HomeMy WebLinkAboutProject_Narrative_EVGO_v1.pdfPROJECT NARRATIVE Please respond to these criteria; use a separate sheet if needed. 1.Project Name. 105100809 RENTON EV CHARGER. 2.The name, source, intensity, and location of the sound/project limits. POTELCO , trucks and Sawzall. 3.Description of work. OPEN SPLICE PIT , PULL NEW CABLE APPROX 600' GOING NE AND APPROX 120' GOING SW, TRANSFORMER INSTALLATION, SWITCHING CIRCIRTS-CAUSING OUTAGE TO COMMERICAL PROPERTIES. 4.The equipment and vehicles used for the work (please provide a table of the equipment to be used with its appropriate decibels). Vehicles: 3 LINE TRUCKS 85db @ 50' 1 TON TRUCK 85db @ 50' Sawzall: 85db @ 50’ 5.Proposed Noise Mitigating Measures the applicant will implement to minimize the sound level violations. Use hand tools when possible. Limit run time of gas‐powered equipment. 6.Any additional information or studies regarding any aspect of the requested variance that is deemed necessary to complete the review of the variance request. No 7.The hours during the day and/or night the noise will occur. 10Pm‐5am 8.The number of days and/or nights the noise will occur. 2 Night 9.The ambient sound level during the time of day or night for which the variance is being sought. 84db‐85db 10. The time period (include start date and end date) for which the variance is requested. We will need 1-2 nights to complete work. The date will depend on when the noise variance is issued. 11. The reason for which the noise violation cannot be avoided, i.e. why work cannot be performed within allowed times. OUTAGE NEEDED FOR COMMERICAL CUSTOMERS TO SWITCH CIRCIRTS. 12. Mitigating conditions that the applicant will implement to minimize the sound level violations. Use hand tools when possible. Limit run time of gas‐powered equipment.