HomeMy WebLinkAboutCO 89 CITY OF RENTON Public Works Department IWO CITY OF RENTON FEB 13 2C'2 RECEIVED CITY CLERK'S OFFICE CONTRACT CHANGE ORDER' AGREEMENT CONTRACT: CAG 09-x.71-- 2009 Earlington Water and Sewer Improvements Project C.O.# 8 CONTRACTOR: Laser Underground and Earthworks,'inc. SUMMARY OF PROPOSED CHANGE: Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below: 11 CIVI Aaaitional Quantities under I-nis [mange uraer unit quantity unit -rotas Price C08 Change order for additional striping in the intersection of LS1 $2573.17 $2573.17 SW 4th PI and SW Sunset Blvd. Subtotal $2573.17 9.5% Sales Tax $244.45 Total $2817.67- ORIGINAL 2817.62 ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NET CHANGE THIS ORDER ESTIMATED CONTRACT TOTAL AFTER CHANGE $2,162,511.12 $2,451,547.73 $2817.62 $2,454,365.35 Cost Allocation Water Utility 425.455170.018.595.34.63.000 $1,408.81 Sewer Utility 426.465405.018.595.35.63.000 $1,408.81 SIGNATURES: Contractor: Date: Project Engineer:Date:zi Approved By, V uvl/ Date: Z 1J (Water Utility Supervisor) T-TAMI. R.. M -M _ T-IAn14nn Wm— Tl lihAUM-17 9nnQ Farlinatnn Water and Crwnr Ttnnrnvi \i .ntgkr.nnclnlelinnlPav