HomeMy WebLinkAboutAdden 05 j
Washington State _* O-09-077 , Adden #5-11
VAf Department of Transportation
Supplemental Agreement Organization and Address
BergerABAM
Number 5 33301 Ninth Avenue S., Suite 300
Federal Way,WA 98003
Original Agreement Number
CAG-09-077 Phone: 206/431-2300
Project Number Execution Date Completion Date
4/17/2009 1 2/29/2012
Project Title New Maximum Amount Payable
Update Project Definition Report, Strander Blvd. $ 2,214,900.00
Description of Work
Extend completion date to provide time to receive bids and to execute Supplement No. 6 for construction
administration and inspection,plus design construction support services.
The Local Agency of City of Renton
desires to supplement the agreement entered into with BergerABAM Inc.
and executed on 4/17/2009 and identified as Agreement No. CAG-09-077
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Section 1, SCOPE OF WORK, is hereby changed to read:
$udgets for tacks revised ac shown on Exhibit F-?
I I
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days for
completion of the work to read: Project completion date extended 9
III
Section V, PAYMENT, shall be amended as follows:
No c�hnnge
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the appropriate spaces
below and return to this office for final action.
By: Tames 4 Clunrre,RergPrARAM Inc By: C itv of Renton
C
Consultant Signature proving Authority Signature
DOT Form 140-063 EF Date
Revised 9/2005
I
• 9/2/2011
Exhibit E-2-Supplement No.5 Page 1 of 2
Strander Boulevard Effort and Fee Estimate
Summary of Budget Allocations per Task/Sub-Task
Tasks/Sub-Tasks Budget Allocation
Lump Sum thru Supplement 1 $ 19,900
100-Start-up Services $ 262,000
105-Technical Memorandum(35%Design) $ 155,000
110-30%Submittal to BNSF $ 62,000
115-Preliminary Geotechnical $ 45,000
200-Project Admin,Coord,and Mgmnt $ 154,248
205-Design To Budget ind in other tasks
210-Invoicing and Progress Reports $ 15,676
215-Subconsultant Coordination $ 26,676
220-Project Management and Administration $ 21,696
225-Meetings with City and Others $ 86,200
200.1 Additional Project,Admin,Coord,and Mgmnt $ 4,000
230-Quality Assurance and Control Intl in other tasks
Task 300-Railroad Engineering(Hanson) $ 379,821
305-Project Management $ 33,952
310-60%Submittal to BNSF $ 123,511
315-100%Submittal to BNSF $ 175,475
315.1-Revised 100%Submittal to BNSF $ 37,160
315.2-Resolve Track Geometrics $ -
320-Design Support during Advertisement $ 8,723
320.1-Design Support during Award $ 1,000
Task 400-Geotechnical Engineering(S&W) $ 165,631
405-Evaluate Geotechnical Issues $ 72,896
405.1-Evaluate Geotechnical Issues Budget Adjustment $ (34,369)
410-Prepare Dewatering Memorandum $ 26,917
410.1-Prepare Dewatering Memorandum budget increase $ 8,000
415-Construct Pumping Test Wells and Refine Analysis $ 79,759
415.1-Construct Pump Test Wells budget decrease $ (10,000)
420-Trench Excavation/Testing $ 17,359
420.1-Trench Excavation/Testing budget decrease $ (2,000)
425-Design Support during Advertisement $ 6,069
425.1-Design Support during Award $ 1,000
Task 500-Civil/Structural Engineering $ 925,180
505-Field Verification Survey $ 20,649
505.1 Field Verification Budget adjustment $ (10,445)
505.2 Field Verification Track Survey $ -
510-Roadway Design $ 200,420
510.1-Revise Roadway Design $ 50,000
515-Utilities $ 20,600
515.1-Revise Utilities Design $ 5,000
520-Storm Drainage $ 67,030
520.1-Revise Storm Drainage $ 15,000
525-Pump Station $ 79,710
525.1-Revise/Complete Pump Station Design $ 5,000
Q:\FederalWay\2009\FAPW7-09-175\ProjMgt\Contract Development\Supplement No.5\Exhibit E-2 to Supplement No.5.xlsx
i0 9/2/2011
Exhibit E-2-Supplement No.5 Page 2 of 2
Strander Boulevard Effort and Fee Estimate
Summary of Budget Allocations per Task/Sub-Task
Tasks/Sub-Tasks Budget Allocation
Task 500-Civil/Structural Engineering(Continued)
530-Structural $ 144,960
530.1-Revise Retaining Wall Design $ 25,000
535-Construction Staging&Schedule $ 35,780
535.1-Revise Construction Staging and Schedule $ 5,000
540-60%Submittal $ 16,533
545-90%Submittal $ 39,119
550-Final PS&E Submittal $ 39,119
550.1-Revise/Complete 100 Percent PS&E Submittal $ 22,000
550.2-Revise/Complete Ad PS&E Submittal $ 39,142
555-Design Support during Advertisement $ 42,000
555.1-Design Support during Award $ 14,000
560-RH2 Pump Station Electrical Design $ 26,727
560.1-Revise/Complete Pump Station Electrical Design $ 9,904
560.2-Design Support During Advertisement $ 2,500
565-BCE Illumination Design $ 8,100
565.1-Revise/Complete Illumination Design $ 1,431
566-Design Support during Advertisement $ 900
Task 600-Right of Way $ 176,328
605-Title Reports $ 23,680
610-ROW Plans $ 33,060
615-Boundary Line Survey $ 34,671
620-Boundary Line Adjustment $ 8,918
625-Title Review $ 23,012
630-Property Acquisitions $ 58,125
630.1 Property Acquisitions Budget adjustment $ (18,038)
630.2-Revise Boeing R/W Easements $ 12,900
630.3-Revise ST R/W Documents $ -
Task 700-Value Engineering $ 46,892
705-OAC TASKS $ 43,890
705.1 Revise OAC Task Amount $ (5,302)
710-BA Management and Support $ 8,304
Subtotal Initial Lump Sum+Tasks 100 thru 700 $ 2,130,000
Task 800-Remaining Allowance for Design Construction Support
Services(DCSS) $ 84,900
Management Reserve Fund(MRF)-Authorized 6/15/11
Total of above $ 2,214,900
Total Authorization through Supplement No 4 $ 2,214,900
Q:\FederalWay\2009\FAPWT-09-175\ProjMgt\Contract Development\Supplement No.5\Exhibit E-2 to Supplement No.5.xlsx