HomeMy WebLinkAboutSWP272714(1) W�A
4
� a �
��t4
taw 41
:<
va
sK.
a
f
Earth Consultants Inc.
Geotechnical Engineers.CwUbgisis&Environmental Scientists
' 4 a`
MOM ZMAIWEM
GEOTECHNICAL ENGINEERING STUDY
PROPOSED RENTON CROWN APARTMENTS
RENTON, WASHINGTON
E-7186 y� ta�
�
March 21, 1996
PREPARED FOR
RENTON CROWN LLC
1
'`---Ikaymond A. Coglas
Staff Engineer
S-
���WAS
' j4691
Robert S. Levinson, P.
' Principal 312'l�tk
wims 03/07/9 iK
' Earth Consultants, Inc.
1805 - 136th Place Northeast, Suite 201
Bellevue, Washington 98005
' (206) 643-3780
IMPORTANT INFORMATION
ABOUT YOUR
GEOTECHNICAL ENGINEERING REPORT
More construction problems are caused by site subsur- technical engineers who then render an opinion about
face conditions than any other factor. As troublesome as overall subsurface conditions, their likely reaction to
subsurface problems can be, their frequency and extent proposed construction activity, and appropriate founda-
have been lessened considerably in recent years, due in tion design. Even under optimal circumstances actual
' large measure to programs and publications of ASFE/ conditions may differ from those inferred to exist,
The Association of Engineering Firms Practicing in because no geotechnical engineer, no matter how
the Geosciences. qualified,and no subsurface exploration program, no
The following suggestions and observations are offered matter how comprehensive,can reveal what is hidden by
' to help you reduce the geotechnical-related delays, earth, rock and time. The actual interface between mate-
cost-overruns and other costly headaches that can rials may be far more gradual or abrupt than a report
occur during a construction project. indicates.Actual conditions in areas not sampled may
' differ from predictions. Nothing can be done to prevent the
unanticipated, but steps can be taken to help minimize their
A GEOTECHNICAL ENGINEERING impact. For this reason, most experienced owners retain their
REPORT IS BASED ON A UNIQUE SET geotechnical consultants through the construction stage, to iden-
tify variances,conduct additional tests which may be
OF PROJECT-SPECIFIC FACTORS needed, and to recommend solutions to problems
A geotechnical engineering report is based on a subsur-
face exploration plan designed to incorporate a unique SUBSURFACE CONDITIONS
set of project-specific factors. These typically include:
the general nature of the structure involved, its size and CAN CHANGE
configuration; the location of the structure on the site
and its orientation; physical concomitants such as Subsurface conditions may be modified by constantly-
access roads, parking lots, and underground utilities, changing natural forces. Because a geotechnical engi-
and the level of additional risk which the client assumed neering report is based on conditions which existed at
by virtue of limitations imposed upon the exploratory the time of subsurface exploration, construction decisions
r program. To help avoid costly problems, consult the should not be based on a geotechnical engineering report whose
geotechnical engineer to determine how any factors adequacy may have.been affected by time. Speak with the geo-
which change subsequent to the date of the report may technical consultant to learn if additional tests are
affect its recommendations. advisable before construction starts.,
Unless your consulting geotechnical engineer indicates Construction operations at or adjacent to the site and
otherwise. your geotechnical engineering report should not natural events such as floods,earthquakes or ground-
be used: water fluctuations may also affect subsurface conditions
.When the nature of the proposed structure is and, thus, the continuing adequacy of a geotechnical
changed, for example, if an office building will be report. The geotechnical engineer should be kept
erected instead of a parking garage, or if a refriger- apprised of any such events,and should be consulted to
e ated warehouse will be built instead of an unre- determine if additional tests are necessary
frigerated one;
.when the size or configuration of the proposed GEOTECHNICAL SERVICES ARE
structure is altered; PERFORMED FOR SPECIFIC PURPOSES
.when the location or orientation of the proposed AND PERSONS
structure is modified;
.when there is a change of ownership, or Geotechnical engineers' reports are prepared to meet
' •for application to an adjacent site. the specific needs of specific individuals. A report pre-
Geotechnical engineers cannot accept responsibility for problems pared for a consulting civil engineer may not be ade-
which may develop if they are not consulted after factors consid- quate for a construction contractor,or even some other
' ered in their report's development have changed. consulting civil engineer. Unless indicated otherwise,
this report was prepared expressly for the client involved
and expressly for purposes indicated by the client. Use
MOST GEOTECHNICAL "FINDINGS" by any other persons for any purpose,or by the client
ARE PROFESSIONAL ESTIMATES for a different purpose, may result in problems. No indi-
vidual other than the client should apply this report for its
Site exploration identifies actual subsurface conditions intended purpose without first conferring with the geotechnical
only at those points where samples are taken, when engineer. No person should apply this report for any purpose
they are taken. Data derived through sampling and sub- other than that originally contemplated without first conferring
sequent laboratory testing are extrapolated by geo- with the geotechnical engineer.
A GEOTECHNICAL ENGINEERING der the mistaken impression that simply disclaiming re-
REPORT IS SUBJECT TO sponsibility for the accuracy of subsurface information
always insulates them from attendant liability. Providing
MISINTERPRETATION the best available information to contractors helps pre-
Costly problems can occur when other design profes- vent costly construction problems and the adversarial
sionals develop their plans based on misinterpretations attitudes which aggravate them to disproportionate '
of a geotechnical engineering report. To help avoid scale.
these problems, the geotechnical engineer should be READ RESPONSIBILITY
retained to work with other appropriate design profes- ,
sionals to explain relevant geotechnical findings and to CLAUSES CLOSELY
review the adequacy of their plans and specifications
relative to geotechnical issues. Because geotechnical engineering is based extensively
on judgment and opinion, it is far less exact than other '
design disciplines. This situation has resulted in wholly
unwarranted claims being lodged against geotechnical
BORING LOGS SHOULD NOT BE consultants. To help prevent this problem, geotechnical
engineers have developed model clauses for use in writ- ,
SEPARATED FROM THE ten transmittals. These are not exculpatory clauses
ENGINEERING REPORT designed to foist geotechnical engineers' liabilities onto
someone else. Rather, they are definitive clauses which ,
Final boring logs are developed by geotechnical engi- identify where geotechnical engineers' responsibilities
neers based upon their interpretation of field logs begin and end. Their use helps all parties involved rec-
(assembled by site personnel)and laboratory evaluation ognize their individual responsibilities and take appro-
of field samples. Only final boring logs customarily are priate action. Some of these definitive clauses are likely '
included in geotechnical engineering reports. These logs to appear in your geotechnical engineering report, and
should not under any circumstances be redrawn for inclusion in you are encouraged to read them closely. Your geo-
architectural or other design drawings, because drafters technical engineer will be pleased to give full and frank
may commit errors or omissions in the transfer process. answers to your questions. '
Although photographic reproduction eliminates this
problem, it does nothing to minimize the possibility of OTHER STEPS YOU CAN TAKE TO
contractors misinterpreting the logs during bid prepara-
tion. When this occurs, delays, disputes and unantici- REDUCE RISK
pated costs are the all-too-frequent result. Your consulting geotechnical engineer will be pleased to
To minimize the likelihood of boring log misinterpreta- discuss other techniques which can be employed to mit- '
tion, give contractors ready access to the complete geotechnical igate risk. In addition, ASFE has developed a variety of
engineering report prepared or authorized for their use materials which may be beneficial. Contact ASFE for a
Those who do not provide such access may proceed un- complimentary copy of its publications directory.
Published by '
THE ASSOCIATION
OF ENGINEERING FIRMS
PRACTICING IN THE GEOSCIENCES
8811 Colesville Road/Suite G 106/Silver Spring, Maryland 20910/(301) 565-2733
0788/3M ,
Earth Consultants Inc.
i
Geotechnical Engineers.Geologists&Environmental Scientists
March 21 , 1996 E-7186
Renton Crown LLC
704 Northeast Northlake Way
Seattle, Washington 98105
' Attention: Mr. Mark Lundberg
Dear Mr. Lundberg:
' We are pleased to submit our report titled "Geotechnical Engineering Study, Proposed Renton
Crown Apartments, Renton, Washington." This report presents the results of our field
exploration, selective laboratory tests, engineering analyses, and review of the following
geotechnical engineering studies previously performed at the subject site:
' 1 ) Shannon & Wilson, Inc., Boring and Test Pit Logs, dated August 1979 and June
1988.
2) Golder Associates Geotechnical Engineering Study 883-1538, dated November
1988.
Based on the results of our study,it is our opinion the proposed development is geotechnically
feasible. Medium to high plasticity silt was predominantly encountered at our test pit
' locations. Some shallow deposits of silty sand were also encountered at some of the test pit
locations. With the exception of test pits T-P-8 through TP-11 , the medium to high plasticity
silt encountered at our test pit locations was generally soft to depths of six to twelve feet
' below existing grades. The soft silt was encountered to depths of two to three feet below
existing grades at test pits TP-8 through TP-1 1 . Below the upper deposits of soft silt, stiff,
medium to high plasticity silt was encountered to the depths explored.
' Varying depths of fill were generally encountered at test pits TP-3, TP-7, and TP-8 through
TP-1 1 . Fill depths generally ranged between approximately two feet to twelve feet with the
' deepest fill encountered at test pits TP-3 and TP-7. Slide debris was encountered at test pit
locations TP-2, TP-4 and TP-5. This deposit was characterized by approximately six feet to
ten feet of loose silty sand and silt, with isolated zones of moderate to heavy organics.
In our opinion, the proposed buildings can be supported on conventional spread and
continuous footings bearing on the native stiff silt, or on at least two feet of structural fill,
' provided the recommendations contained in this report are incorporated into the final design
recommendations.
1805 - 136th Place N.E., Suite 201, Bellevue, Washington 98005
' Bellevue (206)643-3780 Seattle(206)464.1584 FAX(206) 746.0860 Tacoma(206) 272-6608
Renton Crown LLC E-7186
March 21, 1996 Page 2
iWe appreciate this opportunity to have been of service to you. If you have any questions, or
if we can be of further assistance, please call.
Respectfully submitted,
EARTH CONSULTANTS, INC.
�r
1
Robert S. Levinson, P.E.
Principal
RAC/RSL/kml
1
1
1
1
1
i
i
1
TABLE OF CONTENTS
E-7186
' PAGE
INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Project Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
' SITE CONDITIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Surface 2
Subsurface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
' Fill/Slide Debris . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Native Silt . . . . . . . . . 3
Groundwater . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
' Laboratory Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
DISCUSSION AND RECOMMENDATIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
General . . . . . . . . . . . . . . . . . . . . . . 4
. . . . . . . . . . . . . . . . . . . . . . . . . . . .
Site Preparation and General Earthwork 4
Foundations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Slab-on-Grade Floors . . . . . . . : : : : : : : : : : : : : : : : : : : : : : : : :' : : : : ; : : : : 7
Seismic Design Considerations 7
Excavations and Slopes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Site Drainage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Utility Support and Backfill 9
Pavement Areas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
LIMITATIONS 10
Additional Services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
APPENDICES
' Appendix A Field Exploration
Appendix B Laboratory Test Results
ILLUSTRATIONS
' Plate 1 Vicinity Map
Plate 2 Test Pit Location Plan
Plate 3 Typical Footing Subdrain Detail
Plate 4 Utility Trench Backfill
Plate Al Legend
' Plates A2 through Al Test Pit Logs
GEOTECHNICAL ENGINEERING STUDY
PROPOSED RENTON CROWN APARTMENTS
RENTON, WASHINGTON
' E-7186
INTRODUCTION
' General
' This report presents the results of the geotechnical engineering study completed by Earth
Consultants, Inc. (ECI) for the proposed Renton Crown Apartments located along Renton
Avenue South in Renton, Washington. The general location of the site is shown on the
Vicinity Map, Plate 1 . The purpose of this study was to explore the subsurface conditions at
the site, and based on the conditions encountered, develop geotechnical recommendations
for the proposed site development. In developing these recommendations, we reviewed
subsurface information at the site previously obtained by Golder Associates and Shannon &
Wilson, Inc. At the time our study was performed, the building location, and our exploratory
locations were approximately as shown on the Test Pit Location Plan, Plate 2.
Project Description
We understand it is planned to develop the site with approximately seven, two to three story,
wood-framed apartment buildings with first-floor level parking garages at Buildings D, E and
G only. The remainder of the site will consist of asphalt pavement areas and landscaping.
We understand considerable regrading of the site will be required. It appears the most
substantial cuts will be required primarily along the north and east portion of the site. We
understand the existing 4H:1 V (Horizontal:Vertical) slope along the south side of the site will
be regraded to an inclination of approximately 3H:1 V.
At the time this report was written, specific structural design information was not available.
However, based on our experience with similar projects, we would anticipate wall loads of
approximately two kips per lineal foot, and floor loading of less than seventy (70) pounds per
square foot.
If any of the above design criteria are incorrect or change, we should be consulted to review
' the recommendations contained in this report. In any case, ECI should be retained to perform
a general review of the final design.
Earth Consultants, Inc.
' GEOTECHNICAL ENGINEERING STUDY
Renton Crown LLC E-7186
March 21 , 1996 Page 2
SITE CONDITIONS
Surface
' The subject site is located along the west side of Rainier Avenue South, approximately in the
vicinity of 119th Street South in Renton, Washington (see Plate 1 , Vicinity Map). The
property is irregularly shaped and is approximately 7.5 acres in size. The east boundary of
' the property borders approximately 530 feet of Rainier Avenue South. An existing warehouse
and office development is present along a portion of the north property boundary. No
developments are immediately adjacent to the western and southern boundaries of the
property. There are, however, residential developments along the top of the bluff that borders
the west and northwesterly sides of the site.
' The predominant topographic features include a ravine and the previously mentioned bluff that
generally trend north to south along the west side of the site. A small drainage course runs
1 to the north along the bottom of the ravine at the base of the bluff. The site generally slopes
down to the north with a maximum elevation change of approximately ninety feet. It is
evident that the site has experienced some disturbance in the form of benched cuts along the
middle and lower east portions of the site. It appears some fill and slide debris have also been
deposited primarily along the north and portions of the east sides of the site. An abandoned
asphalt road runs along a portion of the north side of the site and accesses the upper bench
trending east to west through the middle of the site.
The site vegetation consists primarily of grasses with an abundance of blackberry and scotch
broom. Deciduous trees are present along the west and northwestern portions of the site,
along the ravine areas, and along the lower southeastern portions of the site.
' Subsurface
The site was explored by excavating eleven test pits at the approximate locations shown on
' Plate 2. Please refer to the Test Pit Logs, Plates A2 through Al2, for a more detailed
description of the conditions encountered at each location explored. The following is a
generalized description of the subsurface conditions encountered.
Fill/Slide Debris
' Fill and some slide debris was encountered primarily at test pit locations along the north and
east portions of the site. The previously referenced Golder Associates Study indicates varying
' depths of fill are also located along the west side of the site. The fill ranged in depth between
approximately two feet to twelve feet, and was encountered at Earth Consultants test pit
locations TP-1 , TP-3, and TP-7 through TP-11 . The fill was wet, and was generally
characterized as soft, medium to high plasticity silt and loose silty sand.
Earth Consultants, Inc.
GEOTECHNICAL ENGINEERING STUDY
Renton Crown LLC E-7186
March 21, 1996 Page 3
It appears some slide debris ranging in depths between approximately six to ten feet is present
' at test pit locations TP-2, TP-4 and TP-5. It appears this deposit has resulted from periodic
instability of the upslope regions of the site, primarily along the ravine located on the west
side of the site. The slide debris was wet, and contained a significant amount of organic
material. The soil conditions were generally characterized as loose silty sand and soft,
medium to high plasticity silt.
' Native Silt
Below the fill and slide debris, medium to high plasticity silt was encountered to the depths
explored. The silt was stiff and generally fractured. Some mottling was observed along the
upper portions of this deposit.
Groundwater
1 Light groundwater seepage was encountered at varying depths in the majority of the test pits.
These seepage zones generally occurred at the contact between the loose fill and slide debris,
and the native silt. Groundwater levels and the magnitude of seepage, however, are not
static; therefore, fluctuations can be expected depending on the season, amount of rainfall,
surface water runoff, and other factors. Generally, the water level is higher and seepage rate
is greater in the wetter winter months (typically October through May).
Laboratory Testing
' Laboratory tests were conducted on several representative soil samples to verify or modify
the field soil classification and to evaluate the general physical properties and engineering
characteristics of the soil encountered. Moisture content tests were performed on all samples.
' The results of laboratory tests performed on specific samples are provided at the appropriate
sample depth on the individual test pit logs. It is important to note that these test results may
not accurately represent the overall in-situ soil conditions. Our geotechnical recommendations
are based on our interpretation of these test results and their use in guiding our engineering
judgement. ECI cannot be responsible for the interpretation of these data by others.
' In accordance with our Standard Fee Schedule and General Conditions, the soil samples for
this project will be discarded after a period of fifteen days following completion of this report
Iunless we are otherwise directed in writing.
' Earth Consultants, Inc.
GEOTECHNICAL ENGINEERING STUDY
Renton Crown LLC E-7186
March 21, 1996 Page 4
rDISCUSSION AND RECOMMENDATIONS
' General
Based on the results of our study, it is our opinion that the proposed development can be
' constructed generally as planned provided the recommendations contained in this report are
incorporated into the final design. The critical geotechnical aspects of the planned
development are primarily associated with foundation support and reducing post-construction
differential settlements. Based on our understanding of the proposed site grading and building
locations, it appears some of the buildings will be located in zones of cut/fill transition. The
western two buildings on the north side of the site, and the southeast building appear to be
at greatest risk for differential movement due to cut/fill transitions. Portions of the two
northern buildings may be located in zones of existing fill ranging in depths between
approximately four to six feet.
1 To help reduce post-construction differential settlements, portions of the buildings located in
zones of existing fill, or on newly constructed fill, should be supported on at least two feet
of structural fill. Additional removal of unsuitable fills may be required, depending upon the
condition of the existing fill and final grades. Building slabs not supported on competent
native soils should be supported on at least one foot of structural fill. The requirements for
' structural fill are defined in the "Site Preparation And Genera/ Earthwork" section of this
report.
' This report has been prepared for specific application to this project only and in a manner
consistent with that level of care and skill ordinarily exercised by other members of the
profession currently practicing under similar conditions in this area for the exclusive use of
' Renton Crown LCC and their representatives. No warranty, expressed or implied, is made.
This report, in its entirety, should be included in the project contract documents for the
information of the contractor.
' Site Preparation and General Earthwork
The building and pavement areas should be stripped and cleared of all organic matter, and any
other deleterious material. Based on the thickness of the root mat and topsoil encountered
during our exploration, we estimate a stripping depth of approximately_ four to six inches.
However, these depths may vary and will depend on conditions encountered during the
stripping operation. In building areas where greater than two feet of fill is to be placed, and
' in paved areas with more than one foot of fill, the existing surface need not be stripped.
However, long grasses should be cut and trees and shrubs should be removed prior to fill
placement. Stripped materials should not be mixed with any materials to be used as structural
fill.
' Earth Consultants, Inc.
GEOTECHNICAL ENGINEERING STUDY
Renton Crown LLC E-7186
March 21 , 1996 Page 5
Once stripping operations are complete, excavations to building and pavement subgrades can
begin. Pavement subgrades and the ground surface where structural fill is to be placed,
should be proofrolled. All proofrolling should be performed under the observation of a
representative of ECL Any areas that are found to be yielding or unstable should be repaired
either by re-compacting the area, or overexcavating and replacing with structural fill. The use
of a woven geotextile placed on the overexcavated surface may be useful in bridging over
' unstable areas.
' Existing utility pipes to be abandoned should be plugged or removed so that they do not
provide a conduit for water and cause soil saturation and stability problems.
' Due to the fine-grained nature and in-situ moisture content of the soils encountered during our
exploration, the use of on-site soils as structural fill may be difficult. Much of the existing fill
encountered during our exploration was significantly above its optimum moisture content,
1 therefore, considerable moisture conditioning of these soils would be required. The moisture
content of the competent native silt encountered during our exploration was generally at or
slightly above its optimum moisture content. These soils will degrade quickly when exposed
to wet weather conditions. The success of compacting these soils to the requirements of
structural fill will depend on the moisture content of the soil at the time of construction. To
help stabilize wet soils, the use of cement, or cement kiln dust may be considered.
1 Structural fill is defined as any compacted fill placed under buildings, roadways, slabs,
pavements, or any other load-bearing areas. Structural fill under floor slabs and footings
' should be placed in horizontal lifts not exceeding twelve (12) inches in loose thickness and
compacted to a minimum of 90 percent of its laboratory maximum dry density, except for the
top twelve (12) inches which should be compacted to 95 percent. The maximum dry density
should be determined in accordance with ASTM Test Designation D-1557-78 (Modified
Proctor). The fill materials should be placed at or near the optimum moisture content. Fill
under pavements and walks should also be placed in horizontal lifts and compacted to 90
' percent of maximum density except for the top twelve (12) inches which should be
compacted to 95 percent of maximum density.
Earth Consultants, Inc.
' GEOTECHNICAL ENGINEERING STUDY
Renton Crown LLC E-7186
March 21, 1996 Page 6
Foundations
Assuming compliance with the recommendations outlined in the "Site Preparation and Genera/
p
Earthwork" section of this report, the proposed structure may be supported on a conventional
spread and continuous footing foundation bearing on competent native soils or on a minimum
of two feet of structural fill. As stated previously, it appears the western two buildings along
the north side of the site will be partially located in zones of existing uncontrolled fill. To help
resist differential movement at the cut/fill transitions, additional reinforcement in the
foundation elements, ten feet on either side of the transition, should be considered. All
' footing overexcavations performed in the uncontrolled fill zones should be observed by a
representative of ECI to determine if additional overexcavation is required. Structural fill
placed in overexcavations should extend outward from the edge of the footing a distance
equal to one-half the depth of the overexcavation. Footing excavations performed in
competent native soils should also be observed by a representative of ECI prior to placement
of foundation elements.
Exterior foundations elements should be placed a minimum depth of eighteen (18) inches
below final exterior grade. Interior spread foundations can be placed at a minimum depth of
twelve (12) inches below the top of slab, except in unheated areas, where interior foundation
elements should be founded at a minimum depth of eighteen (18) inches.
With foundation support obtained as described, an allowable soil bearing capacity of two
thousand five hundred (2,500) pounds per square foot (psf) can be used for foundations
supported on competent native soils or structural fill. Continuous and individual spread
footings should have minimum widths of eighteen (18) and twenty-four (24) inches,
respectively. Loading of this magnitude would be provided with theoretical factor-of-safety
in excess of three against actual shear failure. With structural loading as expected, total
settlement in the range of one inch is anticipated with differential movement of about
three-quarters of one inch. Most of the anticipated settlements should occur during
construction as dead loads are applied.
Horizontal loads can be resisted by friction between the base of the foundation and the
supporting soil and by passive soil pressure acting on the face of the buried portion of the
' foundation. For the latter, the foundation must be poured "neat" against the competent
native soils, or backfilled with structural fill. For frictional capacity, a coefficient of 0.35 can
be used. For passive earth pressure, the available resistance can be computed using an
tequivalent fluid pressure of three hundred (300) pcf. These lateral resistance values are
allowable values, a factor-of-safety of 1 .5 has been included. As movement of the foundation
element is required to mobilize full passive resistance, the passive resistance should be
neglected if such movement is not acceptable.
Earth Consultants, Inc.
1 GEOTECHNICAL ENGINEERING STUDY
Renton Crown LLC E-7186
March 21, 1996 Page 7
1
Slab-on-Grade Floors
Slab-on-grade floors may be supported on competent or recom acted native soil, or on at least
9 Y PP P P
one foot of structural fill. The slab should be provided with a minimum of four inches of free-
draining sand or gravel. In areas where slab moisture is undesirable, a vapor barrier such as
a 6-mil plastic membrane may be placed beneath the slab. Two inches of damp sand may be
' placed over the membrane for protection during construction and to aid in curing of the
concrete.
Seismic Design Considerations
The Puget Lowland is classified as a Seismic Zone 3 by the Uniform Building Code (UBC). The
largest earthquakes in the Puget Lowland are widespread and have been subcrustal events,
ranging in depth from thirty (30) to fifty-five (55) miles. Such deep events have exhibited no
surface faulting.
Structures are subject to damage from earthquakes due to direct and indirect action. Direct
action is represented by shaking. Indirect action is represented by foundation soil failures and
is typified by ground failure or liquefaction.
The UBC Earthquake regulations contain a static force procedure and a dynamic force
procedure for design base shear calculations. Based on the encountered soil conditions, it is
our opinion that a site coefficient of SZ = 1 .2 should be used for the static force procedure
as outlined in Section 1628 of the 1994 UBC. For the dynamic force procedure outlined in
' section 1929 of the 1994 UBC, the curve for deep cohesionless or stiff clay soils (Soil
Type 2) should be used for Figure 16-3, Normalized Response Spectra Shapes.
Liquefaction is a phenomenon in which soils lose all shear strength for short periods of time
during an earthquake. Groundshaking of sufficient duration results in the loss of grain to grain
contact and rapid increase in pore water pressure, causing the soil to behave as a fluid. To
have a potential for liquefaction, a soil must be cohesionless with a grain size distribution of
a specified range (generally sands and silt); it must be loose to medium dense; it must be
below the groundwater table; and it must be subject to sufficient magnitude and duration of
groundshaking. The effects of liquefaction may be large total and/or differential settlement
for structures founded in the liquefying soils.
1 Provided the recommendations in this report are followed, in our opinion, the potential for
liquefaction on the site is low.
Earth Consultants, Inc.
GEOTECHNICAL ENGINEERING STUDY
Renton Crown LLC E-7186
March 21, 1996 Page 8
Excavations and Slopes
The followinginformation is provided solely as a service to our client. Under no circumstances
P Y
should this information be interpreted to mean that ECI is assuming responsibility for
construction site safety or the Contractor's activities; such responsibility is not being implied
and should not be inferred.
rIn no case should excavation slopes be greater than the limits specified in local, state and
Federal safety regulations. Based on the information obtained from our field exploration, the
' soils encountered would be classified by OSHA as Type C for the existing fill and upper soft
portions of the native silt, and Type B for the competent native silt. As such, temporary cuts
greater than four feet in height should be sloped at an inclination no steeper than 1 .51-1:1 V in
the existing fill and upper soft portions of the native silt, and no greater than 1 H:1 V in the
competent native silt. If slopes of these inclinations, or flatter, cannot be constructed,
temporary shoring may be necessary. This shoring will help protect against slope or
1 excavation collapse, and will provide protection to workers in the excavation. If temporary
shoring is required, we will be available to provide shoring design criteria, if requested.
All permanent cut and fill slopes should be inclined no steeper than 2H:1 V. All cut slopes
should be observed by ECI during excavation to verify that conditions are as anticipated.
Supplementary recommendations can then be developed, if needed, to improve stability,
including flattening of slopes or installation of surface or subsurface drains In any case,
water should not be allowed to flow uncontrolled over the top of any slopes.
' All permanently exposed slopes should be seeded with an appropriate species of vegetation
to reduce erosion and improve stability of the surficial layer of soil.
1 Site Drainage
The site must be graded such that surface water is directed off the site. Water must not be
' allowed to stand in any area where buildings, slabs or pavements are to be constructed.
During construction, loose surfaces should be sealed at night by compacting the surface to
reduce the potential for moisture infiltration into the soils. Final site grades must allow for
' drainage away from the building foundations. The ground should be sloped at a gradient of
three percent for a distance of at least ten feet away from the buildings, except in paved
areas, which can be sloped at a gradient of two percent.
Earth Consultants, Inc.
' GEOTECHNICAL ENGINEERING STUDY
Renton Crown LLC E-7186
March 21 , 1996 Page 9
Perimeter footing drains should be installed around portions of the proposed buildings where
infiltrating water can damage interior finishes. Drains should also be placed around the
perimeter of below grade foundation walls to help reduce hydrostatic pressures on the wall.
The footing drain should be installed at or just below the invert of the footing, with a gradient
' sufficient to initiate flow. A typical detail is provided on Plate 3. Under no circumstances
should roof downspout drain lines be connected to the footing drain system. All roof
downspouts must be separately tightlined to discharge. Cleanouts should be installed at
strategic locations to allow for periodic maintenance of the footing drain and downspout
tightline systems.
Utility Support and Backfill
Based on the soil conditions encountered at the time of our exploration, the native soil should
provide adequate support for utilities. If remedial measures are necessary to provide adequate
utility support, the unsuitable soil can be overexcavated and replaced with a suitable ballast
and pipe bedding material such pea gravel.
Utility trench backfill is a primary concern in reducing the potential for settlement along utility
alignments, particularly in pavement areas. It is important that each section of utility line be
adequately supported in the bedding material. The material should be hand tamped to ensure
support is provided around the pipe haunches. Fill should be carefully placed and hand
tamped to about twelve (12) inches above the crown of the pipe before any heavy
compaction equipment is brought into use. The remainder of the trench backfill should be
placed in lifts having a loose thickness of less than twelve (12) inches. A typical trench
backfill section and compaction requirements for load supporting and non-load supporting
areas is presented on Plate 4.
' Pavement Areas
The adequacy of site pavements is related in part to the condition of the underlying subgrade.
' To provide a properly prepared subgrade for pavements, the subgrade should be treated and
prepared as described in the "Site Preparation and General Earthwork" section of this report.
Native cut surfaces should be in a firm and unyielding condition when proofrolled and fill areas
should meet the requirements of structural fill. In localized areas of soft, wet or unstable
subgrade, a greater thickness of structural fill or crushed rock may be needed to stabilize
these localized areas.
Earth Consultants, Inc.
' GEOTECHNICAL ENGINEERING STUDY
Renton Crown LLC E-7186
March 21, 1996 Page 10
The following pavement section for lightly-loaded areas can be used:
• Two inches of asphalt concrete (AC) over four inches of crushed rock base (CRB)
material, or
• Two inches of AC over three inches of asphalt treated base (ATB) material.
Heavier truck-traffic areas will require thicker sections depending upon site usage, pavement
life and site traffic. As a general rule, the following sections can be considered for truck-
trafficked areas:
• Three inches of AC over six inches of CRB, or
• Three inches of AC over four inches of ATB.
These pavement thicknesses may be modified based on anticipated traffic loads and
frequency.
Asphalt concrete (AC), asphalt treated base (ATB), and crushed rock base (CRB) materials
should conform to WSDOT specifications. All rock base should be compacted to at least 95
percent of the ASTM D-1557-78 laboratory test standard.
LIMITATIONS
Our recommendations and conclusions are based on the site materials observed, selective
laboratory testing and engineering analyses, the design information provided to us by you, and
our experience and engineering judgement. The conclusions and recommendations are
professional opinions derived in a manner consistent with that level of care and skill ordinarily
exercised by other members of the profession currently practicing under similar conditions in
this area. No warranty is expressed or implied.
The recommendations submitted in this report are based upon the data obtained from the test
pits. Soil and groundwater conditions between test pits may vary from those encountered.
The nature and extent of variations between our exploratory locations may not become
evident until construction. If variations do appear, ECI should be requested to reevaluate the
recommendations of this report and to modify or verify them in writing prior to proceeding
with the construction.
Earth Consultants, Inc.
GEOTECHNICAL ENGINEERING STUDY
Renton Crown LLC E-7186
March 21, 1996 Page 11
Additional Services
As the engineer of record, ECI should be retained to perform a general review of the final
9 P
design and specifications to verify that the earthwork and foundation recommendations have
' been properly interpreted and implemented in the design and in the construction
specifications.
ECI should also be retained to provide geotechnical services during construction. This is to
observe compliance with the design concepts, specifications or recommendations and to allow
design changes in the event subsurface conditions differ from those anticipated prior to the
start of construction. We do not accept responsibility for the performance of the foundation
or earthwork unless we are retained to review the construction drawings and specifications,
and to provide construction observation and testing services.
1
1
Earth Consultants, Inc.
' APPENDIX A
FIELD EXPLORATION
E-7186
Our field exploration was performed on March 15 1996. Subsurface conditions h p p at the site
were explored by excavating eleven test pits to a maximum depth of sixteen (16) feet below
the existing grade. The test pits were excavated by Five Ball Construction Inc.
Approximate test pit locations were determined by pacing from existing landmarks. The test
pit locations should be considered accurate only to the degree implied by the method used.
These approximate locations are shown on the Test Pit Location Plan, Plate 2. The field
exploration was continuously monitored by an engineer from our firm who classified the soils
encountered, maintained a log of each test pit, obtained representative samples, measured
groundwater levels, and observed pertinent site features.
All samples were visually classified in accordance with the Unified Soil Classification System
which is presented on Plate Al , Legend.
tLogs of the test pits are presented on Plates A2 through Al2. The final logs represent our
interpretations of the field logs and the results of the laboratory examination and tests of field
samples. The stratification lines on the logs represent the approximate boundaries between
soil types. In actuality, the transitions may be more gradual.
Earth Consultants, Inc.
1 84j}I - h0 ST N 411
AVALON
�!f N 38TH ST Q c• < 1
W SE ee
M 37TH ST Ala��t.o SE 877
KENNYDALE 36TH S > e E 36TH =
BEACH PARK h
8 7TH �°. 35TH ST, < ti/
ST 34TH < ST D W < sF
_ W Z
SOUTH POINT 33RD PL z t
iv NE 33RD
N 33RD ST £`
> CT :.>
COLEMAN `
POINT N 31ST ST N 31ST ST
N 3OTH a ST CREEK ;
RK
N 29TH
m N 287 PL ItNE 28TH ST
--- ---
N 28TH ST , z NE NE 27TH'
_LADE ` ti . 2TTH
z
CT
N.. 26TH Sr `�`w .
W Z
_ .... +KENN
24TN ST E w N Ll
1 SHI NGTON _ NERD ST m z<
�EN'
1
-r
{L� 'NE 20TH
w z
>
Sr Z r= HE IM
ST
BOAT LAU NCHNE
14TH 3 -
S
e,NEhORIAt � �, c
N� S 112TH ST �BEAGI`PARK', NE "12TH
1 2 AV N N
S .113 S
S 1 o m� ST RENTON
115 ST Lp AIRPORT
m SQ 115 fl PL BOAT LAUNCH NE 10TH
- -
1 6 a ST BOEING •� Z NE 10TH sr
S Film ST s RENTON . , •11 NE 9TH
<> S 117TH PL m PLANT
S Y
118TH > g zt- NE
n NE,-'.BkYN Q I STMAWR
z NE RTH z
1 !' PARK F S 1197H T E _ WE
S Ir120TH ST9 > �< p >
7 ST A w < N TH ST Nf
S ' 121ST D c m
S ;S �' 122ND I STI I TH Ns N H y 6TH vt.
1 7= S S' s 123RD ST t ! NW 1TH ST ? 'r" 2J5 M PARK -Zy} ST
4
6MM CT
Reference:
King County/Map 626
By Thomas Brothers Maps
Dated 1993
Vicinity Map
Earth Consultants Inc. Renton Crown Apartments
Geaechnical Engimners.Geologists&Environmental Scientists
Renton, Washington
' Proj. No. 7186 1 Drwn. GLS Date 3/15/96 Checked RAC Date Mar.'96 Plate 1
1
0
°
0
Slope To Drain
o
°
6 inch min. :o
o °
18 inch min.
.O.o• � _o ,' •e. C' ,e.�.s.' •.O- s� .o 00 roc
• I� O
4 inch min.
Diameter
Perforated Pipe
Wrapped in Drainage _ . o ° e
Fabric :.
i ee.
2 inch min.
2 inch min. / 4 inch max.
12 inch
min.
SCHEMATIC ONLY - NOT TO SCALE
NOT A CONSTRUCTION DRAWING
LEGEND
' Surface seal; native soil or other low permeability material.
Fine aggregate for Portland Cement Concrete; Section 9-03.1(2) of the
WSDOT Specifications.
' O brain pipe; perforated or slotted rigid PVC pipe laid with perforations or
slots facing down;tight jointed;with a positive gradient. Do not use flexible
corrugated plastic pipe. Do not tie building downspout drains into footing
lines. Wrap with Mirafi 140 Filter Fabric or equivalent.
Earth Consultants Inc. TYPICAL FOOTING SUBDRAIN DETAIL
ceo+��� M �&FwArmmmial�„fis,s Renton Crown Apartments
Renton, Washington
' Proj. No. 7186 FDrwn. GLS Date Mar.'96 Checked RAC Date 3/15/96 Plate 3
' Non-Load Supporting Floor Slab or
Areas Roadway Areas
- ° ° ° Varies
° 95 0 °
0 0 0 0
85 104
95 1 Foot Minimum
' Backfill
80. 90
Varies
o. .:.o_Q .• oo PIPE o '0'' •:
0 °.°A;; oo;0..°°a.a°�
"0.0'50 o�aoo: doo
' •.o'D�e. Oo. b•e°.oe••.0•'•.
O oo'• O•..COQ .•O'O.•
Bedding °'� o• .°.0'°' °°oo••od4° °. Varies
70-
'oo•. pdo 0.00 p•o,Ova
.0.p Ooo oOOpOo�Q u O6 .00°9'00, .0'Qo-o
o
OQ..oQ
LEGEND:
Asphalt or Concrete Pavement or Concrete Floor Slab
. o ° °,° .I Base Material or Base Rock
' Backfill; Compacted On-Site Soil or Imported Select Fill
Material as Described in the Site Preparation of the General
Earthwork Section of the Attached Report Text.
' 95 Minimum Percentage of Maximum Laboratory Dry Density as
O Determined by ASTM Test Method D 1557-78 (Modified Proctor),
Unless Otherwise Specified in the Attached Report Text.
Bedding Material; Material Type Depends on Type of Pipe and
Laying Conditions. Bedding Should Conform to the Manufacturers
Recommendations for the Type of Pipe Selected.
TYPICAL UTILITY TRENCH FILL
Earth Consultants Inc. Renton Crown Apartments
G("rchnical Fsglnef r.Ge01o9LUs&FnOrmn ilal Soo isls
Renton, Washington
' Proj. No. 7186 FDrwn. GLS Date Mar.'96 Checked RAC Date 3/15/96 Plate 4
¢ aa LLIzc — x ¢
r� rrG- m
APPENDIX A
Field Exploration
1
i
1
Earth Consultants, Inc.
MAJOR DIVISIONS GRAPH LETTER TYPICAL DESCRIPTION
SYMBOL SYMBOL
O GW Well-Graded Gravels, Gravel-Sand
Anddvel Clean Gravels Q o Q o Q o gW Mixtures, Little Or No Fines
Gravelly (little or no fines) M M
Coarse Soils GP Poorly-Graded Gravels,Gravel-
• � gp Sand Mixtures, Little Or No Fines
Grained �,
Soils More Than GM Silty Gravels,Gravel-Sand-
50% Coarse Gravels With gm Silt Mixtures
Fraction Fines(appreciable
Retained On amount of fines) GC Clayey Gravels, Gravel-Sand-
No. 4 Sieve gC Clay Mixtures
Sand o 00 'p SW Well-Graded Sands, Gravelly
And Clean Sand C o ' o C SW Sands, Little Or No Fines
Sandy (little or no fines) q ;; q;.;.:�
More Than a::> >% ' SP Poorly-Graded Sands, Gravelly
50% Material c:;;A<:::o;::;: s;<: Sp Sands, Little Or No Fines
' Larger Than More Than
No. 200 Sieve 50% Coarse SM Silty Sands Sand Silt Mixtures
Size Sands With Sm
Fraction F ines(appreciable
SevePassing No.4 amount of fines) ' SC Sc
Clayey Sands, Sand-Clay Mixtures
' ML Inorganic Silts&Very Fine Sands,Rock Flour,Silty-
ml Clayey Fine Sands;Clayey Silts w/ Slight Plasticity
Fine Silts Liquid Limit CL Inorganic Clays Of Low To Medium Plasticity,
' Grained And
Soils Clays Less Than 50 / Cl Gravelly Clays, Sandy Clays, Silty Clays, Lean
I I I I I QL Organic Silts And Organic
I I I I I OI Silty Clays Of Low Plasticity
I '1 More Than MH Inorganic Silts, Micaceous Or Diatomaceous Fire mh Sand Or Silty Soils
50% Material Silts
Smaller Than And Liquid Limit Cll norganic Clays Of High
No.200 Sieve Clays Greater Than 50 Ch Plasticity, Fat Clays
Size
OH Organic Clays Of Medium To High
Oh Plasticity, Organic Silts
Peat, Humus, Swamp Soils
Highly Organic Soils Pt With High Organic Contents
Topsoil y y Humus And Duff Layer
Fill Highly Variable Constituents
The discussion in the text of this report is necessary for a proper understanding of the nature
' of the material presented in the attached logs.
DUAL SYMBOLS are used to indicate borderline soil classification.
C TORVANE READING,tsf I 2"O.D. SPLIT SPOON SAMPLER
qu PENETROMETER READING,tsf
W MOISTURE,%dry weight 24'I.D. RING OR SHELBY TUBE SAMPLER
P SAMPLER PUSHED
* SAMPLE NOT RECOVERED i WATER OBSERVATION WELL
pcf DRY DENSITY, lbs.per cubic ft.
LL LIQUID LIMIT, % a DEPTH OF ENCOUNTERED GROUNDWATER
PI PLASTIC INDEX DURING EXCAVATION
t SUBSEQUENT GROUNDWATER LEVEL W/DATE
Earth Consultants Inc. LEGEND
\I I (iuv,i Iuw, 11-94-7rs,Oh A)61,,Is& SCNa11tsis
FProiNO.7186 I Date Mar. '96 1 Plate Al
Test Pit Log
Project Name: __F�hW of
Renton Crow7Artments
Job No. ed by: Date: Test Pit No.:
7186 CP 3 15 96 TP-1
' Excavation Contactor: Ground Surface Elevation:
Fiveball Construction t 75'
Notes:
° o r N a Surface Conditions: Depth of Topsoil &Sod 4-6": blackberry, duff
w r } a
O N O N N
ML FILL Brown medium to high plasticity SILT, soft,wet
' 1
2
' 38.2 3
4
5 ML Native, increasing stiffness, blocky structure
1 39.3 6
7
8
9
34.6 10
11
' 12
13
-becomes grad, medium plasticity, silt, medium stiff, moist, light
32.6 seepage at 13
14
' 15 Test pit terminated at 15.0 feet below existing grade. Groundwater
seepage encountered at 13.0 feet during excavation.
cD
a
N
Test Pit Log
CO Earth Consultants Inc. Renton Crown Apartments
r- Renton,Washington
J
F Proj.No. 7186 Dwn. GLS Date Mar.'96 Checked SDD Date 3/22/96 Plate A2
Subsurface conditions depicted represent our observations at the time and location of this exploratory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations.We cannot accept responsibility for the use or
interpretation by others of information presented on this log.
Test Pit Log
Project Name: Sheet of
Renton Crown Apartments 1 1
Job No. Logged by: Date: Test Pit No.:
7186 1 RAC 3 15 96 TP-2
1 Excavation Contactor: Ground Surface Elevation:
Fiveball Construction t 65'
Notes:
' INu o + ! N o Surface Conditions: Depth of Topsoil &Sod 4-6": blackberry, duff
I U z
� N A N N
SM FILL SLIDE DEBRIS: Blacl to brown silty fine to medium SAND, loose,
wet (moderate organics, branches, stump fragments)
1
2
' 20.6
3 -becomes brown, some interbedded silt
4
17.9 5
Q
-light seepage at 5.5'
6 ML Gray SILT, stiff, moist
29.3
7
8
9 Test pit terminated at 9.0 feet below existing grade. Groundwater
seepage encountered at 5.5 feet during excavation.
`D
a
N
Test Pit Log
Earth Consultants Inc. Renton Crown Apartments
CCO1CC EQO"MCeOi°�` """SdCndWS Renton,Washington
J
F Proj.No. 7186 Dwn. GLS Date Mar.'96 Checked SDD Date 3/22/96 Plate A3
Subsurface conditions depicted represent our observations at the time and location of this exploratory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations. a cannot accept responsibility for the use or
Interpretation by others of information presented on this log.
Test Pit Log
Project Name: Sheet of
Renton Crown Apartments 1 1
Job No. Logged by: Date: Test Pit No.:
7186 RAC 3 15 96 TP-3
Excavation Contactor: Ground Surface Elevation:
Fiveball Construction t 60'
Notes:
o t ! N o Surface Conditions: Depth of Topsoil &Sod 4-6": blackberry, duff
w r 0. .13 } a .
L N O N N
SM FILL- Brown to black silty fine to medium SAND, loose,wet
1
2 ML FILL: Becomes predominantlySILT, loose,wet
26.0 -organics (stum fragments)
3 -interbedded gray silt
4
5
6
7
8 -brown silty sand lens, some organics
30.7 9
10
11
' 12 NIL Gray medium high plasticity SILT, stiff, moist, slightly mottled
-light seepage at 12'
32.2 13
14 Test pit terminated at 14.0 feet below existing grade. Groundwater
seepage encountered at 12.0 feet during excavation.
`a a
N
N
Test Pit Log
Earth Consultants Inc. Renton Crown Apartments
N "t `4vie Enom 'Ceoi°�&Ewu"W`e"`wSdffw°" Renton,Washington
J
a Proj.No. 7186 Dwn. GLS Date Mar.'96 Checked SDD Date 3/22/96 Plate A4
1 Subsurface conditions depicted represent our observations at the time and location of this exploratory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations. a cannot accept responsibility for the use or
interpretation by others of information presented on this log.
1 Test Pit Log
Project Name: Sheet of
Renton Crown Apartments 1 1
Job No. Logged by: Date: Test Pit No.:
7186 RAC 3 15 96 TPA
Excavation Contactor: Ground Surface Elevation:
Fiveball Construction t 60'
Notes:
o r o N o Surface Conditions: Depth of Topsoil &Sod 4-6": blackberry, duff
m A ? U M � ?
M N N N
SM FILL SLIDE DEBRIS: Brown to gray silty fine to medium SAND, loose,
wet, interbedded—saridy SILT
1
' 2 ML FILL/SLIDE DEBRIS: Becomes predominantly SILT
30.2
3
4 -some organics (roots, branches)
5
-1'to 2' silty sand lens
6
41.6 7 -becomes gray,wet, mottled
8
9
17
26.1 10 NIL Brown medium to high plasticity SILT, stiff, moist, light seepage at 10'
11
12 Test pit terminated at 12.0 feet below existing grade. Groundwater
seepage encountered at 10.0 feet during excavation.
o
N
iTest Pit Log
a3 Earth Consultants Inc. Renton Crown Apartments
r- "t `e010Chrkal Ero`ms.Ce &awt°`sr""soffwms Renton, Washington
J
F Proj.No. 7186 Dwn. GLS Date Mar.'96 Checked SDD Date 3/22/96 Plate A5
Subsurface conditions depicted represent our observations at the time and location of this exploratory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations.We cannot accept responsibility for the use or
Interpretation by others of information presented on this log.
Test Pit Log
Project Name: Sheet of
Renton Crown A rtments 1 1 by: D
Job No. Logged ate: Test Pit No.:
7186 RAC 3 15 96 TP-rJ
Excavation Contactor. Ground Surface Elevation:
Fiveball Construction t 65'
Notes:
c s ! N o Surface Conditions: Depth of Topsoil &sod 4-6": blackberry, duff
w L + a U
M N N N
SM FILL/SLIDE DEBRIS: Brown to gray silty fine to medium SAND, loose,
wet, some interbedded silt
1
2 ML FILL SLIDE DEBRIS: Becomes predominantly SILT, mottled
-some Interb d si ty sand
1 3
41.1 4
' S
6
-light seepage at 7'
ML Brown to gray medium to high plasticity SILT, stiff, moist
34.0
a
9 Test pit terminated at 9.0 feet below existing grade. Groundwater
seepage encountered at 7.0 feet during excavation.
o
N
Test Pit Log
cc Earth Consultants Inc. Renton Crown Apartments
r, "t `eoio Er*Vaeem Ce°`°m°'°t°'""w&F W SdCrW°" Renton,Washington
J
F Proj.No. 7186 I Dwn. GLS Date Mar.'96 Checked SDD Date 3/22/96 Plate A6
Subsurface conditions depicted represent our observations at the time and location of this expPloratory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations.We cannot accept responsibility for the use or
Interpretation by others of information presented on this log.
Test Pit Log
Project Name: Sheet of
Renton Crown A rtments 1 1
Job No. Logged by: Date: Test Pit No.:
7186 RAC 3 15 96 TP-6
Excavation Contactor: Ground Surface Elevation:
Fiveball Construction t 80'
Notes:
U � L N o Surface Conditions: Depth of Topsoil &Sod 4f": scotch broom, grass
W C i"CL a
%j M 7 A L A 75
SM FILL Brown silty fine to medium SAND, loose, moist, interbedded silt
1
2 ML FILL Becomes predominantly SILT with silty sand lenses
P Y
41.1
3
4
5
6 ML Brown to gray medium to high plasticity SILT, stiff, moist
38.9
a
9
10
-seepage at 10'
-increasingly stiff
11
' 12
13
34.4 14
15
16 Test pit terminated at 16.0 feet below existing grade. Groundwater
seepage encountered at 10.0 feet during excavation.
L
o
N
Test Pit Log
CO Earth Consultants Inc. Renton Crown Apartments
Renton,Washington
J
F Proj.No. 7186 Dwn. GLS Date Mar.'96 Checked SDD Date 3/22/96 Plate A7
Subsurface conditions d%cted represent our observations at the time and location of this exploratory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations.We cannot accept responsibility for the use or
interpretation by others of information presented on this log.
Test Pit Log
Project Name: Sheet of
Renton Crown Apartments 1 1
Job No. Logged by: Date: Test Pit No.:
7186 RAC 3 15 96 TP-7
Excavation Contactor: Ground Surface Elevation:
Fiveball Construction t 50'
Notes:
o t ! N o Surface Conditions: Depth of Topsoil &Sod 4-6": blackberry, duff
w 'C + a U D
M " a ' � i � a
O V) N N
SM FILL Brown silty fine to medium SAND, loose, moist, some interbedded
silt
1
2 ML FILL' Becomes predominantly SILT gray to brown, mottled loose,wet
p Y � 9 Y
26.8
' 3
4
' 5
6
8 -organics (stump fragments, branches)
s ML Brown to gray medium to high plasticity SILT, medium stiff, moist, light
seepage at 8.5'
10
11
Test pit terminated at 11.0 feet below existing grade. Groundwater
seepage encountered at 8.5 feet during excavation.
tD a
N
N
Test Pit Log
W Earth Consultants Inc. Renton Crown Apartments
` ` "Horan` `Bmtow&rM Renton,Washington
J
a,- Proj.No. 7186 Dwn. GLS Date Mar.'96 Checked SDD Date 3/22/96 Plate A8
Subsurface conditions depicted represent our observations at the time and location of this exploratory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations, a cannot accept responsibility for the use or
interpretation by others of information presented on this log.
Test Pit Log
Project Name: Sheet of
Renton Crown A rtments 1 1
Job No, logged by: Date: Test Pit No.:
7186 RAC 3 15 96 TP-8
Excavation Contactor: Ground Surface Elevation:
Fiveball Construction t 45'
Notes:
t ° o r ! N o Surface Conditions: Depth of Topsoil &Sod 4-6": grass
w r Jo } ' a U
M M ? ILA 7 ]
� N � N N
ML FILL Grat to brown SILT and sandy SILT, loose, wet
1
27.7 2
s ML Brown to gray medium to high plasticity SILT and sandy SILT, stiff,
moist, light seepage at 2.5'
27.1 4
5
6 Test pit terminated at 6.0 feet below existing grade. ,Groundwater
seepage encountered at 2.5 feet during excavation.
i
I
N
N
Test Pit Log
CO Earth Consultants Inc. Renton Crown Apartments
GcooDaw Enorre'`'`�`RwVavr&rAWsuer'°" Renton,Washington
J
F Proj.No. 7186 1 Dwn. GLS I Date Mar.'96 Checked SDD Date 3/22/96 Plate A9
Subsurface conditions depicted represent our observations at the time and location of this expPlorstory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations.We cannot accept responsibility for the use or
interpretation by others of information presented on this log.
Test Pit Log
Project Name: Sheet of
Renton Crown A rtments 1 1
Job No. Logged by: Date: Test Pit No.:
7186 RAC 3 15 96 TP-9
Excavation Contactor: Ground Surface Elevation:
Fiveball Construction t 45'
Notes:
W r o } i ti o Surface Conditions: Depth of Topsoil &Sod 4-6": grass
a U
(%) ° 7 ° L` i 0 a
ML FILL Gray SILT and sandy SILT, loose,wet
1 2
37.8
3 ML Gray to brown medium to high plasticity SILT, stiff, moist, some
23.0 interbedded sandy silt
4
5 Test pit terminated at 5.0 feet below existing grade. No groundwater
seepage encountered during drilling.
o-
N
Test Pit Log
CO Earth Consultants Inc. Renton Crown Apartments
r- `'`°wa"cw Enonee Geoio� awwaimmsmSCdC71 mm Renton,Washington
J
Proj.No. 7186 Dwn. GLS Date Mar.'96 Checked SDD Date 3/22/96 Plate A10
Subsurface conditions depicted represent our observations at the time and location of this exploratory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations. a cannot accept responsibility for the use or
interpretation by others of information presented on this log.
Test Pit Log
Project Name: Sheet of
Renton Crown A rtments 1 1
Job No. Logged by: Date: Test Pit No.:
7186 RAC 3 15 96 TP-10
Excavation Contactor: Ground Surface Elevation:
Fiveball Construction t 45'
Notes:
L + ! H Q Surface Conditions: Depth of Topsoil &Sod 4-6": grass
W . a a
o H ° y v,
SM FILL Brown to gray silty fine to medium SAND, loose, wet, some
Interbedded silt
1
11.5 ML Brown to gray medium to high plasticity SILT, stiff, moist, some
2 interbedded sandy silt
3
4 Test pit terminated at 4.0 feet below existing grade. No groundwater
1 seepage encountered during excavation.
o
N
Test Pit Log
LD
CO Earth Consultants Inc. Renton Crown Apartments
r, "t ``°'° Er4*'O=Ccoio� ewVavnffMSoff"'m Renton,Washington
J
F Proj.No. 7186 Dwn. GLS Date Mar.'96 Checked SDD Date 3/22/96 Plate Al
Subsurface conditions depicted represent our observations at the time and location of this exploratory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations.We cannot accept responsibility for the use or
interpretation by others of information presented on this log.
Test Pit Log
Project Name: Sheet of
Renton Crown Apartments 1 1
Job No. Logged by: Date: Test Pit No.:
7186 RAC 3 15 96 TP-11
Excavation Contactor: Ground Surface Elevation:
Fiveball Construction f 45'
Notes:
° - - -
o L • N a Surface Conditions: Depth of Topsoil &Sod 4$": grass
' O N N N
ML FILL/SUDE DEBRIS: Gray SILT and sandy SILT, loose, wet, some
interbedded silty sand
t
2 NIL Brown to gray medium to high plasticity SILT, stiff, moist
9 Y 9
3
4 Test pit terminated at 4.0 feet below existing grade. Groundwater
seepage encountered at 2.0 feet during excavation.
N
N
Test Pit Log
Earth Consultants Inc. Renton Crown Apartments
le r- "t GeoWchn"Er**-ccmceo&o »&mwu"vr&rtwsdmideft
Renton, Washington
J
a. Prof.No. 7186 Dwn. GLS Date Mar.'96 Checked SDD Date 3/22/96 Plate Al
Subsurface conditions depicted represent our observations at the time and location of this exploratory hole,modified by engineering tests,
analysis and judgment. They are not necessarily representative of other times and locations.We cannot accept responsibility for the use or
interpretation by others of information presented on this log.
� a. a. mzm m
IMAM M M M M M M r r M M r ' M�
f
APPENDIX B
Laboratory Test Results
1
t
1
' Earth Consultants, Inc.
100
80
x 60
w
0
z
�_ CH
U
�- 40 �A-Line
U) - --
Q
J —
a.
C
20
� & 0
CL-ML OL
0 20 40 60 80 100
LIQUID LIMIT
Natural
' Key Boring/ Depth Soil Classification USCS L.L. P.L. PI. Water
Test Pit (ft) Content
' • TP-6 14 Gray SILT ML 49 30 19 34.4
Atterberg Limits Test Data
litEarth Consultants Inc. Renton Crown Apartments
Ge"t hnwalFnglrw rs,Geobgists&EnvironmentalSOeVisfs Renton, Washington
Proj. No. 7186 Date mar. '96 Plate B1
1 DISTRIBUTION
E-7186
4 Copies Renton Crown LLC
1 c/o Mark Lundberg
704 Northeast Northlake Way
Seattle, Washington 98105
1
1
1
1
M
1
1 _
1
1
1
1
i
1 Earth Consultants, Inc.
1
110 100 90 6o 70
60
50
120
r �
r G7P-4 1 _ 40
j
TP- 4 rP-113 -TP-7 r '-, 1 - i 7P-112
TP- -i- P-3 gel
r P-4 - , -• TP-8
' TP-5
Approximate Scale
r TP-toe -e -o-7P-
o- 11 0 50 100 200ft.
- TP-1 40
TP-6_ 1 -o- TP-10�-
8 2 LEGEND
-o
17P-109 TP-1 rP-110
_o�TP GB- TP-1 -:- Approximate Location of
Tp-g m ECI Test Pit, Proj. No.
7P- E-7186, Mar. 1996
-o-
130 -107 ' rP-103
r -o _ _ 0_ GrP-1 -o- Approximate Location of
7p- 0-0 �-105 7P-10M°- G Test Pit by Golder Assoc.,
TP-115 !- Aug. 11, 1988
- - TP-11 t�
G� 1
S'; ' _ 7P-101 -o- Approximate Location of
GrP-10_ -o- -o- rP- Test Pit by Shannon & Wilson,
-�8-1 TP-101 GB-1 June 23, 1988
sa
GB-1-o- Approximate Location of
Boring by Golder Assoc.,
130 ' �
Aug. 19, 1988
—O— 70
120 GTP-2
r 110 -- '� P-1 -0- Approximate Location of
110 120 130 130 120 110 Im 9n so Boring by Shannon & Wilson,
Aug. 10, 1979
' Proposed Building
9
1
Boring and Test Pit Location Plan
Earth Consultants Inc. Renton Crown Apartments
Ce"echn"FsghleM.G ologiSLS 6 Fnvirorvrkmlal$Cien1i5LS
Renton, Washington
Proj No. 7186 Drwn. GLS Date Mar.'96 Checked RAC Date 3/15/96 Plate 2
1
v � � b �#• � t'�`{'•"4R nF +�' d.� %.erg.r. '�` o1't'4+t.
.. � r p�.%.am. r -tee _ «' ••',. "���{;r � � �CS� �`x.'® 3+ *.ec.,
n
5
�9 �,-gig.b a .� ' ar a ��< ,� � yv -,�,• ,�� �.z, a, � '�«�.
R
J 5 F .as
e
OF
Nr
e v
n
a
^ `t', .� ,, ^� t �^+Lt ;� a � , � ;z f':w�� G .✓.�3'�:"°3- :# ,�•� sue:' �' �""��
.. e
a
a n
e °
x
* :'� � ...•' a ��a:. ,.vim .k. � '� �to ^';,�€":
em
n�
m
� y
o-
1
a`
a ,
s
w
n
e x ,
f4�-de. a
a
4
w`
gr
x .� ',#w. tea.. ,'�`" � < Mr,�,,, ,• •�. ON
r
r
K+a
� F��".:. �,�� �.��• �' i :�. °��;x, `sa. �� Pam'. ".�,., ' "_ z �" � 'a z�»� "��,
e x
r
s
r p�
x