HomeMy WebLinkAbout7945.04 E 2023 1011Earth Solutions NWLLC 15365 NE 90th Street, Suite 100 Redmond, WA 98052 Main (425) 449-4704 | Fax (425) 449-4711 esnw.com FIELD REPORT Project No. 7945.04 Page 1 of 3 Report ID 7945.04 E 2023 1011 Date Wed 10/11/2023 Weather 65°F Cloudy Arrival/Departure Time(s) 12PM; 12:30PM Travel Time (hr) 1.0 Project Name Canopy Property Location 4130 Lincoln Ave NE, Renton ESNW Rep. & Phone Willem Scherwin | 206 793 8569 Client Info/Contact Century Communities | Stacia Bloom Reviewed By LAC Initials/Date RAC Initials/Date Field Supervisor Project Manager Limitations: The presence of our field representative at the site is to provide our client with a source of professional advice, opinions, and recommendations based upon the field representative’s observations and testing of the contractor’s work. Our services do not include supervision or direction of the contractor, their employees, or agents. Geotechnical recommendations for obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible for complying with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations, is the sole responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager. ESNW rep was onsite to test compaction of vault access road fill onsite. Road Fill ESNW rep was onsite to observe and test the fill of vault access road A onsite. ESNW rep observed the contractor had placed 1 ¼” minus crushed rock in 12” lifts and compacted it with good effort using a hoe pack. The fill was approximately 1-3’. ESNW rep took compaction tests and observed adequate compaction of at least 95% of the modified proctor at the tested locations. Please see map and table below. Test Number Test Location Elevation Reference Proctor Maximum Dry Density (pcf) Test Moisture (%) Test Dry Density (pcf) % of MDD 194 Vault Access Road A SG 7 135.9 7.5 128.9 95 195 Vault Access Road A SG 7 135.9 6.9 129.4 95 Report ID 7945.04 E 2023 1011 Page 2 of 3 Earth Solutions NW, LLC Report ID 7945.04 E 2023 1011 Page 3 of 3 Earth Solutions NW, LLC 194 195