HomeMy WebLinkAboutConcrete Compressive Strength Test.City of Renton Gene Coulon Memorial Beach Park (T).2022-12-09.M7221137.0009ARev2Report Number:
Service Date:
Report Date:
Task:
Client
Renton, WA
1201 Lake Washington Blvd N
City of Renton Gene Coulon Memorial Beach Park (T)City of Renton WA
Attn: Alan J. Wyatt
1055 S Grady Way
Renton, WA 98057-3232
425-742-9360
Lynnwood, WA 98036-6365
20225 Cedar Valley Rd Ste 110
M7221137.0009A
12/09/22
01/09/23 Revision 2 - 28-day results
CONCRETE COMPRESSIVE STRENGTH TEST REPORT
Project
Project Number: M7221137
Specified Strength:28 days
Mix ID:
Supplier:
Batch Time:
Truck No.:
P2D35476
Cadman
Material Information
1310
353
Plant:
Ticket No.:
54
1343561
Field Test Data
Test
Air Content (%):
Result Specification
4 1/2 4 - 6
4.6 3.5 - 6.5
64 55 - 90
44
5,000
Slump (in):
psi @
Concrete Temp. (F):
Ambient Temp. (F):
Plastic Unit Wt. (pcf):
Yield (Cu. Yds.):
Sample Information
Sample Date:
Sampled By:
Weather Conditions:
Sample Time:12/09/22 1400
Joseph Allen
Cloudy
3 3
0
0
North abutmentSample Location:
Placement Method:Bucket
Water Added Before (gal):
Water Added After (gal):
Accumulative Yards:Batch Size (cy):
North & South bridge abutment Stage II girder stops.Placement Location:
Laboratory Test Data
Set Avg Diam.Area DateDate Test
Age at
Load
Max
Strength
Comp
Frac
No.ID
Spec
Received Tested (days)Type(in)(sq in)(lbs)(psi)
Tested
ByCond.
Cyl.
1 1 3.99 12.5 12/12/22 12/16/22 7 61,050 3 APIGood 4,880
1 2 3.99 12.5 12/12/22 01/06/23 28 81,020 3 CRMGood 6,480
1 3 3.99 12.5 12/12/22 01/06/23 28 76,990 3 CRMGood 6,160
1 4 3.99 12.5 12/12/22 01/06/23 28 77,540 3 CRMGood 6,200
Average (28 days) 6,280
Initial Cure:Final Cure:Inside Moist Room Sample Description:4-inch diameter cylinders
Comments:Average compressive strength of 28 day cylinders complies with the specified strength. Not tested for plastic unit
weight.
3 CY placed. Concrete batched with 100% hot water.
Samples Made By: Mayes/Terracon
Special Inspections / Materials TestingServices:
Reported To:
Contractor:
Report Distribution:
(1) City of Renton WA, Alan J. Wyatt (1) American Construction Co Inc, Aaron McMahill(1) American Construction Co Inc, John Blair (1) Mayes Testing Engineers, Inc, Jim Kay
(1) WSP USA Inc, Garth Nelson, P.E.
Mark Gordon
Department Manager III
American Construction Company Inc
Reviewed By:
ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231Test Methods:
Mayes/Terracon Rep.: Joseph Allen
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
Page 1 of 1CR0001, 3-31-22, Rev.7