Loading...
HomeMy WebLinkAboutCO 3 CITY OF RENTON - CAC-10-120, co #3-11 Public Works Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: CAG 10-120 C.O.# 3 LAKE WASHINGTON BEACH LIFT STATION REPLACEMENT CONTRACTOR: Kamins Construction. SUMMARY OF PROPOSED CHANGE: Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below: Additional items Under This Change Order Unit Quantity Unit Price Total Price NEW ITEM:Removal of a portion of work required under the original LS 1 $(2,360.00) $(2,360.00) contract and bid under Item No.2 Two items of work required(slurry seal and parking lot striping)were removed from the original contract. These items were part of the lump sum Bid Item 2—"Lake Washington Beach Lift Station Replacement'. This change order deducts the value amount of these two items in the original bid. Sub Total $(2,360.00) Sales Tax(9.5%) $(224.20) Total Additional Work $(2,584.20) ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET ESTIMATED CONTRACT TOTAL AMOUNT AMOUNT CHANGE THIS ORDER AFTER CHANGE $293,060.11 $300,918.74 $(2,584.20) $298,334.54 SIGNATURES: Contractor: Date: Project Engineer: Date: /7 c/ I Approved By: Date: G/ TG`G U sties System Director) H:FileSys\WWP-Wastewater\WWP-27-3557\CO-3-Lk Wash Bch Lift Station Replacement/MB