HomeMy WebLinkAboutAdden 1 CAG-96-078, Adden. #1-98
State of Washington
Department of Community, Trade and Economic Development
Public Works Unit
PUBLIC WORKS TRUST FUND PROGRAM
PROJECT CLOSE-OUT REPORT
Loan Agreement . Number: PW-5-96-791-044
NOTE: This report shall serve as a contract AMENDMENT for
determining the final loan amount, interest rate, and local share
and shall be attached and incorporated into the loan agreement.
The report accounts for funds associated with the Public Works
Trust Fund Loan Agreement' s Scope of Work. Costs outside of the
Scope of Work are not accounted for by this report.
Please Type or Print in Ink.
City of Renton
200 Mill Ave. S.
Renton, WA 98055
Name of Chief Executive Officer: Jesse Tanner
Title of Chief Executive Officer: Mayor
This document is to certify that the project, as described in the
Public Works Trust Fund Loan Agreement's Scope of Work, is
completed and has been designed/constructed to current standards.
Section 1. Estimated and Actual Project Expenditures by Cost
Category.
Cost Category Estimated Actual Costs
Preliminary Engineering A. $ 0. 00 L. .00
Design Engineering B. 500, 000. 00 M. 123,142.79
Land/ROW Acquisition C. 0. 00 N.
Sales or Use Taxes D. 207,460*00 0. 181,435.77
Other Fees E. 0. 00 P.
Construction Inspection F. 80, 000. 00 Q. 37,73038
Start-up Costs G. 0. 00 R.
Financing Costs H. 0. 00 S.
Contingency I. 330, 000. 00 T.
Construction J. 2,200, 000.00 U. 2,134,402.11
Total Project Cost K. 3,3171460. 00 V. 2,4760711.45
Page 1 of 2
Page 2 of 2 (Public Works Close-out Report)
Section 2 . Estimated and Actual Project Funding Sources.
Note: The earliest date on which project costs are
considered eligible as local share is 6/17/95.
Source of Funds Estimated Actual Costs
A. Local Share (ie: Cash, In-Kind,
other State and Federal Loans) $ 865, 3.43 . 00 E. 636,143.00
B. Federal Grants 0. 00 F.
C. Other State Grants 0. 00. G. .00
D. Line 1V minus lines 2F and 2G 2.476.711.45
Section 3 . Calculating the Maximum PWTF Funding
A. PWTF Share: multiply line 2D by 70%, 80%,
or 90% as set forth in the loan agreement. . . . . 1,981,369.16
B. Interest Earned on the PWTF money . . . . . . . . . . . . 15.388.31
C. Maximum PWTF share: Line 3A minus line 3B . . . . 1.965.980.85
D. PWTF allocation amount as per contract . . . . . . . $2 ,466,717 . 00
E. Enter the lesser of line 3C or 3D (or an
optional amount less than 3C and 3D) . . . . . . . . . 1.840.568.45
F. Amount drawn to date . . . $ 370, 007 . 55
G. Final draw amount: Line 3E minus 3F (Any
negative amount shall be refunded to PWTF) . . . 1,470.560.90
H. Divide Line 2E by the sum of 2E and 3E . . . . . . . 25.7 %
Section 4 . Attach copies of the following:
Department of Labor and Industries Closure Document(s) ;
Department of Revenue Closure Document(s) ;
Accepted Project Bid(s) with change orders.
Section 5. The chief executive officer of the jurisdiction
certifies that:
-- to the best of his/her knowledge, the data provided in this
report is true and correct as of the date indicated below;
-- records supporting the information provided in this report
are on f ' a and a de available by the jurisdiction
upon eques ; d
-- th a are o outs 'ng liens against this project.
i
i a ni of P ect Engineer or.-Consultant . . . • ' tef
• i
,S'gnature of the Chief Executive officer • • .Notar i nature
9 � G
ate UDate
Worksheet for Calculating the Final Draw (Return with Close-out)
Unlike the first two vouchers, the Public Works Unit is unable to
calculate the amount of the final draw. Two variables essential
to the calculation are known only by the jurisdiction, i.e. , the
actual total eligible project cost and the interest earned on the
Public Works Trust Funds. The instructions and worksheet
provided here are designed to assist the jurisdiction in
calculating the amount of the final draw. Please note:
o Interest earned on PWTF funds drawn by the jurisdiction
are to be applied toward eligible costs.
o PWTF participation can not exceed 70%, 80%, or 90% of
the actual total eligible cost of the project as per
PWTF loan agreement.
Worksheet
Step 1. Identify the actual total eligible
project cost. 1. 2,476,711.45
Step 2 . Identify the PWTF contract' s allocation. 2 . 2,466,717.00
Step 3 . Identify the actual local funds. 3 . 636,143.00
Step 4 . Identify other funds (funds other than
local fund and PWTF) used for eligible
project cost. 4 . .00
Step 5.. Balance of eligible project cost 2,476,711.45
(subtract line 4 from line 1) 5.
* 80
Step 6. Multiply line 5 by either 70%, 80%, or 90%
as set forth in the loan agreement. 6. 1,981,369.16
Step 7. Identify interest earned on PWTF funds. 7. . 15,388.31
Step 8. Subtract line 7 from line 6. 8.. 1,965,980.85
Step 9. Enter the lesser of line 2 or line 8
(or a local option of an elective amount
less than both line 2 and line 8) . 9. 1,840,568.45
Step 10. Tabulate the amount drawn from the
project's PWTF allocation to date. 10. 370,007.55 . _"�-
Step 11. The final draw amount for the project,
subtract line 10 from 1 ine '9 . 11. 1,470,560.90
Step 12 . Percent of local share (divide line 3
by the sum of line 3 and line 9) . 12 . 25.7
FORM STATE Of wASwNGTON
AGENCY USE ONLY —
Al -`IA INVOICE VO HER AGENCY NO. LOCATb11 COOE ( PR OR AUTK NO.
Oiw.S v L)
001
AGENCY NAME
WSTRUCT)ONS TO VENOOR OR CLA"WT: Submit this toem 10
Department of Community, Trade and Bann P&Ymenr for motorists, m«cnanoiae or services. Show corndfefa
detail for each item.
Economic DevelODment
VENDOR OR CLAIMANT (Warrant is to be payable t0) Vendoi s Cartiftcate.1 hereby Candy under penalty of penury that the
items and 101013 listed herein are proper Ctargos lot rnatenaia,
morCiandue Of services lumuhed to the State of Washington,and tat all
goods hrreished and/or 3erwC04 rorWeted have been p(oVide.d Wkhout
discrimination because of age. sex_ marital status, race, creed. color,
national ongat. handicap.religion,of Y»mam era or disabled vetorana
status. /1
City of Renton
200 Mill Ave. S. \ BY
Renton, WA 98055 (s' IN Iwii<')
i
11 E) (DATE)
FEDERAL I.D. NO. OR SOCAL SECURITY NO. (For .ieoonnp aarsonat S,ces Conuact Pa,rnanis io 1 AS, =E=2IVED•SY - . 'DATE RECEIVED UNIT DATE ! DESCRIPTION ! OUANTM I UNST I PRICE ! AMOUNT j FOR AG Y USE
Public Works Trust Fund
PW-5-96-791-044
Voucher Number 2 (Final) :
Loan Amount . . . . . . . . . . . . . . . . . . . . : . . . . . . $2,466,717. 00
Previous Draws . . . . . . . . . . . . . . . . . ... . . . . . $ 370, 007.55
Balance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $2, 096,709.45
J
Total Vouceher #2 (Final) . . . . . . . . . . . . . . $ 1,470,560.90
PREPARED BY TELEPHONE NUaaBER DATE i AGENCY APPROVAL DATE
I
OOG DATE I MIT DUE.OAT-! CURRENT DOC. NO. � REF OOC. NO. I VENDOR NvMBER VENDOR MESSAGE 1USE U& sUMBER
' !TAXI
i
� latS7FlttOfl. •i � ivOlzRtUSStSq CO(x� tin/ttisnl
1EF;
TlAI6 QRG 5(E f501
I�106�tCT .! i„�fit. ! fwurt
i II I � ► I I ! � III
-
. ! � 1 I I ! � I .. I_. .I I t . I •
I - I I I 1 liiitii
AL�tiN0 APPROVAL FOR PAYMENT I DATE i WARRANT TOTAL I WAA%-!
7NT NtJUB£A
Sunset Sewer Interceptor
PWTF Loan Number PW-5-96-791-044
Estimated versus Actual Expenditure Explanation
Design Engineering:
The design engineering for this project is approximately 75% less than what we originally
estimated. At the time of application, the City had anticipated the engineering costs assuming use
of outside consultants to perform the design. In addition, we were not clear at that time whether or
not we would be required to write an EIS during the environmental review. The project ultimately
was designed in-house by City engineering staff and the project was issued a Determination of Non
Significance,thus eliminating the need to provide an EIS.
Construction Inspection:
The total cost of construction inspection was approximately 53% lower than our original estimate.
The reason for this cost savings is similar to that of the design engineering. During the time of the
application we had anticipated the use of specialized construction inspection for the microtunneling
part of the project. At the time we completed design we felt comfortable that the City had qualified
experience on staff and utilized our in-house inspection group.
Contingency:
The project was able to be completed within the original estimated construction costs. We did not
experience any changed conditions during the construction, thus allowing us to keep change order
costs to under 5%of the original construction contract amount.
\\TS_SERVER\SYS2:\COMMON\-H:\DIVISION.S\UTILITIE.S\DOCS\EXPLAIN.DOC\dc
TO: -FINANCE-DIRE CR
FROM: PUBLIC WORKS ADMINISTRATOR
CONTRACTOR: Frank Coluccio Constr. Co. -
CONTRACT NO. CAG 96-125 ESTIMATE NO. 8
Final
PROJECT: Sunset Sewer Interceptor
i
1. CONTRACTOR EARNINGS THIS ESTIMATE $60,000.00
2. SALES TAX @ 8.60% $5,160.00
3. TOTAL CONTRACT AMOUNT THIS ESTIMATE $65,160.00
4. EARNINGS PREVIOUSLY PAID CONTRACTOR $1,974,077.57
5. * EARNINGS DUE CONTRACTOR THIS ESTIMATE $57,000.00
6. SUBTOTAL-CONTRACTOR PAYMENTS $2,031,077.57
7. RETAINAGE ON PREVIOUS EARNINGS $103,898.82
8 ** RETAINAGE ON EARNINGS THIS ESTIMATE $3,000.00
9. SUBTOTAL- RETAINAGE $106,898.82
10. SALES TAX PREVIOUSLY PAID $176,275.77
11. SALES TAX DUE THIS ESTIMATE $5,160.00
12. SUBTOTAL-SALES TAX $181,435.77
* (95%x LINE 9)
** (RETAINAGE: 594.) GRAND TOTAL: $2,319,412.16
FINANCE DEPARTMENT ACTION:
PAYMENT TO CONTRACTOR (Lines 5 and 11):
ACCOUNT # 421.000000.018.5960.0035.65.045125(45125/5460) $62,160.00 # 8
421.000000.018.5960.0038.65.065015(65015/5460)
$62,160.00
RETAINED AMOUNT(Line 8):
ACCOUNT # 421.000000.018.5960.0035.65.045125(45125/5460) $3,000.00 # 8
421.000000.018.5960.0038.65.065015(65015 15460)
$3,000.00
i
. 'I. TOTAL THIS ESTIMATE: $65,160.00
r . .
CHARTER 116, LAWS OF 1965
CITY OF RENTON CERTIFICATION
1,THE UNDERSIGNED 00 HEREBY CERTIFY UNDER PENALTY OF
PERJURY,THAT THE MATERIALS HAVE BEEN FURNISHED,THE
SERVICES RENDERED OR THE LABOR PERFORMED AS DESCRIBED
HEREIN,AND THAT THE CLAIM IS A JUST,DUE AND UNPAID - -
c. OBLIGATION AGAINST THE CITY O RE ON,AND THAT I AM
AUTHORIZED TO AUTHENTICAT AND C TIFY T SAI C
Signed:
9
� t
Printed On:9/4/97 City of Renton Public Works Department Page 1
j
Printed On:9/4/97 City of Reason Public Works Department P e 1
a8
`. _
Project: Sunset Sewer Interceptor Contract Number: CAG 96-125
Contractor. Frank Coluccio Constr.Co. Pay Estimate 8 Closing Date: 9/5/97
FINAL
Item Description Unit Est Unit Previous Previous This This 'Total Total
No. QTY Price Quantity Amount Quantity Amount Quantity Amount
001. Mobilization LS 1 $71,500.00 1.00 $71,500.00 S0.00 1.00 $71,500.00
002. Demobilization LS t 51,000.00 1.00 $1,000.00 50.00 1.00 $1,000.00
003. Construction Survey&As-built LS I $7,000.00 1.00 57,000.00 S0.00 1.00 57,000.00
004. Reestablish existing monuments EA 10 5200.00 10.00 52,000.00 $0.00 10.00 $2,000.00
005. Traffic Control LS 1 S12,150.00 1.00 S12.150.00 $0.00 1.00 S12,150.00
006. Shoring,Design,Construction&Maintenance LS I 56,000.00 1.00 56,000.00 $0.00 1.00 56,000.00
007. Erosion,Sedimentation Control,and Landscaping LS 1 S1,000.00 1.00 S1,000.00 $0.00 1.00 S1,000.00
008, Fumish&Install 84"Manhole,Connection to
existing sewer EA 1 59,000.00 1.00 $9,000.00 $0.00 1.00 S9,000.00
009• Furnish&Install 60"Concrete ME up to 8'deep EA 19 $2,680.00 20.00 $53,600.00 $0.00 20.00 S53,600.00
010. Fumish&Install 60"Concrete MH Ext.for depths
deeper VF 118 5210.00 117.40 524,654.00 $0.00 117.40 $24,654.00
011. Fumish&Install 60"Concrete ME Extensions for
_ Depths 20'and Deeper VF 85 5210.00 84.50 517,745.00 $0.00 84.50 SI7,745.00
i„
f' 012. Fumish&Install 18'Sewer Pipe in Shallow Section L 2654 558.00 2654.00 S 153,932.00 $0.00 2654.00 S 153,932.00
013. Fumish&Install 18"Sewer Pipe in Deep Section LF 3198 S385.00 3198.00 S1.231,230.00 50.00 3198.00 S 1,231,230.00
014. Bore Pis and Receiving Pits in Deep Section LS 1 S 165,000.00 1.00 S165,000.00 $0.00 1.00 S 165,000.00
015. Connections to Existing Manholes EA 1 $1,000.00 1.00 51,000.00 50.00 1.00 $1,000.00
t° 016. Foundation Material Ton 500 $0.10 $0.00 $0.00 0.00 $0.00
017. Select Backfill Ton 3100 57.00 1536.87 S10,758.09 50.00 1536.87 S 10,758.09
f i
f
Printed On:914/97 City of Renton Public Works Department Page 2
Project Sunset Sewer Interceptor Contract Number CAO 96-125
Contractor. Frank Coluccio Constr.Co. Pay Estimate 8 Closing Date: 9/5/97
FINAL
Item Description Unit Est. Unit Previous Previous This This Total Total
No. QTY Price Quantity Amount Quantity Amount Quantity Amount
018. Asphalt concrete patch including crushed surfacing
top course SY 3078 $33.00 4460.00 $147,180.00 $0.00 4460.00 $147,180.00
019. 1-1/2'Asphalt Concrete Overlay Ton 579 $41.00 517.63 521,222.83 $0.00 517.63 $21,222.83
020. Pavement Grinding SY 1487 $3.00 1487.00 $4,461.00 $0.00 1487.00 $4,461.00
021. Pavement Saw Cutting LF 5700 $2.00 6400.00 $12,800.00 $0.00 6400.00 $12,800.00
022. Temporary Striping LS 1 $1,500.00 1.00 S1,500.00 $0.00 1.00 $1,500.00
023. Final Adj of MK Valve Boxes,CB,Monument EA 11 5300.00 11.00 $3,300.00 $0.00 11.00 $3,300.00
024. Curb&Gutter,and Sidewalk restoration LS 1 $1,000.00 1.00 $1,000.00 $0.00 1.00 S1,000.00
025. Traffic Sensor Loop Replacement EA 10 $2,100.00 41.00 $86,100.00 $0.00 41.00 $86,100.00
026. Television Inspection LS I 56,000.00 1.00 $6,000.00 $0.00 1.00 $6,000.00
027. Trench Dewatering LS 1 $10.00 1.00 $10.00 $0.00 1.00 $10.00
028. CO I-Additional work at NE 12th St.Crossing LS 1 $12,333.47 1.00 S12,333.47 $0.00 1.00 $12,333.47
029. CO2-Time and Material Storm Sewer Installation LS 1 $11,100.00 1.00 $11,100.00 $0.00 1.00 $11,100.00
at Kirkland Av.NE
030. CO2-Time and Material Asphalt Patch for Water LS 1 $3,400.00 1.00 $3,400.00 $0.00 1.00 53,400.00
1 cut-iris at NE 12th Street
031. CO3-Time and Material to remove LS I 525,000.00 $0.00 1.00 $25,000.00 1.00 $25,000.00
obstructions
032. CO3-Time and Material to remove LS 1 $35,000.00 50.00 1.00 . $35,000.00 1.00 $35;000.00
additional fill material
i
K Subtotal $2,077,976.39 S60,000.00 $2,137,976.39
8.2%Sales Tax $49,818.90 $0.00 549,818.90
8.6%Sales Tax 5126,456.88 $5,160.00 5131,616.88
!` Total Sales Tax $176,275.78 $5,160.00 $181,435.78
TT Total 52,254;252.17 f 565,160.00 $2,319,412.17
q
CITY-OF RFNTON
Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: Sunset Sewer Interceptor- CAG-96-125 C.O.# 3
CONTRACTOR: Frank Coluccio Construction Company
SUMMARY OF PROPOSED CHANGE:
BID ITEM BID ITEM
NO.
31 Lump sum payment for negotiated time and material work to remove obstructions above and
beyond the Contract at three locations
Quantity ni Unit Cost 591_
1 LS $25,000.00 $25,000.00
BID ITEM BID ITEM
NO.
Lump sum payment for negotiated time and material work to remove additional fill material
3� at construction staging area.
Quantity nit Unit Cot cost
1 LS $35,000.00 $35,000.00
Subtotal $60,000.00
Sales Tax @ 8.6 % $5,160.00
Total $65,160.00
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT
AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE
$2,110,003.87 $2,139,095.68 $65,160.00 $2,204,255.68
E'>
SIGNATURES:
Contractor: Date: 5
Project Engineer., Date: 3
F` Approved'By: Date: g �"
Wt -
f
I
x
�, H:DOCS:SUNC03:DMC:ps
STArg o 9
O
IBBB a 902
STATE OF WASHINGTON
1
DEPARTMENT OF LABOR AND INDUSTRIES
�..4
February 9, 1998 FEB 1311998
C i DI V r [ EN I-O lU
CITY OF RENTON L-n;ineering Dept,
DEPARTMENT OF PUBLIC WORKS
200 MILL AVE S
RENTON WA 98055
Account ID: 204,169-00
Frank Coluccio Construction Company
Contract Number: CAG-96-125
Dear Business Person:
Please be advised that the Department of Labor and Industries does hereby release the City of
Renton from any further liability for Industrial Insurance premiums pursuant to RCW 51.12.050
and RCW 51.12.070 as would otherwise incur in connection with a contract calling for the
Sunset Sewer interceptor.
This certificate does not release Frank Coluccio Construction Company from liability for
additional Industrial Insurance contributions which later may be determined to be due or for any
other obligations under other statutes (e.g. Prevailing Wage)with respect to the above mentioned
contract or any other contracts said contractor may have performed.
Since ely,
Bonnie Fahrnkopf
Industrial Insurance
Accounts Auditor
Contractor Compliance/Release Unit
Phone: (360) 902-4763/Fax(360) 902-4757
CCUI:31cd92
cc: FRANK COLUCCIO.CONSTRUCTION COMPANY
9600 MARTIN LUTHER KING WAY S
SEATTLE WA 98108-5693
� :- iA
STArg o�
i
e yo
o
' 1880
STATE OF WASHINGTON
EMPLOYMENT SECURITY DEPARTMENT
PO Box 9046 • Olympia, WA 98507-9046
CONTRACTOR: Frank Coluccio Construction Co ) CERTIFICATE OF
9600 ML King Jr Way S ) PAYMENT OF CONTRIBUTIONS
Seattle, WA 98118 ) PENALTIES AND INTEREST ON
PUBLIC WORKS CONTRACT
ES Reference No. 200067-00 9
TO: City of Renton
200 Mill Ave S
Renton, WA 98055 2132
The Employment Security Department hereby certifies that contributions, penalties and interest
due from the above named contractor under the Employment Security Act have been paid in full or
provided for with respect to the following public works contract:
CAG 96-125
The Employment Security Department hereby certifies that it has no claim pursuant to RCW
50.24.130 against the public body named above for tax attributable to service performed for said
public body by the above named contractor on the above described contract. The Employment
Security Department releases its lien on the retained percentage which is provided by RCW 60.28.040
.for contributions, penalties and interest due from said contractor.
This certificate does not release said contractor from liability for additional contributions,
penalties and interest which may be later determined to be due with respect to the above mentioned
contract.
Dated at Olympia, Washington on October 8, 1997.
COMMISSIONER
EMPLOYMENT SECURITY DEPARTMENT
Authorized Representative)
Original - Disbursing Officer
Duplicate - Employer
Triplicate - Central Office files
EMS 8449 760 R7-84
State of Washington
Department ores&A e 78 025 601
//- Audit Procedures b Administration
PO Box 47474
Olympia,WA 98504-7474
REVENUE http!/www.wa.gov/dorMador.htm
Certificate of Payment of State Excise
Taxes by Public Works Contractor
Contractor:
FRANK COLUCCIO CONSTRUCTION CO INC
9600 M L KING JR WAY S
SEATTLE WA 98118 5630
We hereby certify that taxes, increases and penalties due or to become due from the above named
contractor under Chapter 180, Laws of 1935, as amended, with respect to the following public works
contract:
CITY OF RENTON
#CAG-96-125 SUNSET SEWER INTERCEPTOR
together with all other taxes, increases and penalties due from such contractor, have been paid in full or
that they are, in the Department's.opinion, readily collectible without recourse to the state's lien on the
retained percentage.
This certificate is issued pursuant to the provisions of Chapter 60.28 Revised Code of Washington
for the sole purpose of informing the state, county, or municipal officer charged with the duty of disbursing
or authorizing the payment of public funds to said contractor that the Department of Revenue hereby
releases the state's lien on the retained percentage provided by this Chapter for excise taxes due from said
contractor.
This certificate does not release said contractor from liability for additional tax which may be later
determined to be due with respect to the above mentioned contract or other activities.
Dated / 7 -q ) at Olympia, Washington,
STATE OF WASHINGTON
DEPARTMENT OF REVENUE
rertifying nOfftricer
To inquire about the availability of this document in an alternate format for the visually impaired or in a language other than English,please
call(360)753-3217.TTY users may call 1-800451-7985.
REV 310028(4-25-96) ROUTING: White Copy-Disbursing Officer White Copy-Contractor Canary Copy-File Pink Copy-Special File
CITY:-OF RWON
Pu��ic'PVorks Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: Sunset Sewer Interceptor- CAG-96-125 C.O.# 3
CONTRACTOR: Frank Coluccio Construction Company
SUMMARY OF PROPOSED CHANGE:
BID ITEM BID ITEM
NO.
31 Lump sum payment for negotiated time and material work to remove obstructions above and
beyond the Contract at three locations
Quantity nit Unit Cost C-QA
1 LS $25,000.00 $25,000.00
BID ITEM BID ITEM
NO.
,Ze Lump sum payment for negotiated time and material work to remove additional fill material
3� at construction staging area.
Quantity nit Unit Cost cost
1 LS $35,000.00 $35,000.00
Subtotal $60,000.00
Sales Tax @ 8.6 % $5,160.00
Total $65,160.00
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT
AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE
$2,110,003.87 $2,139,095.68 $65,160.00 $2,204,255.68
SIGNATURES: �
Contractor: Date: 7
Project Engineer: Date: 3
Approved By: Date: C/ -+
(Utility Systems Director)
H:DOCS:SUNCOJ:DMC:ps.
Washington State City of Renton
Public Works Board
Post Office Box 48319 F,. ®Cl t 2007
Olympia,Washington 98504-8319 U?QC1Ce�IS
October 9 2007
CITY OF RENTON
NOV 0 8 200.7
Mr. Michael Bailey RECEIVED
City Of Renton CITY CLERK'S OFFICE'
1055 S Grady Way
Renton, WA 98058
Regarding: Public Works Trust Fund Loan Agreements
Pr�-9a-065 • PW-5-92-280-033 PW-5-93-280-040 CA�j - q3 05b
-055• PW-5-93-280-041 PW-5-94-784-032 C a 4- qH- 01405
0A4- 7s_058• PW-5-95-791-032 PW-5-95-791-033 CAS- q5- 057
CA�
-q6- 078 • PW-5-96-791-044 PW-5-96-791-045 eAq_ 9l -,'7q
OAQ-q,7 _13o• PW-97-791-028 PW-01-691-PRE-117 lf�C�- 01- 175
C,qh- 02-0-79 • PW-02-691-045
Dear Mr. Bailey:
Enclosed are fully executed originals of amendments to your Public Works Trust Fund
Loan Agreements (see precise loan numbers above). These amendments remove the
.acceleration clause in the above referenced loans. Please keep this original with other
local records related to your approved Public Works Trust Fund Loan Agreements.
If you have any questions please call, Isaac Huang, your Client Services Representative,
at (360) 586-4129 or you may call me at(360) 586-4135.
Sincerely;'_
0
Cathy Brockmann
Contract Specialist
CLB:ac
Enclosure