HomeMy WebLinkAboutChange Order - 9DocuSign Envelope ID: DA38D2E7-E564-4739-990A-5F9D761 F60DB Change Order No. 9 Contract Title: Airport Office Renovation Project Contractor: Reynolds General Contracting, Inc. Contract No. CAG-22-237 Federal Aid No.: � Ordered by Engineer D Proposed by the Contractor (VECP) □Unilateral Amount Original Contract: 679,800 Current Contract: 897,778.52 Estimated Net Change This Order: 48,310.78 New Contract: 946,089.30 Prepared By: �� t/3/Zbt+ City of Renton Project Date Manager Endorsed By: �� 1/2/24 Date Reviewed By: City Attorney Date 9 Notice to Proceed Date Original Calendar Days Previous Substantial Completion Date Revised Calendar Days (This Change Order) Total Revised Calendar Days to D.ate Current Substantial Completion Date Reviewed By: Airport Director Endorsed By: �e>etrt�er1t�: �s�l�!�a�astucha City of Renton Public Works Administrator/ Mayor Change Order No. Contract Title: Contract No. Airport Office Renovation Project CAG-22-237 01/12/2023 180 12/08/2023 89 239 03/06/2024 Date Date 1/8/2024 I 4: 59 PM PST Date Page 1 of 2 CAG-22-237, CO #9-24 Approved by Cheryl Beyer via email 12/19/2023 DocuSign Envelope ID: DA3BD2E7-E564-4739-990A-5F9D761 F60DB THE CONTRACT IS MODIFIED AS FOLLOWS: Description of Change: Adding Change Order Proposal 12. Reason for Change: Low Voltage finishes. Low Voltage receptacles, including access control badge readers, cameras, entry station and master station. = $43,879 + Sales Tax (10.1%) = $43,879 + $4,431.78 = $48,310.78 Materials: See the attached price breakdown for the lump sum labor. Plans: N/A Equitable Adjustment: N/A Extension of Time: The Time for Completion is extended 89 Working Days. Sections 1-04.4 and 1-04.5 of the 2018 WSDOT/APWA Standard Specifications shall govern this Change Order. The Work of the referenced Contract is modified to include the changes detailed herein. The payment provided for herein shall constitute the complete and final settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all other claims that may be made by the Contractor as a result of this change. Attachments: Forms to be attached to Change Order □Plans D Field Directive IZI Change Order Quotation IZI Estimated Change Order Cost IZI Project Labor List □Force Account Equipment Rate Request (DOT Form 422-010 EF)□Equitable Adjustment Determination Change Order No. Contract Title: Contract No. 9 Airport Office Renovation Project CAG-22-237 Page 2 of 2 DocuSign Envelope ID: DA3BD2E7-E564-4739-990A-5F9D761 F60DB REYNOLDS GENERAL CONTRACTING COP General Contractor Breakdown Summary Project Name: Renton Airport Office Renovation Project No. Source Documents: Contractor: Reynolds General Contracting COP No Date: Contractor Ref. No 012 12/13/2023 012 Description: Low voltage and electrical additions as directed by owner to include devices & trim labor of access control, telecommunications, CCTV camera, additional receptacles, and HDMI from floorbox to A/V station. See attached scope of work from Jensen Electric for specific breakdown. I 1. DIRECT CRAFT LABOR COST (from attached cost breakdown form) a. crew (apprentices, journeymen, & laborers) $ b. foreman $ c. lead foreman $ DIRECT LABOR SUBTOTAL $ Labor Markups d. direct supervison (NTE 15% of 1 a) I$ e. safety (NTE 2% of lines 1a, b, & c) 12. MATERIAL COST (from attached cost breakdown form) 13. EQUIPMENT COST (from attached cost breakdown form) 14. SMALL TOOLS (NTE 3% of 1a & b) 5. OVERHEAD & PROFIT a. NTE 16% portion of 1, 2, 3, & 4 up to $50,000 $ b. NTE 10% portion of 1, 2, 3, & 4 in excess of $50,000 $ I&. SUBCONTRACTORS a. Jensen Electric $ b. $ c. $ d. $ e. $ f. $ 7. OVERHEAD & PROFIT ON SUBCONTRACTORS a. NTE 6% of Line 6 up to $50,000 for each sub $ b. NTE 6% of Line 6 in excess of $50,000 for each sub $ 4,252.50 - -4,252.50 85.05 I 714.56 34,514.00 - - - - - 2,070.84 .__ _____ _. 8. INSURANCE a. payroll driven liability insurance b. volume driven liability insurance 19. BONDING COP 012_Additional Electrical & Low Voltage Devices & Trim 2.001% of 1-8 $ $ 1,252.98 Page __ of __ $ 4,338.oo I $ -I $ -I $ 127.581 SUBTOTAL 1 thru 41 $ 4,466.00 I $ 715.00 $ 34,514.oo I $ 2,071.00 $ 1,253.00 $ s6o.oo 1 TOTAL cosT! $ 43,879.oo WSST (10.1%) = $4,431.78 TOTAL = $48,310.78 Printed 12/13/2023