HomeMy WebLinkAboutFabrication Shop Observation.City of Renton Gene Coulon Memorial Beach Park (T).C21005257.2022-12-14.M7221137.0010FABRICATION SHOP OBSERVATION REPORT
Report Number:M7221137.0010
Service Date:12/14/22 20225 Cedar Valley Rd Ste 110
Report Date:12/16/22 Lynnwood, WA 98036-6365
425-742-9360
Client Project
City of Renton WA City of Renton Gene Coulon Memorial Beach Park (T)
Attn: Alan J. Wyatt 1201 Lake Washington Blvd N
1055 S Grady Way Renton, WA
Renton, WA 98057-3232
Project Number: M7221137
Services: Special Inspections / Materials Testing
Mayes/Terracon Rep.: Michael Virgilio
Reported To:American Construction Company
Contractor:American Construction Company Inc
Report Distribution:
(1) City of Renton WA, Alan J. Wyatt (1) American Construction Co Inc, Aaron
McMahill
(1) American Construction Co Inc, John Blair (1) Mayes Testing Engineers, Inc, Jim Kay Reviewed By:____________________________________
(1) WSP USA Inc, Garth Nelson, P.E. Dennis Sanborn
Senior Project Field Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not
necessarily indicative of the properties of other apparently similar or identical materials.
DM010, 04-29-22 Rev.3 Page 1 of 1
Permit No.: C21005257
GENERAL INFORMATION
Terracon Consultants performed Visual and Ultrasonic testing of complete penetration welds for the Gene Coulon
Memorial Park at Rainier Welding in Anacortes WA.
Inspection was performed on the beam splice joints and stiffeners for Girder 1 as shown on the shop drawings
SA-1 and 124, 127, and 130.
Welds were on the following piece marks:
p1024, p1026, p1002, p1033, p1037, p1042, p1044, p1406.
Beam splices on pieces 124 to 127, 127 to 130.
Ultrasonic testing found flaws in piece marks p1024, p1026, p1002, p1033, p1037, p1044.
These welds were marked for repairs and the shop foreman was informed. Repair welding was performed on
each weld and found acceptable to AWS D1.5 on reinspection.
See attached UT report for details.
COMPLIANCE STATEMENT
Based on our observations and testing, the above noted items appear to be in general accordance with the
project documents.
MTE 1521-2C, Rev 1, 9/16/09
Page 2 of 3
Ultrasonic Examination Report
Project No.M7221137 Date:12/14/2022
Project Gene Coulon Memorial park
Specification:AWS D1.5 Weld Process: SMAW FCAW GMAW SAW
UT Equipment:Long Transducer:Shear Transducer:Calibration Block:
Model USMGO+Freq.:2.25 Freq.:2.25 IIW DSC
Serial No.: GOPLS16010180 Size:1"Size:.75 x.75 Other:
Decibels Discontinuity
Location Weld Indication NumberTransducer Angle Indication Level Reference Level Attenuation Level Indication RatingSound
Path Length Depth X Y AcceptRejectRemarks
124-
127 TF 70 38 X Beam Splices
124-
127 BF 70 38 X Beam Splices
124-
127 Web 70 38 X Beam Splices
127-
130 TF 70 38 X Beam Splices
127-
130 BF 70 38 X Beam Splices
127-
130 Web 70 38 X Beam Splices
p1024-
1 70 38 X Near Side Stiffeners
p1024-
2 70 38 X Near Side Stiffeners
p1024-
3 70 38 X Near Side Stiffeners
p1024-
4 70 38 X Near Side Stiffeners
p1024-
5 70 38 X Near Side Stiffeners
p1024-
6 70 38 X Near Side Stiffeners
p1024-
7 70 38 X Near Side Stiffeners
p1024-
8 70 38 X Near Side Stiffeners
p1026-
1 70 41 38 2 1 1.6 6"3/8"0 6"X Far Side Stiffeners
p1026-
2 70 42 38 2 2 1.7 5"3/8"0 8"X Far Side Stiffeners
p1002 70 39 38 2 -1 1.7 7"3/8"0 12"X Far Side Stiffeners
p1033 70 42 38 2 2 1.9 7"3/8"0 8"X Far Side Stiffeners
p1037 70 41 38 2 1 1.7 5"3/8"0 14"X Far Side Stiffeners
Inspector:Michael Virgilio Level:III
20225 Cedar Valley Road,Suite
110 Lynnwood,WA 98036
10029 S.Tacoma Way,Suite E-2
Tacoma,WA 98499
P 425.742.9360
F 425.745.1737
P 253.584.3720
F 253.584.3707
b c d
Distance
a
MTE 1521-2C, Rev 1, 9/16/09
Page 3 of 3
Ultrasonic Examination Report
Project No.M7221137 Date:12/14/2022
Project Gene Coulon Memorial park
Specification:AWS D1.5 Weld Process: SMAW FCAW GMAW SAW
UT Equipment:Long Transducer:Shear Transducer:Calibration Block:
Model USMGO+Freq.:2.25 Freq.:2.25 IIW DSC
Serial No.: GOPLS16010180 Size:1"Size:.75 x.75 Other:
Decibels Discontinuity
Location Weld Indication NumberTransducer Angle Indication Level Reference Level Attenuation Level Indication RatingSound
Path Length Depth X Y AcceptRejectRemarks
p1042 70 38 X Far Side Stiffeners
p1044 70 38 38 2 -2 1.7 13'3/8"0 10"X Far Side Stiffeners
p1046 70 38 X Far Side Stiffeners
p1024-
1 70 38 X Near Side Stiffeners R-1
p1024-
2 70 38 X Near Side Stiffeners R-1
p1024-
3 Web 70 38 X Near Side Stiffeners R-1
p1026-
1 70 38 X Far Side Stiffeners R-1
p1026-
2 70 38 X Far Side Stiffeners R-1
p1002 70 38 X Far Side Stiffeners R-1
p1033 70 38 X Far Side Stiffeners R-1
p1037 70 38 X Far Side Stiffeners R-1
p1044 70 38 X Far Side Stiffeners R-1
p1037 70 41 38 2 1 1.7 5"3/8"0 14"X Far Side Stiffeners
Inspector:Michael Virgilio Level:III