HomeMy WebLinkAboutChange Order - 5Contract Title:
Change Order No. 5
Rainier Ave S Corridor Improvements -Phase 4
Contractor: Pivetta Brothers Construction, Inc.
Contract No. : CAG-22-163
Federal Aid No. : STPUL-1615(005}
181 Ordered by Engineer
Proposed by the Contractor (VECP)
D Unilateral
Lump Sum
181 Bid Item
Force Account
Working Days
Original Contract: 500
Current Contract: 500
Estimated Net Change This Order: 0
New Contract:
Amount
28,284,174.90
28,401,510.54
174,913.89
28,576,424.43 500
ed By: :
L .. 7. t7 2-•3
Date Engineer (City of Renton Transportation
Design Manager)
Reviewed By: Consent By:
7/27/23
ErtgineerbfRecord -:;.: Date Surety (Greater than 25% cost and/or 20%
time increase)
Reviewed By: Endorsed By:
7/27/2023
oject Manager Date Contractor
Reviewed By: Executed By:
City Attorney Date City of Renton Public Works
Administrator/ Mayor
5ChangeOrderNo.
Contract Title: Rainier Ave S Corridor Improvements -Phase 4
Contract No. CAG-22-163
Date
Date
Date
Page 1 of 11
9/12/2023
CAG-22-163, CO #5-23
ATTEST:
Jason A. Seth, City Clerk
Approved by Cheryl Beyer via 8/9/2023 email
Armondo Pavone
9/21/2023
Change Order No. 5
Contract Title: Rainier Ave S Corridor Improvements – Phase 4
Contract No. CAG-22-163
Page 2 of 11
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
D15 – Install 2” Diameter Conduit – PSE Power, -350 LF, $5.95/LF, -$2,082.50
D16 – Install 3” Diameter Conduit – PSE Power, -2,600 LF, $8.10/LF, -$21,060.00
D17 – Install 4” Diameter Conduit – PSE Power, -8,000 LF, $9.45/LF, -$75,600.00
D18 – Install 6” Diameter Conduit – PSE Power, -5,500 LF, $11.35/LF, -$62,425.00
D19 – Install 4” Fiber Optic Conduit – PSE Power, -2,300 LF, $9.45/LF, -$21,735.00
D30 – Install 2” Diameter Conduit – Comcast, -420 LF, $5.95/LF, -$2,499.00
D31 – Install 4” Diameter Conduit – Comcast, -8,900 LF, $9.45/LF, -$84,105.00
D37 – Install 4” Diameter Conduit – Century Link, -22,400 LF, $9.45/LF, -$211,680.00
5-D45 – Install 2” Diameter Schedule 80 Conduit – PSE Power, 350 LF, $7.91/LF, $2,768.50
5-D46 – Install 3” Diameter Schedule 80 Conduit – PSE Power, 2,600 LF, $10.77/LF, $28,002.00
5-D47 – Install 4” Diameter Schedule 80 Conduit – PSE Power, 8,000 LF, $12.57/LF, $100,560.00
5-D48 – Install 6” Diameter Schedule 80 Conduit – PSE Power, 5,500 LF, $15.10/LF, $83,050.00
5-D49 – Install 4” Fiber Optic Schedule 80 Conduit – PSE Power, 2,300 LF, $12.57/LF, $28,911.00
5-D50 – Install 2” Diameter Schedule 80 Conduit – Comcast, 420 LF, $7.91/LF, $3,322.20
5-D51 – Install 4” Diameter Schedule 80 Conduit – Comcast, 8,900 LF, $12.57/LF, $111,873.00
5-D52 – Install 4” Diameter Schedule 80 Conduit – Century Link, 22,400 LF, $12.57/LF, $281,568.00
The Contractor is directed to install the conduit in the joint utility trench as Schedule 80 Conduit
instead of the Schedule 40 Conduit required in the plans.
Reason for Change:
The plans and specifications required the Contractor to install Schedule 40 conduit. City of
Renton standards require that conduit to be installed under the roadway be Schedule 80
conduit. Since a large portion of the conduit to be installed is under the roadway or under
driveways it was determined that all of the conduit should be Schedule 80 to eliminate the
transitions within conduit runs, which would impact the franchise utilities ability to pull cables
through the conduits, and eliminate the risk that conduit is installed with the incorrect wall
thickness.
Affects DBE Work: Yes No
Materials:
Schedule 80 Conduit – Owner Supplied
Plans:
None.
Equitable Adjustment:
This Change Order does include an equitable adjustment per Section 1-09.4 of the 2022
WSDOT/APWA Standard Specifications. See attached.
Change Order No. 5
Contract Title: Rainier Ave S Corridor Improvements – Phase 4
Contract No. CAG-22-163
Page 3 of 11
The new unit prices to install franchise utility supplied Schedule 80 Conduit instead of franchise
utility supplied Schedule 40 Conduit were proposed by the Contractor in Serial Letter 004. An
engineer’s estimate was prepared using estimated production rates, crew sizes, and rates. The
estimated cost to install the Schedule 80 Conduit was $894,959.42. Based on the estimated cost
the Contractor’s proposed pricing of $640,054.70 was accepted. The amount of $640,054.70
was then reduced by $481,186.50, the amount to complete this work using the original bid
items. This resulted in an added cost of $158,868.20 on which the 10.1% sales tax was applied
to come to a total change amount of $174,913.89.
Estimated Cost to Install Schedule 40 Conduit: $481,186.50
Estimated Cost to Install Schedule 80 Conduit: $640,054.70
Estimated Total Change Order Cost with Sales Tax: $174,913.89
Extension of Time:
The Time for Completion is extended __0__ Working Days.
Sections 1-04.4 and 1-04.5 of the 2022 WSDOT/APWA Standard Specifications shall govern
this Change Order. The Work of the referenced Contract is modified to include the changes
detailed herein. The payment provided for herein shall constitute the complete and final
settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all
other claims that may be made by the Contractor as a result of this change.
To be attached to Change Order:
Estimated Change Order Cost
Plans
Field Directive/Request for Information Response/Serial Letter
Change Order Quotation
Project Labor List
Force Account Equipment Rate Request (DOT Form 422-010 EF)
Overhead Adjustment Determination
Item No.Quantity Unit Price
5-D45 18.9 153.00$
5-D46 156 153.00$
5-D47 552 153.00$
5-D48 396 153.00$
5-D49 158.7 153.00$
5-D50 22.68 153.00$
5-D51 614.1 153.00$
5-D52 1545.6 153.00$
5-D45 to 5-D52 $529,988.94 0.31$
5-D45 18.9 25.00$
5-D46 156 25.00$
5-D47 552 25.00$
5-D48 396 25.00$
5-D49 158.7 25.00$
5-D50 22.68 25.00$
5-D51 614.1 25.00$
5-D52 1545.6 25.00$
5-D45 to 5-D52 $86,599.50 0.21$
5-D45 to 5-D52 $799,070.91 0.12$
5-D45 to 5-D52 CALCULATED TOTAL:
ESTIMATED TOTAL TO INSTALL SCHEDULE 40 CONDUIT:
D15 -350 5.95$
D16 -2600 8.10$
D17 -8000 9.45$
D18 -5500 11.35$
D19 -2300 9.45$
D30 -420 5.95$
D31 -8900 9.45$
D37 -22400 9.45$
5-D45 350 7.91$
5-D46 2600 10.77$
5-D47 8000 12.57$
5-D48 5500 15.10$
5-D49 2300 12.57$
5-D50 420 7.91$
5-D51 8900 12.57$
5-D52 22400 12.57$
Per attached determination
Summary of Contractors Quotes:
Item Quote Location
5-D46 to 5-D52 SL004
Total Quoted Added Cost:
Equipment = (6.9 Hours/100 LF) = 0.069 HR/LF x 22400 LF = 1545.6 Hours/LF Hours $38,640.00
24,281.10
3,470.04
93,957.30
236,476.80
Equipment = (5.4 Hours/100 LF) = 0.054 HR/LF x 420 LF = 22.68 Hours/LF Hours $567.00
Equipment = (6.9 Hours/100 LF) = 0.069 HR/LF x 8900 LF = 614.1 Hours/LF Hours $15,352.50
Equipment = (7.2 Hours/100 LF) = 0.072 HR/LF x 5500 LF = 396 Hours/LF Hours $9,900.00
Equipment = (6.9 Hours/100 LF) = 0.069 HR/LF x 2300 LF = 158.7 Hours/LF Hours $3,967.50
Equipment = (6 Hours/100 LF) = 0.06 HR/LF x 2600 LF = 156 Hours/LF Hours $3,900.00
Equipment = (6.9 Hours/100 LF) = 0.069 HR/LF x 8000 LF = 552 Hours/LF Hours $13,800.00
Hours
Hours
23,868.00
84,456.00
60,588.00
Hours
Hours
Hours
Hours
Hours
Labor = (6.9 Hours/100 LF) = 0.069 HR/LF x 8900 LF = 614.1 Hours/LF
Labor = (6.9 Hours/100 LF) = 0.069 HR/LF x 22400 LF = 1545.6 Hours/LF
Labor = (6 Hours/100 LF) = 0.06 HR/LF x 2600 LF = 156 Hours/LF
Labor = (6.9 Hours/100 LF) = 0.069 HR/LF x 8000 LF = 552 Hours/LF
Labor = (7.2 Hours/100 LF) = 0.072 HR/LF x 5500 LF = 396 Hours/LF
Labor = (6.9 Hours/100 LF) = 0.069 HR/LF x 2300 LF = 158.7 Hours/LF
Labor = (5.4 Hours/100 LF) = 0.054 HR/LF x 420 LF = 22.68 Hours/LF
3,322.20
111,873.00
Estimated Change Order Sales Tax Cost $16,045.69
Estimated Total Change Order Cost with Sales Tax $174,913.89
Estimated Costs to Install Schedule 40 Conduit $481,186.50
2,768.50
28,002.00
100,560.00
83,050.00
28,911.00
62,425.00
21,735.00
2,499.00
84,105.00
211,680.00
Install 4" Fiber Optic Schedule 80 Conduit - PSE Power
Install 2" Diameter Schedule 80 Conduit - Comcast
Install 4" Diameter Schedule 80 Conduit - Comcast
LF
LF
LF
LF
LF
LF
LF
LF
LF
LF
LF
LF
Labor Markup Cents/Dollar $164,296.57
Equipment = (5.4 Hours/100 LF) = 0.054 HR/LF x 350 LF = 18.9 Hours/LF Hours $472.50
Description
Engineers Estimate
Unit Estimated Cost
Labor = (5.4 Hours/100 LF) = 0.054 HR/LF x 350 LF = 18.9 Hours/LF Hours $2,891.70
LF -$2,082.50
Install 4" Diameter Schedule 80 Conduit - Century Link
Install 6" Diameter Conduit - PSE Power
Install 4" Fiber Optic Conduit - PSE Power
Install 2" Diameter Conduit - Comcast
Install 4" Diameter Conduit - Comcast
Install 4" Diameter Conduit - Century Link
Install 2" Diameter Schedule 80 Conduit - PSE Power
Install 3" Diameter Schedule 80 Conduit - PSE Power
Install 4" Diameter Schedule 80 Conduit - PSE Power
Install 6" Diameter Schedule 80 Conduit - PSE Power
Change Order No. 5
By: Jordan Howe
Date: 7/27/2023
Rainier Ave S Corridor Improvements - Phase 4
Pivetta Brothers Construction, Inc.
CAG-22-163
STPUL-1615(005)
Perteet
Change Order Cost (Equitable Adjustment)
Project Name:
Contractor:
Federal Aid No:
Contract No:
Construction Manager:
415,995.02$
Mobilization Estimate
TOTAL
Estimated Change Order Cost without Sales Tax
Pennies/Dollar
LF
LF
Install 3" Diameter Conduit - PSE Power LF
Subcontractor Markup
By Agreement
Bid Item Change
Quoted Cost
Overhead
0.00
415,995.02$
21%$0.00
Equipment Markup Cents/Dollar $18,185.90
Materials Markup
158,868.20
158,868.20
0.00
Install 4" Diameter Conduit - PSE Power
LF
Materials EA
75,600.00
281,568.00
0.00
21,060.00
Install 2" Diameter Conduit - PSE Power
95,888.51
Subcontractor Estimate $0.00
894,959.42
640,054.70
0.00
Services Markup 21%$0.00
Services
Schedule 80 Conduit Change - Estimated Change Order Cost
Change Order #5 - Page 4 of 11
Serial Letter:004
April 24, 2023
To: Michelle Faltaous
City of Renton
1055 South Grady Way
Renton, Washington 98057
Reference Project:CAG-22-163, Rainier Ave S Corridor Improvements – Phase 4 Project
Subject:PCO 08 Schedule 80 Conduit at Joint Utility Trench
Mrs. Michelle Faltaous:
Pursuant to section 1-04.4, the City of Renton has requested that Pivetta Brothers Construction, Inc.
Pivetta) provide pricing due to the utilities providing schedule 80 PVC conduit instead of schedule 40
PVC conduit as indicated in note 6 on sheet 162 of the drawings. This change does not affect the City of
Renton or 5G Network conduits since the special provisions identified these as being schedule 80 PVC.
The additional effort for this work was calculated using the National Electrical Contractors Association’s
NECA) Manual of Labor Units which show a 33% increase in labor for Golden Gate Electric. A portion of
this labor can be accommodated with Golden Gates Electric’s manpower but it will impact Pivetta’s
ability to install an average of 100 LF of Joint Utility Trench (JUT). Based on the lower production
identified by the NECA Manual of Labor, we now anticipate installing only 80 LF of JUT per day, on
average. This slower production will add 16 Working Days to Pivetta’s operations and we have included
this pricing as well.
The detailed estimates are attached and summarized per pay item as follows:
Pay Item Added Cost
D15 - Install 2" Diameter Conduit PSE Provided $941.45
D16 - Install 3" Diameter Conduit PSE Provided $9,536.80
D17 - Install 4" Diameter Conduit PSE Provided $34,123.34
D18 - Install 6" Diameter Conduit PSE Provided $27,929.79
D19 - Install 4" Fiber Optic Conduit PSE Provided $9,842.47
D30 - Install 2" Diameter Conduit Comcast Provided $1,129.74
D31 - Install 4" Diameter Conduit Comcast Provided $37,905.96
D37 - Install 4" Diameter Conduit Century Link Provided $94,645.34
D8 – Structure Excavation Class B Incl. Haul for JUT $199,940.13
D6 – Gravel Borrow Incl. Haul Incl. Above
Change Order #5 - Page 5 of 11
Schedule 80 Conduit Change - Change Order Quotation
D9 – Shoring or Extra Excavation Class B for JUT Incl. Above
D13 – Sand Bedding Incl. Haul for JUT Incl. Above
D14 - Controlled Density Fill Incl. Haul, for JUT Incl. Above
Total Cost 415,995.02
Along with the costs associated with this change, Pivetta is also requesting an additional 16 Working
Days pursuant to section 1-08.8.5.a. These additional days were calculated as follows:
Description LF of JUT
Average Daily
Production
Number of Working
Days
Baseline Project Schedule 6,505 LF 100 LF/Day 65 Working Days
PCO-008 Change 6,505 LF 80 LF/Day 81 Working Days
Added Days 16 Working Days
Please feel free to contact me, at (206) 914-2723 if you have any questions or concerns.
Respectfully,
Bill Adams
Sr. Project Manager
w/ Attachments:
PCO-008 Schedule 80 Conduit - Golden Gate Pricing
NECA Labor Change Schedule 40 vs 80 Utilities
NECA Labor Manual Labor Rates Conduit
PCO-008 Schedule 80 Conduit – Pivetta Costs
Cc:
Jordan Howe, Perteet
Russ Owen, Pivetta
Change Order #5 - Page 6 of 11
Schedule 80 Conduit Change - Change Order Quotation
Item Description Unit Plan Quanity
Neca Rate Sch
40 with 20
Foot sticks
Neca Rate Sch
80 with 20 Foot
Sticks
Labor
Unit
Labor
Difference
Percentage
Increase
Bid price per
foot
Revised price
per foot
Allowed
Markup on
Difference
Total ajusted
Price
Orginal Bid
totals Revised bid total
D15 LF 350 4.05 5.40 C 1.35 33%5.50$ 7.33$ 0.57$ 7.90$ 1,925.00$ 2,765.58$
D16 LF 2600 4.50 6.00 C 1.50 33%7.50$ 10.00$ 0.78$ 10.78$ 19,500.00$ 28,015.00$
D17 LF 8000 5.18 6.90 C 1.73 33%8.75$ 11.67$ 0.90$ 12.57$ 70,000.00$ 100,566.67$
D18 LF 5500 5.40 7.18 C 1.78 33%10.50$ 13.96$ 1.07$ 15.03$ 57,750.00$ 82,687.31$
D19 LF 2300 5.18 6.90 C 1.73 33%8.75$ 11.67$ 0.90$ 12.57$ 20,125.00$ 28,912.92$
D30 LF 420 4.05 5.40 C 1.35 33%5.50$ 7.33$ 0.57$ 7.90$ 2,310.00$ 3,318.70$
D31 LF 8900 5.18 6.90 C 1.73 33%8.75$ 11.67$ 0.90$ 12.57$ 77,875.00$ 111,880.42$
D37 LF 22400 5.18 6.90 C 1.73 33%8.75$ 11.67$ 0.90$ 12.57$ 196,000.00$ 281,586.67$
Totals 445,485.00$ 639,733.26$
Install 2" Diameter Conduit Comcast Provided
Install 4" Diameter Conduit Comcast Provided
Install 4" Diameter conduit Century Link Provided
Install 2 " Diameter Conduit PSE Provided
Install 3 " Diameter Conduit PSE Provided
Install 4 " Diameter Conduit PSE Provided
Install 6 " Diameter Conduit PSE Provided
Install 4 " Fiver Optic Conduit PSE Provided
Change Order #5 - Page 8 of 11
Schedule 80 Conduit Change - Change Order Quotation
Description Rev Normal Difficult
Very
Difficult
Company
Experience Unit
NECA Manual of Labor Units
2021-2022 Edition
Section 8: Division 26—Electrical
PVC Duct Bank Conduit Spacers
1/2-inch - 2-inch 12.00 14.00 16.00 C
2 1/2-inch - 6-inch 20.00 25.00 30.00 C
Schedule 40 PVC Conduit Laid In Trenches - 10-foot & 20-foot Lengths with
Glued Couplings
Note: Reduce labor units for 20-foot lengths by 10%
3/4-inch 3.50 4.50 5.50 C
1-inch 3.75 4.75 5.75 C
1 1/4-inch 4.00 5.00 6.00 C
1 1/2-inch 4.25 5.30 6.35 C
2-inch 4.50 5.60 6.75 C
2 1/2-inch 4.75 5.90 7.10 C
3-inch 5.00 6.25 7.50 C
3 1/2-inch 5.25 6.55 7.85 C
4-inch 5.50 6.85 8.25 C
5-inch 5.75 7.15 8.60 C
6-inch 6.00 7.50 9.00 C
Schedule 40 PVC Conduit Laid In Trenches - 90 Degree Elbows
Note: Add 20% for wide sweep elbows
1/2-inch 0.20 0.25 0.30 E
3/4-inch 0.22 0.28 0.33 E
1-inch 0.25 0.31 0.38 E
1 1/4-inch 0.32 0.40 0.48 E
1 1/2-inch 0.40 0.48 0.60 E
2-inch 0.50 0.63 0.75 E
2 1/2-inch 0.60 0.75 0.90 E
3-inch 0.70 0.84 1.05 E
3 1/2-inch 0.85 1.06 1.28 E
4-inch 1.00 1.25 1.50 E
5-inch 1.25 1.56 1.88 E
6-inch 1.50 1.88 2.25 E
Schedule 40 PVC Conduit Laid In Trenches - Threaded Adapters
1/2-inch 0.14 0.17 0.21 E
3/4-inch 0.16 0.20 0.24 E
1-inch 0.18 0.22 0.27 E
1 1/4-inch 0.20 0.25 0.30 E
1 1/2-inch 0.25 0.31 0.37 E
2-inch 0.30 0.37 0.45 E
2 1/2-inch 0.40 0.50 0.60 E
3-inch 0.50 0.62 0.75 E
3 1/2-inch 0.65 0.81 0.97 E
4-inch 0.80 1.00 1.20 E
5-inch 1.00 1.25 1.50 E
6-inch 1.25 1.55 1.85 E
Schedule 40 PVC Conduit Laid In Trenches - Expansion Couplings
1/2-inch 0.50 0.62 0.75 E
3/4-inch 0.60 0.75 0.90 E
1-inch 0.70 0.87 1.05 E
1 1/4-inch 0.80 1.00 1.20 E
1 1/2-inch 0.90 1.12 1.35 E
2-inch 1.00 1.25 1.50 E
2 1/2-inch 1.15 1.43 1.72 E
3-inch 1.30 1.62 1.95 E
3 1/2-inch 1.50 1.85 2.25 E
4-inch 1.75 2.15 2.60 E
5-inch 2.00 2.50 3.00 E
6-inch 2.25 2.75 3.25 E
Field Bend Schedule 40 PVC Conduit & Installation
Note: Add 10% for each field cut & ream
1/2-inch 0.40 0.50 0.60 E
3/4-inch 0.50 0.60 0.75 E
1-inch 0.60 0.75 0.90 E
1 1/4-inch 0.65 0.81 0.98 E
1 1/2-inch 0.80 1.00 1.20 E
2-inch 1.00 1.25 1.50 E
2 1/2-inch 1.20 1.50 1.80 E
3-inch 1.40 1.75 2.10 E
3 1/2-inch 1.70 2.13 2.55 E
4-inch 2.00 2.50 3.00 E
5-inch 3.15 3.94 4.73 E
6-inch 4.20 5.25 6.30 E
2021 National Electrical Contractors Association 269
8
Change Order #5 - Page 9 of 11
Schedule 80 Conduit Change - Change Order Quotation
Description Rev Normal Difficult
Very
Difficult
Company
Experience Unit
NECA Manual of Labor Units
2021-2022 Edition
Section 8: Division 26—Electrical
Schedule 80 PVC Conduit Laid In Trenches - 10-foot & 20-foot Lengths with
Glued Couplings
1/2-inch 4.00 5.00 6.00 C
3/4-inch 4.20 5.20 6.20 C
1-inch 4.50 5.50 6.50 C
1 1/4-inch 4.80 5.80 6.80 C
1 1/2-inch 5.10 6.10 7.10 C
2-inch 5.40 6.40 7.40 C
2 1/2-inch 5.70 6.70 7.70 C
3-inch 6.00 7.00 8.00 C
4-inch 6.90 7.90 8.90 C
5-inch 7.20 8.20 9.20 C
6-inch
Schedule 80 PVC Conduit Laid In Trenches - 90 Degree Elbows
Note: Add 20% for wide sweep elbows
1/2-inch 0.22 0.27 0.32 E
3/4-inch 0.24 0.29 0.34 E
1-inch 0.28 0.33 0.38 E
1 1/4-inch 0.35 0.40 0.45 E
1 1/2-inch 0.46 0.56 0.66 E
2-inch 0.58 0.73 0.88 E
2 1/2-inch 0.69 0.89 1.09 E
3-inch 0.84 1.09 1.34 E
4-inch 1.20 1.70 2.20 E
5-inch 1.50 2.00 2.50 E
6-inch 1.80 2.30 2.80 E
Schedule 80 PVC Conduit Laid In Trenches - Threaded Adapters
1/2-inch 0.16 0.19 0.23 E
3/4-inch 0.18 0.22 0.26 E
1-inch 0.20 0.24 0.28 E
1 1/4-inch 0.22 0.27 0.32 E
1 1/2-inch 0.30 0.35 0.40 E
2-inch 0.35 0.42 0.47 E
2 1/2-inch 0.45 0.55 0.65 E
3-inch 0.60 0.70 0.80 E
4-inch 0.70 0.85 1.00 E
5-inch 0.85 1.15 1.35 E
6-inch 1.20 1.40 1.70 E
Schedule 80 PVC Conduit Laid In Trenches - Expansion Couplings
1/2-inch 0.25 0.30 0.35 E
3/4-inch 0.30 0.36 0.41 E
1-inch 0.40 0.48 0.55 E
1 1/4-inch 0.50 0.60 0.70 E
1 1/2-inch 0.65 0.78 0.90 E
2-inch 0.75 0.90 1.05 E
2 1/2-inch 0.85 1.02 1.17 E
3-inch 1.05 1.26 1.45 E
4-inch 1.40 1.68 1.93 E
5-inch 1.65 1.98 2.28 E
6-inch 1.90 2.28 2.62 E
Field Bend Schedule 80 PVC Conduit & Installation
Note: Add 10% for each field cut & ream
1/2-inch 0.50 0.60 0.70 E
3/4-inch 0.60 0.70 0.80 E
1-inch 0.70 0.85 1.00 E
1 1/4-inch 0.80 0.96 1.12 E
1 1/2-inch 1.00 1.20 1.40 E
2-inch 1.25 1.50 1.75 E
2 1/2-inch 1.50 1.75 2.00 E
3-inch 1.75 2.00 2.25 E
4-inch 2.00 2.25 2.50 E
5-inch 2.40 2.90 3.40 E
6-inch 3.65 4.44 5.23 E
270 © 2021 National Electrical Contractors Association
8
Change Order #5 - Page 10 of 11
Schedule 80 Conduit Change - Change Order Quotation
Job 2022 148 Project Name
Rainier Ave.S
Phase 4
Station
Date:4/24/2023 Bid Item Multiple Customer
E.W.O Phase Weather
Description
Labor
Class Hours O/T Hours Rate O/T Rate Extended
Foreman 30 50 16 94.61$1,513.76$
Operator 15 30 32 89.88$2,876.16$
Foreman 15 30 128 93.82$12,008.96$
Operator 15 30 128 89.88$11,504.64$
Operator 15 30 128 89.88$11,504.64$
Grader/Pipelayer Le 128 69.19$8,856.32$
Laborer 128 65.76$8,417.28$
Flagging TCS 32 63.23$2,023.36$
Equipment
Description Year Hours Stby Hours Rate Stby Rate Extended
P XXX FOREMAN TRUCK 16 25.72$411.52$
P XXX FOREMAN TRUCK 128 25.72$3,292.16$
EX 123 135 Excavator 128 101.38$12,976.64$
EX 140 JD 86 Excavator 128 108.90$13,939.20$
WL 121 L70H Loader 128 89.38$11,440.64$
R 114 Bomag 47"DD 128 31.97$4,092.16$
P 142 SIGN TRUCK 128 25.72$3,292.16$
Z Arrow Board 6.5 128 7.25$928.00$
Speed Shore Jacks 100 128 0.88$113.14$
Steel Plates 20 128 20.94$2,680.75$
Materials
Date Supplier QTY Amount
Subcontractors
Date Type QTY Amount
Information Required
1
2 Name
3 Notified
4 Time
5 Method
Cost Breakdown
Sub Total x M/U Total
58,705.12 29% $75,729.60
WSDOT 1 09.6 Sick Leave $58,705.12 2% $59,879.22
53,166.37 21% $64,331.31
0.00 21% $0.00
0.00 12%/10%/7% $0.00
Calculated Total:$199,940.13
Materials
Subcontractor
Labor
Equipment
Contact Agency Inspection Authority
Name:Work Description
Invoice Material Type
The utilities are providing Schedule 80 conduit for the JUT in lieu of the contract specified Schedule 40.Golden Gate has additional costs
for this effort based on the NECA estimating rates.These costs are only for the costs attributed to Pivetta's work and Golden Gates
Efforts have been priced separately to better accomodate the unit price breakdown for the conduit installation.
Name:First,Last
Trail,Anthony
Phipps,James
Hamilton,Scott
Change Order #5 - Page 11 of 11
Schedule 80 Conduit Change - Change Order Quotation