CHANGE ORDER # 10
AIRPORT..- Renton Municipal Airport DATE: 10 -09 -13
LOCATION: Renton, Washington GRANT #: 3 -53- 0055 -024
CONTRACTOR: ICON Materials
This change order was prepared in accordance with FAA Program Guidance Letter 12 -03. A price
analysis was prepared and it is recommended that the FAA accept the analysis as evidence of cost
reasonableness.
You are requested to perform the following described work upon receipt of an approved copy of this
document or as directed by the Engineer:
Item Description
Taxiway B Edge Light
1 Adjustment
Subtotal
State Sales Tax (9.5 %)
This Change Order Total
Previous Change Order Amount
Original Contract Amount
Revised Contract Total
Recommended by: d' GZz
Approved by.
Accepted by.
Accepted by.
Unit
Unit Price
Quantity
Amount
LS
$1,230.31
1
$1,230.31
JVngineer, Reid Middleton, Inc.
$1,230.31
$116.88
$1,347.19
$463,258.42
$5.460.424.21
$5,925,029.82
Date: l 611 /3
Date: 1� l
Date:
Date:
H:\D0C\23ApV0\007 Renton Twe & Signagel south Taxiway Construction \Change Orders \CO 10.docx
CHANGE ORDER # 10
AIP PROJECT NO. 3 -53- 0055 -024
AIRPORT Renton Municipal Airport LOCATION Renton, WA
JUSTIFICATION FOR CHANGE
This justification for change was prepared in accordance with FAA Program Guidance
Letter 12 -03
Brief description of the proposed contract change(s) and locations(s).
This change order consists of the following:
1. Raise the edge light at Sta. 28 +57 (Left) approximately 6- inches to match the grade
constructed in the South project.
2. Re -grade the soil adjacent to this edge light to match the adjusted base of the edge
light.
Reid Middleton Design Directive #12 dated September 16, 2013, (attached)
documents these revisions.
2. Reason(s) for the change(s) (Continue on reverse if necessary).
When this edge light was installed as part of the Taxiway `B' Rehabilitation North
Portion project, this edge light matched the grade of the surrounded terrain. The Taxiway
`B' Rehabilitation South Portion project plans should have included a construction note
directing the Contractor to adjust the edge light at Station 28 +57 (Left) to match the re-
grading in this area that was part of the South project. This note was not identified on the
plans due to an oversight during the design process. This change order corrects this
oversight.
Re- grading of soil adjacent to this edge light is required so that the adjusted edge light
base is flush with the soil.
3. Justifications for unit prices or total cost:
Justification was prepared in accordance with FAA program guidance letter 12 -03.
4. The sponsor's share of this cost is available from: Port Funds
5. If this is a supplemental agreement involving more than $2,000, is the cost estimate based
on the latest wage rate decision? Yes : No NA X
6. Has consent of surety been obtained? Yes Not Necessary X
7. Will this change affect the insurance coverage? Yes No X
8. If yes, will the policies be extended? Yes No X
H:00C�23ApM007 Renton Tw B & signageVsouth Taxiway Construction \Change Orders \CO l0.docx
J
9. Has this Change Order been discussed with FAA Officials?
Yes X No When 09/10/13 With Whom Peter Dom
H:\D0C\23Ap\1M007 Renton TW B & signageVSoutn Taxiway Construction \Change Orders \CO l0.docx
Air-
Renton Airport
Change Order Cost Analysis /Backup for Taxiway B System Rehabilitation — South Portion
Change Order #10
This cost analysis is prepared in compliance with Program Guidance Letter 12 -03. Comparative costs
have been taken from bid prices for other projects, from construction cost guides and from quotes from
suppliers. The quantities to complete each of the activities listed below are small in comparison to the
quantities for a typical project, therefore unit prices for the items listed will be higher than expected for
a large quantity.
Taxiway B Edge Light Adjustment
This activity consists of the following tasks.
1. Raise Taxiway Edge Light
The work for raising (adjusting) a taxiway edge light is approximately the same work and level of effort
for labor as the WSDOT bid item "Adjust Valve Box ". Review of the unit bid prices for "Adjust Valve Box"
indicates that unit prices within the WSDOT Northwest Region (King County) for comparable quantities
of valve box adjustment range from $250 to $625 per each. Total cost for adjusting one taxiway edge
light can be expected to range between $250 and $625.
The Contractor's lump sum price for this work is $572.80.
2. Soil Re- grading Adjacent to Edge Light
This item consists of crew labor and equipment required to re -grade around the adjusted taxiway edge
light. No materials were required. Labor rates are at the rates established for the contract. Equipment
rates are at the standard rates established for the contract. The Contractor estimates a total time of 6
hours (3 person crew at 2 hours each) for performing this task.
The Contractor's lump sum price for this work is $463.85.
The total cost for raising the taxiway edge light and re- grading adjacent to the edge light can be
expected to range from approximately $715 to $1,090 plus allowable mark -up.
ICON's proposal for adjusting one taxiway edge light and re- grading soil around the edge light
$1,036.65 plus allowable mark -up
Conclusion: The requested change order amount is a fair and reasonable estimate for raising one
taxiway edge light and re- grading adjacent to the edge light.
H:doc /23ap/10/007 Renton TW B & Signage /'south Taxiway Constr /Change Orders /Renton CO #10 Cost Justifi cation. doc.mjc
DD Number:
Owner:
Contractor:
Engineer:
Project:
EM
DESIGN DIRECTIVE
12
Renton Municipal Airport Contract No.
ICON Materials
3 -53- 0055 -24
Reid Middleton, Inc. Engineer's File No.: 232010.007.005
Taxiway B System Rehabilitation - South Portion Reconstruction
DIRECTIVE
Specification Section: Para.: _ Drawing Ref: C6.3 Detail:•
Plan Sheet C6.3 depicts the limits of installation and adjustment of Taxiway B edge lights. The design depicted on this sheet
should have included adjustment of an edge light installed as part of the Taxiway B North project at approximate Station 28 +57
(Left). When installed in the North project, this edge light matched grade at that time; however when the South project raised
the grade in this area, this edge light should be been adjusted to match new grade, but was not identified due to an oversight
during the design process.
The design is revised as follows (see attached Sheet C6.3 with red line revisions):
• Raise the edge light at Sta. 28 +57 approximately 6- inches to match grade constructed in the South project.
• Re -grade soil adjacent to this edge light to match the adjusted top of edge light and the surrounding grade.
Bid item quantity adjustments per schedule will be reconciled as part of progress estimate adjustments. Contractor shall submit
intended adjustments to individual bid items for reconciliation with engineer.
Signed by: MLC�Cree e►v Date: 9/16/13
❑ Attachments
h: \doc\ forms \construction \izone\request for interpretation. do c
cc: Owner
Reid Middleton
09 Ir( SU 4d N'dld in NLLH9f1 3903 AVMIXVl
40196 n
w ;AS X Ia,9S 4llCl 9Z! Nouvi I8VH3 W31SAS 8 AVMIXdl H1f10S
IMUMV NdIOIN(1N NO N3a - NOLN38 30 /•NO
'13
LS LS Wm
x m Z-N.
+ I\
L
i
w
cli
00
Cl I 9g v w
V 1N
•(b,��' 11 1
11 I�
� N
1.L.I
I 2n
1
W
z a�
`\- Z•90 133HS 33S OS+9 VZ 1S 3NI-IHO1VW
bw��n -zoos ure:-wmax� � w^rz:e Hari Cahn
ICON 'Hate i 15
1:508 Valentine Ave. SE
euPacific WA. 9804"
(206) 573 -3200 8 Fax (206) 373 -0319
.mvivAconmateriah.com
Cost Detail with Categories
MOM
Project Name:
Renton Airport Taxiway "B"
Unit
Customer:
City Of Renton
Sob Number:
513302
Quantity UM
Billing Address:
3555 NE 2ND STREET
Bid As:
PRIME
807 - Design Directive #12
1.00 LS
Renton, WA 98056
Estimator:
David Gent
a
$1,230.31 18.68 /o
Phone:
425- 430 -7400
Project Address:
Renton, WA
$8.00
Contact:
Match Existing Grade.
Completion Date:
$63.19
$126.38
Labor Skilled
2.00 HR
Total Allowable Markup = $193.66
General Labor Crew 1.00 HR $463.85 $463.85 JobCostID: 50.300
Labor Equipment Material aubmLltfac ee Trucking Miscellaneous plug
Unit: $343.85 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total: $343.85 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00
Break Bulk Crew
1.00 DY
Unit
Total
(2.00 PH /DY, 0.25 DY)
Description
Quantity UM
Direct Cost
Direct Cost
Unit Price
Total Price MU%
807 - Design Directive #12
1.00 LS
$1,036.65
;1,036.65
$1,230.31
a
$1,230.31 18.68 /o
Raise Edge Light Sta.28 +57 To
$34.00
Plate Compactor
2.00 HR
$8.00
$16.00
Match Existing Grade.
2.00 HR
$63.19
$126.38
Labor Skilled
2.00 HR
Labor Equip1J en
Materisll
Subcontracted
Truckf�nc
Miscellaneous
p q
Unit: $343.85 $120.00
$0.00
$572.80
$0.00
$0.00
$0.00
Total: $34185 $120.00
$0.00
$572.80
$0.00
$0.00
$0.00
CEC - 10/7/2013 9:56 AM:
ICON Allowable Markup as Follows:
Labor @ 29% =$ 99.72
Equipt @ 21% = $25.20
Sub @ 120/c = $68.74
Total Allowable Markup = $193.66
General Labor Crew 1.00 HR $463.85 $463.85 JobCostID: 50.300
Labor Equipment Material aubmLltfac ee Trucking Miscellaneous plug
Unit: $343.85 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total: $343.85 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00
Break Bulk Crew
1.00 DY
$463.85
$463.85
(2.00 PH /DY, 0.25 DY)
JD 410 /Cat 426 Backhoe (7
2.00 HR
$35.00
$70.00
MTons)
i Tn Flatbed
2.00 HR
$17.00
$34.00
Plate Compactor
2.00 HR
$8.00
$16.00
Operator Foreman
2.00 HR
$63.19
$126.38
Labor Skilled
2.00 HR
$47.79
$95.58
Operator Skilled
2.00 HR
$60.94
$121.89
J Innovative Electric Quote
1.00 LS
$572.80
$572.80 JobCostID: 50.460
10/7/2013 10:06:28 AM Page 1 of 2
J
Total Bid Price: $1,230.31
10/7/2013 10:06:28 AM Renton Airport Taxiway 'B" Page 2 of 2
Percent of
Amount
Direct Cost
Labor:
$343.85
33.17%
Equipment Owned:
$120.00
11.58%
Equipment Rented:
$0.00
0.000/0
Materials Owned:
$0.00
0.000/0
Materials Purchased:
$0.00
0.000/0
Subcontracted:
$572.80
55.26%
Trucking Owned:
$0.00
0.00%
Trucking Hired:
$0.00
0.00%
Miscellaneous:
$0.00
0.00%
Plug:
$0.00
0.00%
Direct Cost:
$1,036.65
PIUM
Percent of
Amount
Bid Price
Total Direct Cost:
$1,036.65
84.26%
Total DC Adds /Cuts:
$0.00
0.00%
Total Indirect Cost:
$0.00
0.00%
Total Bond:
$0.00
0.000/0
Total Overall Cost:
$1,036.65
84.26%
Total Overhead:
$0.00
0.00%
Total Profit:
$193.66
15.74%
Total Margin:
$193.66
15.74%
Total Bid Price: $1,230.31
10/7/2013 10:06:28 AM Renton Airport Taxiway 'B" Page 2 of 2
LM
INNOVATIVE
2iQMMY W G:IA�. s � NIi�U b�f R. a4
TO: ICON Materials
ADDRESS: 1508 Valentine Ave. SE
CITY & STATE: Pacific, WA 98047
PHONE:206- 574 -3906
ATTN: Chuck Coffey
EMAIL: ccoffey @oldcastlematerials.com
P 425 - 290.74403
V 425- 359.19h5
P.O. Box 4399
E-ar Tr, WA 90204
1 rvNt7YAT IYS'C4CGT'Pt >C.CTOM
P]
DATE: September 21, 2013
JOB: City of Renton Taxiway B System Rehabilitation South Portion Reconstruction
AIP No. 3 -53 -0055 -024
PROJECT NO: 0001 -2013
Design Directive #12 Raise edge light at Sta 28 +57 6 inches to match existing grade
Labor Hours
Labor markup
Material Costs
Material markup
Permit Costs
Sub contract work
Prime Cost Total
Small Tool Allowance
Sub -Total
Bonds, Permits, Ins.
Sales tax
3.45 Hours @ $66.38
29%
21%
0% of sub total $$
% of TOTAL 3.00%
0.0%
Subtotal
$229.01
$66.41
$215.45
$45.24
$0.00
$0.00
$556.12
$0.00
$556.12
$16.68
$0.00
TOTAL PRICE FOR THIS CHANGE
$572.80
LABOR AND MATERIAL BREAKDOWN FOR THIS CHANGEORDER
DESCRIPTION
QUANITY
MATERIAL
MATERIAL
LABOR
LABOR
EACH
EACH
TOTAL
EACH
TOAL
24" SonoTube 12'
1
$107.76
$107.76
0.5
0.5
Dowel existing base
5
$2.25
$11.25
0.1
0.5
Base extension
1
$194.05
$194.05
0.2
02
Concrete for base ext.
1
$9.90
$9.90
2.25
2.25
Heat shrink
2
$3.76
$0.25
0.2
0.4
R &R edge light
1
$0.00
$0.00
0.1
0.1
Total material cost
$215.45
Total labor hours
3.45
Unit Bid Analysis - Standard Items Report Page 1 of 1
0 Soarch Contact WSDO WSDOT Homo
19 .p..... of Trwaporftflon T Alm_
E`IC .S ftGi DS Ri).: =t_ TS G;.SIfJESS Etd'�IRC ?', ;'Er.Tr L ;`A.FS ;AT:�,
F0_
Bid Item Unit Price Tabulation Standard Items
Region: Northwest Contracts awarded from 10/8/2008 thru 10/8/2013
Total records found: 17 1 New Search
Standard
Item
Unit of
Job
Contract
Planned Low Second Third
Number
Measure Item Description
Number
Number
AD Date Quantity
Bid Bid
Bid
6243
EACH
ADJUST VALVE BOX
08A026
007653
12/15/2008 68.00
$180.00 $315.00
$300.00
6243
EACH
ADJUST VALVE BOX
09A0181
007859
11/23/2009 2.00
$275.00 $200.00
$152.75
6243
EACH
ADJUST VALVE BOX
09AO21
007874
12/21/2009 8.00
$300.00 $265.00
$225.00
6243
EACH
ADJUST VALVE BOX
09AO09
007920
3/15/2010 8.00
$310.00 $270.00
$350.00
6243
EACH
ADJUST VALVE BOX
1 OA009
007921
3/15/2010 1.00
$600.00 $250.00
$625.00
6243
EACH
ADJUST VALVE BOX
1 OA010
007938
4/12/2010 5.00
$200.00 $180.00
$269.59
6243
EACH
ADJUST VALVE BOX
1OA008
007948
4126/2010 1.00
$325.00 $375.00
$375.00
6243
EACH
ADJUST VALVE BOX
1OA055
008051
11/15/2010 15.00
$225.00 $475.00
$280.00
6243
EACH
ADJUST VALVE BOX
1 OA029
008052
11/22/2010 8.00
$320.00 $230.00
$700.00
6243
EACH
ADJUST VALVE BOX
10A017
008053
11/22/2010 17.00
$420.00 $125.00
$480.00
6243
EACH
ADJUST VALVE BOX
1OA039
008055
11/22/2010 3.00
$600.00 $500.00
$350.00
6243
EACH
ADJUST VALVE BOX
1 OA035
008103
2/28/2011 80.00
$420.00 $0.00
$0.00
6243
EACH
ADJUST VALVE BOX
1OA038
008114
3/21/2011 3.00
$245.00 $275.00
$600.00
6243
EACH
ADJUST VALVE BOX
1 OA034
008128
4/4/2011 2.00
$400.00 $350.00
$325.00
6243
EACH
ADJUST VALVE BOX
12AO15
008416
1/22/2013 3.00
$870.00 $0.00
$0.00
6243
EACH
ADJUST VALVE BOX
12AO12
008439
2/25/2013 4.00
$360.00 $425.00
$425.00
6243
EACH
ADJUST VALVE BOX
12AO17
008457
3/25/2013 3.00
$500.00 $400.00
$380.00
NWR AVERAGE LOW BID is $325.35
State AVERAGE LOW BID is $326.06
New Search