HomeMy WebLinkAboutDRAFT Tech Memo - Placement of GAC Contractor and Greensand Filter Pressure VesselsKennedy/Jenks Consultants
Draft Technical Memorandum
Prepared for:
Prepared by:
Reviewed by:
J. D. Wilson, P.E.
Ray Sled, P.E.
City of Renton Water Utility
Chris Kelsey, P.E.
Milt Larsen, P.E., Kennedy/Jenks Consultants
Greg Pierson, P.E., HDR
Date: 27 February 2007
K/J No. 0697005.01
Subject: City of Renton, Washington
Well 5A Treatment Facility Pre-Design Considerations
Placement of GAC Contactor and Greensand Filter Pressure Vessels
Overview and Purpose
This techhical memorandum has been prepared as part of Task 2-300 of the Renton Well 5A
Water Treatment Improvements Project. The purpose of this memorandum is to provide an
overview and comparative evaluation for placement of the GAC contactors and greensand filter
pressure vessels that will be incorporated within the design of the new treatment facility for
Well 5A. The two general alternatives discussed involve the advantages/disadvantages
associated with either interior or exterior placement of the vessels.
The following assumptions are made as part of this memorandum:
• The materials of construction for the pressure vessels, piping, and appurtenances would
remain the same, regardless of interior or exterior placement, and differences in cost for
the specified paint coating systems of each are inconsequential. Grated platforms, to
provide operators access to the access hatches, piping, and equipment located on the
upper portions of the vessels, are assumed to be desirable and equivalent with both
alternatives.
• Operation and maintenance (O&M) costs are considered to be equivalent between the two
options, even though some subtle differences exist. Among these differences are exterior
vessels might require slightly more frequent painting and maintenance due to exposure to
weather, whereas interior vessels would necessitate more energy cost associated with
HVAC (including increased dehumidifying for condensation control) and could also require
additional capital cost for a larger sprinkler system that would be required under a building
"H" occupancy rating. Though the O&M would likely be slightly higher for interior
placement, estimating costs associated with these potential differences are felt to be
unnecessary in making an overall decision on which way the City of Renton (City)
proceeds. Therefore, a life cycle cost analysis is not considered, and cost comparisons
will be based solely on conceptual level opinions of probable construction costs.
• The filter face piping and electric motor actuated valves would be located inside the
building for both options.
W:\2006\0697005.01_HDR Renton Well\06-Corrspnd\6.03-Other\2007\02cwk1tm.Pressure Vessel Placement TM.doc
Kennedy/Jenks Consultants
J. D. Wilson, P.E.
Ray Sled, P.E.
City of Renton Water Utility
27 February 2007
Page 2
Pressure Vessel Sizing
The Well 5A Pilot Test Report by HDR evaluated different hydraulic loading rates across the
granular activated carbon media in the contactors and the greensand/anthracite cap media within
the pressure filters. The loading rates were varied from 5 to 12 gallons per minute (gpm) per
square foot (ft^^ for each of the two treatment processes, which were typically connected in series
under varying chemical treatment techniques and in the presence of different varieties of
greensand media (GS and GS+). The results of testing indicated that effective removal of
manganese, the most difficult constituent to remove, was obtained at maximum loading rates of
12 gpm/ft^, though the efficacy and reliability were better at a rate of 10 gpm/ft^. For this reason, a
design criteria target loading rate for filtration of 10 gpm/ft^ is recommended. Given the City's
desire to attempt to fully utilize their maximum instantaneous water right (Qi) of 1500 gpm, a
surface area of 150 ft^ is needed for both the GAG and greensand media beds.
In order to furnish some level of production redundancy, but at the same time limit the number of
vessels, two GAG contactors and two greensand pressure vessels are recommended. Each of
the four vessels has an approximate square footage of 78.5 ft^. These sizes were endorsed by
three locally represented pressure vessel/greensand filter suppliers. Note with the flow split
between two vessels in a unit process, it will be necessary to shut down the well while the
backwash sequence as it is not desirable to double the flow rate through one vessel to
approximately 20 gpm/ft^ while the other is being backwashed.
The vessel heights are determined through manufacturer recommended media depths necessary
to achieve adequate empty bed contact times (EBGT) that will adequately reduce hydrogen
sulfide levels through the GAG contactors and iron and manganese in the greensand filters.
Additional depth is required for upper and lower distribution systems, and adequate freeboard to
achieve desired media expansion during backwashing. It is anticipated that these design
parameters will be similar to the Maplewood facility.
Conceptual Level Construction Cost Comparison
Based on allowing adequate Spacing between filters for maintenance access and piping
connections, a general footprint necessary to accommodate the filters is recommended to be a
rectangular area of 65 feet long by 18 feet wide, or approximately 1,170 ft^. This area is also
illustrated in the preliminary building layout, included with this memo as Attachment A. If the
vessels were placed within the treatment facility building, they would then logically add 1,170 ft^
of additional square footage to the building size, with associated additional material costs. If the
vessels were placed outside, the building could not only be reduced in footprint, but also in
height, as the vessels would likely govern the necessary eave height. For aesthetic reasons, a
perimeter curtain wall, assumed to be of GMU construction, could be provided on two sides of
the slab that supports the vessels. A security fence could be installed across the backside if
desired.
W:\2006\0697005.01_HDR Renton Well\06-Corrspnd\6.03-Othef\2007\02cwk1tm.Pressufe Vessel Placement TM.doc
J. D. Wilson, P.E.
Ray Sled, P.E.
City of Renton Water Utility
27 February 2007
Page 3
Kennedy/Jenks Consultants
Table 1 offers a conceptual level opinion of probable construction cost for the two alternatives,
and includes only the differing items discussed above in order to establish a comparative cost
associated with this issue. Other building costs are not considered. The table indicates that, on
a conceptual level, approximately $400,000 in capital costs could be saved by placement of the
vessels outside.
Table 1: Table 1;
Costs
Alternative/Item
Conceptual Level Opinion of Probable Construction
Installed Material
Quantity Assumptions
Instaiied Unit Price
Assumptions Capitai Cost
Exterior Piacement
1170 ft^ concrete slab 12-inch slab
$500/CY material
$40/CY excavation/fill $23,400
Structure OMU curtain wall
10-foot height
36 LF for 2 sides
$25/SF material $9,000
Subtotal $32,400
Sales tax 8.8%
Mobilization, bond, and
insurance 10%$29,100
Contractor OH&P 22%
Estimate contingency 30%
TOTAL $61,500
Interior Placement
1170 ft^ Additional Building $200/SF material $234,000
10-to 16-foot eaves
Additional Building Height 165 LF for 4 sides
just building vessel area
$25/SF material $24,800
Subtotal $258,800
Sales tax 8.8%
Mobilization, bond, and
insurance 10%
Contractor OH&P 22%
Estimate contingency 30%
$232,400
TOTAL $491,200
Other Considerations
Table 2 lists other additional considerations not included within the cost comparison, including
advantages and disadvantages for each of the two alternatives.
W;\2006\0697005.01_HDR Renton Well\06-Corrspnd\6.03-Other\2007\02cwk1tm.Pressure Vessel Plaqement TM.doc
J. D.Wilson, P.E.
Ray Sled, P.E.
City of Renton Water Utility
27 February 2007
Page 4
Kennedy/Jenks Consultants
Table 2: Table 2:
Alternative
Other Considerations
Advantages Disadvantages
Exterior Placement
Lower HVAC requirements Operational noise, mostly
associated with actuation of
combination air valves
Potential reduction in sprinkler
system size ("H" occupancy)
• Exposure of vessels and
appurtenances to weather
Lower interior condensation
issues
• Higher security/vandalism risk
Easier vessel access for media
loading/unloading
• Exposure of operators to weather
during maintenance
• Easier control of combination air
valve discharge
Interior Placement
Containment of noise • Higher HVAC requirements
Vessels less vulnerable, more
protected
• Larger sprinkler system required
with building "H" occupancy
Operators protected from weather
during maintenance
• Increased need for dehumidification
for condensation control
• More difficult access for media
loading/unloading
• More difficult control of combination
air valve discharge
Recommendation
Due to the capital cost savings, as well as the overall simplification of O&M requirements, the
City should move forward with design of the new treatment facility for Well 5A with the pressure
vessels located outside of the new building. Photos of a similar installation for a groundwater
treatment facility are included as Attachment B.
Attachments
W:\2006\0697005.01_HDR Renton Well\06-Corrspnd\6.03-Other\2007\02cwk1tm.Pressure Vessel Placement TM.doc
Attachment A
Preliminary Building Layout
W:\2006\0697005.01_HDR Renton Well\06-Corrspnd\6.03-Other\2007\02cwk1tm.Pressure Vessel Placement TM.doc
PLOT DATE: 01/22/07 TIME: 13: 41 Renton Well 5A.dwg<Building)
"fT
CHLORINE
CONTACT BASIN
BW BASIN
AREA RESERVED
FOR FUTURE 02
STORAGE AND AIR
EDUCTOR
t P F ft
PIPE GALLERY
BW RE :ycle
BW TO
PUMPS
10' OR 12"
ROLLUP DOOR
BLOWERS MECHANICA
10'x 14
POLY
PUMPS/BLOWERS
20' X 28
STANDBY
GENERATOR
12'x20
ELECTRICAL
12'x20
CHEMICALS
20' X 24 HYPO
CONTROL
HW TANK
SINK
BACKFLOW PREVFLOUR
LAV
10'x6 J
DOUBLE
DOORS
10'OR 12
ROLLUP DOOR
10' OR 12'
ROLLUP DOOR
HR
City of Renton
Renton Well 5A
Possible Building Layout
January 2007
FIGURE
Attachment B
Photos of Exterior Pressure Vessel installation
W:\2006\0697005.01_HDR Renton Well\b6-Corrspnd\6.03-OtherV2007\02cwk1tm.Pressure Vessel Placement TM.doc
*;?^^\\\\
fi
m