CONTRACT: City of Renton
CAG-18-020
CONTRACTOR: Canber Corporation
CHANGE ORDER: No.1
SUMMARY OF PROPOSED CHANGE:
Reason/Justification:
1. Contract Extension
Contract Change:
1. Contract Extension
DESCRIPTION:
item Qty. Description Unit Price Amount
No. _ w/WSST
1 Contract Extension $ - $
Total this Change Order: $
ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE REVISED CONTRACT
AMOUNT(WI WSST) AMOUNT THIS ORDER(W/WSST) l TOTAL AFTER CHANGE
$ 3,234.00 $ 3,234.00 $ - $ 3,234.00
Additional Calendar Days:
(75)Calendar Days to May 31,2018
The payment specified and agreed to in this change order includes every claim by the contractor for any
extra payment with respect to the work described in this change order. The work covered by this change
order must be performed under the same terms and conditions as that included in the original
agreement. All of the other terms of the original agreement remain in effect.