HomeMy WebLinkAbout7945.04 E 2023 0915Earth Solutions NWLLC 15365 NE 90th Street, Suite 100 Redmond, WA 98052 Main (425) 449-4704 | Fax (425) 449-4711 www.esnw.com FIELD REPORT Project No. 7945.04 Page 1 of 3 Report ID 7945.04 E 2023 0915 Date Fri 9/15/2023 Weather 75°F Clear Arrival/Departure Time(s) 10:45AM; 11:15AM Travel Time (hr) 1.0 Project Name Canopy Property Location 413 Lincoln Ave NE, Renton ESNW Rep. & Phone Willem Scherwin | 206 793 8569 Client Info/Contact Century Communities | Stacia Bloom General Contractor Info/Contact Contractor #2 Info/Contact Reviewed By LAC Initials/Date RAC Initials/Date Field Supervisor Project Manager Limitations: The presence of our field representative at the site is to provide our client with a source of professional advice, opinions, and recommendations based upon the field representative’s observations and testing of the contractor’s work. Our services do not include supervision or direction of the contractor, their employees, or agents. Geotechnical recommendations for obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible for complying with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations, is the sole responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager. ESNW rep was onsite to observe proof roll of roadway. Proof Roll Observation ESNW rep was onsite to observe proof roll of road A. The contractor drove a full water truck slowly over the roadway subgrade. ESNW rep observed two localized areas in need of over excavation. The contractor should over excavate approximately 2’ deep into subgrade to place approximately 12” of quarry spalls. Once the spalls are placed, bring the excavation up to grade with 1 ¼” minus crushed rock. The remainder of the roadway subgrade was observed to be very dense, firm, unyielding, and suitable for asphalt paving. ESNW rep will return to observe over excavation on Monday the 18th. Report ID 7945.04 E 2023 0915 Page 2 of 3 Earth Solutions NW, LLC Report ID 7945.04 E 2023 0915 Page 3 of 3 Earth Solutions NW, LLC Areas of over excavation