Loading...
HomeMy WebLinkAboutSWP272285(2) • • • • • • GEOTECHNICAL REPORT • • • Farwest Steel SW 34th Street • Renton, Washington • • Project No. T-3064 • • 5 `Q .. Y�k 7 4 Terra Associates Inc. • ft l N • '- Prepared for: fu>%Sk y Farwest Steel Corporation • 101111 Eugene, Oregon • CITY vF HENTON� RECEIVED Y Februar 1 , 1996 � • MAY 0 S 1996 BUILDING DIVISIO �Z 4 aY I t° TES, Inc.TERRA ASSOCIA «' -a Consultants in Geotechnical Engineering, Geology i� and Environmental Earth Sciences February 1, 1996 Project No. T-3064 Mr. Dave Forester • Farwest Steel Corporation P.O. Box 889 • Eugene, Oregon 97440 Subject: Geotechnical Report Farwest Steel SW 34th Street • Renton,Washington Dear Mr. Forester: As requested, we have conducted a geotechnical engineering study for the subject project. The attached report presents our findings and recommendations for the geotechnical aspects of project design and construction. In general,the site is underlain by five to six feet of dense granular fill over several feet of organic silt or peat. The organic silt and peat are underlain by medium dense to dense alluvial sands. A six to seven foot thick layer of very soft silty clay is present at a depth of about 32 feet below existing site grades. Medium dense silty sand underlies the very soft silty clay. To reduce post-construction settlements to tolerable levels, we recommend that the building area be pre- loaded with a surcharge fill. Following successful completion of the surcharge program, the proposed steel fabrication facility may be constructed using conventional spread footings placed on the new structural fill pad. The intolerance of the rail cranes to foundation settlement requires using a pile foundation. The piles must extend through the very soft silty clay found at a depth of 32 feet in order to minimize the potential impact to them from differential settlement across the site as a result of long-term compression of the silty clay. 12525 Willows Road, Suite 101, Kirkland, Washington 98034 • Phone (206) 821-7777 • Mr. Dave Forester • February 1, 1996 • • We appreciate the opportunity to be of service during the initial design phase of this project and look forward to working with you during the design and construction phases. We trust the information • presented in this report is sufficient for your current needs. If you have any questions or need additional • information, please call. • Sincerely yours, • TER S INC. 1« �,OV cp v�Qs � • Kev if Robe Proj4ct 1,ngin i•' • 2 4< . U -\o Vh 02-/ - 96, • Theodore J¢ 'e er, P.E. • P� s1` i 97�`� • KPR/TJS:Ih cc: Mr. Bart Treece, Horton Dennis and Associates, Inc. • • • • • • • • • • • • • • • Project No. T-3064 • Page No. ii • TABLE OF CONTENTS Page 1.0 Project Description 1 2.0 Scope of Work 1 3.0 Site Conditions 2 3.1 Surface 2 . 3.2 Soils 2 3.3 Groundwater 3 • 3.4 Seismic Hazards 3 4.0 Discussion and Recommendations 3 4.1 General 3 4.2 Site Preparation and Grading 4 4.3 Surcharge and Settlements 5 4A Spread Footing Foundations 7 4.5 Rail Crane Foundation- Steel H-Piles 7 4.6 Rail Crane Foundation-Augercast Piling 8 4.7 Slab-on-grade Floors 8 4.8 Excavations 9 4.9 Utilities 9 4.10 Lateral Earth Pressures 9 4.11 Drainage 10 4.12 Pavements 10 5.0 Additional Services 11 6.0 Limitations 11 • Fi ures Vicinity Map Figure 1 • Exploration Location Plan Figure 2 Typical Settlement Marker Detail Figure 3 • Reinforced Soil Wall Section Figure 4 Appendix Field Exploration and Laboratory Testing Appendix A { Geotechnical Report • Farwest Steel SW 34th Street Renton, Washington 1.0 PROJECT DESCRIPTION The project will consist of constructing a new steel fabrication plant in Renton,Washington. The location of the project site is shown on the Vicinity Map, Figure 1. A conceptual site plan dated November 15, 1995, shows the location of the 96,000 square foot steel fabrication building and an attached 4,000 square foot office space. Finished floor grades are expected to be seven to eight feet above existing site grades. Access to the building will be from the south from an easement connecting to Lind Avenue. Traffic loading is expected to be heavy along the easement and in parking areas at the perimeter of the structure. • The steel fabrication facility will consist of steel-frame construction with dock-high floors. We understand that the lower portion of the perimeter walls may be constructed using pre-cast concrete tilt-up wall panels, with the ® upper portion finished with a metal skin exterior. Floor loadings are expected to be relatively high, possibly 800 to 1,000 pounds per square foot (pso. We understand you wish to support the building using a spread footing foundation. Overhead rail cranes will also be used in the facility for interior transport of materials and products. We understand the cranes have a low tolerance for differential settlement. lei The recommendations in the following sections of this report are based on our understanding of the project's • design features. We should review final design drawings and specifications to verify that our recommendations have been properly interpreted and incorporated into project design. 2.0 SCOPE OF WORK On January 9 through 11, 1996, we drilled six test borings at the site to depths ranging between 9 and 59 feet below existing site grades. Using the information obtained from the subsurface exploration, we performed analyses to develop geotechnical recommendations for project design and construction. Specifically, this report addresses the following: • Soil and groundwater conditions • Site preparation and grading • Foundation alternatives • Surcharge and settlements • Lateral earth pressures • Slab-on-grade floors • Utilities • Pavements • Drainage requirements • February 1, 1996 Project No. T-3064 3.0 SITE CONDITIONS • 3.1 Surface • The subject site is located on SW 34th Street between Lind Avenue and the East Valley Highway in Renton, Washington. This location is shown on Figure 1. The site is bounded to the south and north by a HomeBase store and SW 34th Street, respectively. Open, undeveloped parcels bound the site on the east and west. The site and vicinity are flat. We noted a large pile of fill and debris near the northwestern corner of the site. An absence of vegetation indicated that relatively recent grading was completed over the central and western portions of the site. The southwestern and eastern portions of the site contained areas of standing water and were vegetated with sparse grasses. The proposed access easement area in the vicinity of Boring B-2 was flat and contained very sparse grasses and some standing water. S Two existing railroad spur tracks enter the property from the north and curve westward v6thin the property to join a railroad line extending west across Lind Avenue. The tracks were raised slightly above surrounding grades. Shallow ditches filled with standing water were observed adjacent to each of the spur lines. No other obvious signs of surface water drainage were observed at the site. 3.2 Soils The soil conditions at the site generally consist of silty sand and sand with gravel fill overlying a variably thick layer of compressible peat or organic clayey silt. The compressible soils were underlain by generally competent sand deposits. The sand was found overlying loose to medium dense silty sand, with a layer of very soft silty • clay present at the northern portion of the site at a depth of about 32 feet. • All of our borings showed fill soil comprised of gravelly to silty sand to depths ranging from four to seven feet. This material was generally dense but became loose near the contact with the underlying native clayey silt and peat. The compressible native soil under the fill consisted mostly of gray to brown-gray, soft to stiff organic • silt, and silty clay occurring to depths of eight to nine feet. As shown by Boring B-1, dark brown soft to medium stiff peat underlies the fill to a depth of about 12 feet at the southern portion of the site. We observed black medium dense to very dense sand underlying the compressible strata. At Borings 13-1 and B- 6, we found dark gray silty sand with shells that was loose to medium dense at a depth of about 36 feet. Boring B-5 also showed gray very soft silty clay with shells overlying the gray silty sand between depths of about 30 and 37 feet. All borings were terminated within the black medium dense to very dense sand or gray medium dense silty sand with shells. Figures A-2 through A-7 in Appendix A present more detailed descriptions of the subsurface conditions encountered in the test borings. The approximate test boring locations are shown on Figure 2. k Page No. 2 • February 1, 1996 Project No. T-3064 The Geologic Map of the Renton Quadrangle, King County, Washington by D.R. Mullineaux (1965) shows that the soils are mapped as peat (Qlp). The peat encountered in Boring B-1 correlates with the published description. However, the native organic silt and clay underlying the fill at the site correlates better with the description of the nearby mapped alluvium(Qaw). _ 3.3 Groundwater j We encountered groundwater in all of the test borings at depths ranging from ground surface to seven feet. Some of the groundwater encountered near the ground surface appeared to consist of a perched zone of infiltration from recent heavy rains. In general,the groundwater table was found at depths ranging between four and seven feet. Due to its flat nature, groundwater depths are not expected to vary significantly over the site. However, we expect some seasonal fluctuations in the position of the groundwater table. • 3.4 Seismic Hazards The Puget Sound area falls within Seismic Zone 3 as classified by the Uniform Building Code (UBC). Based on the soil conditions encountered and the local geology, Table 16-J of the 1994 UBC indicates a site coefficient of 1.5 should be used in design of the structure. We reviewed the results of our field and laboratory testing in order to assess the potential for liquefaction of the site's soils during an earthquake. Liquefaction is a phenomenon where there is a reduction or complete loss of soil strength due to an increase in pore water pressure induced by vibrations from a seismic event. Based on the information obtained and considering the additional confining stresses from the building and fill weight, it is our • opinion that the risk of liquefaction-related impacts to the structure are minimal. • 4.0 DISCUSSION AND RECOMMENDATIONS 4.1 General x Based on our study, in our opinion, there are no geotechnical constraints that would preclude construction of the proposed steel fabrication facility. For building loads, the primary geotechnical concern for construction at this site is the three to five foot thick layer of organic silt and peat at depths of 6 to 12 feet below existing grades. With these conditions, a surcharge program will need to be completed in order to support the facility using standard spread footing construction. The purpose of the surcharge is to consolidate the compressible soil layers to limit post-construction settlements to an amount that the structure can tolerate. l Page No: 3 • February 1, 1996 - Project No. T-3064 The overhead rail crane's intolerance of settlement imposes additional geotechnical constraints on the design and placement of its foundation. Though competent sands underlie the organic clayey silt and peat at the site, these sands are underlain by a seven-foot thick layer of very soft silty clay at a depth of 30 feet. Our analysis indicates that the site will experience long-term total and differential settlement as this layer consolidates under the building and fill pad loads. While these long-term settlements may be tolerated by the building, we expect their magnitude to exceed what could be tolerated by the crane. It will therefore be necessary to transfer the crane's loads through the competent sands and underlying very soft silt to the medium dense to dense sand and silty sand. The following sections provide detailed recommendations regarding the above issues and other geotechnical design considerations. These recommendations should be incorporated into the final design drawings and construction specifications. it 4.2 Site Preparation and Grading -Y Following clearing, the fill surface should be proofrolled with heavy construction equipment prior to placement of additional fill. Soft, }Melding areas should be overexcavated to firm bearing soil and replaced with structural fill. Where excavations to achieve firm conditions are excessive, the use of a geotextile fabric such as Mirafi 500X in conjunction with limited overexcavation and replacement with a structural fill can be considered. Typically, 18 inches of clean granular structural fill over the fabric will achieve a stable subgrade. Our laboratory results show that the existing fill was above its optimum moisture content at the time of our investigation. Some of the fill soils encountered at the site contain up to 14 percent by weight of fines and will be difficult to compact if the moisture conditions cannot be carefully controlled. Extreme care should be taken to ensure that exposed surfaces of the on-site fill do not become disturbed due to weather and construction • traffic. Moreover, the ability to use these soils as structural fill will depend on their moisture content and the prevailing weather conditions at the time of construction. It will be difficult to achieve proper compaction of these soils when their moisture content is above optimum. When the moisture is excessive, the soil can be dried • by aeration to a moisture content which will allow for proper compaction. We recommend that the structural fill required to achieve site grades consist of inorganic granular soil meeting the following grading requirements: Maximum Aggregate Size 6 inches • Minimum Retained on the No. 4 Sieve 25 percent l Maximum Passing the No. 200 Sieve 25 percent • (Based on the Minus 3/4-inch Fraction) (see following narrative) If fill placement takes place during wet weather, or if the moisture conditions of the fill material cannot be controlled, consideration should be given to importing fill soil that conforms with the above gradation, but with the maximum passing the No. 200 sieve reduced to five percent. Page No.4 February 1, 1996 Project No. T-3064 Structural fill materials should be placed in uniform loose layers not exceeding 12 inches and compacted to a minimum of 95 percent of the soil's maximum density, as determined by ASTM Test Designation D-698 (Standard Proctor). The moisture content of the soil at the time of compaction should be within about two i percent of its optimum, as determined by this same ASTM method. Prior to placing foundations and floor slabs, we recommend probing or proofrolling the structural fill surfaces to determine if any isolated soft and yielding areas are present. As discussed above, soft or yielding areas should be overexcavated and filled to grade with structural fill or crushed rock. It may be necessary to protect foundation and slab areas with lean mix or a layer of crushed rock to guard against soil degradation. Construction traffic must not be allowed on subgrades that have been prepared just prior to foundation or slab placement. A representative of Terra Associates, Inc. should observe all proofrollmg operations. We also • recommend field evaluations at the time of construction to verify stable subgrades. 4.3 Surcharge and Settlements As discussed, for spread footing foundation support and slab-on-grade construction, we recommend placing a surcharge fill over the building area. The surcharge program is necessary to limit building settlements to what may be considered tolerable levels. Our surcharge and settlement analysis is based on an assumed existing ground surface elevation of 12 feet. In addition, our analysis is based on a finished floor (top-of-slab) elevation of about 20 feet, and the anticipated floor loads discussed above. We should review the final foundation and grading plans in order to better assess expected settlements. Primary Consolidation The site grades should be raised using structural fill as outlined in the Site Preparation and Grading section. Once grade is achieved, an additional eight feet of fill should be placed as a surcharge. This surcharge fill does not need to meet any special requirements other than having a minimum in-place unit weight of 125 pounds per cubic foot (pcf). However, it may be advisable to use a good quality fill which could be used to raise grades in other portions of the site, such as parking and driveway areas, if necessary. • We do not believe it to be necessary to place a surcharge of fill within the parking and access easement areas if grades at these areas are raised to elevations comparable to the building area. In any case, the structural fill pad in the pavement areas should be placed concurrently with the structural fill in the building areas to allow enough time for consolidation of the compressible layers and reduction of potential settlements. The estimated total primary settlements under the recommended surcharge range from 12 to 18 inches across the building area. These settlements are expected to occur 12 to 16 weeks following full application of the • surcharge loading. The actual period for completion and magnitude of the primary settlements will be governed by variations in subsurface conditions at the site. Page No. 5 February 1, 1996 Project No. T-3064 The rate of consolidation can be accelerated by installing sand or wick drains at regularly spaced intervals • throughout the pre-load fill pad. Alternatively, an additional thickness of fill surcharge will accelerate the rate of primary settlement. The sand drains should penetrate a minimum of five feet into the gray-black fine sand underlying the organic silt or peat layers. With the pre-load pad in place, we estimate the sand drains will be 30 • to 35 feet long. Proprietary wick drains may be used in lieu of sand drains. We can provide specific recommendations for either option if acceleration of the surcharge settlement period is desired. To verify the amount of settlement and the rate of movement, the surcharge program should be monitored by installing settlement markers. A typical settlement marker installation is shown on Figure 3. The settlement • markers should be installed on the existing grade prior to placing any building or surcharge fills. Once installed, elevations of both the fill height and marker should be recorded daily by a registered land surveyor until the full height of the surcharge is in place. Once fully surcharged, readings should continue weekly until the anticipated settlements have occurred. It is critical that the grading contractor recognize the importance of the settlement marker installations. All efforts must be made to protect the markers from damage during fill placement. It is difficult, if not impossible, " to evaluate the progress of the surcharge program if the markers are damaged or destroyed by construction • equipment. As a result, it may be necessary to install new markers and to extend the surcharging time to ensure that settlements have ceased and building construction can begin. We recommend that the surcharge pad extend a minimum of five feet beyond the building perimeter and then slope down at an inclination of 1:1 (Horizontal:Vertical). The conceptual site plan shows the northern building perimeter may be 20 feet from SW 34th Street. This would place the toe of the 15-foot high fill pad at the edge • of the roadway. Where sufficient area is not available to slope the surcharge and to reduce impact of _ settlements due to surcharge on the existing roadways, the surcharge may be supported at a near vertical inclination(minimum 1:12)using reinforced soil wall. Figure 4 shows a typical reinforced soil wall section. Post-construction Settlements Primary consolidation of compressible soils at the site will be achieved upon completion of the surcharge (pre- load) program. Secondary consolidation will continue at the site throughout the life of the structure. During secondary consolidation, you should expect a maximum post-construction total settlement of 1.5 inches, and differential settlement of 3/4 inch. These values represent expected settlements over a 50 year period. We anticipate that most of these settlements will occur within five to ten years after completion of the structure. Impact of Surcharge on Adjacent Roadway and Utilities Depending on its location, the proximity of the surcharge fill pad to SW 34th Street and the railroad spurs may result in settlement of these structures due to soil beneath them being influenced by the preload fill pad. We recommend placing monitoring points on the roadway curbs and pavement to record possible movements during surcharge. A similar monitoring program should be implemented for the railroad spurs if they cannot tolerate possible settlement from the pre-load. 0 Page No. 6 • February 1, 1996 Project No. T-3064 Sufficient monitoring points should be established since some of these points will likely be disturbed by traffic. In addition, we suggest making a photographic survey of the pavement before placing the surcharge to identify development of new cracks during and after the area is surcharged. • We understand a fiber optic telephone transmission cable is located within a utility easement adjacent to SW 34th Street. This utility line as well as other utilities within the easement may experience vertical and/or lateral movement as a result of the stress changes in the soil associated with the placement of a pre-load fill pad. Utility organizations should be prepared to relocate utilities as required prior to construction of the pre-load. • 4.4 Spread Footiniz Foundations Following the successful completion of the surcharge program, if the above estimated settlements are considered tolerable, the building may be supported on conventional spread foundations bearing on a minimum of two feet of structural fill. Existing competent fills may be included in determining the depth of the structural fill. Perimeter foundations exposed to the weather should be at a minimum depth of 1.5 feet below final exterior grades. We recommend designing foundations for a net allowable bearing capacity of 3,000 psf. For short-term loads such as wind and seismic, a 1/3 increase in this allowable capacity can be used. With the anticipated loads and bearing stresses,the estimated total settlements are as discussed in the Secondary Settlements section. For designing foundations to resist lateral loads, a base friction coefficient of 0.4 can be used. Passive earth pressures acting on the side of the footing and buried portion of the foundation stem wall can also be considered. We recommend calculating this lateral resistance using an equivalent fluid weight of 350 pcf. We recommend not including the upper 12 inches of soil in this computation because they can be affected by weather or disturbed by future grading activity. This value assumes the foundation will be constructed neat against competent fill soil or backfilled with structural fill as described in the Site Preparation and Grading section. The recommended lateral resistance value includes a safety factor of 1.5. 4.5 Rail Crane Foundation - Steel H-Piles We understand you are considering using steel H-piles for transferring overhead rail crane loading below the consolidating layers at the site. We estimate that a W l2 x 58 steel pile will achieve an allowable axial load of 30 tons when driven to minimum tip elevations of 40 to 45 feet below existing surface grades. This allowable axial load takes into account potential negative loading caused by dovmdrag on the pile due to consolidation of the compressible layers under building fill and floor slab loading. Full axial capacity can be used provided the piles are spaced at a minimum of three pile diameters. Closer spacing in pile groups will require a reduction in the single pile capacity. This reduction will depend on the number of piles in the pile group and the spacing used. For resistance to lateral loading, a lateral pile capacity of four tons can be used. The estimated pile settlements are 1/4 inch and less, excluding settlement due to elastic shortening of the pile itself. Page No: 7 February 1, 1996 Project No. T-3064 The pile driving hammer used to install the piles should have sufficient energy to drive the piling to the estimated tip elevation without damage to the pile. We also recommend that prior to ordering production piles and their installation, a minimum of three test piles be driven at the site to verify anticipated tip elevations and establish driving criteria for use in evaluating production pile capacities. The test piles should be driven with the same •'" equipment that will be used in the production pile installations. 4.6 Rail Crane Foundation-Augercast Piling Augercast piling can be considered as an alternative to steel piling in transferring rail crane foundation loading below the consolidating layers at the site. For 16-inch diameter pilings with minimum tip elevations of 40 feet below existing surface grades, an allowable axial load of 35 tons is available for design. This loading takes into account the potential negative loading effects due to downdrag. Similar reductions in pile capacity as those discussed above can be expected when piles are placed in groups. For resistance to lateral loads, an allowable lateral pile capacity of four tons is available. The estimated pile settlement is 1/4 inch and less. Augercast piles are formed by the pressure injection of grout through a hollow stem auger which is slowly retracted from the ground after advancement to the recommended tip elevation. The grout pressure used will compress the soils within the immediate vicinity of the pile, thereby increasing to some extent the pile diameter 40 and the amount of grout required to construct the pile. For planning purposes, we suggest considering a 30 percent increase in the amount of grout necessary to form the pile. In construction of agercast piling, a higher than normal reliance on quality Nvorkmanship is required for successful installations. It is extremely important that the grout pressure is consistent and uniform during the installation and that retraction of the auger occurs at a slow uniform pace beneath a sufficient head of grout in the pile column. The contractor should have adequate means for verifying grout pressure and estimating the volume of grout used in the construction of the piles. Because of the compression effects and the possible influence on adjacent pile construction, the installation sequence should be based on a minimum pile spacing of • five pile diameters. Once the grout column has achieved its initial 24 hour set, pile construction in between these spacings can be completed. 4.7 Slab-on-grade Floors With site preparation completed as described in the Site Preparation and Grading section, new structural fill soils should be suitable for supporting slab-on-grade construction. Immediately below the floor slabs, we recommend that an allowance be made for placing a six-inch layer of clean free-draining sand or gravel which has less than five percent passing the No. 200 sieve. This capillary break will guard against wetting of the floor slab due to the underlying soil conditions. Where moisture via vapor transmission is not desired, a polyethylene vapor barrier should also be installed. We suggest that this vapor barrier be placed on an initial four inch layer of the capillary break material and then covered with the final two inches to help protect it during construction and to aid in uniform curing of the concrete floor slab. For slab thickness design with respect to floor deflection due to traffic and point loadings, a subgrade modulus of 300 pci (pounds per cubic inch) can be used. Page No. 8 p • February 1, 1996 Project No. T-3064 Estimated floor slab settlements of less than 3/4 inch are expected due to post-primary consolidation. This movement assumes that settlements due to required building fills would be allowed to occur prior to floor slab construction. The floor movements would be entirely differential with respect to the foundation construction. • 4.8 Excavations Excavations greater than four feet in depth will need to be completed in accordance with local, state, or federal �y regulations. In accordance with the Occupational Safety and Health Administration (OSHA), inorganic soils encountered at the site would be classified as Group C soils. Accordingly, excavations made within the native soils or fill at the site greater than four feet in depth but not exceeding 20 feet in depth will need to be laid back with side slope gradients of 1.5:1. Due to the low strength characteristics of the on-site silty peat, we recommend that excavations within this material be shored using a ditchbox or temporary bracing. Optionally, the use of a trench shoring box to support excavations throughout the lower depth may be used in conjunction with sloping of the upper portion of the excavation as outlined above. Dewatering of the excavation will need to be considered where excavation depths exceed five feet below existing site grade. •' 4.9 Utilities We recommend that all site utilities be bedded and backfilled in accordance with applicable APWA specifications. For site utilities within City rights-of-way, bedding and backfill should be completed in accordance with City of Renton specifications. At a minimum, utility trench backfill should be placed and compacted in accordance with recommendations presented in the Site Preparation and Grading section. Where utilities vczll occur below unimproved areas, the degree of compaction can be reduced to a minimum of 90 percent of the soil's maximum density as determined by the referenced ASTM standard. Because of the potential for long-term settlements, utility pipe joints and connections should be of flexible nature allowing for up to one inch of differential movement. 4.10 Lateral Earth Pressures The magnitude of earth pressure development on retaining walls constructed in loading dock areas will partly depend on the quality of backfill. Where fill is placed behind retaining walls, we recommend placing and compacting it as structural fill. The fill should be compacted to a minimum of 95 percent of its maximum dry unit weight as determined by ASTM Test Designation D-698 (Standard Proctor). To guard against the build up of hydrostatic pressure, wall drainage must also be installed as discussed in the drainage section. With granular backfill placed and compacted as recommended and drainage properly installed, we recommend designing restrained (not free to deflect) retaining walls for an at-rest earth pressure equivalent to a fluid weighing 50 pcf. For unrestrained walls (free to deflect), this value may be reduced to 35 pcf. These values do not include other surcharge loading such as adjacent footings or sloped backfill that may act on these walls. If such conditions will exist, then the imposed loading must be included in the wall design. Friction at the base of foundations and passive earth pressure will provide resistance to these lateral loads. Values for these parameters are provided in the Foundations section of this report. Page No.9 •A • February 1, 1996 Project No. T-3064 4.11 Drainaze Surface Final exterior grades should promote free and positive drainage away from the building areas at all times. i Water must not be allowed to pond or collect adjacent to foundations or within the immediate building area. We -� recommend providing a gradient of at least three percent for a minimum distance of ten feet from the building perimeter, except in paved locations. In paved locations, a minimum gradient of one percent should be provided • unless provisions are included for collection and disposal of surface water adjacent to the structure. Subsurface In our opinion, perimeter foundation drains would not be necessary if the area immediately adjacent to the structure is paved and positive surface drainage maintained. If the grade is not positively drained away from the structure or is landscaped,perimeter foundation drains should be installed. • To guard against hydrostatic pressure development, retaining wall drainage must be installed. We recommend that wall drainage consist of a minimum 12-inch thick layer of washed rock or pea gravel placed adjacent to the wall. A four-inch diameter perforated pipe should be placed on a bed of gravel at the base of the wall footing and gravel drainage column. The pipe should be directed to a suitable outlet. 4.12 Pavements With subgrade soils prepared as described in the Site Preparation and Grading section, suitable support for pavement construction should be provided. HoNvever, regardless of the compaction results obtained, subgrades 1 must be in a stable non-yielding condition prior to paving. Immediately prior to paving, the area of the subgrade should be proofrolled with heavy construction equipment to verify this condition. The required pavement thickness is not only dependent upon the supporting capability of the subgrade soils but also on the traffic loading conditions which will be applied. For light commercial vehicles and typical passenger vehicle traffic the following pavement sections are recommended: • Two inches of asphalt concrete (AC) over four inches of crushed rock base (CRB) • Two inches of AC over two inches of asphalt treated base (ATB) For heavy truck traffic areas, we recommend the following pavement sections: • Three inches of AC over six inches of CRB • Three inches of AC over four inches of ATB • Page No. 10 • February 1, 1996 Project No. T-3064 If there is a potential that pavement construction will be delayed until the wet winter months, the subgrade soils must consist of a clean granular materiat as described in the Site Preparation and Grading section. In addition, �} we strongly suggest that the subgrade be further protected by placing a layer of ATB on which construction • traffic could access the project without excessively disturbing the subgrade soils. The ATB thickness for this purpose should be four inches. Repair of failed ATB areas should be anticipated prior to final paving. However, the overall integrity of the subgrade soils will be considerably less impacted with this protection provided. •E.i • Because of secondary compression of the organic silt layer, some degree of post-construction settlement within the pavement structure should be anticipated. This settlement will probably result in some longitudinal and transverse cracking of the pavement. Cracks in the pavement should be sealed in a timely fashion to prevent excessive surface water infiltration into the subgrade soils. 5.0 ADDITIONAL SERVICES • Terra Associates, Inc. should review the final design and specifications in order to verify that earthwork and foundation recommendations have been properly interpreted and incorporated in the project design. We should also provide geotechnical services during construction in order to observe compliance with the design concepts, i specifications, and recommendations. This will also allow for design changes if subsurface conditions differ from those anticipated prior to the start of construction. We request a minimum of two working days notice be given to schedule our services during construction. 6.0 LIMITATIONS • We prepared this report in accordance with generally accepted geotechnical engineering practices. This report is the property of Terra Associates, Inc. and is intended for specific application to the Farwest Steel project in Renton, Washington. This report is for the exclusive use of Farwest Steel Corporation and their authorized representatives. No other warranty, expressed or implied, is made. • The analyses and recommendations presented in this report are based upon data obtained from the test borings drilled on-site. Variations in soil conditions can occur, the nature and extent of which may not become evident until construction. If variations appear evident, Terra Associates, Inc. should be requested to reevaluate the recommendations in this report prior to proceeding with construction. Page No. 11 s Q. PAft. 'I ISw �(,(f/1 �V,�6C 1 L-7j `ARM7[oi.''•;IY ENTON I I s< �� _ IT • >• sW G ■ S R ON VILLAGE RL s 71 5T ST nouar 24 �i'9+ o , 57 low FRW`t f IT t } 1 �,„ <_ .r 1 SY 2 K.15TH 20 `r 1 A:16T11,1 ST s{ p 1 S3RD` $r S`LI 3 40D 16TH ST ..Q : s lcrii 1640 7W.'LA I sl i = i S 9 J, 4 E1f7N� a ! I I I[ g s 1 , »" IT 1 gLVO }f 5T LO[GLDBES sY 19m 5T MCf r lyll 5 19TH [STs ULOT�i LPVGICRU [Lw Y S ',�,!�•-`'( q; PKWY TRACK Mlw[ 1 WE us7 IT r mn 7> <� 1� pUGET' I G2`EM I 1 r L D V sx 7m ' • - h ` BucER SL �. ,I I SV.23R0. S 23RD •'y ,.�� � mc �I I } O i_�}: �J. �MID 1 BLYD r[ I R NTON $H 1 27TH IT IS 27TH IT I NE 1090o I T NCTI O 5 TN: 25 25TH sr- .i�''J -, •: +' �,sT •s[1Enxyl i I { 30 = it Sy 30TH s 29> E j •ETN W 5M 33RI1 Sv 17RD IT S 1�. n'•l R \ Fj`F •' <'iIT I w �S 7hiN � IErN Y rt SE 8.]�ST ]) 1 yl SW TN sT ,1T �I I R S 77tN05T r :K .. SE 1,ND a _51 ' �i ' CC SIr'`38THLyr sT 1 - '� ai x I� /1 N- $7 $'17<7N 5T —7N y I} W �rni= F$ I/ i �'` r Y� SE 176T =A� a RI LLA I-&5T �- > k f i SITE ,J F s.u�� I F p E_ 6> _ ... 7 ? SW 43RD STT __ .s SY [ 43RD 1ST cE�� °°� [ S:a x x i "� p•°�`+ sE= 162ND:'>< IBM _ JS Ra'WRAOC 31 rErN.r $ E 163RDL To, GREENBELT , i 1.�4 8(✓0 1 I JQ� !! i M �L'-[ 7&THI- SE — 1 $7 5 Ie6TH 111TT S IBBTH IT 5`BET»Er { 5—Is—'TN sTl z i [6.5 IE7�CT 190TH 5T 1 150TN S ]oG7H 7� r,�°:c H - - --j IT i I SSG: 5t [l.:n - ` 51 ]SCl» ��:hM 192ND <r 19, 5T S °STH 1[ Llj $ 5T -J m I S sr 19I7N 57 �I I sH 154TH IT I :t iK ( -- dti-5E is-ld PL >: r s I%TH —IT s 19ETH IT ' SE 296TH S 19eTH IT p•yE•�ri �+�:' rr - I 19BTH ST s<>�:4E•»S7 SE v7 11 r ;I 1 l+: • �:E1799TH 3 = 5 2007H s m{1xn[ 5 <r .I ,,,I S 5 200TH ie1 STD �.-- gl -i �SE 57 200TH S7 m + sr 7c:s7�I i S._ 202N0,^I t7 REFERENCE: THE THOMAS GUIDE, KING COUNTY, WASHINGTON, PAGES 655, 656, 685 AND 686, 1995 EDITION. VICINITY MAP NTERRA FARWEST STEEL ASSOCIATES RENTON, WASHINGTON Geotechnicali Consultants Proj. No.3064 Date 1/96 Figure 1 S. W. 34th. STREET • I I Pt iE Two I �� B-1 ;225oAS tiR ! j I o� B-3 i i o > I i I B-5 i B-4 B-2 LEGEND: REFERENCE: APPROXIMATE BORING LOC/,TION SITE PLAN PROVIDED BY HORTON DENNIS AND ASSOCIATES, INC., JOB No. UNKNOWN, SHEET ------ 10 ft. LANDSCAPE EASEMENT No. SB5.GCD, DATED 1/24/96. ALONG STREET FRONTAGE ......... RAILROAD CENTERLINE APPROXIMATE SCALE - PROPOSED RAILROAD CENT=RLINE 100 0 100 200 feet EXPLORATION LOCATION PLAN x TERRA FARWEST STEEL ASSOCIATES RENTON, WASHINGTON @#Geotechnical Consultants Proj. No.3064 Dote 1/96 Figure 2 • • STEEL ROD PROTECTIVE SLEEVE HEIGHT VARIES SURCHARGE (SEE NOTES) SURCHARGE �1 OR FILL OR FILL • •I �a NOT TO SCALE • NOTES: 1. BASE CONSISTS OF 1/2" THICK, 2'x2' PLYWOOD WITH CENTER DRILLED 5/8" DIAMETER HOLE. 2. BEDDING MATERIAL, IF REQUIRED, SHOULD CONSIST OF CLEAN COARSE SAND. 3. MARKER ROD IS 1/2" DIAMETER STEEL ROD THREADED AT BOTH ENDS. 4. MARKER ROD IS ATTACHED TO BASE BY NUT AND WASHER ON EACH SIDE OF BASE. 5. PROTECTIVE SLEEVE SURROUNDING MARKER ROD SHOULD CONSIST OF 2" DIAMETER • PLASTIC TUBING. SLEEVE IS NOT ATTACHED TO ROD OR BASE. 6. ADDITIONAL SECTIONS OF STEEL ROD CAN BE CONNECTED WITH THREADED COUPLINGS. 7. ADDITIONAL SECTIONS OF PLASTIC PROTECTIVE SLEEVE CAN BE CONNECTED WITH PRESS—FIT PLASTIC COUPLINGS. 8. STEEL MARKER ROD SHOULD EXTEND AT LEAST 6" ABOVE TOP OF PLASTIC PROTECTIVE SLEEVE. 9. STEEL MARKER ROD SHOULD EXTEND AT LEAST 1' ABOVE TOP OF FILL SURFACE. TYPICAL SETTLEMENT MARKER DETAIL P# TERRA FARWEST STEEL ASSOCIATES RENTON, WASHINGTON Geotechnicol Consultants Proj. No. 3064 Date 1/96 Figure 3 SLOPE 12:1(V:H) GEOTEXTILE FACING COMPACTED STRUCTURAL FILL MINIMUM WRAP (typical) 95% MAX. DRY DENSITY t2% OPTIMUM MOISTURE CONTENT PER D-698 (STANDARD PROCTOR) 0.81-1 feet (TYPICAL) . 3 feet (TYPICAL) .. H feet 18 in. (max.) : .. .. MIRAFI 5T GEOGRID :. (TYPICAL) NOT TO SCALE REINFORCED SOIL WALL SECTION TERRA FARWEST STEEL ASSOCIATES RENTON, WASHINGTON Geotechnical Consultants [Proj. No.3064 Date 1/96 Figure 4 APPENDIX A FIELD EXPLORATION AND LABORATORY TESTING •a Farwest Steel Renton,Washington On January 9 through 11, 1996, we performed our field exploration using a truck-mounted hollow stem auger drill rig. We explored subsurface soil and groundwater conditions at the site by drilling six hollow stem auger test borings to a maximum depth of 59 feet below existing grade. The test boring locations are shown on Figure 2. Test hole elevations were interpreted from the USGS Renton Topographic Quadrangle. The Boring Logs are presented on Figures A-2 through A-7. An engineer from our office maintained a log of each test hole as it was drilled, classified the soil conditions encountered, and obtained representative soil samples. All soil samples were visually classified-in accordance with the Unified Soil Classification System shown on Figure A-1. • Representative soil samples were obtained from the test borings using sampling procedures outlined in ASTM Test Designation D-1586 (Modified Proctor). The samples were placed in jars or tubes (ring • samples) and taken to our laboratory for further examination and testing. The moisture content of each sample was measured and is reported on the Boring Logs. Plasticity characteristics of the fine-grained soils were determined by conducting Atterberg limits tests. Consolidation tests were performed on samples of the organic silt and silty clay obtained during drilling of Borings B-5 and B-6. Grain size analyses were performed on eight of the samples. The results of the grain size analyses are presented as • Figures A-8 through A-11. Project No. T-3064 Boring No. B-1 Logged by: KPR Date: 1/9/96 Approximate Elev. 12 Graph/ Q_ (N) Water USCS Soil Description Relative Depth E Blows/ Content Density (ft.) 0 foot N Brown-gray gravelly medium sand Sp FILL cuttinps. saturated. FILL: Dark gray silty SAND with Very Dense SM fine to medium grained,moist. 61 7.8 gravel, FILL: Dark gray silty SAND with Y Sp 5 few gravel,fine to medium Loose X... 4 16.1 X rained saturated. saturated. A A A A A A ft A A h A A I Dark brown PEAT,with some silt, A I fibrous to amorphouse,wet to Medium Stiff 7 202.3 saturated. 7.5 to 9 feet dark • 7 0 1 P T-A A brown PEAT,fibrous with silt,wet. — 10 A A A ft A 10 to 11.5 feet Dark brown silty Soft - 3 171.6 h A PEAT,fibrous to amorphouse,wet. - - -------------------------------------------------------------------- Black SAND, medium-grained, = 24 25.1 Bentonite slurry saturated, 4 inch thick layer Medium Dense - added to hole to of brown, saturated, non- — 15 control heave. plastic silt at.13 feet. X.- 54 18.7 Black SAND, as above but Very Dense without silt layer and very dense. —20 j;. 'Kn* 50+ Black SAND, as above. Very Dense 17.0 — 25 Black SAND, as above but Dense ;g finer grained. = 49 24.3 30 Z V:% Black SAND, medium grained, saturated, interbedded with 4 Medium Dense 29 36.0 inch thick layers of brown, soft, W clayey silt. —35 Black SAND, medium-grained, saturated. SM I Dark gray silty SAND with shells, Medium Dense I 14 25.8 Nfine-grained, saturated. • Test boring terminated at 39 feet. Groundwater encountered at 4.5 feet. Hole plugged with 3 bags of bentonite chips mixed with cuttings. BORING LOG . ........ TERRA FARWEST STEEL ASSOCIATES RENTON, WASHINGTON Geotechnical Consultants Proj. No. T-3064 � Date 1/96 Figure A- Boring No. B-2 Logged by: KPR Date: 1/9/96 Approximate Elev. 12 m Graph/ a (N) Water h/ P Relative Depth E Blows Content USCS Soil Description Density (ft.) o (ft) (%) 7 >' z`I'«> Brown SAND with few gravel and silt fill cuttings, medium grained, wet. ' SP-SM FILL: Brown SAND with few Dense 33 12.3 gravel, medium-grained,wet. ------------- - ------- ------- - --- - -- Gray-brown-organic- -clayey-SILT- ,--- ---------------------- 5 LL=60 I low plasticity, saturated, 1 inch Medium Stiff • ,�iii , � i�:ii P Y 8 64.0 PL=47 i i thick peat layer at 7.5 feet. PI=13 iiOHii Gray-brown organic SILT (as above). Medium Stiff Black SAND with silt, very fine- Medium Dense 28 32.6 grained, saturated. Test boring terminated at 9 feet. Groundwater encountered at 4.5 feet. Hole plugged with 1 bag of bentonite chips mixed with cuttings. 0 41 BORING LOG TERRA FARWEST STEEL ASSOCIATESRENTON, WASHINGTON Geotechnical Consultants Proj. No. T-3064 Date 1/96 Figure A-3 Boring No. B-3 Logged by: KPR Approximate Elev. 12 Date: 1/10/96 Graph/ Relative Depth a (N) Water USCS Soil Description p E Blows/ Content Density (ft') ) foot N Brown, medium rained sand Bentonite slurry ��`::>.•.::.. FILL cuttings with few gravel, added to hole wet. to control heave •a.Sy.Yn.::••:::A.::i:': FILL: As above but saturated. Medium Dense 18 16.9 ove but gray. Loose 5 • i i i Dark brown organic SILT with peat I I I I I I i l fibers,low plasticity,moist to wet. Soft = ill Gray-brown clayey SILT,low plasticity LL=73 OH i i saturated,5 inch thick layer of I I I I I I fibrous peat at 8 feet;black,fine- 5 69.1 PL=64 rained siltysand in sampler tip. Medium Stiff PI=9 10 Dark gray, silty SAND, very SM fine to fine-grained, saturated. Medium Dense 19 33.7 — 15 t:••v • >:�' °`'` Black SAND, with thin interbeds of dark gray silty SAND, fine Medium Dense 17 33.2 i :'•.. ;•. :% :<.::;:: to medium-grained, saturated. 20 ;a SM Dark brown-gray silty SAND, Medium Dense S very fine-grained, saturated. •:#;<::s::>: ::::� Black SAND, fine to medium- Medium Dense ::•;;;a;.x•�;•••>.•;:::: grained, saturated. 25 ' .,gp_'< Black SAND, as above. Dense 36 24.6 <: Test boring terminated at 29 feet. Groundwater encountered at 1.5 feet and 7 feet. Hole plugged with 1 bag of bentonite chips mixed with cuttings. BORING LOG TERRA FARWEST STEEL ASSOCIATES RENTON, WASHINGTON Geotechnical Consultants Proj. No. T-3064 Date 1/96 Figure A-4 Boring No. B-4 Logged by: KPR Date: 1/10/96 Approximate Elev. 12 Graph/ Relative Depth C- (N) Water USCS Soil Description E Blows Content Density (ft.) (ft) (%) {•'>`� :�+:�:.• Brown, medium-grained sand •<� .'s^�`. '.','•f'���.•.+•.�? FILL cuttings, wet. Medium Dense �• :: SP %' FILL: Brown SAND, medium. grained, saturated. 27 13.6 y? + {' w IIIIIIIIIIII Ili Gray-brown organic SILT, low Medium Stiff 5 LL=70 I II I IIIII II I I II plasticity, wet, dark brown 6 60.8 PL=50 1I i IOH i ICI fibrous, wet peat in sampler P1=20 . tip IIIII I I IIIII I IIIIIIIIIiI III II IIIIIIIII III Medium Stiff IIIIII I 10 43.2 SM > <: Dark gray silty SAND,very fine Medium Dense to fine-grained, saturated. �i a BORING LOG TERRA FARWEST STEEL 4 • ASSOCIATES RENTON, WASHINGTON Geotechnical Consultants Proj. No. T-3064 Date 1/96 Figure A-5 i • i Boring No. B-5 Logged by: KPR � Approximate Elev. 12 Date: 1/11/96 • a) i Graph/ Cl (N) Water Relative Depth E Blows/ Content USCS Soil Description Density (ft.) a foot N <'•'{:`•':'`•"s<''.<'': Gray sand FILL cuttings with few gravel, medium-grained, .r. SP . .. moist. SM i FILL: Gray sand with silt and some Dense = 30 9.1 gravel, medium grained,wet to 3.5 feet becoming saturated. i Brown-gray organic SILT,with Stiff 5 LL=78 PL=54 peat fibers, saturated, low 10 71.0 i' i OH i i plasticity. PI=24 Gray clayey SILT, wet, low LL=53 plasticity. Soft 2 69.1 PL=35 Dark gray silty SAND, very fine PI=18 • to fine-grained, saturated. Loose 10 Bentonite slurry added to hole SM " to control heave Dark gray silty SAND, as above. Dense 32 26.2 nn >`w' Sava Black SAND, fine-grained, 15 saturated. :+ ..• .:. Black SAND, as above but with 37 29.2 > :•' '• occasional 1 inch thick silty Dense > : :> very fine-grained sand layers. 20 Black SAND, medium rained, •r�.�: .��;>:<:::>� g Very Dense ? ?��•:?::::,::: saturated. —25 '"`"`j ?''??' Black SAND with silt fine- . '' :>'si.;>•>>'' grained, saturated. SP SM Very Dense :•<?::; 52 25.5 Page 1 of 2 BORING LOG ` TERRA FARWEST STEEL ASSOCIATES RENTON, WASHINGTON Geotechnical Consultants Proj. No. T-3064 Date 1/96 Figure A-6 Boring No. B-5 (Continued) • Logged by: KPR Approximate Elev. 12 Date: 1/11/96 a) Graph/ Relative Depth Q (N) Water USCS Soil Description E Blows/ Content Density (ft•) '3 foot N Cn • Gray silty CLAY,with trace wood bits and clam shells, low plasticity, saturated. Very Soft ML 1 65.4 LL=45 CL PL=24 Gray silty CLAY, with clam 35 e=PI=21 21 1.08 shells, low plasticity, saturated, Very Soft 1 48.2 C,=0.142 with sand at 36.5 feet. Unit Wt.=107.3 - --------------------------------------- ---------- - -- - - pcf Gray silty SAND, with clam shells, medium-grained, 4 25.8 SM :XV ;:::: saturated. Loose ...... ....... 40 Increased drilling :•.;. resistance at . 40 feet :•,fir;.r :.:: SP SM Black SAND with some silt, Dense 37 26.5 k.... :>, medium-grained, saturated. . 4 Dark gray silty SAND/sandy SILT with shells, very fine- Medium Dense 16 44.4 grained sand, saturated. � 50 SM ML Dark gray silty SAND with T occasional shells,very fine Medium Dense r I 11 35.4 to fine-grained and bits of --LL wood, saturated. 55 • I Dark gray silty SAND, as above. Medium Dense 19 25.7 Test boring terminated at 59 feet. Groundwater encountered at 3.5 feet. Hole plugged with 2 bags of bentonite chips mixed with cuttings. Page 2 of 2 i BORING LOG FARWEST STEEL TERRA ASSOCIATES RENTON, WASHINGTON Geotechnical Consultants � Proj. No. T-3064 Date 1/96 Fgure A-6 Boring No. B-6 • Logged by: KPR Approximate Elev. 12 Date: 1/11/96 0 a) Graph/ 0- (N) Water 0 USCS Soil Description Relative Depth E Blows/ Content Density (ft.) C3 foot (%) • V CIO Brown-gray, gravelly medium- • grained silty sand FILL cuttings, i�i� ��ii saturated. • S M FILL: Gray SAND with gravel, Dense 32 9.3 medium-grained, wet. 7.5 feet: FILL: Gray SAND, medium- Loose 5 LL=80 grained, saturated. PL=34 3 62.9 Dark brown PEAT, amorphous,wet. Soft PI=46 ------------------- e.=1.77 I Gray sandy SILT,with clay,very fine- C,=0.467 grained sand,saturated,medium plastic. Soft MH 1 3 58.2 Unit Wt.=94.3 pcf Gray silty SAND, very fine to Loose Bentonite slurry fine-grained, saturated. 10 added to hole to control heave Dark gray silty SAND, very fine to fine-grained, saturated,grades Medium Dense to black sand in sampler tip. 19 28.7 '4 ........... .. . ...................... ............. 15 . ......... . ......... Black SAND, fine to coarse- g rained, saturated. Dense .................................. 33 21.5 ...................... ............... :::::...............:. ...................... :.::.::..:...........::. :::::::.:::::::....::: .................. ::. .:: 20 --- ----------------------------------------- ------------------------ Black SAND, medium to coarse- very Dense grained. 64 20.5 —25 Black SAND, as above. Very Dense 75 26.5 Page 1 of 2 0 BORING LOG FARWEST STEEL ...... . TERRA X ASSOCIATES RENTON, WASHINGTON A A A Geotechnical Consultants Proj. No. T-3064 Date 1/96 Figure A-7 LA Boring No. B-6 (Continued) � Logged by: KPR Approximate Elev. 12 Date: 1/11/96 Graph/ Depth Q- (N) Water USCS Soil Description Relative Dept • Density ( E Blows/ Content foot N Black SAND, as above. Very Dense 54 22.6 ' 35 Dark gray silty SAND with • trace clam shells, fine to medium-grained, saturated. Loose 7 25.1 sM 40 Dark gray silty SAND, as above. • w::: ,sx:::s 58 29.8 trr{: :c •� <••v• : : Dark gray SAND with silt,trace SP-SM clam shells, very fine to fine- Very Dense < grained, saturated. —45 i - --------------------------------------- ----------------------- XX • Dark gray silty SAND,with trace Loose bits of wood, clam shells and to 10 36.9 clay, very fine to fine-grained, Medium Dense saturated. 50 S M Dark gray silty SAND, as above. Loose 6 32.1 55 Dark gray silty SAND, as above. Medium Dense T 28 24.2 Test boring terminated at 59 feet. Groundwater encountered at surface and 7 feet. Hole plugged with 2 bags of bentonite chips mixed with cuttings. Page 2 of 2 BORING LOG TERRAFARWEST STEEL ASSOCIATES RENTON, WASHINGTON Geotechnical Consultants Proj. No. T-3064 Date 1/96 Figure A-7 SIEVE ANALYSIS HYDROMETER ANALYSIS SIZE OF OPENING IN INCHES NUMBER OF MESH PER INCH, U.S. STANDARD GRAIN SIZE IN MM N \ CN _ N \\\\ \ O O O O O O O •� M N O O CO O O O F. 71T7cD 'd' N M M d• N d• c0 N O O O O O O O O O O O 100� NJ 0 90 10 (D O s � M 80 — - 20 o C/) X rn m — O o C7 D n 70 30 m c 60 40 C7 m 50 -_ _ - - — - 50 � m cc) x 40 _- _ 60 M �. = 30 - -- - -- 70 m o - _ 0 20 80 rn 70 G-) rn ;;0 10 90 Z-rj D — o — Z 01 1 _ LJ100 m N O CI CD CD CD O O O OAD d CO00 c ' t'') N ` 00 to d N- K) cV '—00 COcO • t7 00 to d• M cV O O O CO W d- M N O O O O O O O O O O O CDD m GRAIN SIZE IN MILLIMETERS COARSE FINE COARSE MEDIUM FINE rn z ILZ rn D COBBLES V AN FINES ---jr -< 0 Z C/) Boring or Depth Moisture Key Test Pit (ft.) USCS Description Content (%) LL PL CD 1 40B-1 2.5 SM silty SAND with gravel 0 B-1 37.5 SM silty SAND SIEVE ANALYSIS HYDROMETER ANALYSIS SIZE OF OPENING IN INCHES NUMBER OF MESH PER INCH, U.S. STANDARD GRAIN SIZE IN MM N N \\\\ \ O O O O O O O K) N Co Co O O O O c0 d o N ntn .- r7 d CV d c0 N O O O O O O O O O O O 100 0 90 10 (D 0 —— - 0 80 - - 20 _. C/) ;a -D - m c� O D n 70 30 m rn � C D 60 40 n � z M 50 - - 50 rn W 40 - 60 CID v m = �. = 30 - - - 70 rn 0 20 80 rn rn 10 90 z �_ - o p� z CD - Z 0 U100 CO C rn - O O O O O O O O O 00 c0 d M CV —00 l0 st M CV '-"00 c0 d- n cV 300 c0 d M N C CD CD Co 00 t0 d r7 CV O O CD CD CoO O O O O O co D rn GRAIN SIZE IN MILLIMETERS =--I z I COARSE I FINE COARSE-F MEDIUM I FlNE Z m D COBBLES V AN FINES r— � 0 z Boring or Depth Moisture Key Test Pit (ft.) USCS Description Content (�) LL PL CD • B-2 2.5 SP—SM SAND with gravel and silt O B-2 22.5 SP—SM SAND with some silt SIEVE ANALYSIS HYDROMETER SIZE OF O• •� " ww�w�w��:■ww�w��ww� w■w�ww.■ww��■.■■■ww�ww ' j EEEEEE��E�E��E�aEEEEEE�iiiiiEEE�� � wwww�w■�.aE■���E��EEEEEE�iiiiiEEE� , wwww�w■w���w��ww���ww.■www�■■■■■ww�ww wwwwww■w■■�w��ww���ww.■www�■■■■■wwwww wiwww�w■ww�� www�www.w►!ww.■www�■ ■■■wwwww wwww�w■ww� ���� ww.■www�■ ■■■mmw :, wwwww■w■ww�w�C�www.ww.iww.■w■�w�=■■■www� �www�w■ww��• �ww�� �.■w w�■■■■■mm� ■ _w�ww■■ ■wwwlw�:��_�_w.�_■�.■www_�■■■■■ww�ww ' ww�w■ww�w■ww�w�����.�EEwww�iiiiii��� ' �www�w�..w�w���.�w.w.� C■www ■■■■■w . ww�www� ■������■`�����Ci.EEEE�iiiiiEEE�www�w■ww�w����w��i 1001 WE MEN Cn EMIN IN ISM �m� m MIN MEN ■�ii ■w■■� ��_w.Zw.C_w..C..w_w�■�i�■■wwwww w wEMENC■ Ewe �■ OEM ■www� ■EEE�ww1 .. ��www�w■ww�w www�■ ��:■■www�■■■■■ww� • �wwww.w■ww� �_�_.�w.ww`■■www_w■w.=■�■■www aEEEEEEEEEE�=EE EECMISS S: ■EEE •• CEEB EEEEC�'��C� C��EE��:�ECEEE� C■��wwww.w..w�C���w. w.�E..ww�■■■C■wwwww , �www�w■ww�w �w����ww.■www�■■■ ■ww�ww �www�w■ww� w.www�`�ww.■www�■ ■■ w� ��www�w■ww�ECww■����� .■wwwe■�■■CEw�� • wwww�w■■�■w�w��www.�ww�w..www�.....ww� �wwww�w■ wow �ww��� .■www�■■■■■ww�ww . _ ' ww�w�w�w■ww�w �ww��•�.■www�■■■■■ww�ww .' �w �w■ww� ww����.■www�■ ■■■ww� wwEEw.w■www.E SIMMONS �wwww.w■ww�w���w.w.ww:�■.www�■.....w�ww ■wwww�w■.w�w��www.w.�..www�.....ww�� . • � �www�w■ww�w■���EEEEEEEEE�iiiEE�E �������■■�EEEE C�ww��ww.■www�=■■■■mm�w • . �wwwww.w■wm�m �www.w.ww.■www�■■■■■ww�ww ®te r m Moisture Description silty SAND • silty SAND with gravel • WON On • ! • - * • 0 ! • 0 ;,• Llj 4k-! •_ -A -W, • • 0-V V • � SIEVE ANALYSIS 7 HYDROMETER ANALYSIS SIZE OF OPENING IN INCHES NUMBER OF MESH PER INCH, U.S. STANDARD GRAIN SIZE IN MM CV N \\\1-1 \ O O CD CDO O O M N O O O O O O c0 iY r7 N MUl M d N d w N O O O O O O O O O O t: 100� 0 't. 90 10 (D 0 — rn 80 20 m c� O D n 70 30 m m rt D 60 40 c� 50 — -- — — — -- - — 50 C/) m CD _ _ �;a 40 60 � v m �. G7 30 70 _m = G-) o --i Wo 20 80 rn .A G7 — m ;�a 10 90 Z-rt D_ o 0� Z CDZ 0 _ 100 m N O O O O O O O O O 00 cO --0- tO N '— 00 c0 d M N 00 c0 d M cV 00 (0 d I-) cV C CD Co O 00 cD 1-4- to CD O Co 0 O O O O O O O O D-+ 'T' GRAIN SIZE IN MILLIMETERS Z m D COBBLES COARSE FlNE COARSE MEDIUM FlNE GRAVELAN FINES jr � O Z cn Boring or Depth Moisture Key CD Test Pit (ft.) USCS Description Content (%) LL PL D • B-6 37.5 SM silty SAND 0 B-6 52.5 SM silty SAND 1.10 1.05 i j • �j 1.00 '! o v 'o >.95 • .90 of 0.85 .1 .5 1 5 10 50 Pressure (tsf) Boring Depth is ur Dry, Key USCS Soil Description Cc eo Density No. (ft.) e ore After cf • B-5 36.0 CL silty CLAY .14 .005 1.08 46.8 38.0 70.3 3 Cc = Virgin Compression Index C� = Coefficient of Secondary Compression (at 0.83 tsf) eo = Inploce Void Ratio CONSOLIDATION TEST DATA . 9# TERRA FARWEST STEEL ASSOCIATES RENTON, WASHINGTON Geotechnical Consultants Proj. No.3064 TDote 1/96 Figure A-12 1.8 , 1.7 i • 1.6 O > 1.5 • 1.4 • 1.3 .1 .5 1 5 10 50 Pressure (tsf) Key Boring Depth USCS Soil Description Cc C. eo is ur 0 ns b No. (ft.) Before A ter cf • B-6 8.0 MH sandy SILT with clay .47 .0065 1.77 80.6 63.4 50.0 Cc = Virgin Compression Index Q, = Coefficient of Secondary Compression (at 0.83 tsf) eo = Inploce Void Ratio CONSOLIDATION TEST DATA 9#Geotechnical TERRA FARWEST STEEL ASSOCIATES RENTON, WASHINGTON Consultants Proj. No.3064 Date 1/96 Figure A-13