HomeMy WebLinkAboutExhibit 2_Bannwarth EmailFrom: Brianne Bannwarth
Sent: Wednesday, March 07, 2018 8:50 AM
To: 'Richard Cardoza'
Cc: Alex Morganroth
Subject: RE: Verizon LUA 17-000868 Cell on Wheels - Renton Industrial
Attachments: copy-P_Site Plan_171121_v1.pdf
Hello Richard,
After discussion with Public Works, the City will allow you to locate the Cell on Wheels in the location
you proposed under the following conditions:
1. A 10-inch gate valve will need to be installed on the existing 10-inch water main. One gate valve
will need to be installed near the northwest corner of the building, south of the existing hydrant
and fire sprinkler supply line to the building. Please see attached for graphical representation of
the gate valve location.
a. The new isolation valve along with the existing valve at the southwest corner of the
building will allow the City to isolate this section of the water main in case of a main
break and still maintain fire protection service to the building. This will also allow time
for the City to notify Verizon to temporarily move their equipment so that the City can
repair the line.
b. In accordance with City Code, all work on existing water mains needs to be performed
by the City’s Public Works Department, therefore, Verizon will need to pay for City Staff
to install these valves.
c. Estimated cost of the cut in for the 10-inch valves and restoration the parking lot is
between $6,000 to $7,500. If a specialized billing letter is provided, the City can invoice
Verizon for the work.
2. Verizon will need to provide the City with a Hold Harmless Agreement in case equipment is
damaged by a main break near this antenna location.
Please let us know if the above is acceptable and Alex can proceed with the Land Use request.
Take Care,
BRIANNE BANNWARTH, P.E. | Development Engineering Manager
Community & Economic Development Department | Planning Division
City of Renton | 1055 S. Grady Way | Renton WA 98057
BBannwarth@Rentonwa.gov | Phone: 425.430.7299
Please consider the environment before printing this email
EFFECTIVE JANUARY 1, 2018 THE COMMUNITY AND ECONOMIC DEVELOPMENT
DEPARTMENT PERMIT COUNTER WILL CLOSE AT 4:00 P.M. DAILY
Permit Counter 8:00 a.m. to 4:00 p.m.
Financial Transactions 8:00 a.m. to 4:30 p.m.