna Friebel, CJ Shin (Soil and Environmental Engineers)
Project Number: 218-1779-037
Project Name: Thunder Hills Creek
INTRODUCTION
Thunder Hills Creek, located within the City of Renton, begins northwest of the intersection of Grant Avenue
South and South 18th Street, flows to the northwest, crosses under I-405 through a storm drain, and continues
through several ditches and pipes and a three -sided concrete flume before its confluence with Rolling Hills Creek.
Thunder Hills Creek varies from an open stream in riparian areas to concrete channels to enclosed storm drains
and pipe systems. The portion of Thunder Hills Creek of concern is located within a steep confined ravine just
southeasterly of I-405.
A sanitary sewer was constructed along a portion of the stream in approximately 1964. Based on record drawings,
a maintenance access road along the existing sanitary sewer Was generally not constructed with the original
construction of the sanitary sewer. However, a maintenance access road was constructed along a portion of the
stream along the Berkshire Apartments. The access road is approximately 800 feet in length and extends from the
Washington State Department of Transportation (WSDOT) 1-405 right-of-way upstream to the parking lot for the
Berkshire Apartments. When constructed, the Berkshire Apartments were called the Country Hills Apartments.
Based on contours on record drawings for the Country Hills Apartments, this access road existed as of 1980. It is
unknown when the access road was constructed. The width of the access road varies by location and condition.
The width varies from 9 feet to 20 feet.
In November 2008, a storm drain conveying the upper portion of Thunder Hills Creek failed in the vicinity of the
Berkshire Apartments. There was erosion in the vicinity of the storm drain and along the sanitary sewer access
road. In response to the failure, a section of the storm drain was replaced. In November 2009, sediment plugged
the storm drain inlet, the creek flowed overland, and extensive erosion occurred. In November/December 2009,
City of Renton maintenance crews unplugged the storm drain inlet and constructed a trapezoidal overflow channel
above the existing storm drain using large rock and quarry spalls. The rock and quarry spalls that were placed in
the eroded areas as well as at the inlet of the existing storm drain. This was done to minimize the potential of
further erosion, protect the access road, protect the existing sanitary sewer line, and protect the repaired storm
drain.
TECHNICAL MEMORANDUM (CONTINUED)
In addition, the maintenance access road downstream of the Berkshire Apartments toward I-405 is also unstable.
Based on record drawings dated 1984, the city constructed gabion walls along the left bank of Thunder Hills
Creek in various locations along the access road. However, these gabion walls have failed in several locations,
and portions of the access road have washed out.
Thunder Hills Creek, in the vicinity of the Berkshire Apartments and down to I-405, continues to be subject to
erosion and the sanitary sewer line, storm drain, and access road are at risk of being damaged. This memorandum
summarizes options that have been considered to protect the existing sanitary sewer.
Mitigation for stream and riparian impacts due to the emergency riprap placement and permitting associated with
the preferred alternative identified below are discussed in a separate technical memorandum (April 15, 2011,
Parametrix). In addition, restoration and protection of the maintenance access road have been considered because
the road is needed to access the sanitary sewer, or the sanitary sewer is located under the access road, depending
on the location of the sanitary sewer.
Due to changes in soils and topography, the project area has been divided into the Upper Failure Site along the
Berkshire Apartments, and the Lower Reach between the Apartments and I-405. Figure 1 shows the project
location. Figure 2 shows the areas of impact. Figure 3 shows the limits of the project survey and how the project
has been divided.
The City has scheduled a television inspection of the existing sanitary sewer in 2016. Because the condition of the
existing sanitary sewer will not be known until the inspection is performed, this analysis focuses on short-term
solutions to address the stability of the sanitary sewer until 2016. After the television inspection is performed,
long-term options will be developed based on the condition of the existing sanitary sewer, replacement options,
and alignment options.
EXISTING CONDITIONS
Watershed Description
The headwaters of Thunder Hills Creek are located to the southeast and upstream of I-405. Upstream of 1-405, .
Thunder Hills Creek is contained in a ravine through the project area. Upstream of that the stream is still confined
within a steep valley with a narrow floor. The headwaters of the stream are developed with residential
development of varying densities. Downstream of the project area ravine, Thunder Hills Creek flows under I-405
and then flows through several ditches and pipes and a three -sided concrete flume before its confluence with
Rolling Hills Creek. The lower portion of the watershed is intensely developed for commercial land uses and has
little to no natural riparian vegetation. Rolling Hills Creek is a tributary of Springbrook Creek and ultimately the
Green River.
Habitat and Fish Use
Thunder Hills Creek and Rolling Hills Creek do not support anadromous fish. The project reach supports
cutthroat trout, western brook lamprey, sculpin, and threespine stickleback (WSDOT 2008a). Springbrook Creek,
which is approximately 1.5 miles downstream, is the first resource that supports Chinook, coho, and Steelhead
Trout. Based on the WSDOT Environmental Assessment of this watershed, I-405 acts as a complete upstream fish
passage barrier due to the water velocity in the storm drain during high water flows and the report mentions
numerous additional blockages to fish migration throughout Thunder Hills Creek (WSDOT 2008a).
City of Renton 218-1779-037
Upper Failure Site Options 2 June 21, 2011
n Figure 1
(� Thunder Hills Creek
o N aoo Vicinity Map
SCALE IN FEET ,
.�J
PROJECT AREA OF
IMPACT
EXCESS MATERIAL
PLACED AFTER 2009
OVERFLOW CHANNEL
CONSTRUCTION
:y1
EXISTING THUNDER HILLS CREEK CULVERT
\ \ + i �i i +_', •'�:�, 36's DIA INSIDE 4a%DIA PIPE
EXISTIN ANITARY SEWERI
XI N RIPRAP L M T
i
�� ':\';fir=,\�=N �';•\ \ ' :r `.fir z
•\ \ \,\ j EXISTING STORM DRAIN
BASIN
• \ _ } \4 : _ EXISTING THUNDER HILL:
CREEK CULVERT, 48' DIA
RIPRAP AT CULVERT
aG GRAVEL ACCESS ROAD
THUNDER HILLS
-FT FROM CULVERT
ASSUME CULVERT IN
STORIC STREAM
'
IMPACTED AREA =401 SO FT,
AREA IMPACTED DURING 2008
\\��`:,^�' '1`•t."y�(\\1.%L'\i �' POTENTIA
? _ , �•: n, , r �� SITE
\ =-\'y ��� py 4' •\
AND 2009 EMERGENCY
ACTIONS THAT WAS NOT
\ �:=\;,•\;'C' Y��.: j ,,TAt
PREVIOUSLY DISTURBED.
\' < EXISTit
WALLS
LEGEND
— PARCEL LINE��:
\'
— — — — — — — UTILITY EASEMENT LINE
EXISTING RIPRAP LIMITS
Figure 2
Thunder Hills Creek
N Area of Impact
EXISTING WSDOT CULVERT J
GPR
GPR
KJ ..
GPR
\
/ EXISTING SANITARY SEWER) `
\
LOWER REACH \
\ \ 1f
\ \ 1
\ I
GPR 6 OVERALL GROUND SLOPE TO \
; �'•'�rLIMITS OF RIPRAP PLACED
—
TOE �• � "mot
TOE OF RIPRAP: 100 % GPR 6`,r\ +N a >�7� DURING 2008 AND 2009
EMERGENCY ACTIONS \
OVERALL GROUND SLOPE,
STORM DRAIN TO NEAR TOP
OF SLOPE: 10% \ ,l 1t t GPR 7
\`
\' , V GPR9
EXISTING STORM DRAIN
:-GPR 9
V.
--- ---��\,mow\2� �:`'• t Il
t p
GPR 11
LEGEND:
GPR GROUND PENETRATING RADAR SECTION LOCATION
l y.`
GEOTECHNICAL SECTION LOCATION
'arametrlx
UPPER FAILURE SITE
rigureThunder
s
�\ Thunder Hills Creek
0 N fi0 Upper Failure Site
® and Lower Reach
SCALE IN FEET
TECHNICAL MEMORANDUM (CONTINUED)
It is not likely that the stream supported salmon spawning and migration because of the stream slope, the
associated high velocities, and the sandstone layer within the project area. Within the Upper Failure Site, the
sandstone layer is relatively deep and is covered with granular material. However, the sandstone layer has a drop
of over 26 feet and a slope of over 26 percent at the transition to the Lower Reach. Both of these criteria exceed
limits for fish passage. Within the Lower Reach, the sandstone layer is exposed within the normal flow portion of
the stream channel. Because of the smooth walls and high velocities within the sandstone channel, spawning and
rearing habitat could not be sustained.
Site Conditions
The Upper Failure Site begins approximately 355 feet upstream of the I-405 storm drain and continues
approximately 280 feet upstream. The Upper Failure Site is generally the same as the area where the riprap was
placed in November/December 2009 (see Figure 2). In the Upper Failure Site, Thunder Hills Creek has an overall
gradient along the riprap of approximately 10 percent from the top of the existing 48-inch-diameter storm drain to
the beginning of the steep slope. The flow path then has a slope of approximately 100 percent from the top of the
slope to the toe of the slope near the discharge point of the existing storm drain.
The stream channel has a high point in the riprap in an effort to route water through the existing storm drain.
However, based on observations by Parametrix on November 1, 2010, and by the City on December 15, 2010, the
inlet to the existing storm drain was submerged, and flow was routed along the riprap above the pipe. Based on
these observations, the existing storm drain appears to have limited capacity and may be plugged. The storm drain
was not able to be television inspected when field services were performed for the project.
The Lower Reach is located immediately downstream of the Upper Failure Site, where the stream is in a ravine
with steep sidewalls. The channel is incised and largely contained in weathered sandstone with very little in -
stream habitat or gravel. The right bank is made of sandstone and is relatively stable except where noted in the
geotechnical memorandum. The existing sanitary sewer and access road are located along the left bank (looking
downstream). Based on record drawings, portions of the left bank have been armored with gabion baskets, which
were intended to protect the unstable loose materials associated with the historic access road. Many of the gabion
baskets are failing.
Sanitary Sewer
Based on information provided by the City, the existing sanitary sewer is 12-inch-diameter pipe. However, record
drawings of the original construction indicate the pipe is 10-inch-diameter asbestos cement. There are no existing
manholes on the sanitary sewer within the project area. Connections to the existing sewer from the Berkshire
Apartments were made using tees with cleanouts.
The sanitary sewer was not able to be television inspected during site survey. Consequently, the condition of the
line is unknown. Also, because of equipment limitations, survey crews could not locate portions of the sanitary
sewer within the project area. Consequently, the sewer location shown on the project base map is based on data
obtained at selected locations.
Ground penetrating radar (GPR) was used at eleven sections as shown on Figure 3. The location of the existing
sanitary sewer was interpolated between the GPR sections and plotted on geotechnical cross -sections to determine
the potential sewer elevation relative to the soil profile. Based on the geotechnical data obtained and the field
locating results, the existing sanitary sewer appears to be located within the layer of weathered or unweathered
sandstone where geotechnical data was obtained. Where the sanitary sewer is located in the sandstone layer, it is
anticipated that the joints of the existing sewer would not be impacted by lateral stream migration. Also, because
of the relatively steep slope of the existing sewer, it is anticipated that there is limited corrosion in the pipe. The
main cause of corrosion of sewers conveying domestic wastewater is the accumulation of hydrogen sulfide gas
where there is blockage in the sewer or the sewer has a relatively flat slope.
City of Renton 218-1779-037
Upper Failure Site Options 6 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
Existing Storm Drain
An attempt was made to television inspect the existing storm drain that conveys Thunder Hills Creek. However,
blockage was encountered in the existing pipe, and only a limited section of pipe could be inspected.
Consequently, the overall pipe condition and alignment could not be determined. Based on site observations by
the City and by Parametrix, the existing storm drain appears to be plugged and its capacity significantly reduced.
It is not currently known if the pipe was installed following the profile of the sandstone layer or in a trench cut
into the sandstone layer. If the pipe was installed following the profile of the sandstone layer, the pipe would have
a steep slope at the end where the sandstone layer has a significant drop. If the pipe was installed in a trench
within the sandstone layer, this would likely have taken a significant amount of time because of the time and
effort required to excavate into sandstone.
Access Road
The segment of the existing access road located adjacent to the Upper Failure Site and along the Berkshire
Apartments appears stable. This portion of the access road was used to access the Upper Failure Site to perform
the storm drain repairs and emergency riprap placement in 2008 and 2009.
The segment of the access road located between the Upper Failure Site and the Lower Reach has failed and can
only be traversed by foot. This segment of access road could also be traversed by small construction equipment if
it was improved and stabilized by filling in voids and clearing vegetation. Restoring the segment of the access
road located at the failure site for use by heavy maintenance or construction equipment would be costly since a
retaining wall would be needed to limit encroachment into the stream.
The condition of the access road along the Lower Reach varies. The access road is severely degraded in locations
where gabions along the left bank of the stream have failed. The Lower Reach does not appear to be readily
accessible from I-405. Consequently, this memorandum focuses on options for the Lower Reach to stabilize the
access road and temporarily protect the existing sanitary sewer until the television inspection is performed in 2016
and a long term solution identified based on the inspection results. Options were considered that would allow
relatively small construction equipment to access the Lower Reach from the Upper Failure Site.
UPPER FAILURE SITE OPTIONS CONSIDERED
Four options were considered to permanently stabilize the Upper Failure Site and address the mitigation required
for placing the riprap during the emergency response (see Table 1). A detailed description of each alterative is
provided in the following sections.
Table 1. Summary of Upper Failure Site Options
Design Element Option A — Option B — Stream Option C — Option D — Full
Do Nothing Construction Repair/Replace Restoration for
Existing Storm Drain Fish Passage
Existing Riprap Leave in place. Temporarily remove riprap to Leave in place. Remove.
perform channel grading. Install
liner over any remaining loose in
situ material. Install vegetation
along normal flow portion of
channel. Install riprap along
high -flow portion of channel.
Table Continues
City of Renton 218-1779-037
Upper Failure Site Options 7 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
Table 1. Summary of Upper Failure Site Options (Continued)
Design Element
Option A —
Option B — Stream
Option C —
Option D — Full
Do Nothing
Construction
Repair/Replace
Restoration for
Existing Storm Drain
Fish Passage
Existing High
Leave in place.
Remove.
Leave in place.
Remove.
Point
Existing Storm
Leave in place.
Remove/abandon.
Replace/repair.
Remove/abandon.
Drain
Existing Sanitary
Leave in place.
Leave in place.
Leave in place
Leave in place
Sewer
Stream Habitat
On -site mitigation.
On -site mitigation. Provide in
On -site mitigation.
On -site mitigation;
bench areas outside of low -flow
limited design life due
channel and beyond edges of
to velocities and slopes
design water surface elevation
through sandstone
where feasible.
layer.
Existing Access
Leave as is.
Reconstruct as part of stream
Reconstruct as part of
Reconstruct as part of
Road
construction.
storm drain
channel restoration
repair/replacement.
construction.
Upper Failure Site Option A — Do Nothing
Option A would leave the existing riprap in place, leave existing grading as -is, leave the existing storm drain as -
is, and would provide on -site mitigation for placement of the riprap. On -site mitigation would be performed
upstream of the inlet to the existing storm drain. See the mitigation memorandum (Parametrix 2011) for further
information about off -site mitigation.
Flows that cannot be conveyed through the existing storm drain are conveyed through the voids in the riprap and
along the top of the riprap. Although there may be finer grained soils below the riprap that could be transported
out of the riprap, the site appears stable for current conditions. Option A includes annual inspection of the riprap
and site stability until the television inspection in 2016. Any long-term options for the riprap at the Upper Failure
Site would be addressed after the television inspection.
Option A provides the lowest cost solution for the Upper Reach because there are no construction activities in the
Upper Reach.
Upper Failure Site Option B — Construct a Normal Flow Channel
Option B would remove or abandon the existing storm drain and re -grade the'stream channel from approximately
46 feet upstream of the existing storm drain inlet to the top of the riprap near the storm drain outlet. The new
stream channel would be the sole conveyance through this reach. Approximately 245 feet of the new channel
would have a slope of 2 percent and the high point in the profile would be removed. This portion of the stream
channel would be restored with natural streamgravel substrate, a floodplain terrace, and native plants in the
riparian area. At the downstream end of this reach, the stream would transition to a reach with a slope of
approximately 40 percent, which matches the existing slope of the bedrock. This lower reach is approximately
75 feet long and would continue to be lined with riprap for long-term stability.
Option B would be constructed by temporarily removing the existing riprap so that a liner could be installed over
any loose material (historic fill). Once the site was stabilized the new open channel would be constructed using
the retained riprap. Option B would also include restoration of the access road since that would be required for
construction of the channel.
City of Renton 218-1779-037
Upper Failure Site Options 8 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
Option B has the advantage of providing on -site stream restoration for the area impacted during the emergency
riprap placement. Similar to existing conditions, Option B would not provide fish passage because of the steep
slope at the end of the riprap.
Upper Failure Site Option C — Repair/Replace Existing Storm Drain
Option C would leave the existing riprap and high point in place and add additional riprap to the Upper Failure
Site as needed to stabilize the stream. The existing storm drain pipe that historically conveyed the stream in this
reach would be repaired or replaced and would continue to convey most of the stream flows except during flood
events. Option C would require off -site mitigation for the riprap placed during the 2008 and 2009 emergency
responses and for additional riprap placed to stabilize the stream. Option C would include restoration of the access
road since that would be required for construction equipment access for the storm drain repair/replacement.
For the short-term, Option C has a relatively high cost for the storm drain with little benefit to the existing
sanitary sewer. Based on observations by the City and Parametrix, the riprap in the Upper Failure Site appears to
be stable for the current storm drain condition. Repairing/replacing the existing storm drain as part of a long-term
solution will be evaluated after the existing sanitary sewer is television inspected in 2016. If the City wishes to
further consider replacing or repairing the existing stonn drain, the existing debris will need to be removed from
the pipe and the pipe television inspected to determine the condition, size, and material of the pipe. The television
inspection will also give an indication of changes, if any, in the horizontal and vertical alignment of the pipe,
which will be important if a trenchless technology is desired. If the existing storm drain is replaced, the opening at
the end near the riprap drop-off will need to be exposed to allow for construction and a free discharge at the end
of the pipe.
Upper Failure Site Option D — Full Restoration for Fish Passage
Option D would remove all of the riprap placed in the stream during the 2008 and 2009 emergency responses,
remove the existing storm drain pipe, remove historical fill, and reconstruct an open channel using large rounded
river rock. Grade control structures would not likely be used because the slope and velocities would reduce their
long-term viability. The constructed stream would have an overall slope of approximately 11.4 percent.
Construction of this channel would require extensive grading, which would extend into the toe of the valley wall
and would likely extend into the sandstone layer. Option D would provide the greatest restoration of the stream
since all material placed historically as well as during emergency riprap placement would be removed. Sections of
storm drain below the riprap would be plugged. Option D would provide on -site stream restoration.
Option D has a high level of risk because the underlying sandstone layer may preclude the long-term stability of
constructed stream 'restoration measures. Such measures could wash out during high -flow events. Also,
Washington State Department of Fish and Wildlife (WDFW) has published guidelines for determining natural
fish passage barriers. For resident cutthroat, the upper boundary gradient is 20 percent (WDFW 2003). This
gradient is exceeded at the northerly (downstream) end of the Upper Reach. Based on the stream gradient, the
underlying sandstone layer, the gradient of the underlying sandstone layer, and the potential for erosion, it was
determined that restoring the Upper Reach to provide for fish passage was not feasible.
LOWER REACH OPTIONS CONSIDERED
Short-term options for protecting the existing sanitary sewer in the Lower Reach are discussed in the following
sections and summarized in Table 2. These options were identified based on observations by City staff on
December 15, 2010, and by Soil and Environmental Engineers, Inc. on January 27, 2011. These options were
identified because the existing sanitary sewer is generally not located immediately adjacent to the stream bank and
is scheduled for TV inspection in 2016.
City of Renton 218-1779-037
Upper Failure Site Options 9 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
Long-term options for the existing sanitary sewer will be developed after the television inspection is performed in
2016. If the existing
sanitary sewer is in acceptable condition and does not need to be replaced,
then an evaluation
should be performed
to determine if a more permanent wall should be constructed or the sanitary
sewer located in
an alternative alignment. If the existing sanitary sewer is not in an acceptable condition, then replacing the sewer
in a similar or new
alignment or repairing the sewer with a trenchless technology would likely
be considered.
Stabilizing the Lower Reach for a long-term solution would need to be considered at that time.
Table 2. Summary of Lower Reach Options
Option C -
Option D - Replace
Option B - Replace Replace Existing
Existing Gabion
Existing Gabion Gabion Baskets
Baskets with an
Element
Option A - Do Nothing Baskets with a Rockery
Armored Slope
Impacts to
Ongoing gabion failure likely Areas not protected Areas not protected
Areas not protected
Existing Access
with subsequent erosion along may erode in future. may erode in
may. erode in future.
Road
road edge. future.
Impacts to
Potential plugging if access Potential plugging if Potential plugging if
Potential plugging if
Existing WSDOT
road washes out or east bank new areas erode or new areas erode or
new areas erode or
Storm Drain at
fails. east bank fails. east bank fails.
east bank fails.
1-405
Potential damage to 1-405 fill
embankment.
Potential flooding of 1-405.
Overflow riser at
Not included. Install. Install.
Install.
WSDOT Storm
drain at 1-405
Amount of
18,300 cubic feet.a Not applicable unless Not applicable
Not applicable
Erosion
new areas erode. unless new areas
unless new areas
erode.
erode.
Inspection
Every 2 months between Semiannually to review Semiannually to
Semiannually to
Frequency
October and May. status of unprotected review status of
review status of
areas. unprotected areas.
unprotected areas.
Stabilization
Not Applicable. Gabions. Rockery.
Not evaluated; not
Material
considered feasible.
Advantages
No construction costs. Stabilize currently Does not rely on
Not evaluated; not
eroded areas at wire baskets for
considered feasible.
relatively low cost. long-term stability.
Disadvantages
Potential loss of access road
Cost incurred prior to
Earthwork; new
Would require
along sanitary sewer.
2016 television
rockery below
extensive earthwork
Potential loss of sanitary sewer
inspection.
ordinary high-water
and likely changing
if east bank fails and stream
mark (OHWM).
the cross -slope of
realigns.
the existing access
Potential emergency repairs
road.
during winter months.
Potential water quality violations
and fines.
Typical
Not Applicable.
See Attachment B.
See Attachment B.
Not developed; not
Cross -Section
considered feasible.
Permitting
Not Applicable
Would require a
Would require an
Not evaluated; not
Issues/Mitigation
Hydraulic Project
HPA and local
considered feasible.
Approval (HPA) and
critical areas
local critical areas
permits.'
perm its. b
a Amount of erosion assumes washout of approximately half of access road along the Lower Reach and loss of embankment material along the east bank
overhang material as discussed in the geotechnical memorandum. Access road volume reflected is based on 360 linear feet, 7.5 feet wide, 4 feet high. Loss
of east bank overhang materials based on 250 linear feet, 10 feet wide, 3 feet high.
b Refer to Parametrix technical memorandum dated 04/08/2011
City ojRenton 218-1779-037
Upper Failure Site Options 10 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
Lower Reach Option A — Do Nothing
Option A would not take any action to replace the failing gabion baskets, but does include quarterly inspection of
the existing gabions to monitor their condition prior to the television inspection scheduled in 2016. This would
enable the City to identify locations on the access road that may need to be stabilized until the television
inspection is performed.
The existing access road and gabion baskets would continue to be subject to erosive action by the stream, and
there is a high potential for continued failure of gabion baskets and loss of access road material, which could
result in failure of the existing sanitary sewer depending on the extent of erosion and the location. Also, there is
the potential for plugging at the existing WSDOT storm drain under I-405 and flooding of I-405 without a
provision for overflow.
Costs for these types of losses are not included in Table 3. The cost to perform the quarterly inspection is also not
included in Table 3; however, it is anticipated that the inspection could take up to 2 hours of staff time to perform
each inspection.
Under Option A, there is no projected capital cost.
Lower Reach Option B — Replacing Existing Gabion Baskets
Option B includes replacing the existing gabion baskets that have failed with new gabion baskets in their current
location. The condition of the existing gabions varies along the stream. Some gabions have failed. Some gabions
are in the process of failing due to corrosion of the wire mesh. Gabion failure results in loss of the retained
aggregate and the access road material. Some gabions are still intact and some are leaning which indicates lateral
movement of the hillside along the access road. Additional gabion failure and loss of access road material has
occurred from fall 2010 through winter 2011. Uncoated gabion wire can also contribute metals into the stream as
the wire corrodes.
The stream bank erosion along the left bank is encroaching on the alignment of the sanitary sewer. In addition, the
sanitary sewer is also potentially subject to damage if the east (right) bank of the stream fails. The east (right)
bank, which is on the opposite side of the access road, has several locations where soil overhangs the stream
channel. If the soil in the overhang areas fails and falls into the stream, the soil could block the stream flow
because of the large soil volume. This blockage in the stream could cause the stream to realign to the looser
materials along the access road. If the stream washes out the access road material, it could potentially wash out
bedding material for the sanitary sewer, which could result in pipe damage and/or failure and subsequent
discharges of sanitary sewer flows. Stabilizing the right bank was not evaluated because technical and permitting
factors would result in a higher cost than stabilizing the left bank.
The advantage to Option B is that it provides a relatively low cost short-term solution. The gabions are accessible
by relatively small construction equipment, which is an important consideration due to access constraints.
Option B also includes excavating at least two test holes along the alignment of the sanitary sewer to confirm if
the sanitary sewer is located within the sandstone layer.
For Option B, it is anticipated that minor grading could occur along the west bank between the Upper Failure Site
and Lower Reach to restore access between these two sections because there does not appear to be adequate
access to the Lower Reach from I-405. Access would need to be restored to accommodate smaller construction
equipment to transport materials to the Lower Reach. If large equipment was used, a retaining wall would likely
be required, which would increase the costs reflected in this technical memorandum.
City of Renton 118-1779-037
Upper Failure Site Options ! 1 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
Lower Reach Option C — Replace Existing Gabion Baskets with a Rockery
Option C includes removing any remaining gabions and constructing a rockery the full height, minimum, of
existing gabions. Although rockeries can provide erosion control, rockeries do not provide lateral stability.
For Option C, it is anticipated that minor grading could occur along the west bank between the Upper Failure Site
and Lower Reach to restore access between these two sections because there does not appear to be adequate
access to the Lower Reach from I-405. Access would need to be restored to accommodate smaller construction
equipment to transport materials to the Lower Reach. If large equipment was used, a retaining wall would likely
be required, which would increase the costs reflected in this technical memorandum.
Lower Reach Option D — Replace, Existing Gabion Baskets with an Armored Slope
Option D would decrease the slope on the edge of the access road and install a slope armoring system. However,
there could be a significant cut within the access road to accommodate the system, depending on the
manufacturer's requirements. Also, an armored slope protects against erosion but does not provide lateral stability
which is necessary for the ongoing stability of the sanitary sewer.
Because Option D is more extensive than Options B and C, it is not likely that minor grading for construction
equipment access between the Upper Failure Site and the Lower Reach would be adequate. Consequently, a
retaining wall would likely be required.
CONSTRUCTION COSTS
Table 3 presents the opinion of probable construction cost for each option considered for the Lower Reach.
Table 3. Conceptual Opinion of Probable Construction Costs for Lower Reach Options
Option B -
Option C - Replace
Option D - Replace
Option A: Do
Replace Existing
Existing Gabion Baskets
Existing Gabion Baskets
Element
Nothing
Gabion Baskets
with a Rockery
with an Armored Slope
One overflow riser
$0
$14,650
$14,650
$14,650
(WSDOT cost)
On -site mitigation for
$2,000
$2,000
$2,000
$2,000
Upper Reach emergency
riprap placement
Off -site mitigation for
Not applicable
Not applicable
Not applicable
Not estimated; not
Lower Reach
considered feasible
Restore access from
Not applicable
Incidental grading
Incidental grading
Not estimated; not
Upper Reach
considered feasible
Remove existing gabion
Not applicable
$5,600
$5,600
$5,600
baskets where failed and
rock
Install new gabion baskets
Not applicable
$21,600
Not applicable
Not applicable
and rock where replacing
failed gabions
Install rockery
Not applicable
Not applicable
$12,600
Not applicable
Install armored slope
Not applicable
Not applicable
Not applicable
Not estimated, not
considered feasible
TOTAL:
$2,000
$43,850
$22,250
Not estimated; not
considered feasible
City of Renton 218-1779-037
Upper Failure Site Options 12 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
EVALUATION PROCESS
The options developed for the Upper Failure Site (Table 4) and the Lower Reach (Table 5) were evaluated
independently using the following criteria:
• Constructibility — Criteria based on whether or not the option would allow smaller construction vehicle
access without having to restore the failed portion of the access road between the Upper Failure Site and
the Lower Reach. A value of 0 indicates that the access road would likely not have to be restored except
for minor grading. A value of 5 indicates that the access road would need to be fully restored for access
by large construction equipment.
• Relative Construction Cost — Criteria based on relative construction cost. A value of 0 indicates that there
is no construction cost. A value of 5 reflects a high relative construction cost. This evaluation criteria does
not reflect inspection time by City maintenance staff.
• Long-term Channel Stability — Criteria based on whether or not the option would provide long-term
stability for the Upper Failure Site or short-term stability for the Lower Reach. A value of 0 reflects that
stability is anticipated. A value of 5 reflects that failure is anticipated during a high -flow event. A lower
value is preferred.
• Maintenance Concerns — Criteria based on anticipated frequency of inspection. A value of 0 reflects an
inspection frequency of less than one per year because stability is. anticipated. A value of 3 reflects
quarterly to annual inspection frequency but that no maintenance is required because stability is
anticipated. A value of 5 reflects that maintenance will need to be quarterly at a minimum and some
amount of maintenance activity would be required because stability is not anticipated.
• Off -Site Mitigation — Criteria based on if the option requires off -site mitigation. A value of 0 reflects no
off -site mitigation required. A value of 5 reflects off -site mitigation will be required. Because of the small
area disturbed during the emergency riprap placement in 2008 and 2009, it appears that mitigation can be
provided on -site. Consequently, off -site mitigation is not likely to be required for any of the options.
• These criteria were not evaluated for the Lower Reach since the Lower Reach is outside the limits of the
emergency riprap placement.
Table 4. Evaluation of Options for Upper Failure Site
Option C - Option D - Full
Option A - Option B - Stream Repair/Replace Restoration with
Evaluation Criteria Do Nothing Construction Existing Storm Drain Open Channel
Constructibility
0
5
5 5
Relative Construction Cost
1
3
4 5
Long-term Channel Stability
2
3
2 5
Maintenance Concerns
2
3
3 5
Off -Site Mitigation
0
0
0 0
Upper Failure Site Score: 5 14 14 20
City of Renton 218-1779-037
Upper Failure Site Options 13 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
Table S. Evaluation of Options for Lower Reach
Evaluation Criteria
Option A —
Do Nothing
Option B — Replace
Existing Gabion
Baskets
Option C — Replace
Existing Gabion
Baskets with a
Rockery
Option D — Replace
Existing Gabion
Baskets with an
Armored Sloped
Requires full access restoration
from Upper Failure Site to
Lower Reach
0
0
0
5
Relative Construction Cost
0
2
1
5
Long -Term Channel Stability
5
3
3
3
Maintenance Concerns
4
2
2
2
Fish Passage
N/A
N/A
N/A
N/A
Off -Site Stream Habitat
N/A
N/A
N/A
N/A
Lower Reach Score:
9
7
6
15
PREFERRED ALTERNATIVE
For the Upper Failure Site, Option A ranked the lowest and is the preferred alternative. Option A provides the
lowest cost solution for the Upper Failure Site because there are no construction activities in the Upper Failure
Site.
The following options are not recommended for the Upper Failure Site:
• Option B is not recommended because of concerns with the long-term stability of the streambed
aggregate that would be placed in the new channel and does not increase protection of the existing
sanitary sewer in this portion of the project area.
• Option C is not recommended because the cost to repair or replace the existing storm drain does not
increase protection of the existing sanitary sewer in this portion of the project area.
• Option D is not recommended because of the cost and concerns with long-term stability of the stream
restoration.
For the Lower Reach, Options B and C are ranked similarly and have the lowest ranking. Options B and C
provide the lower cost solutions to address short-term stability for the Lower Reach until the television inspection
is performed in 2016. Option B (replace gabions) would use materials similar to existing conditions and could
possibly reuse and recovered basket fill material. Option C (rockery) would require materials that are different
from existing conditions. However, Option C has the advantage of not relying on the long-term stability of the
gabion wire. If it is determined that the existing sanitary sewer can remain in its current location after the 2016
television inspection, the rockery installed in Option C could be left in place without long-term concerns
regarding corrosion of the wire.
This technical memorandum focused on impacts to previously constructed elements within the Upper Failure Site
and Lower Reach, for example, potential options to address existing gabions. However, based on field
observations by the geotechnical engineering firm, Soil and Environmental Engineering, there are locations along
the west (left) bank of the Lower Reach where additional stabilization should be considered if Option B or C are
implemented. The additional stabilization would include construction of approximately 95 linear feet of new
rockery from 150 to 195 feet and 215 to 265 feet upstream of the existing WSDOT storm drain under I-405.
Currently, there are no existing gabions at these locations but the west (left) bank is eroding.
City of Renton 218-1779-037
Upper Failure Site Options 14 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
The following options are not recommended for the Lower Reach:
• Option A is not recommended because of the potential risks to the existing sanitary sewer and the existing
WSDOT storm drain if the gabions continue to fail or the right bank fails.
• Option D is not recon-u-vended because the high cost could be a short-term solution if the existing sanitary
sewer needs to be rerouted.
Additional surveying, geotechnical field exploration, and engineering as well as television inspection of the
existing sanitary sewer will be required to support future design phases of the preferred alternative.
The cost of the preferred alternative is summarized in Table 6. The cost opinion includes the following
assumptions:
• There is no work in the Upper Failure Site;
• Stream restoration will occur on -site;
• The construction will occur outside of the rainy season;
• Existing gabions will be replaced with new gabions based on the limits shown on as -built drawings;
• Approximately 95 linear feet of rockery infill will be constructed; and
• A long-term solution will be evaluated after the television inspection in 2016.
Table 6. Summary of Cost Opinion for Preferred Alternative
Item
Opinion of
Cost
Approximately 400 square feet of on -site riparian restoration, including weed removal and understory plantings
2,000
Emergency Overflow Riser on WSDOT storm drain
14,650
Install approximately 56 cubic yards of gabion wall along Lower Reach access road
27,105
Install approximately 84 cubic yards of rockery infill along Lower Reach access road
15,575
Allowance for Temporary Erosion and Sediment Control
3,000
Subtotal, Construction:
$62,330
Contingency
18,700
Sales Tax
5,920
Survey, Engineering, Geotechnical, TV Inspection
12,470
Permitting
3,120
Allowance for Temporary Construction Easements
3,120
Administration
3,120
Construction Management
6,230
TOTAL:
$115,010
REFERENCES
Parametrix, Inc. 2011. Thunder Hills Creek Permitting Options. Technical Memorandum to City of Renton.
Puyallup, Washington.
WDFW (Washington Department of Fish and Wildlife). 2003. Design of Road Culverts for Fish Passage. Fish
Passage Technical Assistance. May 2003.
City of Renton 218-1779-037
Upper Failure Site Options 15 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
WSDOT (Washington State Department of Transportation). 2008a. I-405, Tukwila to Renton Improvement
Project (I-5 to SR 169 — Phase 2) Ecosystems Discipline Report. Prepared by Anchor Environmental, LLC.
WSDOT. 2008b. Thunder Hills Creek Culvert Emergency Replacement, I-405, MP 3.05, Summary Report.
City of Renton 218-1779-037
Upper Failure Site Options 16 June 21, 2011
ATTACHMENT A - SCORING CRITERIA
CITY OF RENTON
Thunder Hills Creek
1
I
I
Ranking of Project Options
I
I
�
I
I
I
Option C - Repair
Option B -
/ Replace
Option D - Full
Option A - Off-
Stream
Existing Storm
.Restoration with
Evaluation Criteria
site Mitigation
Construction
Drain
Open Channel
Comments
UPPER FAILURE
SITE
Requires full access restoration
from Upper Failure Site to
Lower Reach
0
5
5 5 0 = does 1 require; 5 = required
_
_
10 = none; 3 = medium range of options
'considered; 5 = high. Does not reflect
cost for maintenance staff for inspection
Relative Construction Cost
1
3
4
5
for maintenance actions
I
10 = long term stability anticipated. 2 or 3
concern of loss of looser material
under existing riprap. 5 = subject to
Long Term Channel Stability
2
3
2
5
!failure during high flow event.
IO = none or low if option is considered
!stable for the long term. 3 = quarterly to
'annual inspection frequency to review
stability but option is considered
relatively stable for the long term. 5 =
Maintenance Concerns
2
3
3
5 !subject to failure in high flow event
_
;Not evaluated since stream was not
Fish Passage
N/A
N/A
N/A
N/A ,likely fish passable. _
_
I
10 = not required since option provides on
Off -site Stream Habitat
0
0
0
0 site stream restoration. 5 = required.
Upper Failure Site Score 5 14 14 20
LOWER REACH
i
Option D -
Option C - Replace Existing
Option B - Repair Replace Existing Gabion Baskets
Option A - Do ExistingGabion Gabion Baskets with an Armored
Evaluation Criteria Nothing I Baskets with a Rockery Sloped (Comments
Requires full access restoration
i
from Upper Failure Site to
I
Lower Reach
0
0
0
5 10 = does not require; 5 = required
0 = none or low; 3 = medium range of
options considered; 5 = high. Does not
;reflect cost for maintenance staff for
Relative Construction Cost
0 1 2
1
5 inspection or maintenance actions
0 = long term stability anticipated. 2 or 3
= concern of loss of looser material
under existing nprap. 5 = subject to
Long Term Channel Stability
5
3
3
3 !failure during high flow event.
0 = none or low if option is considered
stable for the long term. 3 = quarterly to
annual inspection frequency to review
stability but option is considered
'relatively stable for the long term. 5 =
Maintenance Concerns
4
2
2 Isubject to failure in high flow event
_
__2_
'Not evaluated since stream was not
Fish Passage
N/A
I N/A
N/A
N/A Iiikely fish passable.
Not evaluated since Lower each is
!outside the emergency riprap placement
Off -site Stream Habitat
N/A
WA
N/A
N/A !area.
Lower Reach Score 9 7 6 15
218-1779-037 (01/04) Prepared February 2011
Data and Analyses.xlsx \ 201 10208 Ranking Page 1 of 1
ATTACHMENT B -
CONCEPTUAL GABION OR
ROCKERY SECTION SKETCHES
1
NOTES:
1. INSTALL NEW GABION BASKET ON TOP OF EXISTING GABION IF
EXISTING GABION WIRE IS STILL IN TACT. WHERE EXISTING
GABION WIRE HAS FAILED IN LOWER COURSE, REMOVE
EXISTING GABION AND INSTALL TWO LAYERS OF GABIONS.
2. DO NOT REMOVE MORE THAN 10- TO 15-FT OF EXISTING
GABION MATERIAL AT A TIME.
3. SECTION BASED ON INFORMATION NEAR GPR 3. GABION
FAILURE, EROSION OF ACCESS ROAD, LOCATION OF EXISTING
SANITARY SEWER. AND LOCATION OF STREAM VARIES.
EXISTING ACCESS ROAD
\ BACKFILL WITH 2" MINUS
CRUSHED ROCK WITHOUT FINES
i
EXISTING SS J
LEAVE EXISTING GABION IN PLACE EXCEPT
WHERE EXISTING WIRE HAS FAILED
CONCEPTUAL SECTION
NOT FOR CONSTRUCTION
NTS
STREAM BOTTOM
/
i
/ EXISTING GROUND
�T ON SANDSTONE LAYER
Parametrlx GATE: AP114, 2011 FILE: SU37S4813F-04
Thunder Hills Creek
Lower Reach Option B
Replace Existing Gabion Baskets
NOTES:
1. WHERE UPPER COURSE OF EXISTING GABION HAS FAILED,
REMOVE ANY REMAINING PORTIONS OF BOTH THE UPPER AND
LOWER COURSE AND INSTALL TWO LAYERS OF 3- OR 4-MAN
ROCK.
2. DO NOT REMOVE MORE THAN 10- TO 15-FT OF EXISTING
GABION MATERIAL AT A TIME.
3. SECTION BASED ON INFORMATION NEAR GPR 3. GABION
FAILURE, EROSION OF ACCESS ROAD, LOCATION OF EXISTING
SANITARY SEWER, AND LOCATION OF STREAM VARIES.
I
\ EXISTING ACCESS RC
\ BACKFILL WITH 2" MINUS
CRUSHED ROCK WITHOUT FINES
�l
EXISTING SS
CONCEPTUAL SECTION
NOT FOR CONSTRUCTION
NTS
Parametrlx GATE: April 14. 2011 FILE: SU3784813F-04
No STREAM BOTTOM
J
6 %
i
� EXISTING GROUND
iET ROCK ON SANDSTONE LAYER
Thunder Hills Creek
Lower Reach Option C
Replace Existing Gabion Baskets
with a Rockery
ATTACHMENT C - CONCEPTUAL OPINION
OF PROBABLE CONSTRUCTION COST
of
Unit
Unit Cost I Amount
Includes 12 cubic yards for
Furnish and install 1 ea 84-inch ID CB Type 2 with Structure Excavation Class B
1 EA house -style opening and beehive grate. $14,650.00 $14,650 Including Haul.
Based on 168-If of existing
gabions per survey and 3-ft by 3-ft
existing gabion section per record
drawings. Assumes only 1 layer
is removed. Unit cost based on
Structure Excavation Class B
56
CY
Remove top course of existing gabions
$100.00
$5,600 Including Haul.
Furnish and install new gabion baskets and
168
LF
crushed rock
$128.00
$21,504 Assumes 1 course of gabions
Assumes 1 layer of 4-man rock
48
TONS
4-man Rdck *ton ockery infill `J
$125.00
$6 000 ' for 95 If
Structure Excavalon Class B Including Haul for,' 1
Assumes 95 If at 6-ft wide by 4-ft
84 CY
rockery infill' 4:
$100.00
:$8 400 : high for new rockery
t
w Assumes 2-fl wide by 4-ft high
r :: aggregate section behind large
47 TONS
Backidl for'Rock Wall alorid rockev ihfill 9
$25.00
$1 175 -; rock.
Furnish and install 1 ea 84-inch ID CB Type 2 with
1 EA
jailhouse-style opening and beehive grate.
$14,650.0
48 TONS
4-man Rock for rockery infill
$125.00
_
Structure Excavation Class B Including Haul for
84 CY
,rockery infill
$100.00
47 TONS
Lackfill for Rock Wall along rockery infill
$25.00
I
112 1 CY Remove two course of existing gabions
I
I
168 TONS i4-man Rock for replacing existing failed gabioi
Structure Excavation Class B Including Haul fc
74 CY rockery to replace existing failed gabions
IBackfill for Rock Wall along rockery to replace
168 TONS existing failed gabions
Furnish and install 1 ea 84-inch ID CB Type 2
1 EA jailhouse-style opening and beehive grate.
48 TONS 4-man Rock for rockery infill _
Structure Excavation Class B Including Haul f
84 CY rockery infill
I
47 TONS Lackfill for Rock Wall alono rockery infill
1 1 LS
$125.00
$100.00
I Includes 12 cubic yards for
Structure Excavation Class 8
$14,650
Including Haul_
(Assumes 1 layer of 4-man rock
$6.000
for 95 If
Assumes 95 If at 6-ft wide by 4-ft
$8,400
� high for new rockery
Assumes 2-ft wide by 4-ft high
aggregate section behind large
$1,175
rock.
,Based on 168-If of existing
;gabions per survey and 3-ft by 3-ft
existing gabion section per record
jdrawings. Assumes 2 layers are
removed. Unit cost based on
Structure Excavation Class B
$11,200
:Including Haul.
,Weight from WSDOT Standard
Specifications. Assumes 2 layers
$21,000
of 4-man rock.
Assumes 168 If at 2-ft wide by 6-ft
$7,400
I high
'aggregate section behind large
11
$25.00
$4 200 rock
;Assumes
5 days of labor.
Includes 12 cubic yards for
Structure Excavation Class B
$14,650.00
$14,650
iIncluding Haul.
Assumes 1 layer of 4-man rock
$125.00
$6,000
(for 95 If
(Assumes 95 If at 6-ft wide by 4-ft
$100.00
$8,400 high for new rockery
(Assumes 2-ft wide by 4-ft high
aggregate section behind large
$25.00
$1,175 (rock.
I
Not estimated; not considered
cost effective for a short term
solution. Does not provide lateral
support and not considered cost
Not Estimated
Not Estimated
effective for a long term solution.
r. '
x'. lA '
Notes: I I
Does not reflect $2,000 for riparian vegetation restoration for Uppear Failure Site.
218-1779-037(01/05)
Cost Opinions.xls \ 04_05_2011 Prepared February 2011
Page 1 of 1
CITY OF RENTON
Thunder Hills Creek
Concept -level Opinion of Probable Cost for Lower Reach
For Preferred Option
Description
Location
Amount, $
Approximately 400 square feet of off -site stream
restoration, including grading and plantings
Upper Failure Site
2,000
Emergency Overflow Riser on WSDOT culvert Lower Reach
Install<approximately 56 cubic yards of new
dabions to, replace existing failed gabions along
Lower�Reach Lower Reach
Con-tructy,approximatelyr84 cubic yards of�rockery
Lower Reach
Allowance for Temporary Erosion and Sediment Upper Failure Site and Lower
Control Reach
14,650
27,105
3,000
Sub -total,. Construction
62,330
Contingency
-- -- — --- ------------
30% --
9.50%
18,700
-
--
Sales Tax
5,920
Survey, Engienering, Geotechnical
20%
12,470
Permitting
5%
3,120
Allowance for temporary construction easements
5%
3,120
Administration
5%
3,120
Construction management,
10%
6,230
Total
1 115,010
218-1779-037 (01/05)
Cost Opinions.xls \ Preferred Option Prepared February 1
of
Page 1 of 1
ENGINEERING . PLANNING . ENVIRONMENTAL SCIENCES
1019 39th AVE SE, SUITE 100
PUYALLUP, WA 98374
T.253.604.6600 F.253.604.6799
www.parametrix.com
TECHNICAL MEMORANDUM
Date: June 21, 2011
To: Dave Christensen
John Hobson
Ron Straka
Allen Quynn
From: Jenna Friebel ffiyylf�
Subject: Permitting Opti ns
cc:
Project Number: 218-1779-037
Project Name: Thunder Hills Creek
INTRODUCTION
The purpose of this technical memorandum is to summarize the proposed habitat mitigation for both the Upper
Failure Site and the Lower Reach, document the anticipated permits required for the project, summarize impacts,
and outline a mitigation strategy for impacts to riparian habitat. This memorandum was prepared specifically to
address stream and habitat restoration and permitting. See the memorandum dated April 15, 2011, prepared by
Parametrix for further project details, project options, and evaluation of identified options.
PROJECT DESCRIPTION
The project area is located in the steep confined ravine of Thunder Hills Creek just southeasterly of I-405 in
Renton (Figure 1). The project area, which includes 660 linear feet of Thunder Hills Creek (280 feet are located in
a pipe), is divided into two distinct reaches: the Upper Failure Site and the Lower Reach, which are generally
divided by the headwall and steep piped segment of stream.
The original project purposes included determining the location of the existing sanitary sewer relative to the
stream channel, evaluating the condition of the existing sanitary sewer, and identifying mitigation options to
offset environmental impacts associated with the emergency placement riprap that occurred in 2008 and 2009.
However, because the existing sanitary sewer was not able to be television inspected due to limitations in the
ability of the system to accommodate inspection equipment (the City has scheduled television inspection in 2016),
the project purpose has been refined. The current project purpose focuses on evaluating short-term options to keep
the sanitary sewer stable from potential stream migration in the lower reach until the television inspection is
performed and on developing stream mitigation plans to offset impacts associated with both the emergency riprap
placement in the Upper Failure Site and the preferred option for protecting the sanitary sewer in the Lower Reach.
�
=> bra
•fit � ' . � ,y` ` � • ,<' � `- Q3 �. /; �+! „Ss;
ft" r � t EEby •.� � • g� i�t . �+� c+.r�� f� f�"'� �.
,THUNDER HMLS CREEK ... ,
� PROXIMATE LOCATION, P15--v
• @s I �.9�, .ram , j "¢�•+�t '<" y'
r
f T LOCAWIN
' '� ..,,! t 1 •� .^♦r tr r w,; -4-'cra `'n � � rsi..� it
i'�4 its'
Ak
lot
rxf+` t '.' �`•'
OWN
10, Magi
oo
t 3�•, t �,m i . �•i' ` y a . F , s->• � � �. lkr. r +-s. r n a
wf
v { 4 i ` low, t om
aa•.y t'Y�'•r �}�,
ss �'`� S}r � yt...; 1 'tt"•t lb' ;�' ,{�,ws�'& ' irk' µy�,,� £S y��.,g• ',i
FE R w �, a �y,,1lo
✓r :a f AR
fat
9po-' .•4 1l ��. �; - ti ,' � r 4�� y:n- %F" t. -kfRt�,� '�' �L.r� y4 g'. y, i. df,{l
.14
•% i
x,.1 !„Y
pig 5 '`3 v S t �q -�s'3"'
D
���. \���''1 �TTI {F.` ��• �'� SJ1t1• ..T
IX
Ell
J. im
ti . "a� ♦y ;8 � �9
TECHNICAL MEMORANDUM (CONTINUED)
Upper Failure Site
Site Conditions
The Upper Failure Site begins approximately 380 feet upstream of the I-405 storm drain and continues
approximately 280 feet upstream. During the 1960s, an access road was constructed during sewer line installation.
At that time, approximately 280 linear feet of Thunder Hills Creek was placed in a storm drain. In November
2008, this storm drain failed during a large storm event. The failure caused the storm drain to plug which resulted
in the stream flowing overland above the storm drain. This overland flow resulted in erosion above the stone
drain and along the sanitary sewer access road. In response to the failure, a section of the storm drain and the
eroded area was regraded and covered with straw.
In November 2009, material plugged the storm drain inlet which once again led to extensive erosion of the access
road and the area above the storm drain. City of Renton maintenance crews unplugged the stone drain and
constructed a trapezoidal overflow channel above the storm drain. This overflow channel was constructed in
November/December of 2009 using large rock and quarry spalls that were placed in the eroded areas to minimize
the potential of further erosion and protect the integrity of the access road, the existing sanitary sewer line, and the
repaired storm drain. Placement of riprap occurred within previously disturbed areas, the stream channel below
the ordinary high water mark (OHWM) at the upstream entrance to the existing storm drain, and immediately
adjacent to the channel in riparian habitat. The riparian habitat affected was low quality, consisting of herbaceous
species and shrubs, and was dominated by invasive species, primarily Himalayan blackberry (Rubes armeniacus).
Thunder Hills Creek continues to be subject to erosion, although the emergency repairs achieved the desired
goals.
Preferred Alternative for Upper Failure Site
The preferred alternative for the Upper Failure Site is to continue to monitor the site for stability and repair the
riprap as needed to ensure long-term stability at the site. This alternative will not require placement of riprap
outside the area impacted during the 2008 and 2009 emergency response. Any stream or riparian areas disturbed
by equipment during on -going repair work will be restored to the existing condition. See the April 15, 2011,
technical memorandum regarding the options considered for the Upper Failure Site.
Lower Reach
Site Conditions
The Lower Reach is downstream of the upper reach where the stream is located in a ravine with steep sidewalls.
The stream channel is incised and largely contained in weathered sandstone with very little in -stream habitat or
gravel. The right bank is made of sandstone and is relatively stable. The existing sanitary sewer and access road is
located along the left bank. Portions of the left bank have been armored with gabion baskets, which were intended
to protect the unstable loose materials associated with the historic access road. Many of the existing gabion
baskets are currently failing. In many cases, the stream material supporting the gabions or located in the bank
behind the gabions is eroding and/or material within the gabion baskets has been washed out.
Preferred Alternative for Lower Reach
The preferred alternative for the Lower Reach is to stabilize the maintenance access road until the television
inspection is performed in 2016. This would include replacing the existing failing gabions with new gabions or
rockery. Existing gabions would be replaced starting with the most severe failure locations. Gabion replacement
would be performed in short increments, approximately 10- to 20-feet at a time, to reduce the potential for loss of
lateral stability along the access road. The preferred alternative for the Lower Reach also includes installing an
emergency overflow riser on the inlet to the WSDOT storm drain under I-405. Except for installing a new
emergency overflow riser, the proposed actions associated with the Lower Reach are classified as maintenance
and repair, but would still require environmental permits as discussed in the following section.
City of Renton 218-1779-037
Permitting Options 3 June 21, 2011
TECHNICAL MEMORANDUM (CONTINUED)
PERMITTING REQUIREMENTS
The proposed work in the lower reach will require several environmental permits which are summarized in
Table 1.
Table 1. Environmental Permitting Requirements
Environmental Permit
(Environmental Documentation Needed)
Lower
Reach
Average Agency
Review Time
Notes
Renton: Clearing and Grading (Critical Areas Report)
X
1-3 Months
Ecology: Construction NPDES
NA
Construction will disturb less
than 1 acre of land
WDFW: HPA (JARPA)
X
1-2 Months
Will require some work within
OHWM
USACOE: 404 Permit (JARPA)
X
1-6 Months
Nationwide 3 Permit
Biological Assessment
X
1 Month
No Effect Letter assumed
SEPA Checklist
X
1-3 Months
The preferred alternative for the Upper Failure Site would not require any construction activities. Therefore, the
City would not be required to obtain any pen -nits for continued monitoring of the site. If additional riprap is
required to stabilize the channel, then applicable environmental permits, similar to those listed in Table 1, would
likely be required.
MITIGATION
During emergency response efforts in 2008 and 2009, riprap was used to stabilize portions of the Upper Failure
site. Riprap was placed in a portion of the open stream channel and riparian areas adjacent to the upstream end of
the existing storm drain to prevent further erosion, channel instability, and property damage. In general, most of
the riprap was placed in areas impacted by previous projects (Figure 2). However, it is likely that WDFW will
require some mitigation for the placement of the riprap below the OHWM in areas not previously filled with
riprap.
Replacement of the existing failing gabions in the Lower Reach would be performed as a maintenance action to
protect the sanitary sewer until it is television inspected in 2016. Replacement of the existing gabions will not
require mitigation because replacement of the riprap is maintenance- and self -mitigating.
WDFW Policy
WDFW Policy POL-M5002 summarizes the WDFW requirements and recommendations for mitigation for
impacts to streams. The goal of this policy is to achieve no loss of habitat functions and values and to maintain the
functions and values of fish and wildlife habitat. According to WDFW, mitigation ratios shall be greater than 1:1
to compensate for temporal losses, uncertainty of performance, and differences in functions and values.
Mitigation should ensure no loss of habitat functions or values, or fish and wildlife populations.
Although WDFW prefers on -site and in -kind mitigation, off -site and out -of -kind mitigation is also acceptable.
According to this policy, WDFW generally requires that mitigation ratios provide equal or better biological
functions and values as compared to the existing conditions. The factors WDFW must consider in making this
decision are identified in RCW 90.74.020 (3).
City of Renton 218-1779-037
Permitting Options 4 June 21, 2011
PROJECT AREA OF
"IPAC7
EXCESS MATERIAL
PLACED AFTER 2009
OVERFLOW CHANNEL
CONSTRUCTION
\ pt
EXISTING THUNDER HILLS CREEK CULVERT
364 DIA INSIDE 48'i DUV PIPE
t
EXISTING SANIT V EWER
EXISTING RIPRAP L M TS
F i
\\
75-FT FROM CULVERT
(j ASSUME CULVERT IN
.t HISTORIC STREAM
CHANNEL
EXISTING STORM DRAIN
CATCH BASIN
EXISTING THUNDER HILLS
CREEK CULVERT, 48' DIA
\ \ .� . �\ .,•. ti \ j.
RIPRAP AT CULVERT
ENTRANCE
EXISTING GRAVEL ACCESS ROAD
!"i / THUNDER HILLS CREEK
C
\,. £\"'m \ ` l� ', of ,`•i `�
IMPACTED AREA=401 SO FT,
AREA IMPACTED DURING 2008
AND 2009 EMERGENCY
ACTIONS THAT WAS NOT
PREVIOUSLY DISTURBED.
LEGEND
— — _ PARCEL LINE
UTILITY EASEMENT LINE
EXISTING RIPRAP LIMITS
iMetrl][ o..r. w...n n,i me. sunsieisa,
75-FT FROM
CE
y
-�?'.
STREAM
"'y`^5.�,.✓1 \\ �+
\ ,
POTENTIAL
SITE
k`
EXISTID
WALLS
Figure 2
Thunder Hills Creek
N Area of Impact
TECHNICAL MEMORANDUM (CONTINUED)
Functional Assessment
Based on review of design drawings of the original 1960s project, projects constructed in the early 1980s, and an
evaluation of the site, there was very limited in -stream or riparian habitat in the project area even before the
emergency responses in 2008 and 2009. Prior to 2008, the stream channel was already located in a storm drain
and the riparian area was primarily a gravel road, grass, and low -growing shrubs or weeds. Therefore, at the time
of the emergency actions, the existing functions normally provided by streams and riparian areas were already
degraded. Specifically, the riparian buffer did not provide adequate levels of LWD recruitment, overhead stream
cover, bank stability, leaf litter recruitment, and water quality maintenance.
In addition, Thunder Hills Creek does not support anadromous fish use. The stream supports cutthroat trout,
western brook lamprey, sculpin, and threespine stickleback, but likely in the reaches upstream of the Upper
Failure Site (WSDOT 2008). Springbrook Creek, which is located approximately 1.5 miles downstream, is the
closest stream that supports Chinook, coho, and steelhead trout. Based on the WSDOT Environmental
Assessment of this watershed, 1-405 acts as a complete upstream fish passage barrier due to the water velocity in
the stonn drain during high water flows and the report mentions numerous additional blockages to fish migration
throughout Thunder Hills Creek (WSDOT 2008). In addition, hydrologic and sediment conditions in the project
reach is not conducive to salmonid spawning or rearing. The stream gradient within portions of the project reach
exceeds 20 percent, which is on the extreme high end of gradient range which can support upstream salmonid
migration. In addition, in the absence of properly installed bank protection, the erosion of fine sediment would
likely result. The mobilized sediment would then be transported downstream, and potentially deposited in
downstream reaches that may support salmonid spawning.
Direct Impact Calculation
Impacts to the stream and riparian area from the 2008 and 2009 emergency response and the proposed project
were calculated using the methodology described in the following section.
• Areas impacted in the 1960s and early 1980s were delineated on the base map (see Figure 2).
• Areas where riprap was placed during the 2008 and 2009 emergency responses were delineated on the
base map.
• Areas not impacted by previous projects where "new" riprap was placed during the 2008 and 2009
emergency responses were identified. This area (approximately 400 square feet) is assumed to be directly
impacted by riprap, which has potentially caused some minor loss of riparian functions and in -stream habitat.
Proposed Mitigation Strategy
WDFW bases mitigation on loss of function and determination of appropriate mitigation for lost function is
somewhat subject and varies from project to project. Because such a small area of riparian area was impacted by
riprap placement (approximately 400 square feet) and no in -stream habitat was impacted by the project and
because the site provided limited function prior to 2008, a mitigation ratio for riparian impacts of 1:1 is proposed
to offset the direct impacts of the riprap placement.
Although the impacts occur in the Thunder Hills Creek basin, which does not provide habitat for anadromous fish,
on -site mitigation is preferable if feasible. Enhancement of approximately 400 square feet of degraded buffer
(blackberry and herbaceous species) of Thunder Hills Creek with native trees and shrubs will enhance riparian
buffer functions, at an equal or greater level than the areas affected by placement of riprap (see Figure 2). Any
invasive vegetation present within the mitigation area would be removed prior to planting.
REFERENCES
WSDOT (Washington State Department of Transportation). 2008. I-405, Tukwila to Renton hnprovement Project
(1-5 to SR 169 — Phase 2) Ecosystems Discipline Report.
City of Renton 218-1779-037
Permitting Options 6 June 2/. 2011
I_.DEl""WOOD Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Index
Page
Index..........................................................................................................................................1
Letter of Interest
Letterof Interest.............................................................................................................2-3
Proposal
A. Specialized Experience and Technical Competence.........................................4-9
Project Team — Organization Chart ................................................................................... 5
ProjectTeam — Narrative...............................................................................................6-9
B. Work Plan/Level of Effort (LOE)............................................ Not Included in 20 Page Limit
Work Plan — Narrative........................................................................................... WP 1-15
Levelof Effort .........................................................................................................LOE 1-2
C. Record of Past Performance & Project Examples ......................................... 10-16
Record of Past Performance — Narrative..................................................................10-12
ProjectExamples......................................................................................................12-16
Resumes
Project Team Resumes................................................................ Not Included in 20 Page Limit
M 11 [�7
INDEX Page 1 C* 1.111111
Included in 20 pages CCONSULT,I TS
Letter of Interest
j.
_ v
CON S_ 0 LTA N T S
Engineers Planners
September 10, 2010
Bob Hastings, Construction Project Manager
Alderwood Water & Wastewater District
3626 156th Street SW
Lynnwood, WA 98087-5021
BHC Consultants, LLC
1601 Fifth Avenue, Suite 500
Seattle, WA 98101
206.505.3400
206.505.3406 (fax)
www.bhcconsultants.com
Subject: Proposal for Professional Services — S12-2010 Queensborough Sewer
Rehabilitation Project
Dear Mr. Hastings:
BHC Consultants, LLC (BHC) is excited to provide you with this proposal for the
Queensborough Sewer Rehabilitation Project. This project requires the involvement of a number
of different and specialized disciplines and expertise. It also requires the involvement of
experienced senior level individuals to not only perform the work, but work closely with you and
others at the AWWD. We have assembled a talented team, some of whom you and other staff
are probably already familiar with, to provide the necessary expertise.
Our team includes BHC for project management, rehabilitation of the sewer, maintenance
access, community outreach, easement acquisition and oversight of the stream's restoration
and mitigation; Herrera Environmental Consultants for environmental and permitting;
Shannon & Wilson for geotechnical; Hammond Collier Wade Livingstone for surveying and
mapping; Macaulay & Associates for property appraisals; Interactive Pipe Inspection for
inspection of the pipe and manholes and; Cascadia Archaeology for archaeological survey.
Each member of the team brings specialized expertise to the table which will allow us to make
certain the needs of the project are met.
We have worked with all of the firms on past projects and have developed good working
relationships with one another.
There are many reasons the BHC team is worthy of the AWWD's selection. We believe the
BHC team offers the District the following:
® A solid understanding of project issues and requirements
® Demonstrated successful and relevant experience
® A talented and dedicated team that has worked together on sewer related projects
A Solid Understanding of Project Issues and Requirements — The BHC team understands
the project issues and requirements. We can claim this as over the past month our team has
met with the AWWD, reviewed available information, and performed field reconnaissance along
the interceptor sewer's alignment. In addition, our key team members have all worked on
similar projects, and consequently, have a good understanding of the typical and likely issues
and requirements that will be involved with this project.
LETTER OF INTEREST Page 2
Included in 20 pages : {JNSULTAr=4TS
Alderwood Water & Wastewater District
S12-2010 Queensborough Sewer Rehabilitation
September 10, 2010
Demonstrated Successful and Relevant Experience — We have successfully completed a
number of sewer rehabilitation and cross country sewer projects. We are experienced with 1/1
studies, trenchless technologies, environmental and permitting requirements as well as
easement acquisition and effective community outreach. Over the last ten years, BHC
professionals have successfully completed more than 200 sewer system projects. Our capable
and experienced staff have planned, studied, designed, permitted and constructed numerous
sewer system improvements for municipalities, counties, and districts throughout western
Washington. In the last decade, Reed Kelly, our proposed project manager, has completed
over 30 sewer system improvement projects for municipalities in Washington.
A Talented and Dedicated Team that has Worked Together on Sewer Related Projects —
The BHC team is comprised of some of the most experienced, capable and respected firms and
individuals in the Puget Sound region. This team of talented and dedicated individuals will give
priority, and be responsive, to you and the project. Reed Kelly is the proposed project manager
and has project management experience on wastewater projects ranging from feasibility studies
to preliminary engineering, final design and construction management over the past 27 years.
Reed is an experienced, hands-on, communicative project manager who enjoys managing,
being involved in the design work, and working side by side with the client and team members.
Reed has worked with Shannon & Wilson on several projects over the years (Juanita Bay Pump
Station, Lake Forest Park Sewer System Expansion, Kitsap County South Central Force mains).
BHC has also worked with Herrera Environmental on a number of projects (Vashon Landfill,
Southwest Regional Transfer Station, Cedar Hills Landfill). Reed as well as others at BHC have
also worked a great deal with Macaulay and Associates (City of Marysville Trunk Sewer,
Edgewood Sewer, Carlsborg Sewer, Bainbridge Island Sewer). Lastly, Reed has been working
recently with Hammond Collier Wade Livingstone on a recent sewer project for the City of
Fircrest.
The BHC team is sincerely interested in working with AWWD on this project. We look forward
to being given the opportunity to present ourselves and further demonstrate that the BHC team
is the best suited to assist the AWWD implement this project. Should you have any questions
or require additional information, please feel free to contact me at 206-505-3400.
Respectfully Submitted,
Reed Kelly,'}PE
Project Manger
LETTER OF INTEREST Page 3 0
Included in 20 pages CO'N' 1ATAN-t
Proposal
A. Specialized Experience
& Technical Competence
►,_r i R'yV00D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
A. Specialized Experience and Technical Competence
BHC Consultants, LLC (BHC), is
® ■ an employee owned and managed
C QN' ,cLTAN i 1 consulting engineering and
planning firm located in Seattle, Washington
comprised of 45 engineers, planners, and support
personnel. Our civil and structural engineering staff
is one of the most experienced in municipal utility
design and construction in the Northwest. We are
very adept at providing efficient design and study
services on small as well as large complex projects.
Most of our civil engineering staff have worked
together in the northwest for 30 years and have
collectively solved some of the more intriguing
design and construction challenges found in the
region.
Our main focus and bread and butter for the last 20 years has been wastewater projects,
including the planning, design, rehabilitation, and construction services for all elements of the
wastewater industry. Our attention has been on, and the main focus of our expertise centers on
collection, conveyance, treatment, and disposal. The following table concisely illustrates our
areas of expertise.
B
ME
■ Gravity ■ Submersible ■ MBR
■ Saltwater ■ Comprehensive
Pump
Outfalls Sewer Plans
Stations
■ STEP/Grinder
■ Wet Well/Dry
■ Activated
■ River
■ Inflow &
Well Pump
Sludge
Outfalls
Infiltration
Stations
■ Vacuum
■ Self Priming
■ Oxidation
■ Spray
■ LID & ULID
Pump
Ditch
Irrigation
Formation
Stations
■ Vacuum
■ SBR
■ Subsurface/
■ Rate Analysis
Stations
Infiltration
■ Interceptors
■ Recirculating
■ District
Sand Filters
Management
Assistance
■ Siphons
n
SPECIALIZED EXPERIENCE & Page 4
0
TECHNICAL COMPETENCE
C0i':SUICT NITu
Included in 20 pages
LD17, R\V00D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Project Team — Organization Chart
The commitment, availability, and expertise of your project team will determine the successful
outcome of this project. BHC has assembled a project team that will provide creative and
practical solutions to the District.
Team Key
1- BHC Consultants
2- Herrera
3- Shannon & Wilson
4- Hammond Collier Wade Livingstone
5- Macaulay & Associates
6- Interactive Pipe Inspection
7- Cascadia Archaeology
Larry Amans, PE 1
Project Engineer
Julie Hampden z
Environmental Scientist
Kris Lepine, PWS 2
Ecologist
Greg Wadell
Chris Brummer, PhD, PE, LEG s Planner
Geomorphologist
Dave Harms, PE 1
Hydrologic Analysis
Ian Mostrenko, PE 2
Hydraulic Analysis
& Stream Restoration
Les Hillebrand, PLS 4
Survey Manager
Dennis Smith 6
Inspection Lead
Bill Laprade, LEG 3
Geologist
Larry West, LHG 3
Hydrogeologist
Brian Reznick, PE 3
Geotechnical Lead
Stan Boyle, PhD, PE 3
QC & Design Review
John Hatch 1
Design/Construction Review &
Schedule
Gary Bourne, PE'
Easements/Outreach
Bob Macaulay 5
Lead Appraiser
Archaeology?
Archaeologist
SPECIALIZED EXPERIENCE & Page 5 ©� �
TECHNICAL COMPETENCE 0IN'SULTA NT5
Included in 20 pages
t_Dr_RNV`O«D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Project Team — Narrative
The following narrative briefly highlights our team members' relevant
experience and technical competence in their disciplinary specialties.
Detailed resumes for each of the key team mernbers identified are
provided under the "'Resume" tab in this proposal.
CONIS rLTANTS
Reed Kelly, PE is our proposed Project Manager and will have overall responsibility for the
scope of work, budget and schedule compliance, coordination with the District and
subconsultants, and the overall technical aspect and quality of the work. Reed is a senior
project manager and principal engineer with over 27 years of diverse experience in planning,
permitting, designing, and constructing water, wastewater (municipal and industrial),
stormwater, solid waste, and general civil facilities. He has specialized experience with
wastewater conveyance systems that includes comprehensive sewer system planning,
infiltration/inflow studies, trenchless technologies, rehabilitation, as well as the design and
construction of collection facilities, pumping systems and often related odor control facilities. He
has been involved with wastewater facility planning for dozens of communities both in
Washington and California, and has been responsible for, and prepared numerous engineering
reports, preliminary engineering feasibility studies, and plans and specifications for collection
system improvements (6- to 36-inch sewers), small to large pumping systems (50 gpm to 4,000
gpm) and odor control facilities and forcemains (<4-inch to 36-inch).
Craig Chambers, PE is our proposed Project Principal. Craig will assure that Reed has the
resources and staff needed to successfully complete the project, and will be available to provide
technical guidance as appropriate and review the work for quality assurance/quality control.
Craig has over 30 years of experience in the planning, design, and construction of wastewater
systems and was the project manager for the most recent Update to the District's
Comprehensive Sewer Plan.
Larry Amans, PE will be the Project Engineer for pipe and manhole investigations and
rehabilitation. Larry has over 35 years of experience designing and providing construction
support services for hundreds of thousands of feet of sewer and water pipelines.
Gary Bourne, PE will lead the charge for Easement Acquisition and Community Outreach.
Gary has over 35 years experience in providing engineering and community outreach services
for municipal infrastructure projects throughout the Puget Sound region.
Dave Harms, PE will provide Hydrologic Analysis. Dave has over 25 years of experience with
comprehensive sewer planning and design studies Dave is well versed in using state of the art
hydraulic and hydrologic computer models for analyzing these types of systems.
John Hatch will assist in the development of the preliminary Construction Cost and
Construction Schedule and review and critique the design. John has over 40 years of
experience in design, construction management, and inspection of numerous wastewater and
water facilities for both public and private clients.
SPECIALIZED EXPERIENCE & Page 6
TECHNICAL COMPETENCE C "t7NG0i-T,,D]TS
Included in 20 pages
I. DER:\V'(_) 0 D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
To supplement our in-house team and address all the elements of the project, we have included
the following subconsultants to our team.
HERRER4 Herrera Environmental
E:h:+AioO:.h:Et.TAC CGht;ULTF.UiS
Consultants (Herrera) staff
will provide Stream Geomorphology & Restoration and
Environmental Assessments and Permitting. Herrera is a
Seattle -based consulting firm, established in 1980, providing
scientific and engineering services to public and private clients
throughout the Pacific Northwest. With over 110 highly
qualified engineers, environmental scientists, biologists, and
planners, Herrera has the staff and experience for providing
comprehensive services and solutions on natural resource projects. Herrera's expertise
encompasses all phases of environmental planning and analysis, conceptual through PS&E,
and construction and post -construction monitoring.
Chris Brummer, PhD, PE, LEG and Ian Mostrenko, PE will provide Stream Geomorphology &
Stream Restoration services to the team. Chris is a professional engineer and licensed
engineering geologist with 19 years of both applied and research experience in the fields of
geology and engineering geology. Ian is a senior civil engineer with 17 years experience in civil
and environmental engineering projects including stream restoration, surface and ground water
quality, stormwater design, and general civil site development design.
Julie Hampden and Kris Lepine will be responsible for Environmental Permitting. Julie is a
senior environmental scientist and policy analyst with 14 years of experience in fisheries,
wildlife, natural resource management, education, and policy analysis. Kris has 12 years of
professional experience in wetland assessment, wildlife biology, fisheries biology, restoration
and mitigation, wetland mitigation banking, environmental permitting, and environmental
chemistry.
Q1 SHANNON6WILSON,INC. Shannon & Wilson staff will provide will provide Geologic,
°°.a,,. Hydrogeologic, and Geotechnical services. Since 1954,
Shannon & Wilson geotechnical engineers have completed field exploration and geotechnical
engineering studies for pump stations, wastewater treatment plants, and related conveyance
systems for sewer, water, and public utility districts throughout the Puget Sound. Their ability to
provide a full range of in-house expertise from geologic reconnaissance and characterization,
slope stability, seismicity, environmental services and geotechnical foundation design provides
reliable support in the siting design and construction of wastewater and water related systems
and facilities.
Bill Laprade, LEG will be the team's Engineering Geologist. Bill has more than 37 years of
experience in all phases of geotechnical consulting. His specialties include interpretation of
glacial stratigraphy for design of civil works projects, slope stability evaluations in a multitude of
geologic conditions, and the geotechnical aspects of hydroelectric facilities, including small and
large diameter pipelines.
SPECIALIZED EXPERIENCE & Page 7
TECHNICAL COMPETENCE GU NSULT; ,NTS
Included in 20 pages
1::IZ`V00D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Larry West, LHG will be the team's Hydrogeologist. Larry has 37 years of experience in
ground water management, development, control, and protection. He has conducted over 150
construction dewatering evaluations and dewatering system designs across the United States
and overseas.
Brian Reznick, PE will provide Geotechnical Engineering support. Brian has 8 years of
professional experience in geotechnical engineering developing subsurface exploration and
laboratory testing programs, managing field and laboratory work, completing design analyses,
preparing reports, managing staff for the analyses and report preparation, and reviewing plans
and specifications.
Stan Boyle, PhD, PE will provide QC & Design Review and Support of the geotechnical work.
Stan has 25 years experience in construction and design including evaluating and designing
trenched and tunneled pipeline installations, retaining structures, highway and railroad
embankments, excavation shoring systems, and structure and bridge foundations.
Hammond Collier Wade Livingstone (HCWL) staff will
provide Surveying and Mapping services. HCWL, an
employee -owned municipal engineering and land
surveying firm established in 1943, offers a full range of
professional land surveying services that include topographic and
boundary surveys, parcel descriptions for easements and acquisitions
plotting, along with construction staking.
Les Hillebrand will be the Survey Manager. Les has 30 years of
survey experience and is responsible for overseeing all aspects of
HCWL's survey department including surrey crews, fieldwork, and
work products. He has extensive experience in both engineering
surveying and land surveying including topographic surveys, ALTA
surveys, boundary surveys, construction surveys, and route surveys
`,1t1` at uCit� rJ.l`s"eiatcs. L.1ci� Macaulay and Associates, Ltd, will prepare Property
Appraisals for the project. Macaulay and Associates,
established in Everett in 1962, provides appraisals and real estate consultation services for
governmental and public agencies, financial institutions, corporations, developers, institutional
investors, non-profit organizations, and individuals.
Bob Macaulay will lead the appraisal process. Bob has been involved with numerous large
road and utility infrastructure projects and feasibility studies, as well as large, multi -parcel right-
of-way partial and total acquisition assignments.
SPECIALIZED EXPERIENCE & Page 8 [�
TECHNICAL COMPETENCE C 0NSULT,'.r11"S
Included in 20 pages
l._t_)1-4\%V OD Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
(I* P' Interactive Pipe Inspection (IPI) will provide
lNiFaACT E Po3E:NSS EC, Pipe and Manhole Inspection services. IPI is a
division of Pipe Experts LLC, a leader in
inspection of wastewater and water piping systems and trenchless
technology since 1995. IPI was established in 2009 as a corporation
specializing in advanced technology for the inspection of
underground pipe systems.
Dennis Smith will oversee the pipe and manhole inspection. Dennis
has over 30 years experience in the wastewater inspection and
rehabilitation field.
Cascadia Archaeology will provide an Archaeological
---cam cA��A A�ci�Ae°�°cv - Survey. Cascadia Archaeology is a consulting firm that
specializes in archaeology and historic preservation in the
Pacific Northwest. For the past 12 years, it has provided a
wide variety of cultural resources management and planning
services to help clients achieve their preservation goals.
Margaret Nelson will be the lead Archaeologist. Margaret
has worked in the Pacific Northwest as an archaeologist for the
past 28 years. Her experience includes managing numerous
Section 106 process projects and preparation of cultural
resource overviews, and evaluations for NEPA EA and EIS,
and SEPA.
Project Team — Resumes
Resumes for our team members identified above are provided for review under the Resume tab
in the submittal.
SPECIALIZED EXPERIENCE & Page 9 0 1�7
TECHNICAL COMPETENCE C��P�s1_ LTNTS
Included in 20 pages
B. Work Plan/LOE
IX R\1r00D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
B. Work Plan/Level of Effort (LOE)
Work Plan — Narrative
TASK 100 — PROJECT MANAGEMENT
Because of the project's location and the rather unique situation, this project has a number of
different elements and aspects that need to be both properly managed and conducted. The
project will require the expertise of a number of different specialties, disciplines, and seasoned,
experienced, senior level personnel. The BHC team has and brings the varied expertise and
senior level personnel to this project to properly accomplish the work and assure that this is a
successful project for the District.
Project Kick -Off
The BHC team will start by meeting with District staff to obtain the staffs ideas, thinking,
desires, objectives, concerns, issues, etc. for the project. Discuss design requirements. At this
same time, the BHC team will review and discuss project information and data that was
obtained through various sources and made available such as the plans, flow data, and TV
video of the sewer.
More detail about our steps to project management is presented in the Record of Past
Performance Narrative of this proposal.
TASK 200 — ENGINEERING SERVICES
It is understood that this is a sewer pipeline rehabilitation project and that while it is possible that
some sewers may need to be replaced based on condition or location, the District's primary
project objectives are:
® Providing access for inspecting and maintenance of the sewer
® Rehabilitating and protecting the manholes that are in the stream bed
® Re -aligning the stream (if necessary) and/or protecting and reducing erosion of the
stream bed and banks where there are sewer manholes (and possibly sewer piping) that
are at risk
® Eliminating major sources of infiltration/inflow (1/1) (and exfiltration)
It is further understood that this project is not intended to be a stream restoration project. The
District is interested in protecting and reducing erosion of the stream bed and banks in the areas
of the manholes and sewers that are in or near the stream (and the new maintenance access),
and is willing to do some additional restoration/mitigation to offset impacts and improve the
situation to satisfy the regulatory agencies, but the District is not interested in performing
wholesale restoration of the stream.
WORK PLAN WP 1 0
Not Included in 20 pages .J, a k2w,
C C)IN'S U LT=,,r,iT;
i _I)t _RAN` 00D Proposal
` S12-2010 Queensborough Sewer Rehabilitation Project
Pipe and Manhole Inspection
The comprehensive sewer plan indicates that this 2,600 foot
section of 12-inch ductile iron pipe does not have a capacity issue
and does not need to be upsized. Although almost 40 years old,
it is anticipated that the pipe should, in general, be in reasonable
condition and not need to be replaced. It is understood that the
District recently TV'd a portion of the upper section and found this
to be the case. The District also did not encounter any root
intrusion or see obvious evidence of 1/1 or potential sources of 1/1
(spalled lining or dislocated joints). The District was not able to
TV the entire section due to limitations of its equipment. It is
possible though that certain portions may need to be repaired or
possibly replaced, either because of its condition or perhaps its
location. Given the slopes of the pipe, it's possible that the lining
along the invert of the pipe may be eroded due to scouring. It is
anticipated that there will be 1/1 found at pipe joints, manhole
penetrations, and manhole joints. (Since this is an interceptor line, there are no laterals
connected to it; however, we understand that there may be one lateral connected to it in the
lower section.) We are anticipating, however, that due to the pipe material and installation date,
most of the 1/1 will be at the manholes.
It will be necessary to conduct a TV inspection of the pipe as well as a detailed physical
inspection of the interior (and visible exterior) of all of the manholes to determine where
rehabilitation is needed and the best approach for the rehabilitation. Since it is anticipated that
most of rehabilitation work will be to correct 1/I, this work would be scheduled during the winter
months. Our approach is to use the sewer inspections to isolate and identify localized areas
needing rehabilitation. The recommendations would then be formulated to target these specific
areas, rather than entire pipe runs. We believe that this is approach will be more economical for
the District.
The BHC team has the firm Interactive Pipe Inspection (IPI) for this work. IPI has the
equipment and capability to TV the entire section from either of the available access points.
They also have equipment for root removal should roots be encountered that prevent the TV
camera from progressing further. There are essentially three options for TV'ing the pipe.
Option 1: If the night time flows are low enough, the entire section of pipe would be TV'd from
Meridian Avenue. Option 2: If the night time flows are not low enough, and the system capacity
is such that the pipe could be plugged for a short period of time without surcharging upstream
services, the pipe would be plugged and a section of the pipe between manholes TV'd. The
plug would be removed after each section was TV'd to allow the upstream system to drain. This
process would be repeated until the entire length of pipe was TV'd. Option 3: If the night time
or wet weather flows are too high, pumps and a temporary bypass line would have to be
installed to TV the pipe. Because of the equipment noise (engine -driven pumping equipment),
this work would be done during the day time. We would suggest that the District consider the
increased cost and need and potential additional value of conducting the TV inspection during
high flows/wet weather. Doing so may not yield better or more information on the condition of
the pipe or 1/I. This, coupled with the additional cost for a temporary bypass, may not justify TV
inspection during such times.
WORK PLAN WP 2
3
Not Included in 20 pages C0N,S, Ul,G-cl1
1..[ LI-\M!00D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
It is understood that the District has two flow meters in place, one at each end of this section of
sewer, and is currently in the process of collecting flow data. These meters will remain in place
and data will be collected for some months, for analysis and comparison of dry and wet weather
flows. This data will be provided to BHC for review and analysis. This analysis will provide flow
information for the TV inspection and determine the magnitude of 1/I. In analyzing the 2006
peak flow data that is in the comprehensive sewer plan, we found that the 1/1 in the microbasin in
which this section of sewer is located was high (-r11,400 gallons/ac-day or 1,800 gpcd). The
EPA considers 1/1 above 400 gpcd to be excessive. We were also able to obtain from King
County, the flow meter data from their 1/1 study that was collected in the winter of 2001/2002.
This flow meter was located at the manhole at the bottom of the ravine just off 4th Avenue SE.
Although the District's flow metering data will be specific to this reach of sewer, this flow data
may still be found to be of some value. Based on this finding, we are assuming that the 1/1 in
this section of sewer will be fairly significant. However, if the 1/1 is found to be minor, our
proposed testing and approach would likely be modified.
Assuming that the flow data suggests that there is appreciable 1/I, all of the manholes will be
visually inspected by IPI. [nspection of the manholes will require that there be reasonable
access as there will be need to bring in equipment for confined space entry (e.g., tripod,
portable generator, blower(s), and lights). Vacuum testing the manholes is another test that is a
relatively quick test and could help to assess any leakage if the visual findings were
inconclusive and/or help locate the sources of 1/1 (if the groundwater is high enough water will be
drawn into the manhole). This testing, however, would require better access given the
equipment that is required for it. The need and value of vacuum testing would be determined
after the manhole inspections.
We are proposing to conduct the manhole inspections using a "plug and release" approach to
identify the reaches with significant 1/I. This entails two inspection crews working and
coordinating together. One crew would plug an upstream manhole while another crew in the
downstream manhole observes the flow. If there is little or no flow after the flow has subsided
(-5 minutes), then this would suggest that there is little to no 1/1 in this section of pipe. If
however there is flow, this would suggest that there is 1/1 in this section of pipe. A portable V-
notch weir could be installed to estimate the flow. At the same time, the manholes would be
inspected and any 1/1 at the manhole penetrations, joints, cracks or otherwise would be
observed and documented. Vacuum testing of the manholes would follow after the visual
inspections and review of the findings. Depending on the findings of the manhole inspection
and condition of the manholes, vacuum testing may or may not be recommended. If there
appears to be significant 1/1 in a section of pipe, air testing could also be used to determine the
area that is leaking. Except for perhaps the initial air testing of the pipe sections (i.e. manhole to
manhole), air testing would require temporary bypassing to isolate the location(s) of the leak(s)
if the initial test of the section fails. Air testing of the pipeline has not been included in the level
of effort. This information will help the TV inspection to focus on those particular pipe sections
that were found to leak and/or have appreciable 1/1 and determine if the source(s) of 1/1 or leaks
can be located during the TV inspection. By isolating the major sources of 1/1, spot repairs
[using for example cured in place pipe (CIPP)], can possibly be used instead of having to
rehabilitate the entire section wholesale which will help to reduce construction costs.
Sewer inspections will be performed in accordance with NASSCO's Pipeline Assessment and
Certification Program (PACP) standards. The camera used will have color, pan, tilt, and zoom
capabilities.
WORK PLAN WP 3
Not Included in 20 pages ,c N'S,ULT;-. dTv
l__DI_I\`\\." )OD Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
In addition to participating in some of the sewer and manhole inspections, sewer videos and
assessment reports along with the manhole inspection photographs and reports will be
reviewed and assessed by BHC (Larry Amans).
Access/Maintenance Road
It is understood that the District desires to have a 10 to 12 foot wide maintenance road along the
alignment for access, preferably, by a 4WD pickup truck. This road would be developed and
used for access during the pipe rehabilitation work. Although it is possible that some retaining
structures (e.g., gabions) will be necessary in places, the District is not interested in having to
install structures to cross the stream. Access does not necessarily have to be from one end to
the other. Access to the sewer could be provided from both directions. Another possibility that
the District might consider is a narrow road/trail (— 6 feet wide) that could be accessed by a 4-
wheel UTV/ATV to reduce construction requirements, environmental impacts, and mitigation
requirements. This type of narrow road/trail may be more readily accepted by the regulatory
agencies and others.
Based on our reconnaissance of the sewer alignment, it appears that the sewer is situated to a
greater extent on the south side of the creek. The terrain and grade on the south side of the
creek seemed better suited for an access road and was probably used for access during
construction of the sewer back in the early 1970s. As such, it would appear based on this initial
field review that an access/maintenance road would be best situated and most likely located on
the south side of the creek/ravine. BHC (Larry Amans, Reed Kelly) will investigate and
evaluate the constructability of an access/maintenance road.
Stream Bed and Bank Restoration
Geomorphic investigations, hydrologic and hydraulic analyses, stream re -alignment, stream bed
and bank restoration will be performed by Herrera (Chris Brummer) and BHC (Dave Harms).
Herrera (Chris Brummer) conducted a field reconnaissance of the ravine in 2004 to document
sediment sources for the City of Bothell's Stormwater Management Plan. A comprehensive
geomorphic investigation of the ravine will be performed to document existing geomorphic
processes, project constraints for maintenance access and project construction, other utilities,
adjacent land use, potential mitigation sites, and design opportunities that provide solutions to
overcome the identified constraints and construction challenges.
The geomorphic investigation conducted in this task and the critical areas characterizations
(Task 400) should occur prior to any brush clearing to document existing conditions. A
preliminary hydraulic analysis using HEC-RAS will be performed to determine flow depths and
velocities in support of the restoration design. Cross -sections required for the development of
the HEC-RAS model will be flagged in the field during the geomorphic investigation and tied in
during the field survey. Hydrologic modeling of the basin will establish design flows for the
ravine. WWHM3 will be used to perform the hydrologic modeling and to establish the design
flows for input to the HEC-RAS model. WWHM3 is Ecology's standard hydrologic model that
generates a hydrologic response based on drainage basin land use and soil types. After the
WWHM3 model is developed, the results will be compared to anecdotal data as a check on the
model.
WORK PLAN WP 4 01.. Ca
Not Included in 20 pages ( )N'SULT- 'ITS
1__ h \V C)0 D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Pipe and Manhole Evaluation and Rehabilitation
BHC (Larry Amans, Reed Kelly) will be responsible for the pipe and manhole investigations,
evaluation, and rehabilitation. Our general approach is to isolate and identify the major sources
of 1/1 or deterioration in the pipe sections and target them for spot repairs using CIPP rather than
rehabilitating the entire section between manholes wherever possible to reduce costs. We
would not advocate pressure grouting of joints since our experience has shown this to be a
short-term fix/repair. Based on the findings of the manhole investigation, it is possible that some
repairs might need to be made by excavating and replacing a particular pipe section. This
would only be recommended if it was determined to be truly necessary after taking into account
equipment and material needs and construction access.
We anticipate that most of the 1/1 is occurring at manhole
penetrations and manhole joints. Some deterioration of
the interior concrete and spalling could also be found.
There could also be some root intrusion at joints as well
as cracks in the manholes due to settlement. Based on
our reconnaissance of the sewer alignment, all of the
manholes need to have the frame and cover replaced.
Those that are exposed in the stream and other places
may need to have the cone and riser section replaced. If
the manhole penetrations are deteriorated and leaking,
these would need to be chipped out to sound concrete
and repaired. If the interior of the manhole has
numerous issues, the major issues would need to be
repaired and the manhole either epoxy -lined or have a cured in place liner installed. Both of
these methods are costly and need to be used only where absolutely required. There are other
repair/rehabilitation methods that could and will be considered and used as well. We will work
closely with the District to determine the preferred repair methods.
TASK 220 — MITIGATION AND RESTORATION WORKSHOPS
Based on the findings from the pipe inspection and geomorphic and geotechnical investigations,
the BHC team.would work with the District to develop a conceptual (10 percent design)
restoration plan that mitigates impacts from pipe repairs and construction of the access road.
The plan will include design elements that address ongoing migration of the creek into the
manhole cones and channel incision that is currently destabilizing steep slopes within the
ravine. The concept plan will be presented to the District staff in a workshop setting along with
a summary of construction materials and methods, preliminary opinion of probable construction
cost, preliminary construction time frames, estimated environmental impacts, potential utility
conflicts, and the extent of temporary (construction) and permanent easements. The concept
drawings presented at the workshop will provide the basis for the evaluation of various
restoration options and the recommendation for a preferred restoration plan. The preferred plan
and the process leading up to its selection will be summarized in a technical memorandum.
It is proposed that another similar workshop be held at the draft predesign report stage.
WORK PLAN WP 5 :+ 1" [�.
Not Included in 20 pages GQIN3 Ut.T,!NT5
I._DI--`RWOOD
Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
TASK 230 — COORDINATION WITH JURISDICTIONS AND AGENCIES
The BHC team will assist the District with presenting the preferred conceptual design,
mitigation, and restoration plans to local and state agencies to solicit additional feedback and
gain consensus. Comments received from the coordination with the jurisdictions and agencies
will be used to refine the preferred restoration plan and develop a predesign report documenting
the design criteria, selection process, and supporting information (inspections and geomorphic
and geotechnical investigations). The predesign report will also include refinements to the
preliminary opinion of probable construction cost, construction schedule, estimated
environmental impacts, and the extent of temporary (construction) and permanent easements.
TASK 240 — PREDESIGN REPORT
The information, investigations, analyses, findings, and conclusions for the completed
tasks/activities will be summarized and documented in a preliminary design report, with tables
and figures as appropriate to illustrate the conditions, investigations, assumptions, analyses,
alternatives and findings. The 30% design drawings will be appended as well as other
documents, as appropriate, that were completed in other tasks. A draft report will be prepared
by the BHC team and submitted to the District for review and comment. Following the District's
review, the BHC team will meet with the District to discuss the draft report and the District's
comments. Review comments will be addressed, and incorporated into a final report.
TASK 250 - 30% DESIGN DRAWINGS
Following acceptance of the.restoration plan by the District and consensus with the appropriate
public agencies, the BHC team will develop 30 percent design drawings in accordance with
District standards. The 30 percent design drawings will incorporate findings from the
geomorphic and geotechnical investigations, engineering analyses, and topographic survey.
The 30 percent design drawings will include the access road design, stream restoration and
mitigation design, and any rehabilitation to the sewer interceptor or manholes deemed
necessary based on findings from the pipe and manhole inspections.
TASK 300 — SEPA SUPPORT
SEPA support will be provided by BHC (Greg Waddell) along with Herrera (Julie Hampden).
The lead agency will be the District. Based upon initial project evaluation, a SEPA
Environmental Checklist form will be prepared, and it is anticipated that the appropriate
threshold determination of the project will be a mitigated determination of non -significance
(MDNS). The checklist, per WAC 197-11-960, will include project information on background
and environmental elements (earth, air, water, plants, animals, energy and natural resources,
environmental health, land and shoreline use, housing, aesthetics, light and glare, recreation,
historic and cultural preservation, transportation, public services, and utilities). Prior to beginning
work on the checklist, we will coordinate with the District to agree upon the specific
environmental elements that are applicable to the project. SEPA documentation and required
accompanying documentation will be prepared in compliance with City of Bothell requirements
as specified in the Bothell Municipal Code Section 14.02 and will be prepared consistent with
City of Bothell Permit Center guidance.
We propose to complete the environmental site assessments and surveys early in the project
timeline, not only to substantiate interceptor rehabilitation and environmental mitigation designs,
to] 11 [�7
WORK PLAN WP 6 =
Not Included in 20 pages C,�0N SUI.T.!,FIT6
L. [) E R \VOO D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
but also to serve as the basis for the environmental technical documentation prepared for the
project including the Environmental Checklist and permit applications.
We will complete a draft and final Environmental Checklist in this task, assuming that the 30-
percent design provides a level of detail that is sufficient for SEPA documentation. Per the
scope of work accompanying the RFP, we will assist the District with the scheduling and
publication and or coordination of requisite public notices and meetings. The District will sign the
Environmental Checklist and route the SEPA decision to the regulatory agencies.
TASK 400 — PERMITTING
Permitting services will be provided by Herrera (Julie Hampden, Kris Lepine). The
Queensborough sewer rehabilitation project will require permits and approvals at the federal,
state, and local levels. Early coordination with permitting agencies will be essential to obtaining
permits in an efficient and timely manner. Permitting (along with possibly easement acquisition)
will likely drive the project's schedule. Based on an initial evaluation of the project, it is
anticipated that all necessary environmental permits can be obtained to allow a construction
start date in spring 2012.
The permitting task will be partially implemented in Phase 1 of the Project and completed in
Phase 2. Given the scope of work included in the RFP culminates in 30 percent designs, it is
assumed that the permitting support task for Phase 1 will include preliminary coordination with
permitting agencies, development of a permit management plan, and development of
preliminary draft permit applications. The level of detail required by permitting agencies
generally requires that project designs be 60-percent or greater prior to making application. As
such, the JARPA and supporting documentation in addition to local permits applications will not
be finalized or submitted until 60-percent designs have been completed in Phase 2 of the
project.
At the federal level, project work adjacent to and in the creek will require a Clean Water Act
Section 404 permit from the U.S. Army Corps of Engineers (Corps). We are anticipating that a
Nationwide Permit will be required. In support of the Corps permit, a critical areas report for the
project is necessary including delineation of all wetlands, identification of ordinary high water
mark, and plans for mitigating impacts to wetlands and streams. The Corps involvement will
trigger the need for an archaeological survey in accordance with Section 106 of the National
Historic Preservation Act. The archaeological survey will be conducted by Cascadia (Meg
Nelson). In addition, the Corps involvement will necessitate compliance with the Endangered
Species Act (ESA) and Magnuson Stevens Fishery Conservation and Management Act
(MFCMA).
At the state level, work within the creek will require a Hydraulic Project Approval (HPA) from the
Washington Department of Fish and Wildlife (WDFW). Impacts to wetlands may require a Water
Quality Certification from the Washington Department of Ecology (Ecology) according to the
Clean Water Act (Section 401). In addition, depending on the extent of the project, earth -moving
activities may require a National Pollutant Discharge Elimination System (NPDES) permit from
Ecology according to the Clean Water Act (Section 402). The project is located within a coastal
county; therefore, will require consistency with the Coastal Zone Management Act, which is also
coordinated with Ecology. The project will also require local permits including a land use
WORK PLAN WP 7
Not Included in 20 pages ; oINS ,LTANTS
I._DERWC- OD Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
development permit (e.g., Clearing and Grading) from the City of Bothell and associated
approvals including SEPA (described above) and critical areas ordinance compliance.
In Phase 1, we will assist the District in preliminary meetings with permitting agencies. Once
final permit applications are completed in Phase 2, we will provide the District with permitting
support in the form of permit submittal meetings and ongoing coordination with permit reviewers
to help expedite the approval or review process. The level of effort presented in this proposal is
not inclusive of all the necessary permitting effort. The level of effort that will be required for
Phase 2 has not been included.
We propose the following sequence of sub -tasks in support of expedited permitting:
1. Prepare Permit Management Plan
2. Conduct pre -application meetings with the Corps, WDFW, and City of Bothell
3. Conduct delineations and baseline characterization of critical areas
4. Prepare a Critical Areas Report
5. Prepare Endangered Species Act (ESA) and Magnuson -Stevens Fishery Conservation
and Management Act (MFCMA) compliance documentation
6. Prepare preliminary draft Joint Aquatic Resources Permit Application (JARPA)
Each of these sub -tasks are discussed in greater detail below.
Permit Management Plan
The Plan will consist of: 1) a plan summarizing project -specific permit requirements, and 2) a
project -specific permitting -timeline showing the strategic sequencing of anticipated projects.
We would first familiarize ourselves with the project by reviewing project site materials provided
by the District and meeting with the District to discuss the project. Next, we would visit the
project site to review the permitting issues involved, and then we would review applicable city,
county, state, and federal regulations.
Pre -Application Meetings
At this point, having reviewed available information so that we understood the project and the
permitting issues involved, we would meet with the City of Bothell Planning and Development
department as well as federal and state permit reviewers. The purpose of these initial
meeting(s) would be to verify the District's initial determination of the permitting issues involved,
to obtain up-to-date information on the processes and timing for all permits required, and to
determine who the permit contact would be at the City of Bothell and each regulatory agency.
Obtaining current information regarding local permit processes is important to do each time a
permit management plan is developed because for many cities and counties permit processes
and timing may change frequently. These meetings also serve to introduce the involved local,
state, and federal agencies to the project and to determine proactively what their concerns may
be about the project. At this point, a permit management plan can be completed. The
permitting plan would include the following information:
1) A brief description of the project.
2) A list of the required permits.
3) For each required permit the plan would include:
1. The name of the permitting agency
2. The name of the contact at the permitting agency
WORK PLAN WP 8
Not Included in 20 pages C01'. S1ii ,T;hiT
f..I:)I R%\ C- 0D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
3. A description of all materials required for submittal including the content, scale, size,
and number of all supporting materials (plan sheets and narratives)
4. The application fee
5. A description of the permit process (e.g. the need for formal pre -application or intake
meetings, whether the decision process would be administrative or would involve a
public hearing)
6. The expected timing of permit processing
4) An overall permitting schedule with detail regarding the steps in the preparation of each
permit submittal and a demonstration of how permit processes would dovetail with
project design and environmental documentation, such as SEPA, ESA, and NHPA
Section 106/05-05. Through the course of the project, the permitting schedule would be
revised as necessary.
Environmental/Critical Areas Assessments
During field investigations, our biologists will assess existing habitat conditions and ecological
functions provided at the project site, determine suitability of habitat for wildlife, delineate
wetlands, and identify the ordinary high water mark of the creek. Site assessments will be
conducted in accordance with Bothell Municipal Code (BMC) section 14.04. The boundaries of
identified wetlands located within the project site limits will be delineated. The wetland
conditions within 300 feet of the project site will be estimated to determine if buffers associated
with off -site wetlands will be affected by the project.
The wetland determination and delineation will be conducted using the routine determination
method outlined in the Washington State Wetland Identification Delineation Manual, the U.S.
Army Corps of Engineers Wetland Delineation Manual, and the Interim Regional Supplement to
the Corps of Engineers Wetland Delineation Manual: Western Mountains, Valleys, and Coast
Region. Delineated wetlands will be classified according to U.S. Fish and Wildlife Service
(USFWS) and hydrogeomorphic classification systems, and rated in accordance with the BMC
and Washington State Department of Ecology (Ecology) Washington State Wetland Rating .
System for Western Washington. The functions of wetlands will be assessed using the Ecology
rating system. The Bothell Municipal Code (14.04) will be used to identify the regulated buffer
widths of the wetlands. The boundaries of the wetlands and all test plots will be flagged.
Biologists will delineate the ordinary high water mark (OHWM) of the creek during the field
investigation. The OHWM will be determined using the definition set forth in WAC 173-22-
030(11). This involves using sequentially numbered flags to identify the OHWM as evidenced by
abrupt changes in topography, dominance of perennial vegetation, sediment deposits, drift lines,
and signs of scouring. The boundaries of OHWM will be flagged.
These delineations and site assessments will be compiled in a Critical Areas Report, which is
anticipated to include information on the creek, wetlands, and habitat conservation areas. As
part of this environmental site assessment, impact minimization and mitigation opportunities will
be identified by Herrera biologists and communicated to project engineers to inform project
designs. The Critical Areas Report will include mitigation measures for impacts to the creek,
wetlands, buffers, and habitat conservation areas in accordance with the BMC. Preliminary
draft permit applications and a preliminary draft Critical Areas report (for local permits and
Critical Area Project Review) will be prepared in Phase 1. The final local utility permit application
materials (per City of Bothell requirements) and the final Critical Areas Report will be submitted
WORK PLAN WP 9 c S
Not Included in 20 pages u0NS:., LT..A N T5
V(�)0 D
Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
once project impacts and associated mitigation have been comprehensively designed to the 60-
percent design level (Phase 2).
Endangered Species Act and Magnuson Stevens Fishery Conservation and Management
Act Compliance
Based on a preliminary evaluation of the project site, the project should qualify for a No Effect
letter because listed threatened and endangered species (e.g., Chinook salmon steelhead, and
bull trout residing); and critical habitat are located far enough away from the site that they would
not be affected. The no effect evaluation will be based on site reconnaissance, available
published documentation, and contacts with resource agency staff and other knowledgeable
individuals. Biologists will coordinate with the Corps to make a no effect determination, because
the Corps will be the lead agency responsible for ESA. Similarly, we will prepare documentation
assessing potential impacts to Essential Fish Habitat (EFH) for MFCMA compliance. Project
related impacts to the creek are not anticipated to adversely affect EFH. We will coordinate this
determination with the Corps, as lead agency. These letters will be completed in Phase 1, and
submitted to the District for subsequent submittal to the Corps.
Joint Aquatic Resources Permit Application (JARPA)
BHC (Greg Waddell) along with Herrera (Julie Hampden) will prepare a preliminary draft of
the Joint Aquatic Resources Permit Application (JARPA) form and supporting figures in support
of acquiring permits from the Corps, WDFW, and Ecology. A final JARPA form will, however, not
be prepared until 60-percent designs have been developed in Phase 2 of the project. We will
prepare the application form including information pertaining to the applicant, property owners,
project location, project description, wetlands, streams, and necessary permits. The JARPA
figures will be prepared according to Corps formatting guidelines including a vicinity map,
property ownership information, plan views, and representative cross -sections. The JARPA
figures will identify all work proposed in wetlands and waterward of the ordinary high water mark
including quantities of excavation and fill.
TASK 500 — COMMUNITY OUTREACH
Community outreach will be provided by BHC (Gary Bourne,
Reed Kelly). We recognize the importance of clearly and
effectively communicating the project's issues and requirements
to property owners that are directly impacted by the project as well
as others that are within the general area of the project, and other
interested parties.
Although this is not a capital project it is certainly not a typical
maintenance project. Because of the proximity of the existing
interceptor to the creek and the associated environmental
concerns it is imperative that the Project team communicate with
the surrounding neighborhoods in an effective manner. This will
require that the team understand the methods of communications normally employed on
projects by the District. The result will be more effective communications particularly in the
beginning of the project.
=3S[
WORK PLAN WP 10 ■
Not Included in 20 pages ,'�tr stJi,TA.h.TS
R11'(-)0D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Residents surrounding the project will be most interested in the impacts that the project may
have on their neighborhood. Some of the impacts that could be anticipated during pre -design
could include the following.
Pre -Design Neighborhood Impacts
® Increased activity in the neighborhood from all of the field trips by pre -design personnel
which will include numerous field trips by; surveyors, clearing specialists, civil engineers,
geotechnical engineers, and permit and environmental specialists.
® The existing sewer pipe easement alignment through the creek regime will need to be
cleared which presents the potential of attracting the neighborhood kids.
Although this contract does not include final design and construction management during the
course of communications with the residents the topic will arise and needs to be addressed by
the project team and a public fashion. Some of the impacts that might be anticipated during
construction might include the following.
Construction Neighborhood Impacts
® General increased noise and traffic
® Working hours will need to be addressed
® Trucks hauling import material will cause increased noise and street sweeping
® Transferring material from trucks to equipment suitable for transport to the site will
increase activity and may require a specific site be obtained
® The new maintenance road will attract every kind of wheeled vehicle and will need to be
secured when not in use by the contractor
® Work in the creek will need to be detailed and mitigation will need to be addressed
At this point it is not feasible to develop the solutions to these impacts but rather address the
methods by which the District's team will communicate with the neighborhood residents. From
our work with communities we have found that communications need to be "early and often."
Some of the tools that work well for communicating with property owners include: mailers, a
project website, project emails, general meetings, and individual discussions.
For this project we anticipate the following general tasks to be accomplished under the
Community Outreach Task:
1. Develop with the District a summary of the key elements and goals of the project and
why the project needs to happen now.
2. Develop with the District the details of the communication plan and how best to interact
with the public in general and in particular the neighborhood.
a. Discuss potential of Citizens Advisory Committee
3. Establish with the District the boundaries of the neighborhoods that should be included
in the core impacted neighborhoods and prepare a list of such properties. Anyone
outside that are can ask to be included on the list.
4. Assist the District in holding two public meetings to discuss the project.
a. Key elements of the first meeting to be held at the beginning of the work could
include the following.
i. Prepare a mailer for the District announcing the public meeting
WORK PLAN WP 11 0 1
Not Included in 20 pages C()NSULTr.NTS
I_Dl_I �VOOD Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
ii. Prepare display materials and boards for the meeting
iii. Prepare Power Point presentation as a visual aid to assist in the
description of the need for the project, elements of work, environmental
concerns and the challenges anticipated during completion of the work.
Other information presented would include; schedule, anticipated budget,
funding sources, and contact information
iv. Prepare attendee handouts with a recap of the information presented at
the meeting including information on how to sign up to receive project
updates.
v. Provide time for a Q&A session with the attendees
vi. Should a Citizens advisory Committee be contemplated this is a good
time to hand out a sign-up sheet to volunteer for the CAC. Even if a CAC
is not established such a list can also be used to enlist the assistance of
individuals that are community minded and who may be able to assist the
team in understanding the character and concerns of the neighborhood.
vii. Assist the District with the preparation of written responses to public
comment.
b. Key elements of the second meeting which would most likely be held at our near
the completion of design development could include the following.
i. Prepare a mailer for the District announcing the public meeting
ii. Prepare display materials and boards for the meeting
iii. Prepare Power Point presentation as a visual aid to assist in explaining
how the proposed project elements were selected and presenting
updates on the schedule, budget, and other information presented at the
first meeting.
iv. Prepare attendee handouts recapping the information presented at the
meeting.
v. Provide time for a Q&A session between the attendees and the
presenters.
vi. Assist the District with the preparation of written responses to public
comment.
TASK 600 — EASEMENT ACQUISITION
Rights -of -Entry (ROEs) will need to be obtained prior to any work being performed. BHC (Gary
Bourne) will be responsible for ROEs and easement acquisition. HCWL (Les Hillebrand) as
part of their surveyor responsibilities will provide necessary legal descriptions. Easement
appraisals will be prepared by Macaulay and Associates (Bob Macaulay).
Work under this task will include the following:
is Obtain Rights -of -Entry from the owners of property over which access is needed during
the Pre -Design work. There may be more or less ROEs than the number of properties
affected by easements. At this time we will assume the number is the same. For this
project it is not recommended that ROE forms be mailed to effected property owners
before first contact because the majority of property over which an ROE is required will
be on property for which additional easements are required. Consequently it is
WORK PLAN WP 12 , [
Not Included in 20 pages Gc�h u�Jt,z,,NT S
I [_� 1: I\` \-V (_.)0 D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
recommended that those property owners be contacted personally before a blind mailing
of the ROE forms and before any public meeting is held on the project.
® BHC will develop a list of properties for which a ROE and/or easements will be required.
This list will be used to develop owner contact information and to obtain Title Reports for
each ROE or easement required.
® Performing Field Surveys to locate the boundary of the existing easements, proposed
easements, and property lines when needed. Writing legal descriptions, calculating
areas of take and preparing exhibit drawings for new permanent and temporary
easements.
® Perform real-estate appraisals of the value of the easements to be obtained. BHC will
assist the appraiser in understanding project impacts on the properties.
® Prepare easement documents and supporting information which will assist in
communications and negotiations with property owners.
IN Communicate and negotiate with property owners of property over which new
permanent and temporary easements will be required. It is expected that BHC and the
District will discuss in detail the Districts policies for negotiating easements and that any
negotiations are within predetermined Districts guidelines.
® Be prepared to assist the District's legal counsel in condemnation proceedings.
It is understood that depending on the District's workload at the time, the District may
perform the work of obtaining ROEs themselves. If not, the District will provide BHC with its
standard ROE forms and document(s). In the latter case, we will coordinate with the
property owners and will obtain the ROEs for the District. It appears that there are about
fifteen properties that could be impacted by the project over which new temporary and/or
additional permanent easements may be required.
Based on record drawings provided by the District, it is appears that the District has a 20 foot
easement along the sewer alignment (10 feet each side of the sewer). It is generally anticipated
that an additional 30 to 40 feet of temporary easement will likely be required to allow for the
sewer improvements (50 to 60 feet total). However, this remains to be determined and will
depend on a number of factors. For instance, additional temporary easements may be
necessary for construction of the maintenance road and additional permanent easements may
be required depending on the location of the pipeline relative to the existing easement and
creek. In addition the details of a typical road section and construction requirements will impact
easement requirements.
Based on our reconnaissance of the sewer alignment, it appears that the sewer is situated to a
greater extent on the southerly side of the creek. The terrain and grade on the south side of the
creek appears to be better suited for an access road. As such, it would appear based on this
initial field review that a greater amount of easement would be required on the southerly side of
the creek/ravine. However, where the manholes are situated within the creek bed itself,
additional easement will likely be required on the northerly side as well.
The calendar time to obtain right of way has become longer in the recent past due in part to
changes in RCW addressing right of way acquisition by public agencies as well as a rise in
property values. Consequently it is important that communications with the owners of the
properties affected regarding ROE and the need for easements begin as soon as possible. We
will need to have detailed discussions with the District relative to its' policies and procedures for
WORK PLAN WP 13 1�7
Not Included in 20 pages }I S1)LT:N'TS
Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
obtaining ROE and Easements considering the neighborhood nature of the alignment. It will be
important to have a consistent message when talking to each property owner.
In addition two large parcels are owned by the Snohomish County Parks Department.
Obtaining necessary ROE and easements may require considerable discussions regarding the
nature of the work and the location and nature of the road. Discussions with Parks may lead to
the potential of a collaborative effort under which Parks could benefit from Project environmental
and permit mitigation and thereby reduce actual cash outlay for new easements.
Although it is anticipated that new easement documents will be prepared following the District
standards it is also expected that additional documents may need to be prepared and work
performed as part of the negotiation process. Communications with Parks and investment
group property owners would normally take place during normal working hours. However it is
expected that communications with private property owners would take place during the evening
or weekends and often times it will take a number of meetings.
Site visits with property owners to visually expect the easement locations are anticipated. This
effort will require that property lines and easement boundaries be clearly delineated. Often
times this survey effort needs to be repeated a number of times due to the attractive nature of
flagging to the youth in the neighborhood.
TASK 700 — CONSTRUCTION COST ESTIMATES AND SCHEDULE
Preliminary opinions of probable construction cost and the schedule will be prepared by BHC
(John Hatch, Larry Amans) and Herrera (Chris Brummer). Cost estimates will be developed
based on unit costs obtained from recently constructed projects and will include the appropriate
contingencies.
TASK 800 — GEOTECHNICAL INVESTIGATION
Shannon & Wilson (Bill Laprade, Larry West, Brian Reznick, and Stan Boyle) will be
providing geologic, hydrogeologic and geotechnical services. It is understood that there is no
existing geotechnical information or detailed construction records for the sewer. Our approach
to the geologic and geotechnical investigation for preliminary project concept development will
consist of reviewing historic aerial photographs and available geologic information. The
geotechnical team will join the design team to complete a reconnaissance of the pipeline
alignment to assess existing conditions and observe geologic exposures and creek erosion and
depositional environments. Following this reconnaissance, a brief technical memorandum
summarizing our observations and interpretation of ground conditions and geotechnical
considerations will be prepared. After preliminary concepts for construction of an
access/maintenance road, rehabilitation of the sewer, re -alignment of the creek, restoration of
the creek including the stream's bed and banks are better established (i.e., at the 30% design
level), an appropriate geotechnical exploration plan can be developed for the project.
A geotechnical investigation will be made and a report will be prepared in Phase 2 that
summarizes and presents the data collected; exploration results; and our interpretation of
geotechnical, geologic, and groundwater conditions and preliminary recommendations and
guidance for the design and construction of the project. The report will present
recommendations for excavation, dewatering (if necessary), creek bypasses, creek shaping and
WORK PLAN WP 14
Not Included in 20 pages C0N'& 11LTnf'±T
I__D1.1`% `00D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
erosion protection, foundations, and other geotechnical related design, mitigation, and
restoration measures.
TASK 900 — SURVEYING AND MAPPING
Following the clearing of brush and deadfall (see below), the alignment will be surveyed and
mapped, within 50 feet on each side of the existing sewer. Trees in excess of 8-inches in
diameter will be located as well. The surveying and mapping will be provided by HCWL (Les
Hillebrand).
TASK 1000 —ARCHAEOLOGICAL SURVEY
The archaeological survey will be conducted by Cascadia (Meg Nelson). Project work adjacent
and in the Creek requires a Clean Water Act Section 404 permit from the Corps of Engineers.
The Corps permit triggers the need for an archaeological survey in accordance with Section 106
of the National Historic Preservation Act.
TASK 1100 — CLEARING AND TRAIL CONSTRUCTION
It is understood that the District would like to have the pipeline alignment cleared of brush and
deadfall to improve access for maintenance to the extent allowed by easement agreement and
regulatory agencies. The District would also like to have a foot path/trail of some kind. Since
better access and a trail of some kind will be necessary for the manhole inspections as
discussed earlier, it is proposed that a trail be developed for conducting the work. Prior to the
surveying and mapping, a brushing/trail building contractor will be retained to remove brush and
deadfall within a 20 foot swath and construct a foot path along the pipeline's
easement/alignment. Several local brushing/trail building contractors were contacted to provide
us with an estimate of the level of this effort. Manholes that are currently inaccessible due to
trees, tree roots, and brush will also be made accessible. This clearing will be done by hand
and not include trees greater than 6-inches in diameter or as otherwise desired by the District or
regulatory agencies. Clearing in and along banks and edges of the stream will also be done
with some care and consideration of the stream and wetland ecology.
WORK PLAN WP 15 p ® �
Not Included in 20 pages ; 0p N,55 .
i;t,TANTS
C. Record of Past
Performance & Project
Examples
� R\V(.)0D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
C. Record of Past Performance & Project Examples
Record of Past Performance — Narrative
Our project team is committed to the successful completion of the Queensborough Sewer
Rehabilitation Project. Project management, project communication, and quality control will be
important to this projects success.
Project Management
Our proposed Project Manager, Reed Kelly, PE will have overall responsibility for the scope of
work, budget and schedule compliance, coordination with the District and subconsultants, and
the overall technical aspect and quality of the work. Reed's role will also be to ensure that
timely and clear communication occurs with the District and amongst BHC staff and team
members; that the District receives exemplary service; and that the work satisfies your needs
and requirements. Once the District notifies us of selection, we will meet with the District and go
over our preliminary scope of work. While developing the scope and budget, we will
concurrently define the project's initial needs and coordinate assignments as appropriate, so
that when we receive notification to proceed; our team will be in place and ready to begin work.
As a principal of the company, Reed is committed to the project and will ensure that the project
has the resources and staff needed for its success.
Reed will monitor the project's progress such as work products, costs, and schedule on a
weekly basis. BHC establishes project cost control by setting up major phases and tasks with
discrete budgets in our project accounting software. Time records and expenses, including
subconsultant expenses, are entered every Friday. Each week, Reed will have a record of total
charges for the week by phase and task, and the same record for the project -to -date. Every four
weeks, the job cost control system will create an invoice for Reed's review, and following this
review for correctness, it is forwarded to the District.
BHC has established a strong professional reputation for high quality work. Each day we stake
our reputation on our ability to operate efficiently and effectively within the parameters set forth
by our clients, our government, and the natural world. With extensive years of combined
experience, BHC staff have learned the crucial importance of bringing their projects in on time
and within budget.
We are confident in our ability to meet the schedule required for this project. This confidence is
based on a history of success on past projects and our attention to detail when putting together
a plan for a project including work scope, schedule, and budget. We will provide a hands-on
project manager, partnership with the District, proven management and design capabilities,
familiarity with applicable standards, and strong project experience.
Project Communication
A key element common to all successful projects involves effective communication between the
client and project team and other entities such as regulatory agencies. Reed will coordinate
closely with District staff through phone communications, regularly scheduled meetings, and
various means of electronic and written communications.
RECORD OF PAST PERFORMANCE Page 10:3 - 1". 0 1�7
& PROJECT EXAMPLES CNSULT NTS
Included in 20 pages
ER'\-Vc 0 D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Historically, we have prepared monthly project status reports, which provide a global summary
of the project that is helpful in presentations to the Board. These reports typically have included
a summary of challenges, changes, a listing of major accomplishments completed during the
previous month, work anticipated to be completed for the coming month, and a comparison of
original schedule and budget against the current schedule and budget.
Each month, a brief monthly project report will be prepared and submitted along with our
invoices that will summarize the status of work and the activity on each task and an explanation
of work to be completed.
As an additional client benefit, BHC has established a formal process of obtaining feedback
from our Clients. For active projects, Jon Davies, Director of Business Development, arranges
a meeting with our client's project managers about every three months (free of charge) to ask
the "how are we doing" questions.
QA/QC
The BHC Team has a quality assurance/quality control (QA/QC) system in place to ensure that
our projects are consistently delivered with the same quality and thoroughness. Each of our
technical staff is familiar with our QA/QC policy and QA/QC resources to develop a project
specific QA/QC Plan that is followed on every project. Our designs also go through a rigorous
internal review process that involves an independent senior level review in addition to Project
Manager. These signed review documents remain in the project file and are available for client
review at any time. Our assigned QA/QC engineer, Craig Chambers, will be consulted not only
at submittal milestones (30%, 60%, & 95% designs), but also early in the project to collaborate
on various technical matters and value -engineer design concepts and approach.
Wastewater Pipeline Experience
Our wastewater pipeline engineering and design encompasses gravity sewers, force mains,
siphons, grinder pump/pressure sewers and vacuum sewers. Pipeline design is.usually a two
phase process, that is, preliminary design followed by final design. With perhaps some
exceptions, BHC will typically prepare a preliminary design report or technical memorandum
that develops, considers, evaluates, and presents: flows, hydraulic analyses, potential alignment
and material alternatives and considerations, appurtenances, costs, project implementation
(environmental conditions, issues and permits, design and construction issues and
requirements and schedule), and final design requirements. In essence, the preliminary design
report establishes the basis of design and is an important first step.
The design of wastewater pipelines typically involves surveying and mapping, geotechnical
engineering, environmental assessments and permitting. If portions of the project are not within
the rights -of -way or existing easements, easement acquisition will be required. Depending on
the project's location specialty consultants may be required, such as traffic engineers, real
estate appraisers, and property acquisition consultants. Some of this information and these
investigations will be obtained or done during preliminary design while other or more detailed
investigations and efforts will be deferred until final design. BHC has worked with, and
established solid working relationships with many consultants in the Puget Sound area. BHC is
well versed in coordinating and orchestrating the work of multiple consultants on a design team.
Often times wastewater pipelines involve the use of trenchless technologies, such as jack and
bore, horizontal directional drilling, microtunneling, and other methods to cross underneath
RECORD OF PAST PERFORMANCE Page 11 Q
& PROJECT EXAMPLES ,CONSULT,^.NITS
Included in 20 pages
1._UERWOOD Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
streams, major roads and highways, railroads and wetlands. At times, existing pipelines can be
replaced by pipe bursting or cured -in -place -pipe (CIPP). BHC staff are knowledgeable in the
different technologies and understand the conditions and requirements for their use.
Project Examples
Backyard Sewer Relocation, City of Fircrest, WA
BHC Consultants completed a preliminary design report to
replace sewers that were constructed in the backyards between
homes in various parts of the City. These backyard sewer
mains were old and deteriorated and had considerable root
intrusion. The landscaping was mature and well developed and
there were other improvements such as garages, sheds, walls,
fences, etc. constructed over or near the sewers. As such, it
was very difficult for City Staff to find and access these sewers
for inspection, maintenance, and repair. Sewer improvements for three different areas within the
City of Fircrest (areas designated A, B & C) were determined. A preliminary report was
prepared. Rehabilitation and replacement of the existing sewer using trenchless technologies
such as pipe bursting and CIPP was considered and evaluated. Sewer improvements consisted
of gravity sewers as well as pressure sewers located within the right of way. Although the City
was looking to proceed with final design and construction of improvements in all three areas,
due to budgetary constraints and uncertainty of construction funding, the City was unable to
proceed with final design in all three areas. The City determined that the priority improvements
were in Area B, and BHC prepared final design for these improvements.
The sewer improvements consisted of approximately 3,500 feet of 8-inch gravity sewer and
related appurtenances (manholes and laterals). Most of the properties were served by gravity,
but approximately six (6) properties were served by grinder pump systems.
Owner's name/ Telephone: City of Fircrest, 253-564-8900
ro�ect Manager/Te/ephone _,.�BiIlwLarkirn no�longer of the�Ci
Contract value: $288,980 (fee)
Construction contract price Not constructed at this time due to lack of
at time of completion: funding
Names and title of Firms' project Reed Kelly* — Project Manager; Gary Bourne* —
personnel on the project with a Community Outreach; John Frech — Project
description of their project Engineer; Noah Allen — Staff Engineer; Aaron
responsibility: Werner — Staff Engineer
RECORD OF PAST PERFORMANCE Page 12 0 [
& PROJECT EXAMPLES CONSULTANTS
Included in 20 pages
L_I 1`_:RW 00D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Beach Sewer Line Rehabilitation, Southwest Suburban Sewer District, Burien,
BHC was selected by Southwest Suburban Sewer District to
design improvements for the failing sewer beach line in
Seahurst Pak. In the 1950's, installing buried sewer mains in
the tidal zones of Puget Sound was commonly done because
it offered unobstructed corridors. However, these pipes, which
are subjected to brackish water and shifting foundation
support, have approached, and in some cases, exceeded their
useful life. Dislocated joints, differential settlement, and
thinning pipe wall thicknesses have resulted in increasing
maintenance issues and the need for routine flushing.
For this project, coordination with the stakeholders included
Corps of Engineers, Shoreline Management, Department of
Fisheries, City of Burien Park's Department, the Marine Research Center, and all the private
single-family residences along the route.
r
Alternatives evaluated included: abandonment of the beach line and re -directing flow from the
beach into a different drainage basin; installation of a new beach line; repair of the gravity line in
place; and sliplining the existing pipe with a new force main.
The selected option involved sliplining the main with a 4-inch force main, constructing a new
waterfront pump station, and serving the parcels along this 6,000 foot segment with grinder
pumps.
Permits obtained included a Corps Nationwide Permit (wetlands), Shoreline Permit, Biological
Evaluation (endangered species), JARPA, SEPA Checklist, and WSDOT agreements.
Owner's name/Telephone: Southwest Suburban Sewer District, 206-244-
9575
"'Owner's Project Manager/Telephone ' Rbh Hall 206 24�4 9575
Contract value $478 000 (fee)
.. s
r
Project start date`- September, 2008
Project end date Estimated Dec 2011
s-Construction contract price` NIP; j " Y K z �
i 4 at time o f award'
.�,.
Construction contract price N/A
at time of completion
Firm'sRole , Pnme <, _ , f
4
_(f?rlme,'Subconsultant,;or'OtherL
Names and title of Firms' project Craig Chambers* — Project Manager; Chen -Wei
personnel on the project with a Shen — Project Engineer; Peter Cunningham —
description of their project Staff Engineer
responsibility:
RECORD OF PAST PERFORMANCE Page 13
Is
& PROJECT EXAMPLES C0145ULT.AN1TS
Included in 20 pages
Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Combined Sewer Overflow (CSO) Project, City of Snohomish, WA
BHC provided preliminary engineering, final design, and
services during construction for facilities to intercept and control
existing combined sewer overflows (CSO) in the City of
Snohomish. The new facilities include a new 6,500 gpm
combined CSO and stormwater pump station, nearly 6,200 feet
of 18-inch and 24-inch force main and gravity sewer pipe, 3,000
feet of 18- to 30-inch stormwater pipe, and 1,200 feet of 12-inch
water main.. Special design considerations include stabilization
of the pump station site using a stone column system,
architectural pump station features to conform to the historic
neighboring community, and location of separate sanitary
sewer, stormwater, and potable water pipelines within one
relatively narrow existing City street. The pump station consists
of two suction lift pump sets, one at 6,500 gpm (sewer), and one at 5,400 gpm (storm).
A key factor in the project was the crossing of an SR-9 interchange under a WSDOT bridge.
We secured WSDOT approval of a Channelization Plan and Franchise Agreements. We also
convinced WSDOT to agree to closing off -ramps and on -ramps to SR-9 for weeks at a time to
allow for phased, efficient pipeline installation. A six -stage traffic control plan was developed to
maintain and detour traffic while pipe installation work proceeded.
BHC was the lead design firm for the project and retained several subconsultants for specialized
design and permitting services. Subconsultant disciplines included surveying, geotechnical
engineering, electrical engineering, architectural services, wetlands specialists, traffic control,
and archeologists. BHC is also providing services during construction including field
observation, office engineering, and the preparation of an operations/maintenance manual.
Permits obtained included a Corps Nationwide Permit (wetlands), Shoreline Permit, Biological
Evaluation (endangered species), JARPA, SEPA Checklist, and WSDOT agreements.
Owner's name/ Telephone: City of Snohomish, 360 568 3115
AOwners Pro�ect,Manager/Telephone � ;Steve Schuller 360'568y31,15 �,�si,�,r.� :�;
Contract value $2,523 996 (fee)
ti:..y�
xPro�e'ct start date :, Aug", 2007
Project end date Estimated December 2011
. �, f ;....:x .-. a_.,.•� ¢at time ofaward,; � -� 1� _:. (Y ; d ., x _._'_�`��,k f.�. �_ � .._' : �. .. ,{
Construction contract price Not yet complete
at time of completion
fir m's,Role Y `Prime
W (PIIm0' Sub'cbnsi►ltant, or::Other)`
Names and title of Firms'project Marty Harper— Project Principal; Larry Amans*
personnel on the project with a — Project Manager; Jim Lutz — Structural
description of their project Engineer; John Frech — Project Engineer;
responsibility: Aaron Werner — Construction Engineer
RECORD OF PAST PERFORMANCE Page 14
8c PROJECT EXAMPLES �tgS1iLTP.N1T5
Included in 20 pages
I_DERA1'O0D Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Meridian Ave Sewer LID No. 1, City of Edgewood, WA
This project consists of the design and construction of
three pump stations, approximately 11,000 linear feet of
sanitary sewer force main and 25,000 feet of gravity
sewer main. The scope of work included preliminary
design, design, permitting, and construction management
services as well as assistance with the formation of a
Local Improvement District (LID). The preliminary design
services consisted of evaluating potential service areas,
reviewing probable construction costs, and defining the
LID boundary. Design efforts included preparing the
construction documents for the gravity sewer, force
mains, and sewage pump stations, developing detailed
construction cost estimates, applying for the required permits, assisting in the acquisition of
easements, and assisting the City with the formulation of the LID. The design team also
prepared environmental reports, provided survey, and geotechnical support. Design challenges
included highly saturated ground conditions, two Jack and Bore operations to maintain traffic in
SR 161 and multiple utility crossings. The construction management services involved
observing the contractor's work for compliance with the contract, interfacing with the public to
determine the location for the side sewers, administering the construction contract, and
coordinating with the numerous regulatory agencies.
Owner's name/ Telephone City of Edgewood 253 952 3299
' ;Owner's Project Manager/Telephone EncPhillips, 253 952 3299
Contractvalue: $1 189 811 (BHC s fee)
1 ..: •ys,.. .* T '.:� ilB. N f _e'�` -. H 3 7fdr t l� lyv f.. ti
1 Project start.date .
Project end date: Estimated December 2011
Construction contract price, $5, 8.15,161;75 wF
;. at time of -award
Construction contract price Not yet complete
at time of completion
Names and title of Firms' project Gary Bourne* — ULID Specialist, Public
personnel on the project with a Involvement, Principal -in -Charge; Tony Fisher —
description of their project Project Manager; Jordan Zier — Design
responsibility: Engineer
RECORD OF PAST PERFORMANCE Page 15 a3 11 Dn
4.1
& PROJECT EXAMPLES l-ON ULTANTS
Included in 20 pages
L_1 ERWOOD Proposal
S12-2010 Queensborough Sewer Rehabilitation Project
Upper Vasa Creek Storm Damage Repair Project, City of Bellevue, WA
Herrera assisted the City of Bellevue with permitting and
design for the repair of a series of check dams along upper
Vasa Creek that were damaged during major storm events in
December of 2007 and created vulnerability for a city sewer
line adjacent to the stream channel. Due to grant
requirements associated with funding provided by the
Federal Emergency Management Agency (FEMA), and a
need to complete repairs within permitting windows before
the winter of 2008, Herrera expedited the completion of
construction plans, contract specifications, and repair costs
on a very short schedule. Additional design challenges
included limited site access and restrictions to the
construction budget. Herrera also assisted with permit
documentation by preparing figures for the Joint Aquatic Resource Permit Application (JARPA)
submittal and coordinated with the City project manager to provide project details to the local
Emergency Management Division to satisfy requirements related to the FEMA funding
mechanism. The project was successfully constructed in September of 2008.
Owner's name/ Telephone: City of Bellevue, 425.452.5271
Contract value: $49,900.
eject start,date` 6/20084
oiect end date: 9/2008
g
t;
Construction contract price N/A
at time of completion:
=(Pnme,iSubconsulfant;_orOther)"
Names and title of Firms' project Kris Lepine* — Lead Ecologist and Permit
personnel on the project with a Coordinator; Ian Mostrenko* — Senior Design
description of their project responsibility: Review; Chase Barton — Project Manager;
Katheryn Seckel — Permit Assistance
RECORD OF PAST PERFORMANCE Page 16
& PROJECT EXAMPLES C0NSULTI"NTS
Included in 20 pages
Resumes
Reed A. Kelly, PE
Project Manager
Education: MS, Environmental/Ocean Engineering, Oregon State University, 1987
BS, Civil, California State University at Sacramento, 1983
Registration: Professional Civil Engineer, Washington, Oregon, Alaska, and California
Associations: Water Environment Federation, American Water Works Association,
North American Society of Trenchless Technology
Reed Kelly is a senior project manager and principal engineer with over 27 years of diverse
experience in planning, permitting, designing, and constructing water, wastewater (municipal
and industrial), stormwater, solid waste, and general civil facilities. He has specialized
experience with wastewater conveyance systems that includes comprehensive sewer system
planning, infiltration/inflow studies, trenchless technologies, as well as the design and
construction of collection facilities, pumping systems and often related odor control facilities. He
has been involved with wastewater facility planning for dozens of communities both in
Washington and California, and has been responsible for, and prepared numerous engineering
reports, preliminary engineering feasibility studies, and plans and specifications for collection
system improvements (6- to 36-inch sewers), small to large pumping systems (50 gpm to 4,000 .
gpm) and odor control facilities and forcemains (<4-inch to 36-inch). In addition to his
engineering experience, Reed has provided construction support and management, and
management of multi -disciplinary teams of engineers and subconsultants for both sewer and
water projects.
® Backyard Sewer Relocation Final Design, City of Fircrest, WA — Project manager for
the preparation of plans, specifications and cost estimate for sewering one of the three
areas investigated. The improvements generally consisted of 3,500 feet of 8-inch gravity
sewer and appurtenances (manholes and laterals) and 6 grinder pump systems. The
design was unique in that designs were prepared for the on -site side sewers. The
construction cost was approximately $2 million.
® Backyard Sewer Relocation Preliminary Design Report, City of Fircrest, WA —
Project manager for the preparation of a preliminary design report that investigated
rehabilitation, replacement and relocation of backyard sewers in three different areas
within the City. In the three areas over 100 properties were connected to backyard
sewers that were failing. Access for inspection, maintenance, and repair was a major
problem. Conceptual designs and cost estimates were determined for each area.
Trenchless technologies were investigated but were determined not to be feasible due to
the presence of compacted and cemented glacial till in all of the areas. Although CIPP
could have worked in some situations, its use was limited since access for maintenance
was still and issue. In addition, TV inspection could not be performed due to severe root
intrusion and other issues. The recommendation involved installing gravity sewers within
the streets fronting the properties. Since some of the homes were significantly lower
than the sewers, some homes required grinder pumps. Total construction cost for
relocating the sewers (including the on -site improvements) for the three different areas
was estimated to be $6,000,000.
® Everett Basin Study Technical Memorandum, Alderwood Water and Wastewater
District, WA — Project engineer for a preliminary investigation to reroute sewage flows
from several basins within the South Everett area. A conceptual design for rerouting and
conveying the flows for seven alternatives was developed. The alternatives included
CD] : [�
CONSULTANTS
Reed A. Kelly, PE
Page 2
pump stations (capacities of 1,300 to 5,200 gpm), force mains (12-24 inch), and gravity
sewers (12-42 inch). From these conceptual designs, planning level project costs were
developed for near term and future flows. Allied costs included potential capacity
charges. Project costs varied from $10 million to $47 million.
® South Central Force Main Replacements Final Design, Kitsap County, WA — Project
engineer for the preparation of specifications for both Schedules 1 and 2, including
assistance with various aspects of the design. The project also included the addition of
6,500 feet of 18-inch HDPE reclaimed water transmission main parallel to the 34-inch
HDPE sewage force main for the Silverdale Water District (Schedule 2).
® South Central Force Main Replacements Preliminary Design Report, Kitsap
County, WA — Project manager for the preparation of a preliminary design report that
investigated and evaluated alternatives for replacing 3,300 feet of 12-inch AC sewer
force main with 12 or 14-inch force main (Schedule 1) and 6,500 feet of 30-inch Techite
sewer force main with 30-inch force main (Schedule 2). Transient analyses were
conducted on both projects. HDPE pipe was selected for both projects for its corrosion
properties, reduction in transients, and reduced vulnerability to seismic events.
Schedule 1 was situated in County roads while Schedule 2 was situated in open
pastures, woodlands, and wetlands/streams. Schedule 1 included investigation and
evaluation of four alternatives/options: 1) parallel replacement with a 12 or 14-inch force
main; 2) replacement with a 12 or 14-inch force main using pipe bursting; 3)
abandonment of a lift station with installation of a 15-inch gravity sewer and; 4)
extending the sewer force main to a lift station. Project costs for Schedule 1 were
estimated at over $4 million. In addition to different pipe materials and use of trenchless
technologies, two different alignments were investigated for Schedule 2: 1) parallel
replacement and; 2) alternative alignment for a portion. As the force main could not be
shut down, hot tapping and line stopping were required at both ends of the project.
Project costs were estimated at $12.9 million.
® Sanitary Sewer Expansion — Phase I, City of Lake Forest Park, WA — Project
manager for the preparation of plans and specifications for sewering one of several
unsewered and topographically challenging areas within the City. A combination of
gravity sewer and individual grinder pump systems were designed. The project involved
1,800 feet of 8-inch gravity sewer, 54 grinder pumps and 3,400 feet of 2-inch HDPE
force main and appurtenances.
® Trunk Sewer, City of Marysville, Marysville, WA — Project manager for the design of
5,000 feet of 18-inch sewer. Project included environmental field reviews (cultural
resources, biological assessment and wetland's delineation) and permitting (SEPA,
NPDES, US Army Corps, JARPA). Trenchless techniques were needed to cross two
streams along the project's alignment. Due to high groundwater and sandy soils,
dewatering was a significant aspect of the project. Easement acquisition was also
performed.
I"I■1~
CONSULTANTS
Craig P. Chambers, PE
Principal Engineer
Education: MS, Civil Engineering, University of Washington, 1976
BS, Civil Engineering, Oregon State University, 1972
Registration: Professional Engineer, Washington
Associations: Water Environment Federation
Craig Chambers has more than 30 years of experience in the design, construction, and
management of wastewater, stormwater, and water projects for municipalities, counties, and
special service districts. Craig has successfully evaluated, designed, and provided construction
services more than 60 wastewater projects. This experience includes authoring 15
comprehensive sewer plans, 10 wastewater treatment plants, 22 pump stations and pipelines
projects (including vacuum sewers, grinder pumps, and traditional gravity collection systems),
and 1/1 reduction projects under the King County program.
® Update to Sewer Comprehensive Plan, Alderwood Water and Wastewater District,
WA — Craig was the project manager of the BHC team selected by the District to update
its comprehensive sewer plan. Alderwood Water and Wastewater District provides
service to a population of more than 200,000, covering an area of approximately 60
square miles. As one of the largest special service districts in the state, the District
desired a useable planning tool that would anticipate the needed infrastructure
improvements to match growth. To meet this need, the BHC Team, in concert with the
District staff, evaluated several hydraulic models, and is in the process of selecting,
calibrating, and training District staff to use the model.
Working with 13 Cities and Districts that are either served by, or adjacent to the District,
population forecasts and resulting flows were projected. Combining this information with
the calibrated model, conveyance and treatment facilities were evaluated and, where
necessary, slated for improvement as part of the CIP program.
® Beach Sewer Line Rehabilitation, Southwest Suburban Sewer District, Burien, WA
— Craig is the project manager responsible for designing improvements to this 50 to 60
year old sewer line installed at the beach at Seward Park. The project includes slip lining
the existing main with 4-inch pipe and installing a new 4-inch force main, installing
grinder pumps to serve 24 parcels, and constructing a new pumpstation and
modifications to an existing station.
is Bainbridge Island South Island Sewer System LID #20, City of Bainbridge Island,
WA — Project manager for LID formation assistance, design, and construction services
for the City of Bainbridge Island's South Island Sewer System. This project provided
sanitary sewers to 220 homes in four neighborhoods and an elementary school in an
area with 71 documented (DOH) septic system failures. The septic failures impacted a
sensitive wetland or flow directly into Puget Sound in the sensitive Blakely Harbor. The
Project included providing on -site sewer facilities and related service connections,
collection and conveyance piping, pump stations, and connection to the existing sewage
treatment plant. There are 220 residential lots or approximately 500 people in the
project service area and close coordination with the residents was key to the project's
success. Weekly coordination meetings with the School District, home owners
associations, and emergency service providers were held to insure that construction
activities did not disturb traffic flow. Traffic control plans were reviewed, published, and
distributed to all affected agencies.
CONSULTANTS
Craig P. Chambers, PE
Page 2
13 Marians Park Addition Sewer Rehabilitation, Southwest Suburban Sewer District,
WA — Project manager for the engineering design and construction assistance for the
sewer pipe rehabilitation of the Marians Park Addition. The project consisted of the
replacement of 3,000 linear feet of 8-inch diameter sewer main with associated
manholes, sewer stubs and surface restoration. Open cut, cured in place pipe (CIPP),
and pipe bursting methods were specified for the work. Tasks included: preparation of
specifications and contract documents, cost estimation, and construction services. The
project included coordination with King County Real Estate Services Section for traffic
control plans and right-of-way permits.
® Interceptor/Collectors, Several Locations, City of Auburn, WA —Project manager for
interceptor sewers, as follows:
LID 310: 2500 feet of 30- to 42-inch interceptor; 170 feet of 8-to 12-inch collectors; 2
crossings of Mill Creek.
LID 314: 300 feet of 30- to 36-inch; 1300 feet of 18-inch; 2900 feet of 12-inch; 2
crossings of Mill. Creek; 1 jacked highway crossing of SRI 8.
LID 318: 3350 feet of 21-inch interceptor; 250 feet of 10-to 18-inch pipe; 2 jacked
railroad crossings; pump station abandonment.
LID 330: 1270 feet of 12-inch; 1 jacked crossing of SR 167.
Pay 'N Save: 1450 feet of 12-inch; 1 jacked railroad crossing; 1 jacked crossing of
SR 167 Extension
® King County 1/1 Project, King County, WA — Served as a Local Area Manager for the
$30 million Regional 1/1 Reduction Program. LAM responsibilities included:
• Liaison with several north sewering agencies in northern King and southern
Snohomish Counties.
• Selection of pilot projects to investigate the effectiveness of various 1/1 removal
techniques
• Provided QA/QC control for all 1/1 design documents
• Workshop involvement throughout the five year course of the work
® Monroe East Side Interceptor — Monroe's growth and North Hill developments were
destined to overload the City's main pump station. Nearly 60% of the City wastewater
flow currently is directed through this single station. The added anticipated flow would be
more than the station could accommodate and expansion of the station was infeasible.
Prompted by the need to redirect sewage flow away from the main pump station and
motivated to accommodate the new developments the City elected to combine several
improvement projects under a single design and construction effort. The Eastside
Interceptor included the following elements: 5200 LF of 24-inch sewer interceptor;
40-inch borings under SR2 and an active railroad line; 3800 If of water main
replacement; rechannelization of Main Street and cross streets; elimination of all
overhead electrical and telephone lines; and new street lighting
This project was complicated by the fact that the sewer interceptor ran through the heart
of old downtown Monroe. The temporary inconvenience of construction disruption
eventually resulted in a revitalized downtown core.
®111
CONSULTANTS
Larry Amans, PE
Project Engineer
Education: BS, Civil Engineering, Oregon State University, 1970
Registrations: Professional Civil Engineer, Washington, California
Larry Amans has over 35 years of experience in planning, design, preparation of plans and
specifications, and construction management for a wide variety of civil engineering projects,
concentrating mainly on utility designs for sewage, water, and drainage systems.
® CSO Reduction Project, City of Snohomish, WA — Project manager for design of a
two-part pump station and pipelines to separate sewage from stormwater, thus stopping
combined sewer overflows (CSO's) to the Snohomish River. The pump station consists
of two suction lift pump sets, one at 6,500 gpm (sewer), and one at 5,400 gpm (storm).
Sewer and storm piping to convey both flow streams to the City's treatment plant
included 2,100 feet of sanitary sewer force main, 3,000 feet of storm drain, and 50 new
manholes. Permits obtained included a Corps Nationwide Permit (wetlands), Shoreline
Permit, Biological Evaluation (endangered species), JARPA, SEPA Checklist, and
WSDOT approval of Channelization Plan and Franchise Agreements (pipes and
roadwork within WSDOT right-of-way.)
® 1&I Reduction Program, City of Sultan, WA — Engineer for the design of a two-phase
program to reduce I&I in the City's downtown sewer system. Phase I included lining and
repairs on fourteen leaking manholes, and re-routing several storm drain lines connected
to the system. Phase II replaced 2,900 linear feet of leaking 8-inch sewer pipe with new
18-inch sewer pipe, and reconnecting 38 existing side sewers along 1st Street. The
pipeline was up -sized to provide for future extensions.
® 1st Street Sewer Improvements, City of Sultan, WA — Project Manager for the design
of 7,000 feet of 12-inch storm drain, 18-inch sewer, and 8- and 12-inch water lines in
Sultan, WA. All pipes are in existing City streets and replace aging or undersized
infrastructure. Pipes had to be positioned to maintain existing pipes in service, and to
provide minimum water and sewer pipe separation distances
State Route (SR) 20 Sewer Relocation, State Parks, Deception Pass State Park,
WA — Project manager for the design of 2,000 feet of 6-inch sewer force main along SR
20 near Deception Pass. WSDOT planned to lower the highway by up to 10 feet in this
area, which necessitated the relocation of Parks' sewer line. Staged construction was
specified to mesh with the concurrent highway construction and keep sewer downtime to
an absolute minimum. To maintain continuous sewer service to the park, we worked
closely with Parks' staff to develop a program for providing 36 portable toilets at 11
comfort stations during a one-time nighttime shutdown of the force main to connect the
new pipeline to the old.
® Wastewater Conceptual Engineering Study for Lower Elwha Klallam Tribe, Port
Angeles, WA — Designer and author of a preliminary design study for a new sewage
collection and disposal system to serve 370 homes at buildout, with new grinder pumps.
Disposal alternatives studied included an onsite treatment plant, onsite drainfield, and a
lift station with a 2-mile-long force main. Services of special value to the Tribe included:
quick turnaround time in responding to requests by staff; explaining the details of
different technologies at community meetings and in conversations with staff; and
developing a detailed cost model of monthly homeowner charges for 100, 150, 200, and
370 homes.
■ [~
CONSULTANTS
Gary Bourne, PE
Easement Acquisition/Community Outreach
Education: Civil Engineering, Arctic Engineering, University of Washington
Registration: Professional Civil Engineer, Washington, Alaska
Professional Land Surveyor, Washington
Award: Engineer of the Year, ACEC Washington, 2007
Gary Bourne has over 35 years of experience in the design, management, and administration of
public works facilities. He is also skilled in grant writing, leading public involvement efforts,
making presentations to councils and boards, and assisting clients with funding allocations and
permitting. Gary's broad knowledge and experience allows him to work with municipal clients
as a senior engineer, representing their interests and guiding their development.
He has distinguished himself among colleagues and clients alike for his attention to technical
excellence and client service. The long-standing professional relationships that he has
developed throughout his career are evidence of his ability to consistently deliver projects that
are successful and meet client expectations.
® South Island Sewer System LID, Bainbridge Island, WA — Lead LID formation and
public involvement process to this project that provided sanitary sewers to 220 homes in
four neighborhoods and to an elementary school in an area with 71 documented (DOH)
septic system failures. The Project included providing on -site sewer facilities and related
service connections, collection and conveyance piping, pump stations, and connection to
the existing sewage treatment plant. Public involvement included weekly coordination
meetings with the School District, home owners association, and emergency service
providers.
® Sanitary Sewer System Expansion, Phase II & III, City of Lake Forest Park, WA —
Project manager responsible for preliminary engineering, final design, community
outreach, and construction administration for installation of 13,000 LF grinder pump
force mains and 5,600 LF of gravity lines required to serve previously unserviced areas.
Resolution of service details for each property required the design team to work closely
with the property owners and develop unique design details to couple the new grinder
pump system with new and old gravity collection systems.
® Meridian Avenue Sewer Improvements, City of Edgewood, WA — This project
consists of the design to install three pump stations, approximately 14,000 linear feet of
sanitary sewer force main and 15,000 feet of gravity sewer main. Included in the scope
of work is a preliminary design effort to review probable construction costs and the LID
boundary; prepare construction documents for gravity sewer, sewage pump stations,
and forcemains; prepare permit and environmental documentation; assist the City in the
formulation of a local improvement district (LID); assist in property acquisition
negotiations and preparation of the conveyance documents, survey, and geotechnical
support; and probable cost estimating.
CONSULTANTS
David C. Harms, PE
Hydrologic/Hydraulic Modeling
Education: BS, Civil Engineering, University of Washington, 1982
Registration: Professional Engineer, WA, 1992, 28532
Associations: American Water Works Association, Washington Hydrologic Society
Dave has over 26 years of experience in wastewater, stormwater, and water projects, including
comprehensive planning and design studies for wastewater collection systems, stormwater
conveyance and control facilities, and water distribution systems. His professional engineering
experience is primarily in drainage basin and utility systems modeling and design studies using
state of the art hydrologic and hydraulic computer models to analyze a wide range of scenarios.
Dave has extensive experience using HSPF, MIKE Urban (MOUSE), SWMM, WWHM3,
MGSFIood, KCRTS, StormShed, HEC-RAS, HYDRA, INFOWater, WaterCAD, H2ONET,
EPAnet, HAMMER and SURGE5 modeling software.
® Stormwater System Improvements, City of Bothell, WA — Dave oversaw the
hydrologic/hydraulic analyses for four areas experiencing localized flooding within the
City. He defined the modeling approach; generating subbasin hydrology using
WWHM3PRO and extracting resultant hydrographs for input to XPSWMM models of
local conveyance systems. Dave provided Q/C for the analyses, which identified
conveyance inmprovements to resolve the localized flooding.
® Stormwater System Plan, City of Monroe, WA — Dave was project manager for this
project, responsible for overall coordination with subconsultants and the City. Dave
oversaw the hydrologic/hydraulic analysis for three study areas within the City. Each
study area experiences localized drainage problems and the analysis identified
alternative solutions using infiltration and/or improved conveyance. Dave coordinated
the subconsultant regulatory analysis effort addressing NPDES II requirements and their
update of O & M practices. He also lead the development of an updated CIP, as well as
overall document preparation.
® Sea-Tac International Airport Natural Resource Mitigation/Master Plan Update,
Seattle, WA — Dave performed hydrologic analyses for the Port of Seattle 3rd runway
Stormwater Management Plan, using the HSPF computer model. Dave
updated/calibrated the Des Moines Creek model and determined detention facility
requirements for multiple scenarios. He assisted with recalibration of the Miller Creek
mode and determined detention requirements for airport facilities discharging to Miller
Creek. Dave utilized the KCRTS model to determine preliminary detention volume and
control structure requirements. Detention facility requirements were then verified in
HSPF by performing statistical analyses of long term simulations. Impacts of Airport
development on creek base flows were also analyzed.
® Hydrologic Analysis, Snoqualmie Ridge Development, WA.— Dave performed a
comprehensive hydrologic analysis for a large scale residential Master Drainage Plan.
He developed and calibrated the HSPF computer model to streamflow for two
independent drainage basins. Dave was responsible for management of flow monitoring
data used for model calibration and for development of baseline hydrologic response.
Model calibration consisted of annual and seasonal volumes, together with
characteristics of individual storm events. Calibration parameters were applied to
additional drainage basins within the project area, based on corresponding soil, slope
and ground cover types. Existing conditions model simulations were performed for all
CONSULTANTS
David C. Harms, PE
Page 2
basins, using the entire 40-year precipitation record. Statistical analyses were performed
on model output to determine baseline peak recurrence interval flows and flow duration
curves.
Model calibration parameters were modified to simulate developed conditions, using
USGS regional calibration parameters as an initial basis for the change from forested to
grass ground cover. Stormwater detention and conveyance facility requirements were
initially determined independently from HSPF, then input to the HSPF model and verified
by performing statistical analyses on long term simulations. Resulting peak recurrence
interval flows and flow duration curves were compared to baseline data to verify facility
performance. Requirements for flow diversion to direct discharge pipelines were
determined using HSPF. The combined routing from developed conditions detention,
conveyance and diversion to direct discharge was then analyzed in HSPF for each
drainage basin. A separate hydraulic analysis was performed on the direct discharge
pipeline to verify adequate capacity.
® Comprehensive Stormwater Management, City of Kirkland, WA — Dave developed
HSPF models for Juanita and Forbes Creeks. GIS based land use from the City was
categorized and formatted for input to the HSPF input files. He coordinated field
investigations to define stream channel characteristics for model input; developed future
conditions model scenarios by incorporating projected increases in impervious acreages
for each subbasin; and utilized the models to analyze future increases in stream flows
and determine regional versus on -site detention volume requirements necessary to hold
flow durations to current development levels and also to retrofit to a predeveloped
condition. His analysis included investigation into synergistic impacts of regional versus
on -site detention, on a watershed scale. Dave prepared a summary report identifying
hydrologic, financial, O & M and other advantages and disadvantages of regional versus
on -site detention practices, recommending a policy for the City to adopt.
® Stormwater Outfall Study, City of Oak Harbor, WA — Dave oversaw the hydraulic
analysis of alternatives for the replacement of the City's existing 42-inch diameter Dry
Creek Basin western stormwater outfall into the harbor. XPSWMM modeling software
was used to analyze the effectiveness of the alternative solutions in lowering the
hydraulic gradient at an up stream intersection experiencing recurring flooding.
® Dayton Avenue NE and NE 22nd Street Drainage Improvements Project, City of
Renton, WA — Dave performed a hydrologic/hydraulic analysis using XPSWMM software,
to identify improvements to the City's existing stormwater conveyance system that would
mitigate existing drainage problems in the project vicinity. System improvements included
collection and conveyance piping, catch basins, related system appurtenances, and
existing facility adjustments and/or connections.
® SR 520 West Lake Sammamish Parkway, Redmond, WA — Dave assisted with
conceptual drainage configuration for the Phase 3 widening of SR 520, from the
interchange with West Lake Sammamish Parkway, to the interchange with SR 202. The
phase 3 widening project involves Bear Creek Buffer and FEMA floodway issues, as well
as changes in stormwater management requirements based on regulatory, project, and
physical changes in the project vicinity. Dave assisted with stormwater detention and
water quality requirements, working with challenges including flat topography and limited
available space. Prime consultant: CH2M Hill, Inc.
M 3101~,
CONSULTANTS
Greg Waddell
Planner — Permitting Support
Education: BA, Urban & Regional Planning, Western Washington University, 1969
Greg Waddell has over 30 years of planning experience including master planning, urban
design, and environmental studies. Greg was Director of Planning and Community Development
for the City of Bellingham for eight years and was SEPA Responsible Official for all City
sponsored projects and private development proposals. He has been project manager and
contributing author of numerous Environmental Impact Statements and has provided permitting
assistance on BHC water and wastewater engineering projects. His experience includes:
19 SE Transmission Main (Bear Creek), City of Redmond, WA
Is South Central Sewer Forcemain Replacement, Kitsap County, WA
® Combined Sewer Overflow Facilities, City of Snohomish, WA
® Shoreline Master Plan Compliance Analysis, City of Everett, WA
® NEPA Environmental Report, Hartstene Pointe Sewer & Water District, WA
® Water Tanks #4 Safety & Seismic Improvements, Covington Water District, WA
® South Central Conveyance Sewer System Replacement, Kitsap County, WA
® The Bellingham Plan, City of Bellingham, WA
® Snoqualmie Pass Design & Development Plan, Snoqualmie Pass, WA
® Development Code Update, City of Auburn, WA
® Freeland Sub -Area Plan, Island County WA
IN Downtown Plan, City of Kelso, WA
® Growth Management Planning Services, City of Leavenworth, WA
® Development Code Update, City of Orting, WA
® Design Guideline Visioning, City of Milton WA
South County Subarea Plan, Lewis County, WA
CONSULTANTS
John Hatch
Design/Construction Review & Schedule
Education: Continuing education classes, University of Washington
Continuing education classes, Bellevue College
OSHA 10 Hour Construction Training Course
John Hatch has over 40 years of experience in design, construction management, and
inspection of numerous water and wastewater facilities for both public and private clients. John
has been the Construction Manager on many multi -million dollar projects, with six to eight of
those projects between five and eight million dollars in construction cost. His construction
management experience includes site development, utilities, all types of structures for
treatment, storage, and complex pumping facilities, related equipment and system installations,
electrical and control systems, and facility commissioning.
Skills and Accomplishments
• Lead presenter for CEU-qualified worships in utility construction management and
inspection given in Federal Way, Edmonds, and Spokane
• Created Construction Services Management and Inspection Manual for utility projects
• Completed numerous on-line company traning programs in ethics, diversity, project
management, and office and construction safety.
® Senior Project Manager/Construction Services Manager
• Onsite inspection and construction engineer support for upgrade of an industrial
wastewater treatment facility in eastern Washington
• Assisted with design of modifications to the digester system of a wastewater
treatment facility in western Washington
• Performed constructability reviews of infrastructure on light rail facilities for
Sound Transit.
• Assisted with design and provided construction management support for water
and wastewater improvements to Safety Rest Area facilities for WSDOT
• Project management, design and design assistance for over one hundred water
and wastewater facilities ranging from utilities to pump stations to reservoirs to
treatment plans in Washington.
• Provided construction services management and inspection for twenty plus
potable water, and municipal and industrial wastewater facilities with construction
costs ranging from $100,000 to over $6 million in Washington.
• Assisted with development of facilities plans and technical reports for water and
wastewater facilities in western Washington.
® Project Manager/Construction Services Manager
• Performed project management, design, and design assistance for more than
fifty wastewater and water treatment plans, pump stations and utilities in
Washington.
• Construction services manager and inspector for over fifteen water and
wastewater facilities with project costs exceeding $200,000 in Washington.
GQNSULTANTS
John Hatch
Page 2
® Senior Design Technician
• Design assistance for several water and wastewater facilities in Washington
• Provided construction management and inspection for utilities, reservoirs, pump
stations, and treatment plans in Washington.
• Supervised drafting group.
13 Design Technician
• Assisted with design and drafting of a number public works projects in
Washington, Oregon, and Saudi Arabia.
• Inspected water and wastewater facilities in western Washington.
® Drafter
• Lead drafter for projects ranging from water and sewer utilities to an industrial fire
pump station.
CONSULTANTS
Christopher J. Brummer, PhD, PE, LEG
Senior Engineer/Geomorpho(ogist
Chris Brummer is a professional engineer and licensed engineering geologist with 19
years of both applied and research experience in the fields of geology and
engineering geology. Dr. Brummer brings an interdisciplinary approach to the
solution of complex environmental problems by drawing on his diverse background
in fluvial geomorphology, geotechnical analysis, engineering design, and permitting.
Dr. Brummer specializes in debris -flow hazards in alluvial -fan environments,
sediment supply and transport in mountain and lowland channels, the stability and
transport of woody debris, the influence of woody debris on sediment aggradation
and channel migration zone delineation, scour analysis, and channel rehabilitation
and bank protection using bioengineering methods. Dr. Brummer has applied these
tools to perform reach -scale river and floodplain assessments and develop design
alternatives for bank stabilization, levee setback, infrastructure protection, and
habitat restoration. He has performed numerous slope stability and seismic analyses
of bedrock slopes, engineered soil embankments, and geosynthetic-lined slopes. His
engineering experience also includes the preparation of construction plans and
specifications for river and floodplain projects.
Key Project Experience
Erosion and Bank Stability Assessment for Private Property near Jim
Creek, Snohomish County, WA
Herrera assessed the erosion and bank stability for a private tax parcel located
adjacent to Jim Creek, a tributary to the South Fork Stillaguamish River in
Snohomish County, Washington. The erosion and bank stability assessment was
conducted to support an application for a Shoreline Variance Permit with the
Washington State Department of Ecology. Herrera conducted a site visit to assess
existing erosion and slope stability, and completed a report summarizing the field
investigation and assessment of the existing erosion and bank stability. Dr.
Brummer provided assisted in preparation and review of the final report, which
included channel cross-section data, a geomorphic base map, and a summary of
findings. Herrera concluded that the property may be at risk from erosion due to
unstable banks both at and adjacent to the property.
City of Bothell Surface Water and Drainage Master Plan
Snohomish County, WA
Herrera assisted the City of Bothell with engineering and geomorphic assessments
of two sites proposed for capital improvement projects under the Surface Water and
Drainage Master Plan. Dr. Brummer conducted a one -day field reconnaissance of
the Queensborough tributary to North Creek to determine the source of excess fine
sediment deposition and turbidity between 4th Avenue SE and I-405 in Bothell.
Herrera staff also performed a field reconnaissance of Perry Creek to evaluate the
performance of several stormwater detention ponds. Dr. Brummer assisted with
the development of several conceptual solutions for channel stabilization and
erosion control and the development of preliminary cost estimates for each
measure. Recommendations were incorporated into the City's Master Plan Update.
Lower Boise Creek Channel Relocation, King County, WA
The King County Water and Land Resources Division proposes to relocate the
lowermost 500 feet of Boise Creek into a newly constructed stream channel. The
purpose of the project was to improve fish and wildlife habitat in lower Boise Creek
Herrera Environmental Consultants, Inc.
www.herrerainc.com
Chris Brummer, PhD, PE, LEG, page 2
and the floodplain of the White River by restoring habitat -forming riverine processes on property owned by
King County. The newly constructed channel and floodplain areas will provide spawning, rearing, and refuge
habitat for juvenile salmonids including Chinook, pink, coho, and chum salmon, as well as resident and sea -
run cutthroat trout, and rainbow/steelhead trout. Dr. Brummer is the project manager for this work order,
which rapidly developed a 100% plan set suitable for use in construction by King County crews during
summer 2009 and 2010. Dr. Brummer performed a shear stress and incipient motion analysis to properly size
the channel width, depth, and slope and the proper spacing of large woody debris structures providing
hydraulic roughness. Dr. Brummer also conducted a compensatory storage analysis to evaluate flood impacts
on the proposed grading plan and authored the basis of design report.
Upper Puyallup River Bank Stabilization and Road Repair
Pierce County, WA
The Puyallup Tribe of Indians operates and maintains a fish ladder at the Electron Dam near river mile 41.5
of the Puyallup River. The fish ladder was installed in 2000 to restore fish passage to 30 miles of riverine
habitat and constructed rearing ponds for Chinook and coho salmon. Peak flows in November 2009
destroyed a bridge and caused channel migration into the only other access road to the Tribe's facility.
Herrera's project manager, Chris Brummer, worked with Hancock Timber Resources, the property owner of
the road, to provide design services for bank repair and reconstruction of the access road. Dr. Brummer
conducted a geomorphic assessment, completed an inventory of floodplain wood for use in bank
reconstruction, assisted in the developed a hydraulic model of the project reach and two nearby problem
sites, and supervised the design of 250 lineal feet of a log crib -wall for reconstruction of the bank and
roadway. Herrera received the notice to proceed in July 2009 and completed the geomorphic assessment,
permit application, and final construction drawings within two months. Herrera also provided on -site
construction oversight. The project was successfully completed under budget in fall 2009 and restored access
to the Tribe's fish ladder, which had been inaccessible for three years.
Mashel River Restoration for South Puget Sound Salmon Enhancement Group and
Nisqually Indian Tribe, Eatonville, WA
Herrera is assisting the South Puget Sound Salmon Enhancement Group (SPSSEG) and the Nisqually Indian
Tribe (NIT) with the feasibility analysis, hydraulic modeling, and engineering design of four restoration
phases in the Mashel River located in Eatonville, Washington. The first phase was completed in 2007 and
involved the design and construction of 14 engineered logjams (ELJs) in three river reaches of the Mashel
River in order to reconnect floodplain areas and enhance instream salmonid habitat. Dr. Brummer was the
project manager for the second and third phases of restoration involving the design and construction of 22
more ELJs in two river reaches in 2009 and 2010. Preliminary designs for the fourth phase include the design
and construction of 12 ELJs near at confluence with the Little Mashel River. Herrera is using both
conventional one-dimensional hydraulic modeling (HEC-RAS) and more sophisticated two-dimensional
(FLO-2D) modeling to evaluate alternative restoration options that will maintain or reduce existing flooding
and erosion risks to surrounding property while also expediting the restoration of riparian and aquatic habitat
to these ecologically degraded reaches of the Mashel River. Considerable design challenges in the three
reaches include sedimentation from an active landslide and eroding banks, water and sediment inputs from a
major tributary, artificial bank hardening, an exposed log crib wall retaining an abandoned mill pond, and
potential flooding of adjacent private properties. In addition to project management duties, Dr. Brummer
performed geomorphic assessments, developed concept designs, and assisted with construction oversight for
various project phases.
WSDOT SR 542 Alternatives Analysis: Glacier and Gallop Creek at confluence of North
Fork Nooksack River, Whatcom County, WA
Dr. Brummer developed sediment rating curves for Glacier and Gallop creeks in support of detailed 2D
hydraulic and sediment transport modeling of flooding and debris flow risks to the town of Glacier and the
SR 542 Glacier and Gallop Creek bridges.
Herrera Environmental Consultants, Inc.
www.herrerainc.com
Ian B. Mostrenko, PE
Hydrologic Analysis
Ian Mostrenko is a senior civil engineer with 17 years experience in civil and
environmental engineering projects including stormwater design, surface and
ground water quality, stream restoration, and general civil site development design.
His area of expertise is in stormwater quality, conveyance and detention. As a
professional engineer, he has performed design and construction management for a
wide variety of stormwater related civil engineering projects involving grading;
drainage; stormwater conveyance, treatment, and detention; stream restoration; and
stormwater issues related to Municipal Solid Waste landfills. For river and stream
restoration related projects, Mr. Mostrenko has conducted construction
management and prepared the design plans, specifications, and cost estimates for
several projects involving rivers, streams, and wetland areas. In collaboration with
biologists at Herrera, Mr. Mostrenko has designed streambed controls and habitat
structures such as log weirs, rootwads, boulder bed -control structures, deflector logs
and bank protection structures for erosion control.
Key Project Experience
City of Bellevue Coal Creek Parkway Culvert Replacement
Bellevue, WA
Mr. Mostrenko developed a hydraulic model to evaluate the hydraulic performance
of the existing 96-inch culvert that conveys Coal Creek beneath Coal Creek
Parkway. The hydraulic analysis included a concrete box flow control structure just
upstream of the culvert to define the extent of backwater and flow attenuation
provided by both structures. The existing culvert is undersized, structurally failing,
and is located near substantial infrastructure such as a natural gas pipeline, sewer
force, power transmission lines, and two Williams pipeline trunk lines. Mr.
Mostrenko used the hydraulic model to simulate new culvert sizes and orientations
to assess fish passage and to compare the backwater and flow attenuation with and
without the concrete flow control box. He also used the model to provide
recommendations for log grade control and instream habitat structures and to assist
the City of Bellevue with the environmental permitting application process.
City of Kent Downey Farmstead Restoration Project
Unincorporated King County, WA
Herrera is assisting the City of Kent with feasibility analysis and preliminary design
of a habitat restoration and floodplain improvement project on 20 acres of uplands
adjacent to the Green River in unincorporated King County. The restoration site is
bounded by Frager Road, State Route 516, and Mullen Slough. Frager Road parallels
the river bank at this site and confines the river channel. Mr. Mostrenko is part of
Herrera's multidisciplinary team of engineers and scientists that is evaluating
restoration alternatives to maximize salmonid rearing habitat in a new side channel
or backwater slough while accounting for effects on existing wetlands, flooding and
flood storage, sediment transport, recreational uses, pedestrian and vehicle traffic
movement, historical and cultural resources, seismic stability of the State Route 516
embankment, and environmental permitting considerations. Mr. Mostrenko is
responsible for the hydraulic modeling, concept design development, and evaluating
the hydraulic and geomorphic response and performance of the proposed designs
with respect to the design goals and objectives to improve salmonid rearing habitat.
Herrera Environmental Consultants, Inc.
www.herrerainc.com
Ian B. Mostrenko, PE, page 2
Hansen Creek Alluvial Fan and Adjacent Wetlands Restoration
Sedro-Woolley, Skagit County, WA
Mr. Mostrenko is the lead design engineer and project manager for the restoration of the Hansen Creek lower
alluvial fan for the Upper Skagit Indian Tribe. Key elements of the design include 1) levee removal, 2) the
placement of instream large woody debris structures to control bedload movement and passively engage the
floodplain over time as vegetation establishes, 3) the creation of a channel network in the fan and wetland
areas to jumpstart the initial availability of off -channel habitat, 4) conversion of disconnected depressional
wetlands to a large flow -through riverine wetland, and 5) the placement of large woody debris in the
floodplain to increase and enhance salmonid rearing and overall floodplain health. Mr. Mostrenko developed
a hydraulic model using FLO-2D to complete a two-dimensional hydraulic analysis comparing flood depths,
inundation areas, and floodplain velocities under existing and proposed conditions. The hydraulic model
provided a basis for the concept design as well as an understanding of the processes that influence salmonid
habitat formation and natural channel maintenance. Mr. Mostrenko led preparation of the final design plans
and specifications for construction, and provided oversight during construction in the summer of 2009.
Preliminary Stormwater Management Systems Analysis for the 1-5 and 196th Street
Southwest Interchange Project, Phase C
Lynnwood, Snohomish County, WA
Mr. Mostrenko was the design engineer responsible for analysis and preliminary design of the drainage
systems for the widening and interchange expansion project along a 2-mile length of I-5 in Lynnwood,
Washington. The large commercialized drainage basin with multiple subbasins resulted in a challenging
design given the large stormwater volumes, limited space, nearby streams, and numerous high quality
wetlands adjacent to the highway. The project drainage analysis and design included two options:
modification of existing drainage structures and maxi.-nizing existing space in the highway right-of-way for
ponds and treatment facilities, and a complete retrofit option including adjacent land acquisition to satisfy
current Washington Department of Ecology standards. Mr. Mostrenko reviewed previous drainage studies
and related design analyses of existing stormwater treatment and detention facilities, reviewed available
information on streams, wetlands, ground water, and soils in the project area, performed field reconnaissance,
analyzed the treatment and flow control facilities using MGSFlood, and prepared a preliminary design report
so that the Washington State Department of Transportation can assess the strategy for drainage planning on
the project.
Alternatives Analysis and Preliminary Design of Construction Water Treatment System for
Skagit Gorge Dam Tunneling
Whatcom County, WA
Mr. Mostrenko provided engineering services to Seattle City Light to assess treatment options to manage
discharge water from a tunnel boring machine (TBM) used to construct a new companion tunnel to improve
power generation efficiency and output of the Skagit River Gorge Powerhouse. The TBM generates silt -
laden discharge water with varying discharge rates depending on localized geologic characteristics such as
fissures or changes in rock composition. The construction site is located in a confined gorge of the Skagit
River so the TBM operation and construction support activities will occur in a very tight work area. Herrera
developed several options to treat and discharge the water generated from the TBM operation assuming
limited available space and the potential for significant variability in flows rates and suspended solid
concentrations. The treatment options included onsite treatment train with a chitosan enhanced filtration
system and offsite treatment using long distance pumping with infiltration ponds or land dispersion
techniques depending on pumping distances and suitable locations. Herrera conducted an alternative analysis
on the options to assess treatment efficiencies, complexity, flexibility to handle variable flow rates and
concentrations, maintenance, and monitoring requirements. Herrera compared the performance rating of
each option and compared that to the capital costs and maintenance/monitoring costs to assess the preferred
alternative for the most effective treatment option.
Herrera Environmental Consultants, Inc.
www.herrerainc.com
Julie H.N. Hampden
Associate Environmental Scientist /Policy Analyst
,Julie Hampden is a senior environmental scientist and policy analyst with 14 years of
experience in fisheries, wildlife, natural resource management, education, and policy
analysis. She has worked with local agencies in preparing environmental procedures
manuals to ensure compliance with existing regulations. Ms. Hampden has
developed course materials and conferences on environmental regulations and
technical issues, and has instructed WSDOT courses addressing the Endangered
Species Act and its requirements for the last 8 years. She coordinated the
development of eight Aquatic Habitat Guidelines white papers addressing aquatic
habitat preservation and restoration for the Corps of Engineers and Washington
state departments of Ecology, Fish and Wildlife, and Transportation. For 9 years,
Ms. Hampden has served as an in-house consultant biologist for WSDOT,
preparing and reviewing programmatic and project specific biological assessments
(BAs) for the agency, developing policy and educational materials, and conducting
ESA section (7) consultations at the U.S. Fish and Wildlife Service reviewing BAs as
a liaison for WSDOT. She has extensive field experience involving salmonid
sampling, stream survey/riparian habitat research and classification, assessment of
fish population distributions and presence in freshwater systems, spotted owl
surveys, marbled murrelet surveys, and carnivore tracking surveys. Most recently,
Ms Hampden helped WSDOT, FHWA, NMFS and USFWS develop a model and
procedures for evaluating stormwater impacts to ESA -listed aquatic species.
Key Project Experience
Carlsborg Urban Growth Area Sewer Facilities Biological Assessment
Carlsborg, WA
Clallam County and Public Utility District No. 1 of Clallam County (PUD) plan to
jointly develop a sewer system for the Carlsborg Urban Growth Area (UGA), with
the PUD becoming the system owner and operator. The County and PUD
contracted BHC Consultants to develop a Sewer Feasibility Study (2007) and a
Sewer Facilities Plan (2009) for Carlsborg UGA. In November 2009, Herrera was
contracted by BHC to assist the County and PUD in developing a biological
assessment for Endangered Species Act (ESA) Section 7 consultation with USFWS
and NOAA Fisheries. Ms. Hampden was the project manager, lead project biologist,
and primary author of the biological assessment.
City of Kent Downey Farmstead Restoration Project
Unincorporated King County, WA
Herrera is assisting the City of Kent with feasibility analysis and preliminary design
of a habitat restoration and floodplain improvement project on 20 acres of uplands
adjacent to the Green River in unincorporated King County. The restoration site is
bounded by Frager Road, State Route 16, and Mullen Slough. Frager Road parallels
the river bank at this site and confines the river channel. Herrera's interdisciplinary
team of engineers and scientists is evaluating restoration alternatives to maximize
salmonid rearing habitat in a new side channel or backwater slough while accounting
for effects on existing wetlands, flooding and flood storage, sediment transport,
recreational uses, pedestrian and vehicle traffic movement, historical and cultural
resources, seismic stability of the State Route 16 embankment, and environmental
permitting considerations. Ms. Hampden is providing technical review of the
permitting and environmental documentation deliverables for the project.
Herrera Environmental Consultants, Inc.
www.herrerainc.com
Julie H.N. Hampden, page 2
City of Federal Way: Joe's Creek Stream Modification
Federal Way, WA
Ms. Hampden assisted the City of Federal Way in preparing required permit applications and securing
approval from state and county agencies. Permits includes critical areas review, Endangered Species Act
Review, Section 404, Section 401 certification, SEPA review, clearing and grading review, and Hydraulic
Project Approval.
Welcome Lake Dam Safety Improvements Project
Woodinville, WA
Ms. Hampden assisted the Lake of the Woods homeowners association in preparing all required permit
applications and securing approval from state and county agencies. Permits include critical areas review, dam
safety review, SEPA review, clearing and grading review, and Hydraulic Project Approval.
Endangered Species Act Lead for WSDOT's Tacoma High Occupancy Vehicle Lane, General
Engineering Contract
Tacoma, WA
Ms Hampden is serving as the Endangered Species Act lead for WSDOT's Tacoma HOV lane program. This
program consists of nine projects, to be completed by 2015 that will enhance the "people -carrying" capacity
of urban highways throughout the Central Puget Sound area. Ms. Hampden is writing multiple biological
assessments and coordinating with federal, state, and tribal resource agencies to ensure ESA compliance for
the program, and to address the timing constraints and natural resource issues associated with these projects.
Programmatic Biological Assessment Evaluating the Environmental Impacts of
Washington State Shoreline Guidelines for NOAA Office of Coastal Resource Management
Washington
Ms. Hampden was the principal author and project manager for the preparation of a programmatic biological
assessment for NOAA's Office of Ocean and Coastal Resource Management. The programmatic biological
assessment evaluated the potential impacts to listed species and their habitats associated with the new
shoreline guidelines for Washington State. The geographic scale of the assessment was extensive and
included all the coastal counties of Washington State. Ms. Hampden coordinated and helped to oversee the
formal section (7) consultation process with NOAA Fisheries and USFWS.
Federal Lands Highways Divisions' Program Development and Design Manual Chapter 3
Update
Ms. Hampden served as project manager and one of the primary authors for a revision of the Environmental
Procedures chapter of the Federal Lands Highways Divisions' Program Development and Design Manual.
The revised chapter is comprised of the following sections: introduction; laws, regulations, policies and
guidance; coordination with other agencies; environmental procedures; environmental compliance; and
environmental documentation requirements. The chapter was rewritten to ensure it's usefulness to all three
divisions of the Federal Lands Highways program of FHWA and to ensure that it more accurately reflects
current environmental standards, procedures, and best practices.
City of Seattle Department of Transportation Environmental Procedures Manual
Seattle, WA
Ms. Hampden assisted the City of Seattle Department of Transportation (SDO-f) in developing an
environmental procedures manual to replace an outdated manual. The manual was intended help the Capital
Improvement Project and Environmental divisions of the agency document their policies and procedures, as
well as to provide agency project managers with the procedures, contacts, and resources needed to ensure
environmental compliance.
Herrera Environmental Consultants, Inc.
www.herrerainc.com
Kris Lepine, PWS
Associate Ecologist
Kris Lepine has 12 years of professional experience in wetland assessment, wildlife
biology, fisheries biology, restoration and mitigation, wetland mitigation banking,
environmental permitting, construction management, monitoring, water quality
analysis, and environmental chemistry. He performs a variety of environmental
studies for private and public development projects, which include wetland
delineations, wildlife and habitat assessments, stream surveys, and mitigation plans.
Mr. Lepine has completed several National and State Environmental Policy Act
(NEPA and SEPA) studies such as checklists, environmental assessments, and
environmental impact statements involving thorough analysis of project alternatives.
He performs biological assessments and evaluations in support of Endangered
Species Act (ESA) compliance for a variety of fish and wildlife species, which
address project impacts, assess environmental baselines, and provide best
management practices and minimization measures. In addition, he coordinates a
wide range of local, state, and federal environmental permits and approvals on
projects including Clean Water Act (CWA) section 404 permits, CWA section 401
water quality certifications, Hydraulic Project Approvals, storm water permits, tribal
approvals, shoreline permits, and consistency with local critical areas ordinances. He
has extensive experience with preparing various permit applications (e.g., joint
Aquatic Resource Permit Applications) and compiling necessary supporting
documentation.
Key Project Experience
Hall Creek Culvert Removal and Ballinger Lake Golf Course Sewer
Replacement
Mountlake Terrace, WA
Mr. Lepine is the lead ecologist and permit coordinator responsible for
environmental permitting and mitigation on a City of Mountlake Terrace Public
Works project that involves removing a culvert and provide stream channel and
bank restoration along Hall Creek. The project also involves replacing a sewer line
that crosses underneath the stream. Mr. Lepine is responsible for conducting
wetland delineations and stream surveys; preparing a critical areas study;
contributing to design including revegetation and mitigation measures; and
coordinating all permits on the project. He is also responsible for Endangered
Species Act compliance on the project. Permits are necessary from the U.S. Army
Corps of Engineers, Washington State Department of Ecology, and Washington
Department of Fish and Wildlife.
136th/Redmond Way Stormwater Bypass and Bank Stabilization
Redmond, WA
Mr. Lepine served as Herrera project manager and lead biologist responsible for
environmental assessment, mitigation, and permitting for a City of Redmond Public
Works project that involved stabilizing a severely eroded gully on a steep slope by
relocating a stormwater outfall and reconstructing a segment of a tributary to
Willows Creek. In support of permitting, he produced a variety of reports including
a Wetland Delineation and Functional Assessment; Wildlife Study and Habitat
Survey, Stream Reconnaissance, Stream Mitigation Plan, and SEPA Checklist. He
identified the ordinary high water mark throughout the project area. He provided
design and oversight of stream restoration, which involved approximately 210 feet
Herrera Environmental Consultants, Inc.
www.herrerainc.com
Kris Lepine, PWS, page 2
of stream channel, including extensive large woody debris installation for grade control structures, bank
stabilization, and stream cover. The design included single and multi -log grade control structures that
minimise erosion and provide fish habitat. Mr. Lepine prepared a planting plan for the site that improved
habitat by replacing dominant Himalayan blackberries with a diverse assortment of native shrubs. He
coordinated all environmental permits and approvals on the project including a Section 404 permit from the
U.S. Army Corps of Engineers, a Hydraulic Project Approval permit from the Washington State Department
of Fish and Wildlife, City of Redmond Permits, Endangered Species Act compliance, and approval from the
Muckleshoot Indian Tribe.
Talbot Road/Perrinville Creek Drainage Improvement and Habitat Enhancement
Edmonds, WA
Mr. Lepine is the lead ecologist responsible for environmental permitting and mitigation on a City of
Edmonds Public Works drainage project that involves replacing a storm water pipe and relocating an outfall
to Perrinville Creek. Mitigation measures include improving fish passage and habitat. Mr. Lepine identified
the ordinary high water mark of Perrinville Creek and delineated a wetland associated with the stream. He co-
authored a Critical Areas Report for the project, which includes stream restoration and wetland mitigation
measures. He is working alongside stream engineers to develop fish -passable structures, riparian wetlands,
and a streamside native planting plan. In addition, he co-authored a No Effect letter in support of
Endangered Species Act (ESA) compliance. Mr. Lepine is coordinating permitting efforts on the project,
which includes obtaining a Section 404 nationwide permit from the Corps of Engineers, a Hydraulic Project
Approval from the Washington Department of Fish and Wildlife, and a critical areas review from the City of
Edmonds.
City of Bellevue Vasa Creek Check Dam Repairs
Bellevue, WA
Mr. Lepine is the lead ecologist and permit coordinator responsible for environmental permitting and
mitigation on a City of Bellevue Utilities project that involves repairing nine check dams on Vasa Creek,
which are needed to stabilize the stream within a steep ravine that is at risk of severe erosion. Mitigation
measures include installing wood structures to provide habitat and restoring wetlands and buffers that are
temporarily disturbed during construction. Mr. Lepine is providing oversight of wetland and stream
delineation and has authored the mitigation component of the Critical Areas Report which included designing
a native planting plan. He is also responsible for in-house technical review of the No Effect letter in support
of Endangered Species Act compliance, SEPA Environmental Checklist, and the Joint Aquatic Resource
Permit Application.
Brightwater Wastewater Treatment System Predesign
King/Snohomish County, WA
During the predesign phase of the Brightwater Regional Wastewater Treatment System project, Mr. Lepine
prepared environmental documents for the King County Wastewater Treatment Division (KCWTD) in
support of permitting the construction of various sites associated with the conveyance system. He conducted
wetland delineations and ordinary high water mark surveys for sites in unincorporated Snohomish County,
the City of Kenmore, and the City of Bothell. In addition, he prepared conceptual wetland mitigation plans
for sites where impacts to wetlands and or streams are unavoidable. These documents were submitted to
federal, state, and local jurisdictions in support of Section 404 Clean Water Act, Shoreline Substantial
Development, and grading permits.
Kent/Auburn Conveyance System Improvements
Pacific, Algona, Auburn, and Kent, WA
Mr. Lepine served as lead biologist conducting environmental studies for the King County Wastewater
Treatment Division in support of a wastewater conveyance project that will increase the capacity of the sewer
system in the Green River South Planning Area by installing new pipes, re-routing flows, and replacing pipes.
Herrera Environmental Consultants, Inc.
www.herrerainc.com
William T. Laprade, LEG
Engineering Geologist
Education: BS, Geological Sciences, University of Washington, 1981
MA, Geography, Arizona State University, 1973
BA, Geography, Clark University, 1967
Post -Graduate Studies, Engineering
Registration: Certified Engineering Geologist, Oregon, E844, 1982
Licensed Engineering Geologist, Washington, 111, 2001
Associations: Association of Engineering Geologists
Geological Society of America, Fellow
Northwest Geological Society, Past -President
Seattle University, adjunct professor, Engineering Geology
American Water Works Association
Washington State Geologists Licensing Board, Chair
Bill Laprade has more than 37 years of experience in all phases of geotechnical consulting:
geologic reconnaissance, field exploration planning, drilling operations and logging, feasibility
studies, design, construction monitoring, and construction management. His years of
experience in the Pacific Northwest have made him an expert on local geology and soil
conditions. His specialties include interpretation of glacial stratigraphy for design of civil works
projects, slope stability evaluations in a multitude of geologic conditions, timberland mass
wasting in mountainous terrain, and the geotechnical aspects of hydroelectric facilities, including
small and large diameter pipelines. He has also served as an expert consultant for the geologic
aspects of construction claims. Bill was the principal investigator for a study that involved more
than 1,400 landslides for the City of Seattle.
■ Snohomish County PUD, Low Impact Hydroelectric Sites, Snohomish County, WA.
Bill evaluated a group of 30 potential sites for development of hydroelectric power
facilities on creeks and rivers in the Cascade Mountains with civil engineers and
biologists. Using existing geologic information and previous reports (where available) on
the sites, Bill and the other professionals pared down the sites to 10 through a ranking
process, and then visited the top four sites for a more definitive evaluation. He provided
the group with decisive analysis of the geologic conditions and the geotechnical issues
at each site, along with conceptual methods to overcome the physical constraints of the
sites.
■ Puget Sound Energy, Thunder Creek Hydroelectric Project, Skagit County, WA. As
Project Manager, Bill performed engineering geologic reconnaissance for 5 miles of
pipeline, transmission lines, and access roads and managed subsurface exploration
program (including helicopter -borne access) in rugged mountainous terrain at the
Thunder Creek Hydroelectric Project. He also prepared Sediment & Erosion Control
Plan for submission to state and federal agencies.
■ Seattle Public Utilities, Burke -Gilman Drainage Basin Studies, Seattle, WA. As
Project Manager and Geologist, Bill provided reconnaissance of a steeply sloping
drainage basin that is tributary to Lake Washington, and identified 20 potential landslide
problem areas that may affect water supply, storm sewers, and sanitary sewers.
Preliminary cost estimates were produced for remedial measures for each potential
problem area.
111 SHANNON MMILSON, INC.
William T. Laprade, LEG
Page 2
■ Southwest Suburban Sewer District, Seahurst Beach Sewer Line Restoration
(Pump Station No. 7), Burien, WA. Bill supervised geotechnical studies for this project,
including subsurface explorations, a data report and feasibility evaluations of the
dewatering and excavation. Shannon & Wilson biologists are also providing local, state,
and federal permitting assistance for proposed improvements and expansion of an
existing sanitary sewer line and pump stations in the vicinity of Seahurst Park.
■ City of Bremerton Department of Public Works & Utilities, Bremerton Sewer and
Boardwalk Project, Bremerton, WA. Bill served as Project Manager for the
replacement of about 3,900 feet of sewer force main in a Puget Sound beach and a new
3/-mile-long, off -shore, pile -supported boardwalk. Bill supervised geologic evaluation of
beach and unstable sea bluff; barge -borne, off -shore exploration program; and
evaluation of erosion along shoreline.
■ Des Moines Utility District, Geologic Studies for Sewer Line, Des Moines, WA. Bill
performed explorations and geologic studies for sewer line along the edge of the 50-foot-
high Zenith Bluff in Des Moines where geologic conditions make utilities risky.
■ City of Renton Public Works, Honey Creek Interceptor Sewer, Renton, WA. Bill
performed geologic reconnaissance, geotechnical report, and construction monitoring for
Honey Creek Interceptor Sewer in the bottom of a narrow, steep -walled ravine.
■ Geologic Engineering at Inverness Park, Seattle, WA. Bill performed construction
monitoring for subdrainage interceptor trench system at Inverness Park in Seattle where
recent and pre -historic landsliding had created chaotic topography. The drain has kept
the hillside stable for more than 20 years. .
■ King County Department of Natural Resources, Wastewater Treatment Division,
Fairwood Interceptor, Renton, WA. Bill served as Project Manager and Geologist for
three phases of a sewer conveyance system including a 2,600-foot-long horizontal
directional drill (HDD) beneath a 200-foot-deep ravine that is a tributary to Madsen
Creek. He directed the field explorations, interpreted the geologic conditions, and
completed the geotechnical reports for the project.
■ JUB Engineers, Richland Sewer Interceptor, Richland, WA. Bill managed the
exploration program and prepared a report for the Richland sewer interceptor and
treatment plant in alluvial and glacial outwash deposits.
■ STS, Heislers Creek Hydroelectric Project, Acme, WA. Bill completed a geologic and
soils report and the Erosion and Sediment Control Plan for the proposed Heislers Creek
Hydroelectric Project near Acme. Complex geologic conditions (sedimentary and
igneous rocks and glacial soils) provided a challenge for siting the project.
■ Weyerhaeuser, Watershed Analysis, Willapa Headwaters and Stillman Creek, WA.
As Project Geologist, Bill completed the mass -wasting module for watershed analyses in
the Willapa Headwaters and Stillman Creek watershed administrative units. This
involved analyzing aerial photographs and field reconnaissance to create a landslide
inventory, writing the mass wasting module report, and participating in the synthesis,
handoff, and prescription phases of the process.
E M SHANNON MMILSON, INC.
Lawrence M. West, LHG
Hydrogeologist
Education: BS, Geology, California State University, Northridge, 1972
MBA, Seattle City University, 1981
Registration: Registered Geologist, Oregon, #188, 1977
Certified Engineering Geologist, Oregon, #E188, 1977
Licensed Geologist, Engineering Geologist, Hydrogeologist, #1257,
Washington
Associations: Association of Ground Water Scientists and Engineers
Geological Society of America
Larry West has 37 years of experience in ground water management, development, control and
protection. Mr. West has conducted a number of ground water investigations, focusing on both
the ground water influence on surface water, and the influence of surface water on groundwater.
In addition to the projects listed below, Mr. West has conducted over 150 construction
dewatering evaluations and dewatering system designs across the United States and overseas.
■ Alderwood Water and Wastewater District, North Creek Sewer Replacement Pre-
Design/Design Dewatering Evaluations, Snohomish County, WA. Larry conducted
analyses for alternative alignments for 3.5 miles of sewer in Bothell, Washington.
Analyses included determining most appropriate approach for construction dewatering,
evaluation of dewatering discharge disposal options and cost estimates. Final design
studies include installation of deep confined aquifer observation wells, pumping tests,
calculation of dewatering flows and preparation of dewatering specifications for bidding.
■ Alderwood Water and Wastewater District, Everett Basin Study Technical
Memorandum, Snohomish County, WA. Larry served as Project Engineer for a
preliminary investigation to reroute sewage flows from several basins within the South
Everett area. A conceptual design for rerouting and conveying the flows for seven
alternatives was developed. The alternatives included pump stations (capacities of
1,300 to 5,200 gpm), force mains (12-24 inch), and gravity sewers (12-42 inch). From
these conceptual designs, planning level project costs were developed for near term and
future flows. Allied costs included potential capacity charges. Project costs varied from
$10 million to $47 million.
■ HDR Engineers, Kent/Auburn Interceptor Sewers Dewatering Evaluations, Green
River Valley, WA. Larry managed and conducted dewatering evaluations for 3 King
County Wastewater Division sewer replacements extending from Kent to Auburn and
Pacific, Washington. Larry provided review of prior geotechnical studies, determined
dewatering issues and estimated dewatering flows. He also prepared specifications for
contract documents.
■ Dewatering Evaluation, Keyes Improvement Project, Stanislaus, County, CA. Larry
estimated dewatering flows and dewatering approaches for a new wastewater pump
station and 12,000 feet of sewer trench excavation. His evaluation included an
assessment of the impact of the existence or absence of a low permeability aquitard
beneath the pump station excavation and drawdown with distance to determine the
potential for structure settlement due to dewatering.
116 SHANNON 6WILSON, INC.
Lawrence M. West, LHG
Page 2
■ Seattle Public Utilities, Thornton Creek, Jackson Park Golf Course Detention Pond
Dewatering, Shoreline, WA. Larry investigated and evaluated dewatering
requirements for the construction of three detention ponds constructed as part of the
Thornton Creek restoration. Excavations required depressurization of a shallow but
highly artesian aquifer (potentiometric levels 12 feet above ground surface). Larry
designed the dewatering system for the City, prepared specifications and oversaw the
contractor's installation and operation of the complex well and wellpoint system. He
worked with the contractor for the City to ensure excavations did not result in a breach of
the confining layer and flooding of the golf course and project area. The successful
dewatering resulted in a smooth -running project that was under schedule and no change
orders due to dewatering problems.
■ Redwood Water and Sewer Utility, Redwood Conveyance Dewatering, Grants
Pass, OR. Larry evaluated the available geotechnical data to assess the best approach
for bidding construction dewatering along 7,000 feet of pipeline in the Grants Pass area
for the Redwood Water and Sewer Utility. Analyses included two pump stations and four
stream crossings. Larry recommended a specification and bidding approach that
allowed contractors to provide competitive and reasonable bids for the construction
dewatering of the project.
■ City of Tacoma Department of Public Works, Puyallup Avenue Sewer Dewatering
System, Tacoma, WA. Larry developed sump, wellpoint and deep well design for
nearly 12,000 feet of 8-foot diameter sewer excavation through an old industrial part of
Tacoma, Washington. The program included disposal options to handle the
contaminated soil and groundwater encountered during excavation and dewatering.
■ Pierce County Public Works Department, Pierce County Sludge Disposal Siting
EIS, Pierce County, WA. Larry developed hydrogeologic siting criteria and siting
suitability map for disposal of municipal treatment plant sludge. He conducted a site -
specific evaluation of six most favored sites and performed environmental impact
assessment of selected 8,000-acre site.
■ City of Longview, Emergency Sewer Dewatering, Longview, WA. Larry provided
design and system installation oversight for a 10 well, 1,500 GPM dewatering system to
allow repair for a ruptured sewer. The design, well construction and drawdown was
achieved in less than 3 weeks allowing the contractor to effect repairs in a shored
excavation in record time.
■ Northeast Sammamish Sewer & Water District, Lift Station #3 Sewer Dewatering,
Redmond, WA. Larry managed and conducted hydrogeologic evaluations for the
design and construction of a dewatering system to depressurize an artesian aquifer
along the 600-foot alignment for the connection sewer between the old and new lift
stations. The project included the construction of 10 dewatering wells, pumping tests
and computer modeling to ensure contractor had sufficient capacity to control artesian
pressures during excavation and sewer installation.
110 SHANNON WLSON, INC,
Brian S. Remick, PE
Geotechnical Engineer
Education: MS, Civil Engineering, Oregon State University, 2002
BS, Civil Engineering, Oregon State University, 2000
Registration: Registered Professional Engineer, Washington, 42820, 2006
Associations: American Society of Civil Engineers (ASCE)
Management & Public Administration Committee (MPAC), Registration
Coordinator, August 2008 to Present
Brian Reznick has 8 years of professional experience in geotechnical and civil engineering.
During his career, Brian has worked on several levee projects in the Puget Sound region,
including levees on the Cedar, Green, Snoqualmie and Skagit Rivers. He was responsible for
preparing levee project scopes and budgets, developing subsurface exploration and laboratory
testing programs, managing field and laboratory work, completing design analyses, preparing
reports, managing staff for the analyses and report preparation, and reviewing plans and
specifications. His technical expertise encompasses design of shoring, ground improvement,
piles, slope stability analysis, and liquefaction evaluation. He has been involved in construction
observation including mass soil excavation, fill placement and compaction, pile installation, and
shoring installation and testing.
■ City of SeaTac, Sunrise View Stormwater Bypass, SeaTac, WA. The city of SeaTac
proposed a stormwater bypass pipeline to alleviate flooding of down slope residences
from stormwater runoff. As Project Manager, Brian managed the subsurface exploration
and sampling, laboratory testing, and geotechnical engineering analyses for the project.
Engineering recommendations included loads on buried pipes, uplift pressures due to
groundwater, ground settlement, and a permanent earth retention structure at the pipe
outfall. Temporary excavation, shoring, and dewatering recommendations were also
included in our report.
■ University of Washington, Clark Road Culvert Replacement, Seattle, WA. The
Clark Road culvert replacement project is located at Clark Road, along the northeast
portion of the University of Washington campus. The project area is part of the Ravenna
Creek drainage basin flowing year round into Lake Washington through the former
Montlake Landfill. Due to settlement damage and the need for greater flow capacity, the
existing 42 inch diameter culvert was replaced with a 14- by 8.58-foot corrugated metal
pipe arch culvert. The new culvert was partly filled with a gravel mix to promote fish
habitat. Soil conditions consisted of loose sand mixed with wood and municipal solid
waste underlain by peat. As Project Engineer, Brian provided the geotechnical
recommendation for the cofferdam shoring, temporary cut slopes, and subgrade
overexcavation and backfill for the project. The new subgrade was improved with
geotextiles and quarry spalls for foundation support, and a clay liner to mitigate
contamination. Brian oversaw the geotechnical recommendations and project plan
design for the Mechanically Stabilized Earth (MSE) abutment walls surrounding the
culvert and supporting Clark Road. Brian also managed the construction excavation and
shoring observation for the project.
■ King County, Cedar Rapids Geotechnical Study, Renton, WA. King County plans to
install engineered wood structures anchored with timber piles along a section of the
Cedar River to limit the lateral extent of channel migration and to support the formation
of complex aquatic habitat. Brian was the Project Manager and coordinated efforts with
Ili SHANNON 6WILSON, INC.
Brian S. Reznick, PE
Page 2
the owner and design team, and supervised staff during subsurface explorations, timber
pile analyses, and report preparation. Brian also contacted local contractors in an effort
to identify construction feasibility and cost for the project.
■ King County, Reddington Setback Levee, Auburn, WA. King County is proposing to
construct a setback levee and extension along river miles 27.5 to 29.5 of the Green
River to increase flood and sediment capacity, improve ecological habitat, and reduce
the flood hazard to neighboring county residences and the associated costs of flood
hazard management. As Project Manager, Brian is currently managing the project,
coordinating efforts with the owner and design team, and supervising staff during the
analysis. The project will include collection and review of surface and subsurface
information, and performing subsurface explorations, in -situ soil testing, and laboratory
testing. Geotechnical and hydrogeologic analyses will be performed to identify a
proposed levee location and provide design and construction recommendations.
Analysis will include characterizing foundation soils and evaluating slope stability,
seepage, liquefaction, and uplift. Shannon & Wilson will also provide geotechnical
recommendations for protecting and/or moving existing utilities in the proposed
construction zone, and conceptual geotechnical recommendations for relocation of the
Auburn Pump Station.
■ United States Army Corps of Engineers, Skagit River Levee General Investigation,
Skagit County, Washington. The project is a study of flood risks for levees along the
lower 30 miles of the Skagit River. Brian is the Project Manager for the study. He
coordinates efforts with the Corps, Skagit County, and the surrounding Dike Districts. He
compiled existing Corps geotechnical information about the levees including: subsurface
exploration logs; flood damage reports and repair letters; levee plans, cross -sections,
and profiles; and aerial and ground photographs. After the information was presented
to the Corps, Brian coordinated efforts to perform subsurface explorations and soil
sampling along specific levee sections where seepage has been documented. The
exploration program included paired borings with groundwater monitoring wells in and
behind the levee. With the paired borings, the groundwater response to river level
fluctuations can be analyzed to improve seepage analyses. The study included
characterizing the geologic conditions, in situ groundwater testing, and geotechnical
laboratory data that included soil index, permeability, consolidation, and strength testing.
■ King County, South Fork Snoqualmie Levee Evaluation, King County, WA. King
County proposes to rebuild and strengthen a select portion of the existing levee system
in the North Bend area between South Fork Snoqualmie River miles 2 and 7. The levee
system has geotechnical deficiencies including potential overtopping, seepage,
seepage -induced slope instability and scour. Brian was the Project Manager for the
levee evaluation and coordinated efforts with the owner. Brian helped develop a
subsurface exploration and sampling program, and supervised the staff during the field
program and hydrogeologic field tests, sample review, and laboratory testing.
_=1 1SHANNON &WILSON, INC.
Stanley R. Boyle, PhD, PE
Geotechnical QC & Design Review
Education: PhD, Geotechnical Engineering, University of Washington, 1995
MS, Structural Engineering, Carnegie-Mellon University, 1984
BS, Civil Engineering, University of Vermont, 1983
Registration: Registered Professional Civil Engineer, WA, 35805, 1999; CO, 26991,
1990; AK, 11831, 2007
Associations: American Society of Civil Engineers (ASCE)
Geo-Institute Task Force on MSE Wall Design
North American Geosynthetics Society; Intl. Geosynthetics Society
American Council of Engineering Companies
Dr. Stanley Boyle has 25 years experience in construction and design. Since joining Shannon &
Wilson, Stan has evaluated and designed trenched and tunneled pipeline installations, retaining
structures, highway and railroad embankments, excavation shoring systems, impoundment
dikes, structure and bridge foundations. He has developed recommendations for improving
stability of landslides throughout the western United States, for reconstruction of riverbanks, and
for construction near rivers and waterways. He has developed recommendations for shoring
and dewatering of excavations for trenches, pump stations, and tunnel access shafts; evaluated
and developed recommendations for mitigating liquefaction susceptibility of a water pipeline and
embankment foundations; developed recommendations for staged embankment construction of
embankments over weak and compressible soils; developed recommendations for compaction
grouting of loose soil below a large structure; designed pile -supported utility protection
structures; and designed embankments constructed of lightweight materials to reduce
settlement.
■ Alderwood Water and Wastewater District, Low Pressure Area Improvements
Project, Alderwood, WA. The Water District needed a second water line to supply
additional water pressure for an area of the City. Stan evaluated the feasibility of
proposed alignments and construction alternatives, and assisted in production of the
geotechnical report and specifications. Most of the approximately 10,000-foot long water
line was installed in trenches. The project included a 110-foot long 24-inch diameter jack
and bore crossing under SR-525 and an approximately 50-foot long 12-inch diameter
HDPE Horizontal Directional Crossing under environmentally sensitive Swamp Creek.
® Seattle Public Utilities, Atlas Place Drainage Improvements, Seattle, WA. Stan was
the Project Geotechnical Engineer for this slope stability evaluation project. The goal of
the project was to evaluate the risk to public utilities that traverse a known landslide area
in a residential community. Subsurface explorations and geologic reconnaissance were
performed and used in conjunction with previous explorations that had been performed
the project area to evaluate geologic and hydrogeologic conditions. Slope stability
analyses were performed and recommendations presented for protecting the utilities.
■ City of Tacoma Public Works Department, Reservation Junction Sewer Relocation,
Tacoma, WA. Stan was the Project Engineer and Manager for the installation of a 60-
inch-diameter sanitary sewer. The project included tunneling below four active railroad
tracks. Where cut -and -cover installation of the pipe was feasible, design
recommendations were provided for foundation improvement, shoring, concrete pipe
sleds to support the pipe over soft soils and provide lateral support for the pipe, and
means to resist buoyancy under seasonal high groundwater conditions.
EI11 SHANNON MMILSON, INC.
Stanley R. Boyle, PhD, PE
Page 2
Recommendations were provided for installing augercast piles for a 140-foot-long, three -
span railroad bridge constructed over new and existing pipelines. Specifications were
developed for pipe foundation improvement, tunneling, and augercast piles.
■ Kitsap County South Central Force Main Replacement, Kitsap County Public
Works, Kitsap County, WA. Stan was geotechnical lead for this project to provide
geotechnical recommendations to upgrade and realign two force main sewer pipes and
install a reuse water force main. We performed explorations and analyses to provide
recommendations for excavation, excavation support, dewatering, reuse of excavated
material, and pipe loads. We also provided recommendations for replacing three
culverts to provide fish passage and spread foundations for a farm access bridge.
■ Highline Water District, Three Tree Point Water System Improvements, Burien, WA.
Stan was Project Engineer and Manager for this water system improvement project to
replace aging and undersized pipelines. Stan performed geologic reconnaissance,
supervised the exploration and laboratory testing program, and prepared
recommendations for excavation, pipe bedding and backfill, and horizontal directional
drilling of two pipeline segments.
■ Port of Tacoma, Gog-le-hi-te II Habitat Project, Tacoma, WA. Stan served as
Principal -in -Charge for geotechnical engineering for design and construction of a levee
and wetland along the Puyallup River. About 1800 feet of new levee was constructed
500 to 800 feet behind the existing levee, and the area between the new and existing
levee was shaped for wetland and habitat development. After characterizing subsurface
conditions and soil properties, we provided levee design and construction
recommendations that satisfied Corps of Engineers requirements, short and long-term
embankment settlement, erosion protection, and seepage. Recommendations were
provided for including geosynthetic reinforcement below and in the levee to improve
constructability and static stability, for protecting existing utilities and structures, and for
reuse of onsite materials in levee construction and habitat contouring.
■ King County Department of Natural Resources, Sammamish River Restoration,
Redmond, WA. For the proposed reconstruction of 1,400 feet of the Sammamish River
Channel where it flows through Marymoor Park, Stan served as Shannon & Wilson's
Project Manager. The purpose of the project was to restore meanders that were
removed when the river was straightened approximately 40 years ago, improve fish
habitat, and create a more natural environment at the site. Shannon & Wilson provided
geologic reconnaissance and interpretation, subsurface explorations, laboratory testing
of soils, slope stability analyses, and development of recommendations to stabilize the
channel slopes and bed and perform proposed earthwork.
E III SHANNON &WILSON, INC.
Hammond Collier Wade Livingstone
ROBERT L. HILLEBRAND, P.L.S. - SURVEY MANAGER
Mr. Hillebrand has 30 years of survey
experience and is responsible for
overseeing all aspects of our survey
department
including survey
crews,
fieldwork, and
work products.
He has
extensive
experience in
both
engineering
surveying and
land
surveying.
These areas
include:
topographic surveys, ALTA surveys,
boundary surveys, construction
coordination, and route surveys.
EDUCATION
9' Survey Mathematics; AutoCAD
with Softdesk and LDD; Land
Surveying, Related Law, Legal
Descriptions; and GPS Surveying
Procedures and Practices — 1985 to
Present: Renton Vocational
College
Advanced Cadastral Sur—veying,
Land Surveying — 1996 Bellevue
Community College
LICENSE / REGISTRATION
e Washington State P.L.S. (2000)
CQ National Land Surveyor in Training
(1996)
AFFILIATIONS
T Land Surveyors Assoc. of
Washington (LSAW)
30 TEARS EXPERIENCE
SANITARY SEWER SURVEYS
Mukilteo Water and Wastewater District, Big
Gulch Emergency Sewer Trunk Repair and
Stream Restoration
jt, City of Entiat, Topography and Right-fo-Way
Mapping
`O City of East Wenatchee, Topography and Right -
of -Way Mapping
Douglas County Sewer District, Columbia
Avenue Right -of -Way Mapping
WATER SURVEYS
Woodinville Water District, Topo Survey
City of Bellevue Water Line Improvement
0 Grant County PUD No.2, Nason Creek Weir
Stream
Puget Sound Energy, Datum Resolution at Lake
Tapps
09 Dan Frank DNR Water Way Lease
TRANSPORTATION SURVEYS
City of Kenmore, SR-522 HOV Enhancement
Project
City of Bothell, SR-527 Improvement Project
City of Leavenworth Street Improvement
TO City of Leavenworth, Topography and Right -of -
Way Mapping
City of Steilacoom, Topography and Right -of -
Way Mapping
City of Wenatchee Sidewalk Improvements
OTHER SURVEYS
VO City of Seattle Facilities, Condominium
Conversion of the Talking Book and Braille
Library
CQ Woodinville Water District, Kingsgate Reservoir
Improvement Project
TO Grant County PUD #2 Jacobs Civil, Priest
Rapids Hatchery
HAMMOND
WADE LIVINGSTONE
ROBERT J. MACAULAY, MAI
Washington State License No. 1100517
EDUCATION
1983
B.A. Economics, Washington State University
2009
Almost 100 hours of classes and seminars sponsored by the Appraisal Institute, including Uniform Appraisal
Standards for Federal Land Acquisitions, Evaluating Commercial Construction, Real Estate Finance Statistics and
Valuation Modeling (complete list available upon request).
2007
USPAP National Course
2006
Eminent Domain and Condemnation
2005
Subdivision Valuation, Appraisal Institute
Special Purpose Properties, Appraisal Institute
2004
Real Estate Finance, Value and Investment Performance, Appraisal Institute
Appraisal Consulting, Appraisal Institute
2003
USPAP - Courses 400 & 420
2002
Environmental & Property Dangers, Appraisal Institute & Center for Advanced Property Economics
1986 to 2001
Real Estate Appraisal Principles IA-1; Basic Valuation Procedures IA-2; Capitalization Theory & Techniques IB-
A; Capitalization Theory & Techniques IB-B; Case Studies in Real Estate Valuation 2-1; Standards of
Professional Practice - SPP; Report Writing and Valuation Analysis 2-2; Standards of Professional Practice,
Module A; Advanced Applications; Standards of Professional Practice, Module B; Comprehensive Appraisal
Workshop; Advanced Sales Comparison and Cost Approach Analysis; Partial Interest Valuation - Undivided; Case
Studies in Commercial Hi hest and Best Use, Standards of Professional Practice, Part C (430).
EXPERIENCE
10/89 to present Macaulay & Associates, Ltd.
2/86 to 10/89 Schueler, McKown & Keenan, Inc., Seattle, WA.
8/84 to 1/86 UnderwTiter/Secondary Market Analyst Weyerhaeuser Mortgage Co., Los Angeles, CA.
Appraisal assignments include a wide variety of commercial, industrial and residential properties for financial institutions, governmental
entities, law firms, corporations and private individuals. Examples include office buildings, retail shopping centers, multi -family
residential complexes, industrial warehouses; restaurants, retail stores, mobile home parks, service stations, single family subdivisions
and special purpose properties. Other valuation assignments cover rental valuations, partial interest studies (leasehold/leased fee estates),
waterfront commercial and industrial properties for various port authorities, together with remote large acreage agricultural and forest
land. Also, experience with real estate counseling for private individuals.
Local improvement district (LID) special benefit and feasibility study experience includes a variety of road improvement, utility and
other infrastructure projects. The firm's extensive experience with these projects dates back to 1975. Between 1990 and 2000, in
addition to over 30 other feasibility and special benefit studies, almost a dozen major assignments were completed for projects costing
from $1.5 to $82 million. Clients included the cities of Bothell, Issaquah, Lacey, Lake Stevens, Lynnwood, Ocean Shores, Redmond and
Spokane. Details on individual projects will be provided upon request. Since 2000, major special benefit/proportionate assessment
studies have included road improvement projects for the cities of Burien and Covington (2003), a freeway interchange and arterial
improvement project for the City of Sumner (2002 to 2004), a utility local improvement district for the City of Lake Stevens (2005), a
city-wide road improvement project for the City of Ocean Shores (2006 to 2007) and a project improving access to the Southcenter
regional shopping mall for the City of Tukwila (2006 to 2008). In the last two years (2006 to 2008), economic feasibility studies have
been completed for the cities of Ferndale, Freeland, Kent, Lynnwood, Ocean Shores and Yelm.
Macaulay & Associates, Ltd.
EXPERIENCE (con't.
A wide variety of multi -parcel right-of-way acquisition appraisals have been completed, such as riverbank protection easements for the
City of Tukwila, right-of-way acquisition for road widening for the City of Bellingham and utility line easements, road widening and
other public improvement projects for the City of Everett. A large right-of-way project for the Montana Department of Highways near
Kalispell, Montana was completed several years ago. Also, eminent domain appraisals have been completed for the Washington State
Department of Transportation (WSDOT) and Burlington Northern Santa Fe Railroad in Wenatchee and Tacoma. Other special purpose
assignments are 6,000 acres on the Tulalip Indian Reservation for the Tulalip Tribes, 80 acres on Burrows Island in Skagit County, 900
acres in Skagit County for Skagit County Parks and Recreation Department, and the Eagle Harbor ferry maintenance site on Bainbridge
Island for WSDOT. Various reports on mineral rights have been completed, including an 80-acre operating quarry in Bremerton, WA.
BUSINESS AND PROFESSIONAL AFFILIATIONS
Macaulay & Associates, Ltd., Real Estate Appraisers and Consultants Everett, WA.
MAI designation, Appraisal Institute (Member No. 10,712)
Certified Real Estate Appraiser - General Classification, State of Washington (License No. 1100517)
Approved Appraiser and Review Appraiser, Washington State Department of Transportation
Member International Right -of -Way Association
Board of Trustees - Washington Center for Real Estate Research, Washington State University, Pullman, WA.
COURT AND HEARING
Testified in various cases in King, Snohomish and Skagit counties, together with presentations at LID hearings on preliminary and final
a cvccmrnt mllc Ch'slifie.rl as exnert witness in the states of Washington and Montana.
SUMMARY OF APPRAISAL CLIENTS
Financial Institutions
Private Corporations
AEGON Realty Advisors
Weyerhaeuser Company
Northwest Life Assurance Co. of Canada
The Boeing Company
US Bank of Washington
Coates Field Service, Inc.
First Interstate Bank of Washington
Pharos Corporation
Evertrust Bank
Universal Field Service
First Heritage Bank
Gray & Osborne, Inc.
American First National Bank
Earth Tech
Frontier Bank
Anderson Hunter
Commerce Bank
Foster Pepper Shefelman
Coastal Community Bank
Burgess, Fitzer, Leighton & Phillips
Prime Pacific Bank
Inslee, Best & Dozier
Horizon Bank
Perteet Engineering
North County Bank
Preston, Gates & Ellis
GOVERNMENTAL AGENCIES
City of Everett
National Park Service
City of Lynnwood
US Navy
City of Issaquah
University of Washington
City of Mount Vernon
Everett School District
City of Bellingham
Mukilteo School District
City of Edmonds
Monroe School District
City of Mukilteo
Lake Stevens School District
City of Spokane
Tulalip Tribes of Washington
City of Pacific
Washington State Dept. of Transportation
City of Port Angeles
Montana Department of Highways
City of Stanwood
Snohomish County
City of Washougal
King County
Port of Everett
Island County
Port of Anacortes
Skagit County PUD
US Army Corps of Engineers
Skagit County Parks & Recreation Department
Snohomish County PUD No. I
Macaulay & Associates, Ltd. Robert J. Macaulay, MAI Page 2
IPI: Interactive Pipe Inspection
855 Trosper Rd SW 108-206
Tumwater, WA 98512
360.507.1814
pipeexperts@msn.com
Experience
Dennis i as over 30 years In the l)J`aste Water
Insr;action and Rehabiiitatior Field.
His iri ial start in the irdustry was with Cues inc where
he trained Cities in the operation of Closed Circuit TV!
Tor sevier Inspection.
For over 15 ;'ears, Dennis h-as been at the forefront of
T renc,'iless Sew_r Technology. As a contractor
spec alizing in inspection, rehabilitation, and repair
methods, Dennis founded PIPE EXPERTS. The
Experts pride themselves on taking on the cifficult
projects that other contractors say carnet be done -
and c'onipleting them with success. Dennis has
knov,dedge of all facets of the industry vvhlci r allows
him to problem solve the toughest challenges.
Dennis recently "Mrided IPI' Interactive Pipe
Inspector.; a corporation specializing in high
technology pipeline inspection. IPI s on the cutting
edge of technology and providing asset maragement
data, for municipalities and cities.
Education
Shoreline Community College
United States N:-:vv and Naval Reserve: Ret-ed as
Lieutenant Commander
One of the Foulnders of Washington State Association
oT Collection; Svstern Personnel
Key Projects
King County Metro - Annual TV Contract for large
Diameter Pipe - 21 inch to 12 feet. Have Inspected
over 1 million feet of King County Metro interceptor
Lines
King County i,,.4etrc -Annual Claar!ing Contract.
Cieanina of Sand Catchers and Vaults,
King County ;Metro -TV Inspection of 4 ,gOg Feet of
Serer lines under Lake Washington, All manholes
were under water requiring divers to se, alur i Purr,
ca ssors for nspeotions.
City of Spokane, WA - Annual contract fGr ins13c 701
o` serer lines.
Margaret Nelson
Archaeologist
Education: Ph.C., Anthropology, University of Washington, 1986 (Ph.D abd)
B.A., English, University of Washington, 1978
Margaret has worked in the Pacific Northwest as an archaeologist for the past 28 years
managing cultural resource management projects including surveys, monitoring projects,
testing, and data recovery excavations in western and eastern Washington, Idaho, and
Oregon. Her experience includes managing numerous Section 106 process projects
and preparation of cultural resource overviews, and evaluations for NEPA EA and EIS,
SEPA, and. As a project manager Margaret has been responsible for a wide variety of
archaeological investigations for underground utility lines including most recently
wastewater/sewer system projects for the King County Wastewater Division and the City
of Centralia.
Selected Project Examples:
Riparian Habitat Restoration projects, Chelan County, WA (2007— 2010).
Managed and participated in surveys for salmon enhancement projects subject to
Section 106 for the Bonneville Power Administration and US Forest Service.
Directed fieldwork, authored and co-authored technical reports and Level III
documents for individual and on -call contracts with the Chelan County Natural
Resource Department and Cascadia Conservation District.
Cama Beach Archaeological Data Recovery Project, Camano Island, Island
County, WA (2004 — 2008)
Directed crew of 10 — 25 in data recovery excavations totaling 138 m3 at a large
late prehistoric shell midden. Conducted feature analysis, participated in
archaeo-botanical analysis, wrote/co-wrote sections of technical report, co -edited
technical report; wrote sections of popular summary. Conducted for Washington
State Parks and Recreation Commission. Total cost for archaeological portion of
the project was about $1.6 million.
• Cedar River Municipal Watershed projects, King County, WA (2004 — 2008)
Project manager for survey and monitoring projects for on -call contract with
Seattle Public Utilities. Wrote or co -wrote technical reports. Co-authored study of
ethnographic and prehistoric fire use in central Cascades for predictive modeling
within Cedar River Watershed. Prepared for Seattle Public Utilities, Seattle, WA.
• Archaeological Treatment Plan and Monitoring for the Port Angeles
Graving Dock Remediation Project, Clallam County, WA (2007)
Project manager for monitoring of deconstruction activities at location of large
prehistoric village/cemetery. Co-authored monitoring report and archaeological
site treatment plan for Remediation Project Memorandum of Agreement. 2007
• City of Centralia Sewer Replacement Project, Lewis County, WA (2009).
Project manager for Section 106 survey of 2.3 mile sewer upgrade corridor in
CA5CADIA ARCHAEOLOGY
Margaret Nelson
Page 2
archaeologically sensitive setting. Conducted background research, directed
fieldwork, and prepared technical report.
Cultural Resources Assessment of the Barton, Murry, North Beach, and
South Magnolia Sub -basins, Seattle, King County, WA (2009-2010)
Project manager, conducted background research into historic and prehistoric
cultural resources, developed predictive model for site distribution, prepared
document for use by King County Wastewater Division to define areas with low
cultural resource sensitivity where stormwater overflow facilities could be
installed.
CASCADIA' ARCHAEOLOGY