MAXIMUM EXTENT FEASIBLE (MEF) DOCUMENTATION FORM PAGE | 1
MAXIMUM EXTENT FEASIBLE (MEF) DOCUMENTATION
This form and attached plan include Maximum Extent Feasible (MEF) Documentation for review and
approval for proposed improvements in the public right-of-way that do meet current jurisdictional standards.
CITY OF RENTON Development Engineering 1055 S. Grady Way Renton, WA 98057 Attn: Michael Sippo
Project Name | MEF Location Renton School District - Lindbergh High School Renovation and Expansion
16426 128th Avenue SE, Renton, Washington – Curb Ramp Detail B
City of Renton Permit Number B22002682 (Building Permit)
Request Date 9/16/2022
Applicant Laurie Pfarr, PE, Principal | Owner
Applicant Address and Phone Number LPD Engineering
1932 First Avenue, Suite 201
Seattle, WA 98101
(206) 725-1211
Define the existing standard or design criteria requiring MEF documentation.
The running slope of a curb ramp cannot exceed 8.33%.
Describe why the proposed improvements cannot meet the existing standards.
The slope of the existing roadway around curb return creates a slope that forces the proposed ADA
ramp running slope to exceed 8.33% even if the ramp is extended beyond the typical 6 feet.
APPROVED BY LAURIE J. PFARR, PE, Principal | Owner
LPD ENGINEERING __________________________________________________
City of Renton __________________________________________________
Date
PROJECT AND APPLICANT INFORMATION
EXISTING STANDARD SUMMARY
MEF JUSTIFICATION
JURISDICTION
PROFESSIONAL
ENGINEER
STAMP
MAXIMUM EXTENT FEASIBLE (MEF) DOCUMENTATION
MAXIMUM EXTENT FEASIBLE (MEF) DOCUMENTATION FORM PAGE | 2
NON-COMPLIANT CURB RAMP DETAIL B
MAXIMUM EXTENT FEASIBLE (MEF) SITE PLAN