ENVIRONMENTAL REVIEW COMMITTEE REPORT
ERC Meeting Date: June 3, 2024
Project File Number: PR23-000146
Project Name: New Life Church Office Building
Land Use File Number: LUA23-000330, ECF, CUP-H, SA-H, V-H
Project Manager: Alex Morganroth, Principal Planner
Owner: New Life Church @ Renton, 15711 152nd Ave SE, Renton, WA 98058
Applicant/Contact: John Kay, K+ Architects, 10317 8th Ave NE, Seattle, WA 98125
Project Location: 15711 152nd Ave NE (APN 2323059021)
Project Summary: The applicant is requesting approval of a Hearing Examiner Conditional Use Permit,
Hearing Examiner Site Plan Review, height Variance, two (2) street Modifications, and
Environmental (SEPA) Review in order to construct a new office building on the site. The
subject site is approximately 55.1 acres (2,401,898 sf) and is located at 15711 152nd Ave
SE (Parcel no. 2323059021). The project site is currently developed with a 54,320 square
foot religious institution (New Life Church), a 36,000-square foot church auditorium, and
a 38,680-square foot private school serving children from K-8th grade. The site is also
developed with a parking lot with approximately 796 parking stalls, a storm water system,
outdoor play areas, and a multi-purpose playfield. The applicant proposes to construct a
new 6,400 sq. ft. 2-story office building on the northern-most portion of the existing
surface parking lot. According to the applicant, construction of the building would
eliminate approximately 40 surface parking stalls and require rerouting of some storm
detention pipes. A secondary fire exit is proposed via an exterior stairway off of the south
side of the building. Site access is proposed to remain via two existing curb cuts off of
152nd Avenue SE. Wetlands, a Type F stream, steep slopes, a high erosion hazard, a Special
Flood Hazard area – FEMA Zone A, and a high seismic hazard areas are mapped on the
site. The site is also located within Maplewood Wellhead Protection Area Zone 2. Eight (8)
trees are proposed for removal. Partial frontage improvements are proposed along SR 169
(Maple Valley Hwy). The applicant submitted a Critical Areas Study, TIA, Geotechnical
Report, an Arborist Report, and an Environmental Checklist to evaluate the proposal.
Exist. Bldg. Area SF: 129,000 Proposed New Bldg. Area (footprint):
Proposed New Bldg. Area (gross):
3,200
6,400
Site Area: 56.56 acres Total Building Area GSF: 135,400
STAFF
RECOMMENDATION:
Staff Recommends that the Environmental Review Committee issue a Determination
of Non-Significance - Mitigated (DNS-M).
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
City of Renton Department of Community & Economic Development
New Life Church Office Building
Staff Report to the Environmental Review Committee
LUA23-000330, ECF, CUP-H, SA-H, V-H
Report of June 3, 2024 Page 2 of 11
SR_ERC Report_New Life Church_240603_FINAL
ENVIRONMENTAL REVIEW
In compliance with RCW 43.21C.240, the following environmental (SEPA) review addresses only those project impacts
that are not adequately addressed under existing development standards and environmental regulations.
A. Environmental Threshold Recommendation
Based on analysis of probable impacts from the proposal, staff recommends that the Responsible Officials:
Issue a DNS-M with a 14-day appeal period
B. Mitigation Measures
1) The applicant shall comply with the recommendations of the
Subsurface Exploration, Geotechnical Engineering, and Stormwater Infiltration Feasibility Report,
prepared by Associated Earth Sciences, Inc. dated January 31, 2024, and any future addenda.
2) The applicant’s geotechnical engineer shall review the project’s construction and building permit
plans to verify compliance with the geotechnical report(s). The geotechnical engineer shall submit a
sealed letter stating they have reviewed the construction and building permit plans and in their
opinion the plans and specifications meet the intent of the report(s).
3) The applicant shall submit an Inadvertent Discovery Plan (IDP) prepared by a qualified professional
prior to the start of any construction. The applicant shall provide notification to Tribes’ cultural
committee prior to the start of construction.
C. Exhibits
Exhibit 1: Environmental Review Committee (ERC) Report
Exhibit 2: SEPA Checklist dated April 21, 2023
Exhibit 3: Site Plan
Exhibit 4: Civil Plan Drawing (Overall Site Plan, Grading and Utility Plans, and Fire Access Plan)
Exhibit 5: Landscape Plans
Exhibit 6: Architectural Plan Drawings
Exhibit 7: Arborist Report, prepared by Washington Forestry Consultants, Inc dated November 15,
2023
Exhibit 8: Tree Retention Memo, prepared by Washington Forestry Consultants, Inc. dated October
25, 2023
Exhibit 9: Subsurface Exploration, Geotechnical Engineering, and Stormwater Infiltration Feasibility
Report, prepared by Associated Earth Sciences, Inc. dated January 31, 2024
Exhibit 10: Preliminary Technical Information Report, prepared by PacLand dated June 2023
Exhibit 11: Critical Areas Study, prepared by Altmann Oliver Associates, LLC dated July 8, 2022
Exhibit 12: Stream Buffer Restoration Plan, prepared by Altmann Oliver Associates, LLC dated March
4, 2024
Exhibit 13: Traffic Impact Analysis, prepared by Transpo Group dated August 2023
Exhibit 14: Street Modification Requests
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
City of Renton Department of Community & Economic Development
New Life Church Office Building
Staff Report to the Environmental Review Committee
LUA23-000330, ECF, CUP-H, SA-H, V-H
Report of June 3, 2024 Page 3 of 11
SR_ERC Report_New Life Church_240603_FINAL
Exhibit 15: Conditional Use Permit Request and Justification
Exhibit 16: Transportation Concurrency Memo dated December 15, 2023
Exhibit 17: Duwamish Tribe Comments dated December 4, 2023
Exhibit 18: Department of Fish and Wildlife Comments dated December 11, 2023
Exhibit 19: Construction Mitigation Description
Exhibit 20: Advisory Notes
D. Environmental Impacts
The Proposal was circulated and reviewed by various City Departments and Divisions to determine whether the
applicant has adequately identified and addressed environmental impacts anticipated to occur in conjunction with
the proposed development. Staff reviewers have identified that the proposal is likely to have the following probable
impacts:
1. Earth
Impacts: According to City of Renton (COR) Maps, a high seismic hazard, a high erosion hazard, and
sensitive and protected slopes are located on the project site. As such, the applicant submitted a
Subsurface Exploration, Geotechnical Engineering, and Stormwater Infiltration Feasibility Report,
prepared by Associated Earth Sciences, Inc. dated January 31, 2024 (Exhibit 9). The topography of the
developed portion of the site is generally flat, but ascends significantly to the south behind the existing
church building with a maximum elevation change of approximately 300 feet across the site. According to
the submitted report, the site is underlain by alluvial sediments, which are in turn underlain by Vashon or
pre-Vashon sediments, all soils associated with ridges and hills derived from glacial drift. The report relies
on subsurface exploration information from previous studies completed by the consultant for past
projects between 1998 and 2022. The studies relied on three (3) hand-auger borings, 23 subsurface
exploration borings, eighteen exploration pits, and two infiltration trenches. The report notes that the
nature and extent of any variations between the historic field explorations may not become fully evident
until construction and warns that it may be necessary to re-evaluate specific recommendations in the
report and make appropriate changes in the field.
Exploration borings nearest the project site and included in the report include EB-9, EB 10, EB 11, EB 12,
EB 13, and EB 14. The borings ranged in depth from approximately four (4) to 34 feet. During previous
testing, the geotechnical engineer encountered fill approximately one to nine feet (1’ to 9’) of fill
sediments (not naturally deposited) consisting of very loose to medium dense, silty, gravelly, fine sand, to
silty, sandy gravel with fragments of concrete, brick, and other construction materials. The report states
that due to the variable density and organic content in the fill, it is not suitable for direct structural report
and recommends assessment and remedial preparation of the existing fill to be completed at the time of
construction below all structures that are not pile-supported. Due to the silty and moisture sensitive
characteristics of the fill, the report recommends that construction occurs during dry weather conditions.
Based on past explorations, the site contains alluvium beneath the fill or surfacing materials, consisting of
loose to very loose, moist silt to sand with varying organic content and gravel. These soils are interpreted
as overbank deposits from the Cedar River, formed by flood events since the last glaciation. The fine -
grained alluvium layer, 5.5 to 15 feet thick, is underlain by Holocene-age gravel. In previous work on the
site, loose to medium dense gravel or sandy gravel was found beneath this alluvium in the northern part
of the site, likely deposited by the Cedar River and often saturated with groundwater seepage. Due to its
variable density and susceptibility to liquefaction during seismic events, the report concludes that
Holocene alluvium is unsuitable for structural support and stormwater infiltration. Below the Holocene
alluvium, deeper borings encountered dense to very dense, moist, silty sand with gravel. The material was
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
City of Renton Department of Community & Economic Development
New Life Church Office Building
Staff Report to the Environmental Review Committee
LUA23-000330, ECF, CUP-H, SA-H, V-H
Report of June 3, 2024 Page 4 of 11
SR_ERC Report_New Life Church_240603_FINAL
interpreted as an older Vashon or pre-Vashon-age glacially consolidated deposit and was found in historic
borings EB-1 through EB-3 and EB-7 below approximately 30 feet, and in EB-4 through EB-6, EB-8, and EB-
12 through EB-20 below approximately 15 feet. Other borings near the current project site terminated in
the Holocene alluvium.
In previous studies, groundwater was found at depths of 4.5 to 14 feet below the surface, in dicating a
shallow water table aquifer. In the northwest part of the site, moderate to heavy seepage came from sand
or gravel beds. A monitoring well installed in 2014 showed a seasonal high groundwater level of about
two-feet (2’) below the surface. In August 2022, moderate water flow was observed in Madson Creek, 2
two-feet (2’) below its bank full elevation of 104 feet.
The report next discusses the various geological hazards and if needed, recommended mitigation
measures for the hazard. Regarding the sensitive and protected slopes on the site, the report concludes
that no detailed quantitative assessment was conducted or deemed necessary due to the distance of
approximately 1,000 feet between the toe of slopes and the proposed work. The high seismic hazard
present across the site creates the potential for liquefaction during a seismic event. A liquefaction analysis
for the project completed using Liquefy Pro software found a predicted settlement during a design-level
seismic event range from approximately four to nine inches (4” to 9”). Therefore, the report recommends
the use of pin piles for the new building in order to mitigate the effects of settlements during a seismic
event. Lastly, the report includes various recommendations to mitigate for the high erosion hazard
mapped on the site. Specific recommendations include, but are not limited to, avoiding construction
activity during wet season, implementation of TESC elements and flow control prior to the start of
demolition and grading, and the immediate revegetation of any disturbed areas.
The report concludes that the proposed 6,400 sq. ft. building should be supported on pin piles to reduce
the risk of future floor slab settlement. However, the report also notes that a less expensive conventional
spread footing is acceptable but carries risk of post-construction static and seismically induced settlement
fill due to the weak sediments found below grade. Full infiltration is deemed infeasible due to the wide-
spread prevalence of glacially consolidated soils and shallow groundwater.
Due to the report’s confirmation of the liquefaction potential for the site and recommendations for
mitigating its effects during an earthquake, Staff recommends, as a mitigation measure, the applicant
comply with the recommendations of the geotechnical report, prepared by Associated Earth Sciences, Inc,
dated January 31, 2024, and any future addenda. Staff recommends the applicant’s geotechnical engineer
review the project’s construction and building permit plans to verify compliance with the geotechnical
report. The geotechnical engineer shall submit a sealed letter stating they have reviewed the construction
and building permit plans and in their opinion the plans and specifications meet the intent of the report(s).
Mitigation Measures:
1) The applicant shall comply with the recommendations of the
Subsurface Exploration, Geotechnical Engineering, and Stormwater Infiltration Feasibility Report,
prepared by Associated Earth Sciences, Inc. dated January 31, 2024, and any future addenda.
2) The applicant’s geotechnical engineer shall review the project’s construction and building permit
plans to verify compliance with the geotechnical report(s). The geotechnical engineer shall submit a
sealed letter stating they have reviewed the construction and building permit plans and in their
opinion the plans and specifications meet the intent of the report(s).
2. Air
Impacts: It is anticipated that some temporary air quality impacts could be associated with site work and
building construction. Project development impacts during construction may include dust as a result of
grading and exhaust from construction vehicles and equipment. Dust control would be mitigated through
the use of temporary erosion control measures, watering or other measures to remediate impacts as
needed. Long term emissions from vehicles owned by residents and delivery companies would occur
following project completion.
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
City of Renton Department of Community & Economic Development
New Life Church Office Building
Staff Report to the Environmental Review Committee
LUA23-000330, ECF, CUP-H, SA-H, V-H
Report of June 3, 2024 Page 5 of 11
SR_ERC Report_New Life Church_240603_FINAL
No further site-specific mitigation for the identified impacts from typical vehicle and construction exhaust
is required.
Mitigation Measures: None recommended.
Nexus: Not applicable.
3. Water
a. Surface Water (Stream and Wetlands)
Impacts: The project site is mapped with a wetlands and Type F stream (Madson Creek). As such, the
applicant submitted a Critical Areas Study, prepared by Altman Oliver Associates, LLC, dated July 8, 2022,
and a Stream Buffer Restoration memo, prepared by Altman Oliver Associates, LLC, dated March 4, 2024
(Exhibits 11 and 12). The Critical Areas Study was prepared for a project on the site involving an addition
to the main building that had the potential to impact the wetlands due to its location in the buffer.
However, the proposed new building is located fully outside of both the wetlands and stream buffer. The
report identifies Wetland A, located along the west property line of the site, as a Category II wetland with
seven (7) habitat points, which requires a 150-foot buffer and 15-foot structure setback per Renton
Municipal Code (RMC) 4-3-050G. According to the consultant’s observations, the wetland consists of a
historically excavated pond that consists of a forested plant community dominated by willow, black
cottonwood, and salmonberry. Overflow runoff within Wetland A drains west through a concrete dam
and eventually drains into Madson Creek which flows from northeast to southwest to the northwest of
the proposed project area. Work associated with the new proposed building would be located
approximately 700 feet from the edge wetlands buffer and therefore no impacts are anticipated.
Madson Creek is a Type F stream that requires a 115-foot buffer and 15-foot structure setback per RMC
4-3-050G. The creek flows from south to north adjacent to the existing building and parking a lot, bisecting
the site until it reaches the Maple Valley Hwy right-of-way (ROW). The creek then runs east along the
northern property line of the site until reaching a pipe that crosses under Maple Valley Hwy. The ordinary
high water (OHW) of the north side of the creek was delineated by the consultant on January 25, 2024
and was subsequently surveyed. Per the Complete Street Standards in RMC 4-6-060, the applicant is
required to underground any new utilities proposed as part of the project. The applicant has proposed
the installation of fiber line to connect the new building to a utility pole with fiber near the northwest
corner of the property within the Maple Valley Hwy ROW. The fiber line would be installed in trench dug
between Madson Creek and the sidewalk along the Maple Valley Hwy frontage until reaching the east
property line. The trench, resulting in approximately 2,100 sq. ft. of disturbed area, would be located
inside of the 115-foot buffer, which is heavily degraded between the creek and the sidewalk and mostly
vegetated with manicured grass and Himalayan blackberry. The applicant has proposed restoring
approximately 2,097 sq. ft. of disturbed area with native species including Red-osier dogwood, Ocean
spray, Tall Oregon-grape, Nootka rose, Kinnikinnick, and Salal. The applicant has also proposed
approximately 837 sq. ft. of buffer enhancement outside of the disturbed area. The enhancement
proposed would include replacing manicured grass and non-native Himalayan blackberry with native
plants. The report contends that the proposed restoration and enhancement would provide a higher
quality buffer that increases the stream function. Staff would further evaluate the proposal as part of the
formal site plan review and therefore no site-specific mitigation measures are recommended.
The city received a comment from Washington Department of Fish and Wildlife on December 11, 2023
recommending the applicant begin the free Hydraulic Project Approval (HPA) pre-application process to
determine whether the trenching occurring near Madson Creek would be required to get a HPA (Exhibit
18). Staff forwarded the comment from WDFW to the applicant upon receiving it.
Mitigation Measures: None recommended.
Nexus: Not applicable.
b. Ground Water
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
City of Renton Department of Community & Economic Development
New Life Church Office Building
Staff Report to the Environmental Review Committee
LUA23-000330, ECF, CUP-H, SA-H, V-H
Report of June 3, 2024 Page 6 of 11
SR_ERC Report_New Life Church_240603_FINAL
Impacts: The COR mapping system has identified the property as located within the Maplewood Wellhead
Protection Zone 2. Open facilities and open conveyance systems may require a liner in accordance with
the 2022 Renton Surface Water Design Manual. The implementation of best management practices
(BMPs) for stormwater control is preferable, and BMPs that rely on infiltration are allowed in Zone 2.
However, based on the results of the Subsurface Exploration, Geotechnical Engineering, and Stormwater
Infiltration Feasibility Report submitted by the applicant, infiltration is not feasible due to shallow ground
water and poor quality fill on the site. No fill is anticipated to be brought on the site. However, if fill is
brought on site, fill materials shall be from a verifiable source in order to ensure it is clear of contaminants.
The City’s grading and excavation regulations require imported fill in excess of 50 cubic yards within a
Wellhead Protection Zone to provide a source statement certified by a qualified professional or confirm
the fill was obtained from a WDOT approved source.
Mitigation Measures: None recommended.
Nexus: Not applicable.
c. Stormwater
Impacts: The applicant submitted a Preliminary Technical Information Report, prepared by PacLand,
dated June 2023 (Exhibit 10) and preliminary drainage plan (Exhibit 4). Based on the City of Renton’s flow
control map, the site falls within the Flow Control Duration Standard – Matching Forested. The site falls
within two (2) drainage basins including the Lower Cedar River Drainage Basin and Madson Creek sub-
basin. The proposed office building would interrupt existing drainage patterns in the parking lot and
therefore the applicant proposes new catch basins and a new twelve-inch (12”) storm drainage pipe to
collect and convey stormwater around the building to the existing on-site storm drainage system. No new
impervious surface is proposed as a result of the project.
The majority of stormwater runoff from the site sheet flows towards the north and enters the existing
conveyance system within the site. From there, runoff flows east and north into an existing retention pond
adjacent to SR 169, where it eventually discharges into the public conveyance system in the SR 169 ROW.
Improvements proposed for the project include the installation of a new 12-inch surface water pipe to
the west and north of the proposed building, in addition to three (3) new catch basins. In the preliminary
TIR, the applicant discusses Core Requirements 1 through 9. No new flow control or water quality
treatment infrastructure is proposed. The report concludes under Core Requirement #4 that the proposed
new twelve-inch (12”) pipe would have adequate capacity to convey existing flows.
Project construction is required to comply with the 2022 Renton Surface Water Design Manual (RSWDM).
The TIR submitted is based on a full drainage review as required in the 2022 Renton Surface Water Design
Manual. Core requirements one through nine, as well as the six special requirements, have been discussed
in the Technical Information Report. All requirements would be addressed in the final TIR submitted and
reviewed with the civil construction permit application. The advisory notes (Exhibit 20) highlight several
errors in the TIR that need to be addressed in the Final TIR. Staff’s opinion is that any changes can be
addressed with the civil construction permit review and are not critical at this time.
A Construction Stormwater Pollution Prevention Plan (CWWPPP) and Erosion and Sediment Control plan
(ESC) are also required for the site. The development would be subject to stormwater system
development charges. It is anticipated that the requirements set forth by the 2022 City of Renton Surface
Water Design Manual (2022 RSWDM), or a future stormwater manual adopted by the City of Renton,
would be sufficient to mitigate stormwater impacts generated by the proposed development and no
specific mitigation measures are recommended.
Mitigation Measures: None recommended.
Nexus: Not applicable.
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
City of Renton Department of Community & Economic Development
New Life Church Office Building
Staff Report to the Environmental Review Committee
LUA23-000330, ECF, CUP-H, SA-H, V-H
Report of June 3, 2024 Page 7 of 11
SR_ERC Report_New Life Church_240603_FINAL
4. Environmental Health
a. Noise
Impacts: Noise impacts would primarily result from the construction of the proposed road improvements
and new structure. The construction noise would be regulated through the City’s adopted noise level
regulations per Chapter 8-7, RMC. The City’s noise regulations limit haul hours between 8:30 am to 3:30
pm, Monday through Friday unless otherwise approved by the Development Services Division. Permitted
work hours in or near residential areas are restricted to the hours between seven o’clock (7:00) a.m. and
eight o’clock (8:00) p.m. for multi-family construction activities from Monday through Friday. Work on
Saturdays is restricted to the hours between nine o’clock (9:00) a.m. and eight o’clock (8:00) p.m. No work
is permitted on Sunday. Haul hours shall be restricted to the hours between eight-thirty (8:30) a.m. and
three-thirty (3:30) p.m., Monday through Friday unless otherwise approved in advance by the
Development Services Division. The applicant included a Construction Mitigation Description with the
applicant and noted that all work is anticipated to be completed during normal hours (Exhibit 19).
All noise levels would be required to comply with City of Renton code (Chapter 7 Noise Level Regulations)
and Washington Administrative Code (WAC 173-60, Maximum Environmental Noise Levels). The
anticipated temporary noise impacts would be those commonly associated with mixed-use construction.
No further site-specific mitigation is proposed.
Mitigation Measures: None recommended.
Nexus: Not applicable.
5. Vegetation
Impacts: The area near the location of the new building is primarily developed with impervious surface.
However, construction of the building would result in the removal of three (3) trees within existing parking
lot landscape islands. In addition, the installation of frontage improvements near the northeast corner of
the site will result in the removal of five (5) trees in the Maple Valley Hwy ROW. As such, the applicant
submitted an Arborist Report, prepared by Washington Forestry Consultants, Inc, dated November 15,
2023 (Exhibit 8). The report identifies three (3) Sweetgum trees ranging in size from five-inches (5”) to 6-
inches (6”) DBH, four (4) Freeman maple trees all three-inch (3”) DBH, and one ten-inch (10”) DBH
Scouler’s willow. While five (5) of the trees are located in areas of likely future ROW improvements to be
completed along Maple Valley Hwy as part of the project, City staff would evaluate these five (5) trees at
the time of civil construction permit application review to determine whether adjustments to frontage
improvements can be made in order to retain these trees. The planting of new trees and various ground
cover species would occur as part of the proposal along the street frontage, within the surface parking lot
area, and around the new building. Additional analysis of existing and proposed trees, including analysis
of the location, species, and size of retained trees, would occur during review of both the site plan and
the civil construction and building permits, therefore no site-specific mitigation is recommended.
Mitigation Measures: None recommended.
Nexus: Not applicable.
6. Historic and Cultural Preservation
Impacts: A representative of the Duwamish Tribe submitted a comment (Exhibit 17) to City staff on
December 4, 2023 indicating the project site is located in an area the Tribe considers culturally significant.
In addition, the Washington Department of Archaeology and Historic Preservation mapping tool indicates
a high potential for a historic Native trail in the area. The comment from the Tribe identifies the high
potential for discovery of unknown archeological deposits and requests notification of any archeological
work performed, the submittal of an inadvertent discovery plan (IDP), and the use of native vegetation
for any proposed re-planting. The applicant has already proposed replanting with native vegetation
according to the stream buffer restoration plan (Exhibit 12) and the landscape plan (Exhibit 5). As such,
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
City of Renton Department of Community & Economic Development
New Life Church Office Building
Staff Report to the Environmental Review Committee
LUA23-000330, ECF, CUP-H, SA-H, V-H
Report of June 3, 2024 Page 8 of 11
SR_ERC Report_New Life Church_240603_FINAL
staff recommends as a mitigation measure that the applicant submit an inadvertent discovery plan (IDP)
prior to the start of any construction. The applicant shall provide notification to Tribes’ cultural committee
prior to the start of construction.
Mitigation Measures: The applicant shall submit an Inadvertent Discovery Plan (IDP) prepared by a
qualified professional prior to the start of any construction. The applicant shall provide notification to
Tribes’ cultural committee prior to the start of construction.
Nexus: City of Renton Comprehensive Goals and Policies, L-AA, L-45 and L-46; Chapter 27.53 RCW,
Archaeological Sites and Resources; Chapter 27.44 RCW, Indian Graves and Records; Chapter 197-11 WAC,
SEPA Rules.
7. Transportation
Impacts: The proposed project fronts 152nd Ave SE along the eastern property line. 152nd Ave SE is
classified as a Commercial-Mixed Use & Industrial Access street and has an existing right-of-way (ROW) of
approximately 56 feet. To meet the City’s complete street standards for Commercial-Mixed Use &
Industrial Access streets, a minimum ROW width of 69 feet is required. Complete half street
improvements required for 152nd Ave SE include a 20-foot (20’) wide paved road, an eight-foot (8’) wide
parking lane, a six-foot (6’) wide sidewalk, a one-half foot (0.5’) wide curb, an eight-foot (8’) wide planting
strip, two-foot (2’) clearance between the sidewalk and property line, street trees and storm drainage
improvements. However, the City’s Transportation Department determined the existing curb to curb
width is sufficient. The applicant submitted a modification to retain the existing pavement, which staff
finds conceptually acceptable and will formally evaluate as part of the site plan review process.
The proposed project fronts Maple Valley Hwy (SR 169) along the northern property line. SR 169 is
classified as a Principal Arterial and has an existing right-of-way (ROW) width varying between 150 feet
and 165 feet. The paved roadway width adjacent to the site is approximately 84 feet consisting of two (2)
travel lanes in each direction, a center turn lane, a right turn lane on the south side, and a bus stop lane
on the north side. There is a concrete curb and five-foot (5’) wide sidewalk directly behind the curb along
each side of the roadway. Maple Valley Hwy is owned and maintained by the Washington Department of
Transportation (WSDOT). To meet the City’s complete street standards for Principal Arterial streets with
seven (7) lanes, a minimum ROW width of 125 feet is required. Complete half street improvements
required include six (6) eleven-foot (11’) wide travel lanes, one (1) twelve-foot (12’) wide left turn lane,
and two (2) five-foot (5’) wide bike lanes. A half-foot wide (0.5’) wide curb, eight-foot (8’) wide planter,
eight-foot (8’) wide sidewalk, two-foot (2’) clear space behind sidewalk, street trees and storm drainage
are required along each side of ROW. However, the City’s Transportation Department determined the
existing curb to curb width is sufficient. The applicant submitted a modification to retain the existing ROW
width, relocate approximately 200 feet of sidewalk near the northeast corner of the site behind a new
planter strip varying in width between six and eight feet (6’ – 8’), and retain the existing above-ground
utility lines, which staff finds conceptually acceptable and will formally evaluate as part of the site plan
review process. The applicant will also need WSDOT approval for any modifications to the ROW width or
improvements. ADA improvements are also proposed for the SR 169 and 152nd Ave SE crossings (Exhibits
4 and 19).
A Traffic Impact Analysis (TIA) is required when a project proposal would result in the generation of 20
new a.m. or p.m. peak hour trips. A TIA prepared by Transpo Group and dated August 2023 (Exhibit 13)
was submitted with the land use application. Due to the unique nature of the existing use, which has a
larger number of trips during weekend or non-peak hours due to various events and church services, the
TIA analyzed both typical weekday conditions and event conditions.
Typical Conditions
According to the TIA, the proposed project is estimated to generate 70 new weekday daily trips, with 10
new trips occurring during the weekday AM peak hour (9 in, 1 out), and 9 new trips occurring during the
weekday PM peak hour (2 in, 7 out). The calculation is based on the ITE Manual for Trip Generation, 11th
Edition. The TIA discussed traffic impacts at a future year of 2024 and evaluates the Level of Service (LOS)
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
City of Renton Department of Community & Economic Development
New Life Church Office Building
Staff Report to the Environmental Review Committee
LUA23-000330, ECF, CUP-H, SA-H, V-H
Report of June 3, 2024 Page 9 of 11
SR_ERC Report_New Life Church_240603_FINAL
at two (2) off-site intersections, 152nd Ave SE/SR 169 and 152nd Ave SE/SE 155th Pl. According to the report,
all study intersections are expected to operate at LOS E or better during the weekday AM and PM peak
hours in 2024 with or without the proposed project. Therefore, no project-specific off-site transportation
improvements are proposed as the existing transportation facilities are anticipated to accommodate the
additional traffic generated by the proposed project during typical conditions. Staff concurs with the
assessment provided by the applicant.
Event Conditions
Currently, New Life Church hosts multiple annual events with higher attendance than usual, such as Easter
and Christmas Eve. According to the TIA, the church collaborates with the City and community,
communicates event details in advance, adds traffic control and U-turn enforcements, and provides off-
site parking with shuttle services to minimize impacts and traffic disruptions to the surrounding
neighborhood. The proposed project is not expected to increase event demands or change event
conditions due to the office use-nature of the new building. However, Staff requested the applicant’s
consultant review traffic and parking for events compared to non-events. According to the counts
submitted by the applicant, a typical Sunday in July of 2023 had an attendance totaling 2,155 people
across three (3) services, Easter Sunday in 2023 had a total 3,569 attendees across three (3) services, and
Christmas Eve in December of 2022 had a total of 2,750 attendees. Both holidays have higher peak
attendance than typical Sundays, with Easter having the highest.
The event trip generation was estimated using observations from Easter Sunday, July 2023, calculating an
average vehicle occupancy (AVO) of 2.80 attendees per vehicle. Easter Sunday was used due to it having
the highest attendance among the various events. During the peak hour (10:15 – 11:15 a.m.), there were
626 vehicles (304 outbound for the first service and 322 inbound for the second service). For Easter, this
translates to an estimated peak hour trip generation of 803 vehicles. The consultant acknowledges that
the number may be conservative since holiday services often have more families per vehicle. The peak
hour trip generation calculation shows a 28% increase in peak hour trips (177 additional vehicles) for event
Sundays compared to typical Sundays. The additional trips were added to future 2024 Sunday peak hour
traffic volumes. The TIA discussed traffic impacts at a future year of 2024 and evaluates the Level of
Service (LOS) at two (2) off-site intersections, 152nd Ave SE/SR 169 and 152nd Ave SE/SE 155th Pl during
Sunday peak hour. According to the report, all study intersections are expected to operate at LOS C or
better during the Sunday peak hour in 2024 with or without the proposed project. Therefore, no project-
specific off-site transportation improvements are proposed, as the proposal is not anticipated to increase
the number of Sunday peak hour trips. Staff concurs with the assessment provided by the applicant.
Parking
The parking was reviewed under the event conditions given the reduction in parking supply proposed with
the addition of the office. The site currently has 796 parking stalls, but the project will eliminate 40, leaving
a total of 756 stalls. During peak events, 373 vehicles are estimated for the first service and 430 for the
second, resulting in a potential peak demand of 803 vehicles if services overlap. Typical Sunday demand
is 626 vehicles. Though full overlap is unlikely, the estimated peak demand exceeds the available parking
by 47 vehicles. This excess demand is managed by providing off-site parking and shuttle service from Ron
Regis Park at 1501 Orcas Ave SE across from the site on the north side SR 169, which has 80 parking stalls,
and is sufficient for the largest annual event. The consultant claims the applicant has a formal agreement
with the City of Renton for the use of the 80 stalls, which was verified by staff. Staff will complete
additional parking analysis at the time of formal site plan review to ensure compliance with the parking
regulations in RMC 4-4-080, therefore no further site-specific mitigation is recommended.
Transit Services
Transit service in the study area is provided by King County Metro. The nearest bus stops to the project
site are located at the intersection of Maple Valley Highway (SR 169) and 152nd Ave SE and is served by
Route 907. Route 907 is a dial-a-ride transit (DART) route, which has fixed routing and limited variable
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
City of Renton Department of Community & Economic Development
New Life Church Office Building
Staff Report to the Environmental Review Committee
LUA23-000330, ECF, CUP-H, SA-H, V-H
Report of June 3, 2024 Page 10 of 11
SR_ERC Report_New Life Church_240603_FINAL
routing with hourly service from 8 a.m. and 5 p.m. between Renton and Black Diamond. Additionally, the
project site (New Life Church) serves as a park and ride lot.
Safety
A review of the collision records from January 1, 2018, to December 31, 2022, provided by the Washington
State Department of Transportation (WSDOT) was conducted to identify traffic safety issues around the
project site. The intersection of Maple Valley Highway (SR 169) and 152nd Ave SE/154th Pl SE had the
highest annual average of collisions at about four (4) per year, mostly rear-end collisions causing property
damage, which is typical of congested areas with stop-and-go traffic according to the consultant. Along
152nd Ave SE, near the project site and SE 155th Pl, less than one collision per year was reported. There
were no fatalities or collisions involving pedestrians or cyclists in the study area. Overall, no safety concern
patterns were identified from the collision data and therefore no site-specific mitigation measures are
recommended.
Transportation Concurrency
Staff determined that at completion of the project, the development will have met City of Renton traffic
concurrency requirements (Exhibit 17), which is based upon a test of the citywide Transportation Plan,
consideration of growth levels included in the LOS-tested Transportation Plan, site specific improvements,
and future payment of Transportation Impact Fees. The transportation impact fee that is current at the
time of building permit issuance would be levied. It is anticipated that compliance with the City’s adopted
Street Standards (modified) and the payment of required Traffic Impact Fees would mitigate any adverse
impacts that could be generated by additional traffic attributed to the proposed subdivision; therefore,
no further mitigation is recommended.
Mitigation Measures: None recommended.
Nexus: Not applicable.
8. Fire & Police
Impacts: Police and Fire Prevention staff indicated that sufficient resources exist to furnish services to
the proposed development; provided the applicant constructs Code required improvements and pays
associated impact fees (Exhibit 20).
Mitigation Measures: None recommended.
Nexus: Not applicable.
E. Comments of Reviewing Departments
The proposal has been circulated to City Department and Division Reviewers. Where applicable, their comments
have been incorporated into the text of this report and/or “Advisory Notes to Applicant.”
✓ Copies of all Review Comments are contained in the Official File and may be attached to this report.
The Environmental Determination decision will become final if the decision is not appealed within the 14-day
appeal period (RCW 43.21.C.075(3); WAC 197-11-680).
Environmental Determination Appeal Process: Appeals of the environmental determination must be filed in writing
on or before 5:00 p.m. on June 17, 2024. Appeals must be submitted electronically to the City Clerk at
cityclerk@rentonwa.gov or delivered to City Hall 1st floor Lobby Hub Monday through Friday. The appeal fee, normally
due at the time an appeal is submitted, will be collected at a future date if your appeal is submitted electronically. The
appeal submitted in person may be paid on the first floor in our Finance Department. Appeals to the Hearing Examiner
are governed by RMC 4-8-110 and additional information regarding the appeal process may be obtained from the City
Clerk’s Office, cityclerk@rentonwa.gov.
✓
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
City of Renton Department of Community & Economic Development
New Life Church Office Building
Staff Report to the Environmental Review Committee
LUA23-000330, ECF, CUP-H, SA-H, V-H
Report of June 3, 2024 Page 11 of 11
SR_ERC Report_New Life Church_240603_FINAL
DocuSign Envelope ID: 8DC95E5E-DFD2-4FC3-AECA-A837B4E4B02A
CITY OF RENTON
DEPARTMENT OF COMMUNITY AND ECONOMIC DEVELOPMENT
STAFF REPORT TO THE ENVIRONMENTAL REVIEW COMMITTEE
EXHIBITS
Project Name:
New Life Church Office Building
Land Use File Number:
LUA23-000330, ECF, CUP-H, SA-H, V-H
Date of Meeting
June 3, 2024
Staff Contact
Alex Morganroth
Principal Planner
Project Contact/Applicant
John Kay, K+ Architects,
10317 8th Ave NE, Seattle,
WA 98125
Project Location
15711 152nd Ave NE (APN
2323059021)
The following exhibits are included with the ERC Report:
Exhibit 1: Environmental Review Committee (ERC) Report
Exhibit 2: SEPA Checklist dated April 21, 2023
Exhibit 3: Site Plan
Exhibit 4: Civil Plan Drawing (Overall Site Plan, Grading and Utility Plans, and Fire Access Plan)
Exhibit 5: Landscape Plans
Exhibit 6: Architectural Plan Drawings
Exhibit 7: Arborist Report, prepared by Washington Forestry Consultants, Inc, dated November 15, 2023
Exhibit 8: Tree Retention Memo, prepared by Washington Forestry Consultants, Inc. dated November 15,
2023
Exhibit 9: Subsurface Exploration, Geotechnical Engineering, and Stormwater Infiltration Feasibility Report,
prepared by Associated Earth Sciences, Inc.dated January 31, 2024
Exhibit 10: Preliminary Technical Information Report, prepared by PacLand dated June 2023
Exhibit 11: Critical Areas Study, prepared by Altmann Oliver Associates, LLC dated July 8, 2022
Exhibit 12: Stream Buffer Restoration Plan, prepared by Altmann Oliver Associates, LLC dated March 4,
2024
Exhibit 13: Traffic Impact Analysis prepared by Transpo Group dated August 2023
Exhibit 14: Street Modification Requests
Exhibit 15: Conditional Use Permit Request and Justification
Exhibit 16: Transportation Concurrency Memo dated December 15, 2023
Exhibit 17: Duwamish Tribe Comments dated December 4, 2023
Exhibit 18: Department of Fish and Wildlife Comments dated December 11, 2023
Exhibit 19: Construction Mitigation Description
Exhibit 20: Advisory Notes