HomeMy WebLinkAboutWWP2703628.2SURVEY CONTROL
HORIZONTAL DATUM:
NAD83(91) WASHINGTON STATE PLANE COORDINATE SYSTEM NORTH ZONE
VERTICAL DATUM:
NAVD 1955 CITY OF RENTON PUBLISHED BENCH MARKS
#2068 CASED MONUMENT WITH LEAD AND TACK AT THE INTERSECTION OF SE 139TH PLACE AND 156TH AVENUE SE.
ELEVATION = 372.34
SITE CONTROL:
ESM CONTROL POINT LOCATED 27' NW OF THE INTERSECTION OF SE 136TH ST AND 165TH AVENUE SE.
N 178033.9669, E 1323118.6406, ELEVATION = 466.25
ESM CONTROL POINT LOCATED 511' WEST OF THE INTERSECTION OF SE 136TH ST AND 168TH AVENUE SE ON THE SOUTHERLY EDGE OF
ASPHALT.
N 178031.6592 E 1322625.8698, ELEVATION = 454.97
LEGEND
EXISTING
E
WATER METER
TELEPHONE
FIRE HYDRANT
UNDERGROUND POWER
�Q
GATE VALVE
GAS MAIN
SEWER MAIN
j�
GAS VALVE
SEWER MAIN BY OTHERS
LIGHT POLE
w WATER MAIN
♦
UTILITY POLE
- STORM MAIN
E—
UTILITY POLE ANCHOR
- - CHAIN -LINK FENCE
�
TELEPHONE RISER
EDGE OF PAVEMENT
M
TELEPHONE VAULT
- CURB
STORM DRAIN CATCH BASIN
CONTOUR (2')
STORM DRAIN MANHOLE
CONTOUR (5')
O
SAN. SEWER CLEAN OUT
SECTION LINE
Qs
SAN. SEWER MANHOLE
TREES
-�-
PK NAIL
MONUMENT
GRAVEL
ASPHALT
ASPHALT TO BE REMOVED
DDADf1CCn
GRAVEL GRAVITY SEWER MAIN
PAD MOUNTED TRANSFORMER FORCE MAIN BY OTHERS
AND VAULT (IF NECESSARY) UGP POWER
POWER VAULT TELEMETRY
— SILT FENCE
CONSTRUCTION LIMITS
598__ CONTOUR (2')
--6,00 — -- CONTOUR (10')
CONSTRUCTION NOTES
GENERAL NOTES
1. CONTRACTOR SHALL CALL 1-800-424-5555 FOR UTILITY LOCATES 48 HOURS BEFORE CONSTRUCTION.
2. CONTRACTOR INITIATED CHANGES SHALL BE SUBMITTED IN WRITING TO THE ENGINEER FOR APPROVAL PRIOR TO IMPLEMENTATION OR
CONSTRUCTION.
3. CONTRACTOR MUST KEEP A COPY OF THE APPROVED PLANS ON -SITE WHENEVER CONSTRUCTION IS IN PROGRESS.
4. THE CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO PROTECT THE PUBLIC AND PREVENT NUISANCES. CONTRACTOR
SHALL PROVIDE TEMPORARY BRACING FOR THE STRUCTURE AND STRUCTURAL COMPONENTS UNTIL ALL FINAL CONNECTIONS HAVE
BEEN COMPLETED IN ACCORDANCE WITH THE PLANS.
5. THE CONTRACTOR IS RESPONSIBLE FOR PREPARING COMPLETE AS -BUILT RECORDS,
6. CONSTRUCTION OF IMPROVEMENTS SHALL CONFORM TO THE CURRENT EDITION OF THE CITY OF RENTON AND KING COUNTY
STANDARDS AND THE STANDARD SPECIFICATIONS FOR ROAD, BRIDGE AND MUNICIPAL CONSTRUCTION, 2010 EDITION, AS ISSUED BY
THE WASHINGTON STATE DEPARTMENT OF TRANSPORTATION AND THE AMERICAN PUBLIC WORKS ASSOCIATION. THESE DOCUMENTS
HEREINAFTER REFERRED TO AS THE STANDARD SPECIFICATIONS.
7. THE CONTRACTOR IS REQUIRED TO PROVIDE ALL CONSTRUCTION STAKING ON THIS PROJECT INCLUDING THE PREPARATION OF
COMPLETE CONSTRUCTION RECORDS. STAKING FOR GRADES AND ALIGNMENT SHALL BE PERFORMED BY AN ENGINEERING OR
SURVEYING FIRM LICENSED AND CAPABLE OF PERFORMING SUCH WORK. RIGHT OF WAY AND EASEMENT LIMITS MUST BE CLEARLY
IDENTIFIED IN THE FIELD DURING CONSTRUCTION.
8. A PRECONSTRUCTION CONFERENCE AND 24-HOUR NOTICE WILL BE REQUIRED PRIOR TO STARTING CONSTRUCTION OR RESTARTING
CONSTRUCTION AFTER A PERIOD OF MORE THAN 5 DAYS OF NO WORK BEING PERFORMED.
9. CONTRACTOR SHALL RESTORE ALL AREAS DISTURBED BY CONSTRUCTION TO CONDITIONS EQUAL OR BETTER TO THOSE FOUND PRIOR
TO CONSTRUCTION. CONTRACTOR SHALL HYDROSEED ALL EXISTING GRASS AREAS THAT ARE DISTURBED BY HIS ACTIVITIES.
10. SEE DIVISION 1 OF THE SPECIFICATIONS FOR PERMIT INFORMATION.
11. CONSTRUCTION OF THE SANITARY SEWER GRAVITY AND FORCE MAIN (BY OTHERS) WILL BE PROCEEDING DURING THE CONSTRUCTION
OF THE PROPOSED LIFT STATION, PORTIONS OF THE GRAVITY THIS CONTRACT.
12. CONTRACTOR MAY HAVE TO COORDINATE WITH THE GRAVITY SEWER AND FORCEMAIN CONTRACTORS DURING THE CONSTRUCTION FOR
STAGING AREAS AND CONSTRUCTION ACCESS. DEPENDING ON CONSTRUCTION SEQUENCING, ADDITIONAL COORDINATION IS NEEDED
DURING THE CONNECTION TIE-INS BETWEEN MANHOLES.
13. THE CONTRACTOR SHALL DETERMINE THE SCOPE, TYPE, SIZE, QUANTITY, METHOD OF INSTALLATION, OPERATION, AND REMOVAL OF
THE DEWATERING SYSTEM NECESSARY TO KEEP THE EXCAVATION SITE DEWATERED TO STABILIZE THE SOILS FOR CONSTRUCTION.
14. THE CONTRACTOR SHALL DISCHARGE WATER FROM THE DEWATERING SYSTEM IN ACCORDANCE WITH THE REQUIREMENTS OF STATE
AND LOCAL REGULATIONS AND THE REQUIREMENTS OF THESE PLANS AND SPECIFICATIONS. AT NO TIME SHALL SILT LADEN WATER
BE DISCHARGED OFF SITE. CONTRACTOR MAY DISCHARGE FILTERED STORM WATER INTO THE STORMWATER POND. SEE EXISTING SITE
AND TESC PLAN FOR ADDITIONAL STORMWATER NOTES.
15. THE CONTRACTOR SHALL CLEANUP ALL AREAS AFFECTED BY THEIR ACTIVITIES TO THE SATISFACTION OF THE CITY REPRESENTATIVE
BY THE END OF EACH WORKING DAY OR MORE FREQUENTLY IF REQUIRED BY THE CITY REPRESENTATIVE. THIS INCLUDES REMOVAL
OF ALL DUST, MUD, ROCKS, ASPHALT DEBRIS, AND REFUSE FROM STREETS, SIDEWALKS, DRIVEWAYS, AND ANY OTHER AREAS
AFFECTED BY THE CONSTRUCTION ACTIVITIES. FAILURE TO CLEANUP TO THE SATISFACTION OF THE OWNER'S REPRESENTATIVE WILL
NECESSITATE A SHUTDOWN OF THE PROJECT UNTIL CLEANUP IS PROPERLY PERFORMED. DAILY CLEANUP IS AN INTEGRAL PART OF
EROSION AND POLLUTION CONTROL.
16. ALL EXISTING UTILITIES INDICATED ON THE DRAWINGS HAVE BEEN PLOTTED FROM THE BEST INFORMATION AVAILABLE TO THE
ENGINEER AND SHOULD THEREFORE BE CONSIDERED APPROXIMATE ONLY AND NOT NECESSARILY COMPLETE. THE SOURCE OF
INFORMATION GENERALLY CONSISTS OF CONSTRUCTION RECORDS AND OTHER DATA OBTAINED VERBALLY FROM OFFICIALS ASSOCIATED
WITH THE PARTICULAR UTILITY. OWNER AND ENGINEER DO NOT GUARANTEE AND DO NOT ASSUME ANY RESPONSIBILITY FOR THE
ACCURACY OF THIS INFORMATION. IT IS UNDERSTOOD THAT OTHER ABOVE GROUND AND UNDERGROUND FACILITIES NOT SHOWN ON
THE DRAWINGS MAY BE ENCOUNTERED DURING THE COURSE OF THE WORK. IT IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR
TO INDEPENDENTLY VERIFY THE ACCURACY OF ALL UTILITY LOCATIONS SHOWN TO AVOID DAMAGE AND/OR DISTURBANCE TO SUCH
UTILITIES, AND TO FURTHER DISCOVER AND AVOID ANY OTHER UTILITIES NOT SHOWN HEREON WHICH MAY BE AFFECTED BY THE
IMPLEMENTATION OF THIS PLAN. CONTRACTOR SHALL PRESERVE, PROTECT AND SUPPORT ALL EXISTING UTILITIES ENCOUNTERED
DURING CONSTRUCTION.
17, THE CONTRACTOR SHALL HAVE ALL UTILITIES LOCATED BY THE APPROPRIATE UTILITY LOCATING PROFESSIONALS, PRIOR TO AND
DURING CONSTRUCTION. THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE ENGINEER AND THE UTILITY COMPANY WHEN A CONFLICT
OCCURS.
18. CONTRACTOR SHALL COORDINATE WITH THE ISSAQUAH SCHOOL DISTRICT (DISTRICT) AND THEIR CONTRACTORS REGARDING
MAINTENANCE AND ACCESS TO THE FACILITIES. DISTRICT CONTACT FOR CONSTRUCTION COORDINATION WILL BE LADD STEJSKAL.
FIELD CONSTRUCTION WORK SHALL NOT START UNTIL THE STORM WATER POND CONSTRUCTION WORK IS COMPLETED. THE
COMPLETION DATE OF THE POND IS ESTIMATED AT AUGUST 30 2012.
19. OTHER CONSTRUCTION ACTIVITIES OF THE ISSAQUAH SCHOOL DISTRICT AT LIBERTY HIGH SCHOOL THAT MAY AFFECT THE
CONSTRUCTION OF THE LIFT STATION ARE:
A) SEPTIC HOLDING TANK PUMPING (DAILY)
B) GRAVITY SEWER AND FORCEMAIN CONSTRUCTION
C) STORMWATER POND CONSTRUCTION
D) GAS LINE CONSTRUCTION
THE CONTRACTOR IS RESPONSIBLE FOR COORDINATION WITH THE DISTRICT AND THEIR CONTRACTORS TO FACILITATE CONSTRUCTION
OF THE LIFT STATION. NO ADDITIONAL COST WILL BE PAID FOR CONSTRUCTION DELAYS CAUSED BY THESE OTHER CONSTRUCTION
ACTIVITIES.
PIPE LENGTH MEASUREMENTS
PIPE LENGTHS CALLED OUT ON PLANS ARE MEASURED AS FOLLOWS:
FLANGE x FLANGE (FLxFL) PIPE �I PIPE LENGTH
MEASURED FROM FACE OF FLANGE
TO FACE OF FLANGE.
FLANGE x PLAIN END (FLxPE) PIPE
MEASURED FROM FACE OF FLANGE
TO CENTER OF FITTING.
PLAIN END x PLAIN END (PExPE) PIPE
MEASURED FROM CENTER OF FITTING
TO CENTER OF FITTING.
RESTRAINED JOINT x RESTRAINED
JOINT (RJxRJ) PIPE
MEASURED FROM CENTER OF
FITTING TO CENTER OF FITTING.
PIPE LENGTH i{
PIPE LENGTH —�
uIr
PIPE LENGTH
FITTINGS ARE ASSUMED TO BE STANDARD LENGTH 125#, 250#
FLANGED OR COMPACT CLASS 350 MECHANICAL JOINTS,
CONTRACTOR RESPONSIBLE FOR VERIFYING LENGTHS. IT IS
THE CONTRACTOR'S RESPONSIBILITY TO TAKE INTO ACCOUNT
ANY VARIATIONS IN FITTING DIMENSIONS.
CONSTRUCTION SEQUENCING
THE CONTRACTOR SHALL FIRST ONLY MOBILIZE TO COORDINATE, WITH PUGET SOUND
ENERGY, THE INSTALLATION OF THE PRIMARY POWER CONDUIT. SAID MOBILIZATION
SHALL BE AFTER THE COMPLETION OF THE GRAVITY SANITARY SEWER MAIN
CONSTRUCTION BEING PERFORMED BY OTHERS WHICH IS ANTICIPATED TO BE ON OR
BEFORE JULY 20, 2012. THE CONTRACTOR SHALL COMPLETE THE WORK ON THE
PRIMARY POWER CONDUIT PRIOR TO AUGUST 15, 2012, THE LAST DAY THAT ACCESS
ROAD TO THE PERFORMING ARTS CENTER CONSTRUCTION PROJECT CAN BE SHUT
DOWN TO THROUGH TRAFFIC. THE CONTRACTOR SHALL NOT MOBILIZE ONTO THE
PROPOSED LIFT STATION SITE UNTIL COMPLETION OF THE LIBERTY HIGH SCHOOL
STORMWATER DETENTION POND (BY OTHERS) AND THE POND CONTRACTOR
DEMOBILIZES FROM THAT LOCATION, OR AUGUST 31, 2012, WHICHEVER COMES FIRST.
THE SPLIT MOBILIZATION IS BUILT INTO THE WORKING DAYS AND THERE WILL BE NO
'NON —WORKING DAYS"DESIGNATED BETWEEN THE MOBILIZATIONS. NOTHING IN THIS
SECTION PRECLUDES, WITH OWNERS APPROVAL, THE ABILITY OF THE CONTRACTOR TO
MAKE AGREEMENT WITH THE OTHER CONTRACTOR(S) AND THE SCHOOL DISTRICT TO
ACCESS PORTIONS OF THE SITE OUTSIDE THESE DATES.
H.
WA3
,s727
�E01STSR�O
`SIGNAL
SIGNED: 05123112
�413TF
ZONAL
SIGNED: 05123112
W
O
Uj
Z
J
Lift
®
Q
W
Cr.
Z
LLJ
ca
W
RH2 ENGINEERING, INC.
http://www.rh2.com
mailbox@rh2.com 1.800.720.8052
BELLINGHAM 36o.676.o836
454 West Horton Road
BOTHELL 42S.9S1.5400
22722 29th Drive SE, Suite 210
EAST
WENATCHEE S09.886.2900
300 Simon Street, Suite 5
RICHLAND 509.946.5181
114 Columbia Point Drive, Suite C
SILVERDALE 360.876.7960
2021 NW Mhyre Rd, Suite 107
TACOMA 253.272.3o59
621 Pacific Avenue Suite 104
SCALE: SHOWN
0 1" 2"
DRAWING IS NOT TO SCALE
IF BAR IS NOT 2" LONG
PLOT: 1 DWG N0.
REVISED TO CONFORM ENGINEER. DEB G01
S362802 TO CONPTRUCTION RECORDS
= REVIEWED: EH
6c,�;�� 04/25/12 DATE: April 29, 2013 SHEET O.
RH2 RING INC. DATE CLIENT REN 2
RECORD DRAWING
AHF
EH
04/25/13
Joe ND.: 112-033
717
BY
REVIEW
DATE
FILENAME: LIBHS—D—GEN.DWG
p
b�
m
� my
N
N�>
z
�
N
O
NN
REVISED TO CONFORM TO CONSTRUCTION RECORDS
N0. REVISION