HomeMy WebLinkAboutDraft Scope of Work - Phase 3 Final Design.pdfJune 2007 CITY OF RENTON Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work Draft 1 - 6108107 Purpose and Approach The purpose of Phase 3 of the Well 5A Water Treatment Improvements Project is to prepare the final design and eonstnietion documents for the City of Renton's planned Well 5 A treatment facility. This construction documents will be submitted to the Department of Health (DOH) and the City Council for project approvals and permits. As part of the design process, the HDR- Kennedy/Jenks design team (Consultant) will provide technical assistance to the City for permit applications associated with the project. The Consultant will also provide assistance to the City during the construction bidding phase. The overall approach is to produce key design deliverables by target dates needed for project delivery. These target dates may change per the City's needs and/or changed project conditions. The final design will be based on the basis of design developed in Phase 2 of the project. The specific objectives, work elements, and budget for Phase 3 are more fully described in the Scope of Work section below. At the end of Phase 3, the Scope of Work and budget will be refined and adjusted for the Phase 4 - Assistance During Construction to meet the project requirements and the City's needs. The tasks and work elements to be performed by the Consultant are described below. Outlined for each task are the objectives, work elements, responsibilities of the City, and products/deliverables. Unless otherwise noted, all items listed under the "Work Elements" section for each task will be performed by the Consultant. Work that is specifically not included in this scope or work to be performed by the City is listed under the section "Work Not Included." Key Assumptions Assumptions for this Scope of Work are as follows; 1. The existing well building will be demolished. The existing well casing and pump will be retained. City of Renton Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work June 2007 2. The treatment process will include the following: a) Venturi aeration system to add dissolved oxygen to the water to facilitate sulfide oxidation during the GAC step. b) GAC adsorption/catalytic oxidation system for hydrogen sulfide oxidation. c) Iron/manganese catalytic oxidation/filtration (i.e., greensand) system using Greensand Plus for iron and manganese removal. d) Breakpoint chlorination in a basin under the process building for ammonia oxidation. e) GAC adsorber and greensand filter backwash settling in a basin under the process building. f) Recycle of the backwash supernatant into the process after GAC. g) Disposal of backwash settled solids into a sanitary sewer connection. h) Commercial strength sodium hypochlorite solution will be used for chlorination. 3. The treatment train will be sized to treat a design flowrate of 1500 gpm. 4. A mobile standby generator will be designed to provide emergency power to all Well 5A treatment and pumping systems. 5. A new above-grade treatment building will be necessary to house: a) An operations control room/laboratory, b) An electrical room, c) An accessible restroom, d) A blower room for the blower system for air scouring of the greensand filters, e) A standby generator room, f) A well pump room, g) A treatment gallery to house: - The well pump, - The venturi aeration system, - The GAC system piping and valves, - The greensand system piping and valves, - The hypochlorite system. The sodium fluoride and polyphosphate feed systems, - A backwash water pumping system, - A high-lift pumping system, h) The GAC and greensand vessels will be outside the treatment building but enclosed by screening walls. 6. The chlorine contacting and backwash water basins will be below-grade concrete structures that will be integrated with the foundation for the above-grade structure. 7. The required permits that are anticipated for project approval are: a) SEPA Checklist b) DOH Construction Documents approval (WAC 246-290-120) c) City of Renton Clearing and Grading Permit. The City will apply for this and the Consultant will provide information, if requested. City of Renton 2 Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work June 2007 d) City of Renton Building Permit (including Energy Code requirements). The City will apply for this and the Consultant will provide information, if requested. e) City of Renton Tank Permit. The City will apply for this and the Consultant will provide information, if requested. f) City of Renton Electronic Monitoring of Hazardous Materials Permit. The City will apply for this and the Consultant will provide information, if requested. g) King County Wastewater Discharge Permit. The City will apply for this and the Consultant will provide information, if requested. The preparation of a Hazardous Materials Management Plan to address 2006 International Fire Code requirements may be necessary, if required by the City of Renton Fire Marshall. The Washington State Department of Health will approve the DOH Project Engineering Report within the time allocated by the schedule. Work Not Included Work elements NOT included as part of this Scope of Work include: 1. Legal testimony!*]^*^-, 2. Assistance with property purchases and/or re-zoning; obtaining or vacating right-of- ways; obtaining easements; and boundary line adjustments. 3. Surveying. - 4. Construction phase services. City of Renton Well 5A Water Treatment Improvements Phase 3 - Final Design Scope of Work June 2007 Phase 3 - Final Design The Phase 3 Seope of Work is organized into the following major tasks: 3-100 - Phase 2 Project Management and QA/QC 3-200 - Design Development 3-300 - Construction Cost Estimates 3-400 - Construction Schedule Development 3-500 - Bidding Documents Preparation 3-600 - Permitting and Project Approval Assistance 3-700 - Assistance During Bidding Task 3-100 - Phase 2 Project Management and QA/QC Objectives: 1. Provide for effective coordination and management of the Phase 2 work elements to meet all project objectives. 2. Provide for Phase 2 QA/QC reviews of all key design recommendations and project deliverables. Work Elements: 1. Management and coordination of all work elements described in Tasks 2-100 through 2-900. 2. Prepare a Project Guide, including a project scope and schedule. 3. Prepare for and attend up to six (6) project coordination / design review meetings. 4. Conduct internal quality control reviews on 30%, 60%, 90%, and 100% construction documents. 5. Preparation of monthly project status and budget tracking reports and invoices. 6. Assistance with contract changes, as necessary. 7. Develop a seope and budget for the next phase of work. City Responsibilities: 1. Participate in project coordination meetings. 2. Review of the construction documents at the 30%, 60%, 90%, and 100% levels. 3. Provide review comments and feedback as requested by the project design team. It is assume that the city will return review comments within 10 working days from submittal. Deliverables: 1. Project Guide. 2. Copies of correspondence and records of key decisions, as requested by the City. City of Renton 4 Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work June 2007 3. Monthly proj ect status, budget tracking reports, and invoices. 4. Materials necessary to develop and document contract changes, as required. Task 3-400 - Design Development Objectives: The objectives of Task 2-100 are: 1. Develop the design plans and specifications for the Well 5 A Water Treatment Facility to the 90% completion level. 2. Conduct design reviews with the City at the 30%, 60%, and 90% design completion levels. Task 3-401 - Civil/Site Design Objective: 1. Develop the civil/site plan final design and prepare the associated drawings and specifications. ^ Work Elements: 1. Prepare a vicinity map showing the location of the treatment facility in relation to the Well 5 A site and the City of Renton. The map will be used in the design plans to acquaint bidders with the project site and to satisfy building permit criteria. 2. Complete the site plans showing property lines, easements, existing contours, and roadway structures, existing facilities, pertinent topographic features, proposed facilities including the treatment facility structures, yard piping, driveway/parking area, and areas to be restored. These plans will identify horizontal and vertical control, construction limits, site grading, sub-grade plan, critical elevations, site access for construction, and areas that are not to be disturbed. 3. Develop the stormwater drainage design to include pipelines and hydraulic calculation summary information in eonformanee with approved Best Management Practices outlined in the State Department of Ecology 2001 Stormwater Management Manual for Western Washington. It is assumed that additional on-site stormwater detention will be required. 4. Prepare the temporary erosion and sediment control (TESC) plan. Prepare recommendations for construction de-watering disposal options. 5. Identify critical elevations for the treatment facility. Establish facility floor elevations and buried pipe elevations. 6. Prepare plans, profiles, and details for modifications of the water piping from the existing well to the new treatment facility and to the distribution system piping. 7. Prepare plans and details for any utility/access vaults required. City of Renton 5 Weil 5A Water Treatment improvements Phase 3 - Finai Design Scope of Work June 2007 8. Develop cross sections of utility trenches for additions/modifications to other utility lines to the treatment building. 9. Prepare specifications for the civil/sitework elements. Assumptions: 1. Environmental review and permitting process will he completed via SEPA. AnEISwill not be required. 2. The datum/control information and current boundary information were prepared as part of Phase 2 work. City Responsibilities: 1. Provide for surveying of the site and a base map from which site design development can proceed. 2. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Civil drawings, details, and specifications required for construction of the treatment facility. Stormwater technical information report for inclusion in the SEPA checklist. The estimated number of civil drawing sheets required is Task 3-402 - Structural Design Objective: 1. Develop the facility structural design and prepare the associated plans and specifications necessary for the construction of the new Well 5 A structures. Work Elements: 1. Develop the structural design for the: a) Treatment building h) Chlorine contact basin c) Backwash water basin d) Slab on grade fouiidations e) Structural support for equipment 2. The chlorine contacting and backwash water basins will be helow-grade concrete structures that will he integrated with the foundation for the above-grade structure. 3. Structural designs will he based on current Intemational Building Code 2006 standards and geotechnical recommendations. 4. Provide and document structural calculations for the foundations, walls, roof, structural steel, and seismic restraint. Calculations for manufactured trusses and pre-east concrete items will he provided by the manufacturer of each item. City of Renton ^ Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work June 2007 5. Design and prepare specifications for mechanical/piping supports. Assumptions: 1. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Structural drawings and specifications required for construction of the Well 5A structures. The estimated number of structural drawing sheets is . Task 3-403 - Building Architectural Design Objective: 1. Develop the building architectural design and prepare the associated plans and specifications necessary for Well 5A treatment building. Work Elements: 1. Develop the architectural design, construction documents, and specifications for the Well 5 A treatment building: a) Enclosmes, b) Walls and finishes, c) Roofs and coverings, and d) Internal features including flooring, cabinetry, etc. 2. Perform a building code review for the new treatment structures. 3 . Prepare architectural specifications for Divisions 4-10, including doors, lock sets, other architectural building hardware, and protective coatings for structural and architectural components, including walls, vaults, supports, doors, and railings. 4. Architectural materials, finishes, and colors to be selected at the 60% design development. Assumptions: 1. A new above-grade treatment building will be necessary to house: a) An operations control room/laboratory, b) An electrical room, c) An accessible restroom, d) A blower room for the blower system for air scouring of the greensand filters, e) A well pump room, f) A treatment gallery to house: The venturi aeration system. City of Renton 7 Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work June 2007 The GAC system piping, The greensand system piping. The hypochlorite feed system, A backwash water pumping system, and A how-lift pumping system. a) The GAC and greensand vessels will be outside the treatment building but enclosed by screening walls. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Architectural drawings and specifications required for construction of the Well 5 A facility. The estimated number of architectural drawing sheets is . Task 3-404 - Well Pumping System Modifications Mechanical Design Objective: 1. Design mechanical modifications to the Well 5A pump to meet the hydraulic requirements for the treatment process improvements, as necessary, and prepare the associated drawings and specifications. Work Elements: 1. Establish the hydraulic head requirements for the well pump. 2. Determine the adequacy of the existing pump in relation to the system hydraulic profile requirements. 3. Identify pump modification reqiiirements, if needed. 4. Develop the design and specifications for mechanical modifications to the well pirnip. Assumptions: 1. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Plans and specifications for well pump modifications and associated valves and appurtenances. The estimated number of drawing sheets associated with this design element is City of Renton Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work June 2007 Task 3-405 - Supply Piping and Control Valve Design Objective: 1. Design and prepare drawings and specifications for inlet header piping and control valves necessary for controlling the flow from the Well 5A pump into the treatment process. Work Elements: 1. Finalize the configuration of the plant inlet piping, the control valves, and associated mechanical components required. Size the piping and valves and select materials. 2. Prepare plans and specifications for the inlet header piping system. Assumptions: 1. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Mechanical drawings and specifications for pipeline connections and for isolation and control valves. The estimated number of drawing sheets associated with this design element is . Task 3-406 - Treatment Systems Piping and Mechanical Design Objective: 1. Design and prepare the drawings and specifications for the venturi aeration system, the GAC contacting system, the iron/manganese catalytic oxidation/filtration (i.e., greensand) system, and the associated connecting piping, valves, and mechanical elements. Work Elements: 1. Prepare final sizing calculations and specifications for the venturi aeration system. 2. Prepare layout, elevation, and detail drawings showing the venturi aeration system including the process piping, valves, and associated mechanical features. 3. Prepare final sizing calculations and specifications for the GAC adsorbers. 4. Prepare final sizing calculations and specifications for the control valves for the GAC system. 5. Prepare layout, elevation, and detail drawings showing the GAC system including the adsorbers, process piping, valves, and associated mechanical features. 6. Prepare final sizing calculations and specifications for the greensand filters. 7. Prepare final sizing calculations and specifications for the control valves for the greensand system. City of Renton 9 Well 5A Water Treatment improvements Phase 3 - Finai Design Scope of Work June 2007 8. Prepare layout, elevation, and detail drawings showing the greensand system including the filters, process piping, valves, and associated mechanical features. 9. Establish the point of supply source of backwash water. Prepare drawings and details for piping, valves, and pumps (if necessary) for the backwash water supply system. 10. Prepare drawings and details for the air scour piping from the blower room to the greensand filters. 11. Prepare drawings and details for the manifold piping and associated valves required to deliver treated water to the chlorine contacting basin. 12. Prepare layout, elevation, and detail drawings for the process backwash water piping system. 13. Prepare the design and specifications for insulation systems for all above-groxmd process piping. 14. Select and specify suitable coatings for the adsorbers and filters. Assumptions: 1. The mechanical design will be developed arormd the City-selected treatment equipment for the GAC and greensand systems. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Mechanical design drawings required for treatment systems construction/installation. The estimated number of drawing sheets associated with this design element is . Task 3-407 - Sodium Hypochlorite System Design Objective: 1. Design the sodium hypochlorite generation, storage, metering systems and prepare the associated drawings and specifications. Work Elements: 1. Prepare final sizing calculations for the sodium h3q)ochlorite feed and storage system to meet the treatment process requirements. 2. Prepare plans and specifications for the hypochlorite feed and storage system including the hypochlorite metering pumps, hypochlorite storage tanks, piping, and other associated components. 3. Prepare plans and specifications for the hypochlorite metering system including the piping, metering pumps, and other associated components. City of Reiiton 'tO Well 5A Water Treatment improvements Phase 3 - Finai Design Scope of Work June 2007 Assumptions: 1. The sodium hypochlorite system will be sized per the requirements established in the basis of design. 2. The hypochlorite metering system will be designed to: a) Meter hypochlorite into the treatment process train between the GAC contactors and the greensand filters. b) Meter hypochlorite into treated water exiting the chlorine contact basin. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Mechanical drawings and specifications for construction/installation of the sodium hypochlorite generation, storage, and metering system. The estimated number of drawing sheets associated with this design element is . Task 3-408 - Process and Backwash Water Systems Design Objective: 1. Design the backwash water handling and low-lift pumping systems and piping and associated mechanical components. Work Elements: 1. Based on the design flow requirements, design the high-lift pumping system to convey treated water from the chlorine contacting basin to the 565 pressure zone of the distribution system. Design the backwash water handling pumping system. This system includes: a) The backwash water recycle pumps. b) The backwash water waste pumps. c) The backwash water supply pumps (if necessary). 2. Design the pumping system to conyey treated water from the chlorine contact basin to the selected disposal point (either the sanitary sewer or groundwater reinjection). 3. Finalize hydraulic analyses, and size the pumps, piping, and valves. 4. Prepare mechanical plans and specifications for: piping for the pump suctions and discharges, pressure control valves or regulation, pressure/surge relief, equipment isolation, flow metering, piping support, pressure testing and flushing, and pressure gauge assemblies. Assumptions: 1. City of Renton "11 Well 5A Water Treatment Improvements Phase 3 - Final Design Scope of Work June 2007 City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Mechanical drawings and specifications required for the backwash water and low-lift pumping systems. The estimated number of drawing sheets associated with this design element is . Task 3-409 — Water Quality Monitoring Systems Design Objective: 1. Design the water quality monitoring system for the treatment process. Work Elements: 1. Identify the water quality monitoring equipment requirements. 2. Prepare specifications for the water quality analyzers. 3. Design the mechanical and piping layout for the water quality analyzers within the control room. 4. Design the water sample piping system. Assumptions: 1. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Mechanical drawings and specifications required for the water quality monitoring system. It is estimated that this design element will not require any additional drawing sheets to those produced under other subtasks. Task 3-410 — Building Mechanical Systems Design Objective: 1. Design the piping and mechanical components associated with the Well 5 A treatment building structure and the air scour blower system. Work Elements: 1. Design the mechanical and plumbing systems associated with the new structure including: hatches, sump pumps, hose bibbs and wash-down piping, emergency eyewash and shower units, floor drains, storage, and leak detection equipment. City of Renton 12 Well 5A Water Treatment improvemehts Phase Z - Final Design Scope of Work June 2007 2. Design the building HVAC systems for the new treatment building including: unit heaters, louver/dampers, vents, ducting, and associated controls. 3. Perform State of Washington Energy Code analysis for building insulation requirements and prepare code compliance forms. 4. Design the fire sprinkler system riser. 5. Prepare specifications for the fire detection and suppression system. 6. Prepare specifications for protective coatings for mechanical, piping, and electrical components. 7. Design and prepare specifications for the air scour blower system. Assumptions: 1. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Mechanical drawings and specifications required for constructing the building mechanical systems. The estimated number of drawing sheets associated with this design element is . ^ Task 3-410 - Emergency Generator Design 'y Objective: 1. Design the emergency generator system to provide power to the new Well 5 A facilities. Work Elements: 1. Design the mechanical and plumbing systems associated with the emergency generator. Assumptions: ^ 1. The emergency generator will provide emergency power for all components of the Well 5A facility. 2. The generator set will be mounted on a trailer for mobility, similar to other City generator sets. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. CityofRenton "IS Well 5A Water Treatment Improvements Phase 3 - Final Design Scope of Work June 2007 Deliverables: 1. Mechanical drawings and specifications required for eonstructing the emergency generator. The estimated number of drawing sheets assoeiated with this design element is Task 3-411 - Electrical Design Objective: 1. Prepare the electrieal design for the Well 5 A facilities. Work Elements: 1. Develop the final design of electrical system for the Well 5 A facilities. 2. Verify the power supply requirements. Finalize the one-line diagrams showing equipment layout sizes and breaker sizes. 3. Meet with Puget Sound Energy (PSE) to review the power supply design and to clarify PSE design criteria and requirements and to determine adequacy of existing transformer. 4. Develop the power and signal plan showing equipment and conduit routing and sizes with wire type and size. 5. Develop lighting plans showing equipment, mounting and light patterns. 6. Develop the fixture and panel hoard schedules. 7. Develop tables for the conduit and wire requirements. 8. Prepare instrument plan and details. 9. Develop elementary diagrams. Assumptions: 1. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Electrical drawings, details, and speeifieations. The estimated number of drawing sheets associated with this design element is . Task 3-412 — Instrumentation and Controls Design Objectives: 1. Prepare the instrumentation and controls design for the Well 5 A facilities. City of Renton 14 Well 5A Water Treatment Improvements Phase 3 - Final Design Scope of Work June 2007 Work Elements: 1. Develop the final design of the instrumentation and control system required to operate the new treatment systems as an integral part of the City's SCADA system. 2. Finalize the preliminary Process and Instrumentation Diagrams (P&IDs) showing functional changes necessary for master programming and RTU configuration. 3. Prepare an operations control strategy narrative for each process system to be included in the specifications. 4. Work with the City's Control System Programmer and/or City Water Operations staff to develop design details for telemetry system improvements to interface with existing City telemetry system. Assumptions: 1. The City's control system programmer is Reid Instruments. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. Deliverables: 1. Instrumentation and control diagrams, panel schedules and layouts; P&ID drawings; and control system narrative. The estimated number of drawing sheets associated with this design element is . Task 3-412 - Instrumentation and Controls Design Objective: 1. Prepare detailed shop drawings of the control panelboards from which fabrication of the panalboards can be done by the I&C Integrator. (scope of this task to be completed by HDR) Task 3-500 - Construction Cost Estimates Objective: 1. Prepare preliminary construction cost estimates at the 30% and 60% design development level and the Engineer's Opinion of Probable Construction Cost at the 90% design completion level. Work Elements: 1. Prepare a preliminary construction cost estimate at the 30% design completion level. City of Renton 15 Well 5A Water Treatment Improvements Phase 3 - Final Design Scope of Work June 2007 2. Update the preliminary cost estimate at the 60% design completion level. 3. Prepare the Engineer's Opinion of Probable Construction Cost for the construction project based on the 90% design completion level documents. City Responsibilities: 1. Provide bid cost information from other recent projects to the Consultant, if requested. Deliverables: 1. A preliminary construction cost estimate at the 30% design completion level. 2. Update to the preliminary project cost estimate based on the 60% design completion level for use in the PWTF Construction Loan Application. 3. The Engineer's Opinion of Probable Construction Cost including a detailed cost breakdown at the 90% design completion level. Task 3-600 - Construction Schedule Development Objective: 1. Prepare a target schedule for the construction and startup of the Well 5 A Treatment Facility so that it can be brought online by smnmer (or spring?) of 2009. Work Elements: 1. Develop a project scheiiule (in Microsoft Project format) that encompasses the major tasks and events required to design, construct, and bring the Well 5A Treatment Facility online. 2. The schedule will be based on the Consultant's best esiimate for the elements of the project but is not responsible for other parties' compliance with the schedule. 3. The schedule will include: a) Estimation of construction phase schedules. b) Coordination between the design, pre-purchase, and construction schedules. 4. The schedule will be reviewed by HDR construction specialists to determine additional time saving options. Assumptions: 1. The schedule will not include issues related to the design and construction of a booster pump station. City Responsibilities: 1. Review and provide feedback on the project schedule. Deliverables: 1. The project schedule (in Microsoft Project or PDF format). CityofRenton "IB Well 5A Water Treatment Improvements Phase 3 - Final Design Scope of Work June 2007 Task 3-700 - Bidding Documents Preparation Objective: 1. Prepare the bidding documents. Work Elements: 1. Finalize the design drawings and specifications based on all review comments and permit requirements. 2. Prepare the bidding documents, including plans, specifications, bid schedule, and finalized Engineer's Opinion of Probable Construction Cost. Assumptions: 1. City Responsibilities: 1. Provide review comments and feedback as requested by the Consultant. 2. Advertisement for the construction proj ect. 3. Review the bids and select a contractor. 4. Contract with the selected contractor. Task 3-701 - Prepare Drawings for Bidding Objectives: 1. Finalize the drawings to the 100% completion level based on comments fi-om City staff and the permitting agencies on the 90% plans and specifications. The plans will then be suitable for public bidding of the construction project. Work Elements: 1. Produce the 100% design drawings necessary for the bidding and construction of the Well 5A Treatment Facility. Incorporate the changes and final edits from the reviews of the 90% drawings. The drawings shall be divided into the following disciplines: a) General b) Civil c) Landscape d) Structural e) Architectural f) Mechanical (including piping and building mechanical) g) Electrical h) Process/Instrumentation City of Renton 17 Weil 5A Water Treatment Improvements Phase 3 ~ Final Design Scope of Work June 2007 2. Make final edits and back-checks of the 100% design drawings following the City's final review. Assumptions: 1. DOH comments on the 90% drawings which require changes to the drawings or specifications will have he to handled through addendums in the construction phase of this project. City Responsibilities: 1. Provide the Consultant with the most current versions of the City's standard details that are applicable to the facility design. 2. Review and provide final edits on the 100% design drawings. Deliverables: 1. Three Vi size (11" x 17") sets of final design drawings for review and final edits. 2. One Vi size (11" x 17") proof set of hid drawings (stamped and signed) for final review prior to printing. 3. Fifty (50) ^2 size (11" x 17") sets of hid drawings (with copies of stamp and signatures). 4. One set of final (100%) design drawings plus an electronic copy of the AutoCAD drawing files. Drawings shall he full-size (22" x 34") on mylar with stamps and signatures. AutoCAD drawing files will not include any electronic stamps or signatures. All drawings will he produced in AutoCAD Release 2000 unless otherwise directed. Task 3-702 — Prepare Specifications for Bidding Objective: 1. Finalize the specifications to the 100% completion level hased on comments fi*om City staff and the permitting agencies on the 90% platis and specifications. The specifications will then he suitable for public bidding of the construction project. Work Elements: 1. Produce the 100% technical specifications necessary for the bidding and construction of the Well 5A Treatment Facility Incorporate the changes and final edits from the reviews of the 90% technical specifications. 2. Work with the City to prepare the appropriate bidding forms for inclusion in the hid documents package. 3. The City of Renton uses the Washington DOT Standard Specifications for Road, Bridge, and Municipal Construction and has City Supplemental Provisions. The Consultant will use these standard specifications and will prepare Special Provisions in CSI format for the technical specifications. 4. Prepare the hid schedule and measurement and payment requirements. City of Renton 18 Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work June 2007 5. Finalize the Engineer's Opinion of Probable Construction Cost and format this estimate to follow the bid schedule. 6. Make final edits and back-checks of the 100% specifications following the City's final review. Assumptions: 1. The specifications include the technical specifications (Special Provisions), Supplemental Provisions to the Standard Specifications, and bid schedules. City Responsibilities: 1. Provide applicable bidding and form of contract materials to the Consultant for inclusion in the contract documents. 2. Provide to the Consultant the most current version of the City Standard Specifications. 3. Review and provide final edits on the 100% bid specifications. Deliverables: 1. Three sets of 100% bid specifications for review and final edits. 2. One proof set of bid specification (stamped and signed) for final review prior to printing. 3. Fifty (50) sets of bid specifications (with copies of stamp and signatures). 4. One electronic copy of the final bid specifications. Electronic files will not include stamps or signature. All specifications will be prepared in MS Word. Task 3-800 - Permitting and Project Approval Assistance Objective: 1. Assist the City with the preparation of the permit applications and design reviews by outside agencies that are necessary for project approval. Work Elements: 1. Provide technical information needed for the City to complete and submit the building permit application to the permitting entities within the City. Address questions and issues associated with the technical aspects of the building permit application, as necessary. 2. Provide technical information needed for the City to complete and submit the SEPA checklist to the City Planning Division. Address questions and issues associated with the technical aspects of the SEPA checklist, as necessary. 3. Respond to and provide clarification to questions from the Department of Health resulting from their review of the project construction documents. 4. Respond to and provide clarification to questions resulting from internal City review of the construction documents for the discharge of process wastewater, if required. City of Renton 19 Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work June 2007 Assumptions: 1. The City will be responsible for and take the lead for the coordination and preparation of all permit applications for the project. City Responsibilities: 1. Coordinate, prepare, and submit all necessary applications for City permits. 2. Coordinate, prepare, and submit the SEPA checklist. 3. Submit the construction documents to the Department of Health. Deliverables: 1. Technical information necessary for permit applications and the SEPA checklist. Task 3-900 - Assistance During Bidding Objective: 1. Assist the City during the project bidding and contracting phase. It is assumed that the City will advertise the bid, print and distribute bid documents, and maintain the master plan holders list. Work Elements: 1. Prepare one photo-ready advertisement for bids. 2. Coordinate and conduct a pre-bid meeting and site visit. 3. Respond to and answer bidders' questions. 4. Prepare up to 3 addenda to the bid documents, as required. 5. After receipt of bids, evaluate the bids received for responsiveness, check references of qualified bidders, prepare bid tabulation summary sheet, and prepare a written recommendation of award to the City. City Responsibilities: 1. Provide applicable materials to include in the advertisement for bids. 2. Pay for the costs of reproduction of all bid documents. 3. Maintain the master plan holders list. 4. Distribute addenda to plan holders, as required. 5. Provide a meeting room and time for the pre-bid meeting and have key staff attend the meeting. 6. Conduct the bid opening. Deliverables: 1. One photo-ready advertisement for bids. City of Renton 20 Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work June 2007 2. One pre-bid meeting (including meeting agenda and a summary of significant notes / issues resulting from the meeting). 3. One photo-ready set of addenda material (up to 3 addenda). 4. A letter to the City summarizing the bid evaluations and a recommendation for award. Personnel The following table lists the primary personnel that will be performing work on this project as well as their role. City of Renton Well 5A Treatment Facility Final Design Phase 3 - Consultant Personnel Personnel Project Role Jim Peterson Project Principal Greg Pierson Project Manager Milt Larsen Process & Mechanical Lead Jeff East Civil Design Lead Don Barraza Structural Design Lead Dan Wright Architectural Design Lead Ernie Swanson Electrical Design Lead Randy Geist Instrumentation and Control Design Lead Karissa Kawamoto Permits Lead Allen Fitz Lead QA/QC Reviewer Zipper Zeman Geotechnical Services Schedule Attached is a schedule (to be completed) for the Well 5A Water Treatment Improvements Project. This schedule assumes the following; o The City reviews and comments within two weeks on all of the following documents: a. 30% Design, b. 60% Design, c. 90% Design, and d. 100% Bid Documents. o The contract for Phase 2 is signed by the date the DOH report is sent to DOH. o Phase 2 design starts immediately after DOH report is sent to DOH (i.e., before DOH completes its review). City of Renton 21 Well 5A Water Treatment improvements Phase 3 - Final Design Scope of Work June 2007 The Washington State Department of Health's (DOH) will approve the DOH report within 5 weeks without significant comments. City of Renton 22 Well 5A Water Treatment improvements Phase 3 - Finai Design Scope of Work