Bryan Condon
From:Alex Morganroth <AMorganroth@Rentonwa.gov>
Sent:Wednesday, May 1, 2024 4:47 PM
To:Bryan Condon; Greg Reince; Manuel Cruz; William Adams; Michael Sippo
Cc:Kurt Addicott
Subject:RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow
Up
Attachments:Public Information Sign Handout.pdf
Follow Up Flag:Follow up
Flag Status:Flagged
Hi Bryan –
Apologies for the delay and thanks for your paence . This email will serve as your waiver form when you submit. The
items indicated below are also not waived for the shoreline exempon.
Please note that the Environmental (SEPA) Review and Shoreline Exempon will be processed concurrently . Only one
copy of overlapping submi’al items are needed. I’ve also responded to your specific quesons below in red.
The following items are waived for your submi’al:
Environmental Review
- #7 Rezone, Variance, Modification (assuming no variance or mod requested)
- #8 Density Worksheet
- #13 Architectural Elevations
- #16, 17, 18 Tree Documents (only waived if no trees proposed for removal)
- #19 Wetland Assessment
- #21 Flood Hazard Data (only waived if no work proposed in floodplain or floodway. If any work, structure or not,
is proposed, it is required)
- #29 Traffic Study
- #30 Color Rendering
- #31 Urban Design Regulations
Lastly, I’ve a’ached the public noce sign template . This sign needs to be installed before you submit the land use
applicaon. If you have any addional quesons, ple ase let me know.
Thank you,
ALEX MORGANROTH, AICP, Senior Planner
City of Renton | CED | Planning Division
1055 S Grady Way | 6th Floor | Renton, WA 98057
Virtual Permit Center | Online Applications and Inspections
(425) 430-7219 | amorganroth@rentonwa.gov
From: Bryan Condon
Sent: Wednesday, April 24, 2024 11:47 AM
To: Alex Morganroth <AMorganroth@Rentonwa.gov>; Greg Reince <greince@CenturyWest.com>; Manuel Cruz
2
<MCruz@rentonwa.gov>; William Adams <WAdams@Rentonwa.gov>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Hi Alex-
We have a few items that we’d like to run by you for clarification, if possible, ahead of our upcoming shoreline
exemption submittal:
· Waiver Form: This is described to be provided during the pre-submittal review. That review (and the waiver
form) are forthcoming, correct? See above.
· Land Use Permit Master Application Form: For this project, who would you expect to obtain the
notarizing of this form? Also, does your department provide an initial review of the form prior to the
notarizing (to address any initial comments that may come up)? The property owner should be signing the
master application with a notary. We do provide an initial review, which we refer to as a “presubmittal
review”, but you don’t need to hold off on submitting the master application to start it.
· Site Plan: Due to the orientation of the Airport, in order to accommodate the requirement for the north
arrow to oriented to the top of the paper/ plan sheet, the scale for the site plan will be 1”=350’. No issues.
· Neighborhood Detail Map: same comment as site plan above. No issues.
· Wetland Assessment: This will not be included in our submittal package because there are no wetlands
on-site. Confirmed – this requirement has been waived.
· Flood Hazard Data: Based on the description within the list of requirements, this component seems to be
related more to structures than a pavement rehab project such as this. Can you confirm that this item will
not be needed in our submittal? We do need flood hazard data if any ground is disturbed in the floodplain.
Thanks, Alex. We appreciate your time and guidance,
-Bryan
Bryan Condon, PE
Century West Engineering
765.532.8320 | bcondon@centurywest.com
From: Alex Morganroth <AMorganroth@Rentonwa.gov>
Sent: Monday, April 1, 2024 9:50 AM
To: Greg Reince <greince@CenturyWest.com>; Manuel Cruz <MCruz@rentonwa.gov>; William Adams
<WAdams@Rentonwa.gov>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>; Bryan Condon <bcondon@CenturyWest.com>; Jessica Redman
<JRedman@esassoc.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Hi Greg –
Please see below for responses to your quesons. Ju st an FYI, I will be out of the office starng tomorrow unl April 19 th.
If you’re targeng end of April, sounds like that s houldn’t be an issue.
Thank you,
Alex
ALEX MORGANROTH, AICP, Senior Planner
City of Renton | CED | Planning Division
3
1055 S Grady Way | 6th Floor | Renton, WA 98057
Virtual Permit Center | Online Applications and Inspections
(425) 430-7219 | amorganroth@rentonwa.gov
From: Greg Reince <greince@CenturyWest.com>
Sent: Friday, March 29, 2024 3:35 PM
To: Alex Morganroth <AMorganroth@Rentonwa.gov>; Manuel Cruz <MCruz@rentonwa.gov>; William Adams
<WAdams@Rentonwa.gov>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>; Bryan Condon <bcondon@CenturyWest.com>; Jessica Redman
<JRedman@esassoc.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Hi Alex,
We’re going to try and accelerate the permit submittal for this project (targeting end of April), and we had a few
follow up questions for you:
1. Who is the SEPA contact we should list? Your choice -this is typically the applicant or whoever is
responsible for answering questions related the checklist.
2. I assume we would include the Shoreline Exemption submittal with the permit package – but please
confirm if that should be separate. Yes, both will be reviewed concurrently. No need to provide two copies
of overlapping submittal items (i.e. site plan, master application, etc).
3. Would you be able to provide a Shoreline Exemption permit application template that has been reviewed
favorably by the City? We have the checklist, and all of the items appear straightforward. However, having
a favorable example the City has previously reviewed always helps out when inputting the info.
I’ve attached the submittal items for the Shoreline Exemption. There’s a few other ones floating around the
internet and want to make sure you have the correct one. Are you looking for an example of a specific item
on submittal requirements?
Thanks!
Greg
Greg Reince, PE | Senior Project Manager &
General Aviation Business Development Lead
Century West Engineering
541.322.8962 x301 | greince@centurywest.com
From: Greg Reince
Sent: Friday, March 1, 2024 4:11 PM
To: Alex Morganroth <AMorganroth@Rentonwa.gov>; Manuel Cruz <MCruz@rentonwa.gov>; William Adams
<WAdams@Rentonwa.gov>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>; Bryan Condon <bcondon@CenturyWest.com>; Jessica Redman
<JRedman@esassoc.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.
4
Thank you Alex—appreciate your input on this.
Greg Reince, PE | Senior Project Manager &
General Aviation Business Development Lead
Century West Engineering
541.322.8962 x301 | greince@centurywest.com
From: Alex Morganroth <AMorganroth@Rentonwa.gov>
Sent: Thursday, February 29, 2024 9:21 AM
To: Greg Reince <greince@CenturyWest.com>; Manuel Cruz <MCruz@rentonwa.gov>; William Adams
<WAdams@Rentonwa.gov>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>; Bryan Condon <bcondon@CenturyWest.com>; Jessica Redman
<JRedman@esassoc.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Hi Greg –
Thanks for your paence on this. It does appear tha t this updated scope would sll qualify as a “maint enance and
repair” acvity and as such, would be exempt from o btaining a Shoreline Substanal Development Permit. I’m basing
this off the fact that the project does not include any significant new impervious surface (correct me if I’m wrong
here). Just so you know what I’m looking at when I make that determinaon, I’ve included the criteria for
maintenance/repair exempons below –
c. Maintenance and Repair: Normal maintenance or repair of existing structures or developments, including damage by
accident, fire or elements.
i. “Normal maintenance” includes those usual acts to prevent a decline, lapse, or cessation from a lawfully
established condition.
ii. “Normal repair” means to restore a development to a state comparable to its original condition, including but not
limited to its size, shape, configuration, location and external appearance, within a reasonable period after decay or
partial destruction, except where repair causes substantial adverse effects to the shoreline resource or environment.
iii. Replacement of a structure or development may be authorized as repair where such replacement is the common
method of repair for the type of structure or development and the replacement structure or development is
comparable to the original structure or development including, but not limited to, its size, shape, configuration,
location and external appearance and the replacement does not cause substantial adverse effects to shoreline
resources or environment.
To add to Mike’s response on the Lake Washington erosion control, I’d recommend working with your biologist on what
kind of erosion control is appropriate to prevent impacts to the lake during construcon.
If you have any further quesons, please let me kno w.
Thank you,
Alex
ALEX MORGANROTH, AICP, Senior Planner
5
City of Renton | CED | Planning Division
1055 S Grady Way | 6th Floor | Renton, WA 98057
Virtual Permit Center | Online Applications and Inspections
(425) 430-7219 | amorganroth@rentonwa.gov
From: Greg Reince <greince@CenturyWest.com>
Sent: Thursday, February 22, 2024 10:11 AM
To: Manuel Cruz <MCruz@rentonwa.gov>; William Adams <WAdams@Rentonwa.gov>; Alex Morganroth
<AMorganroth@Rentonwa.gov>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>; Bryan Condon <bcondon@CenturyWest.com>; Jessica Redman
<JRedman@esassoc.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
All,
Thanks again for your me yesterday to discuss this project. I’ve included the notes to this email and also included with
Folder link below.
Alex, there were a few acon items for you to follo w up on summarized below:
VI. Action Items
· Alex
o Look into previous submittal information and look into any changes to required permit info
o Look into shoreline exemption for project
o Follow up questions from email
For the last acon item bullet, we had a few addio nal quesons pop up internally aRer our meeng that we’d like your
input on:
· Do permits need to be issued before we advertise the project for bidding? Or just before construction begins?
· Are there any particular erosion control measures that need to be taken on work near Lake Washington? Recall
that the Taxiway A1 area and sea plane ramp in blue on the project exhibit will be reconstructed with a 16”
pavement section.
Thanks!
Greg
Greg Reince, PE | Senior Project Manager &
General Aviation Business Development Lead
Century West Engineering
541.322.8962 x301 | greince@centurywest.com
From: Greg Reince
Sent: Tuesday, February 20, 2024 11:14 PM
To: Manuel Cruz <MCruz@rentonwa.gov>; William Adams <WAdams@Rentonwa.gov>; Alex Morganroth
<AMorganroth@Rentonwa.gov>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>; Bryan Condon <bcondon@CenturyWest.com>; Jessica Redman
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.
6
<JRedman@esassoc.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Alex and team:
See link below to agenda and a’achments for our discussion Wednesday at 1:00pm.
2024-02-21 City Permit Check In Meeng
Thanks!
Greg
Greg Reince, PE | Senior Project Manager &
General Aviation Business Development Lead
Century West Engineering
541.322.8962 x301 | greince@centurywest.com
From: Greg Reince
Sent: Tuesday, February 13, 2024 2:03 PM
To: Manuel Cruz <MCruz@rentonwa.gov>; William Adams <WAdams@Rentonwa.gov>; Alex Morganroth
<AMorganroth@Rentonwa.gov>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Sounds good Manny—will send for 2:30 on Tuesday 2/20. That’s the me that worked for our team.
Greg Reince, PE | Senior Project Manager &
General Aviation Business Development Lead
Century West Engineering
541.322.8962 x301 | greince@centurywest.com
From: Manuel Cruz <MCruz@rentonwa.gov>
Sent: Tuesday, February 13, 2024 1:58 PM
To: William Adams <WAdams@Rentonwa.gov>; Alex Morganroth <AMorganroth@Rentonwa.gov>; Greg Reince
<greince@CenturyWest.com>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Thanks Will - Tuesday (2/20) between 1pm and 4pm.
From: William Adams <WAdams@Rentonwa.gov>
Sent: Tuesday, February 13, 2024 1:56 PM
To: Manuel Cruz <MCruz@rentonwa.gov>; Alex Morganroth <AMorganroth@Rentonwa.gov>; Greg Reince
<greince@CenturyWest.com>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Manny,
What days/mes below work best for you?
Thank you,
7
WILLIAM ADAMS, P.E. | Civil Engineer III
Renton Municipal Airport (RNT) | Clayton Scott Field
616 West Perimeter Road | Unit A | Renton WA 98057
wadams@rentonwa.gov | www.rentonwa.gov/fly
C: (206) 775-6862
In Office Hours: M,W,Th Telework: T
From: Manuel Cruz <MCruz@rentonwa.gov>
Sent: Tuesday, February 13, 2024 1:53 PM
To: William Adams <WAdams@Rentonwa.gov>; Alex Morganroth <AMorganroth@Rentonwa.gov>; Greg Reince
<greince@CenturyWest.com>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: Kurt Addicott <KAddicott@CenturyWest.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Is there a meeng invite for the next meeng that s omeone can send please.
Regards,
Manny
From: William Adams <WAdams@Rentonwa.gov>
Sent: Tuesday, February 13, 2024 11:49 AM
To: Alex Morganroth <AMorganroth@Rentonwa.gov>; Greg Reince <greince@CenturyWest.com>; Michael Sippo
<MSippo@Rentonwa.gov>
Cc: Manuel Cruz <MCruz@rentonwa.gov>; Kurt Addicott <KAddicott@CenturyWest.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Alex,
I believe Manny will take my place at the meeng si nce I will be out on paternity leave unl March 6 th.
Thank you,
WILLIAM ADAMS, P.E. | Civil Engineer III
Renton Municipal Airport (RNT) | Clayton Scott Field
616 West Perimeter Road | Unit A | Renton WA 98057
wadams@rentonwa.gov | www.rentonwa.gov/fly
C: (206) 775-6862
In Office Hours: M,W,Th Telework: T
From: Alex Morganroth <AMorganroth@Rentonwa.gov>
Sent: Tuesday, February 13, 2024 11:41 AM
To: Greg Reince <greince@CenturyWest.com>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: William Adams <WAdams@Rentonwa.gov>; Manuel Cruz <MCruz@rentonwa.gov>; Kurt Addicott
<KAddicott@CenturyWest.com>
Subject: RE: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Hi Greg –
Mike and I would be happy to meet virtually this week or next. Below are a few mes we’re available.
8
Wednesday (2/14) anyme between 1pm and 4pm
Thursday (2/15) between 3pm and 4pm
Tuesday (2/20) between 1pm and 4pm
Wednesday (2/21) between 1pm and 4pm
I’ll let William at the airport provide his availability and we can set up a me.
Thank you,
Alex
ALEX MORGANROTH, AICP, Senior Planner
City of Renton | CED | Planning Division
1055 S Grady Way | 6th Floor | Renton, WA 98057
Virtual Permit Center | Online Applications and Inspections
(425) 430-7219 | amorganroth@rentonwa.gov
From: Greg Reince <greince@CenturyWest.com>
Sent: Monday, February 12, 2024 4:22 PM
To: Alex Morganroth <AMorganroth@Rentonwa.gov>; Michael Sippo <MSippo@Rentonwa.gov>
Cc: William Adams <WAdams@Rentonwa.gov>; Manuel Cruz <MCruz@rentonwa.gov>; Kurt Addicott
<KAddicott@CenturyWest.com>
Subject: Taxiway A Reconstruction/Rehabilitation and Associated Improvements (PRE23-000088) - Follow Up
Hi Alex and Michael:
I wanted to check in with you about the Airport’s Taxiway A Project (PRE23-000088). We have been in a holding pa’ern
since September awaing the funding agency, Federal Aviaon Administraon (FAA), input on the scope/ap proach to
the project. I won’t bore you with the details, but we had to come up with a plan to reduce the project cost from about
$25 million to $17 million. We have accomplished that, but we won’t be performing all of the work items we originally
proposed with the pre-applicaon meeng last year. I think there would be value in having a brief (no more than ½
hour) conference call to discuss and review next steps and make sure we’re all on the same page with this new
approach. I’d also like to re-confirm environmental and permit applicaon ming with our revised projec t schedule.
We’ll now be adversing the project for contractor bidding later this summer with actual construcon w ork to occur in
2025 and 2026.
Could you please propose some meeng mes you (and whoever else you think needs to parcipate on the C ity side)
are available in the next 1-2 weeks? I can coordinate our schedule with the Airport and setup a teams call once I see
some proposed meeng mes.
Apologies as well if this should just be addressed to one of you and not both—I know I had project correspondence with
both, so I figured I’d at least start with both of you for now.
Thank you!
Greg
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.
9
Greg Reince, PE | Senior Project Manager &
General Aviaon Business Development Lead
1020 SW Emkay Drive, Suite 100 | Bend, OR 97702
541.322.8962 x301 (office) | 208.651.0814 (cell) | greince@centurywest.com