HomeMy WebLinkAboutContractDocusign Envelope ID: 2BC0D1E6-2FEC-4001-BCD1-795829773D3D
PublicWorks
FacilitiesDivision ORIGINAL CONTRACTNO:CAG-17-214 CO NO. 8
REVISEDCONTRACT NO: CAG-24-209
CONTRACTCHANGEORDER(CO)PROJECTTITLE: RCH Elevator Modernization
TO: R. C. Zeigler Company, Inc (CONTRACTOR}
TO: ELTECSystemsLLC (CONTRACTOR}
The following mutually agreed to, and Owner approved Change Order Proposal(s} and/or Field Authorization(s} are
hereby incorporated by reference into the contract.
Description Amount
1 AssignmentofContractand GeneralConditions and Specifications for
Elevator Full-Service Preventative/Extended Maintenance from R. C.
Zeigler Company to ELTEC Systems LLC. No other change in any
contract terms - attached.
2 Deduct Remainder of Extended Five (5} Year Maintenance
Contract Cost from RC Zeigler Company Base ContractAmount
WSST (10.3%}
TotalDeductiveAmount
$(86,516.83}
$(8,911.23}
$(95,428.07)
3 Assign remaining two yearsand sixmonthsof the Maintenance
Contract Cost - including WSST to ELTEC Systems LLC
WSST (10.3%}
Total Additive Amount
$86,516.83
$8,911.23
$95,428.07
CONTRACT SUMREVISION - RC Zeigler Company
NO CHANGE OF: Ninety-five thousand four hundred twenty-eight dollars and $.07
INCREASE (WASHINGTONSALESTAXINCLUDED}
X DECREASE
CONTRACT SUMREVISION - ELTEC Systems,LLC
NO CHANGE OF: Ninety-five thousand four hundred twenty-eight dollars and $.07
X INCREASE (WASHINGTONSALESTAXINCLUDED}
DECREASE
CONTRACTTIME:
X NO CHANGE OF:
INCREASE CALENDARDAYS
DECREASE
The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect.
$95,428.07
0
CAG-24-209
Docusign Envelope ID: 2BC0D1E6-2FEC-4001-BCD1-795829773D3D
CONTRACTSummary(InternalUseOnly)
ORIGINALCONTRACT SUM-RC ZeiglerCompany $1,646,398.00
PREVIOUS ADDITIONS/DELETIONS $ 267,817.92
PREVIOUS TOTAL $1,914,215.92
CHANGE AMOUNT THIS CHANGE ORDER -($95,428.07}
REVISED CONTRACT TOTAL - RC ZEIGLER COMPANY $1,818,787.87
NOTICE TO PROCEED DATE -RC ZIEGLER Company Inc. March1,2018
PREVIOUS CONTRACT CALENDAR DAYS 1063
PREVIOUS SUBSTANCIAL COMPLETION DATE January27,2021
REVISED CONTRACT CALENDAR DAYS THIS CHANGE ORDER 0
ACTUAL SUBSTANTIAL COMPLETION DATE - RCZEIGLER COMPANY January 27, 2021
WARRANTY MAINTENANCE EXPIRATION DATE - RCZEIGLER COMPANY January 27, 2022
EXTENDED FIVE (5) YEAR MAINTENANCE COMMENCEMENT DATE- ELTEC SYSTEMS LLC February 1, 2022
EXTENDED FIVE (5) YEAR MAINTENANCE COMPLETION DATE- ELTEC SYSTEMS LLC February 1, 2027
CHANGE ORDER 8 to the RCH Elevator Modernization Contract CAG 17-214 is by and between the City of Renton
(the "City"}, a Washington municipal corporation, and R.C. Ziegler Company. ("Contractor"}, a Washington
corporation, and ELTEC Systems, LLC ("Contractor/ELTEC}} a Washington Corporation. The City, and RC Ziegler
Company and ELTEC Systems LLC are referred to collectively in this Agreement as the "Parties.". Once fully executed
by the Parties, this Change Order is effective as of the last date signed by all parties.
Whereas, the City contracted with RC Ziegler Company on March 1, 2018, to provide construction
services for the RCH Elevator Modernization project (referred to herein as the "Contract"};
Whereas, the Parties wish to amend the Contract to provide for Consent to Assignment of the Contract from RC
Ziegler Company to ELTEC Systems, LLC (Identified Subcontractor for the Extended two years six months
Maintenance} to provide the Extended Five (2} Year six months left for Maintenance per the terms and conditions of
the original contract.
NOW THEREFORE, it is mutually agreed upon that CAG-17-214 is amended as follows:
1. Successors and Assigns.
The City agrees and consents to the assignment of this to provide the scope of work as defined within CAG-17-214
incorporated by reference in this Change Order to provide the scope of work per the attached Contract and General
Conditions and Specifications for Elevator Full-Service Preventative/Extended Maintenance (Exhibit A-8} from R. C.
Zeigler Company to ELTEC Systems LLC. as follows:
A.The executed Change Order and fees described in attached Exhibit A-8 are accurate and complete.
B. The Contract terms and conditions per Exhibits A-8 are in full force and effect. For tracking purposes
Exhibit A-8 will be assigned CAG-24- 209 .
C.Eltec Systems LLC will provide insurance documents to the City pursuant to the terms of CAG-17-214.
D.Eltec Systems LLC will provide a payment and performance bond equal to 100% of the value of
the Extended two years six months Maintenance Agreement.
E. Prevailing Wage Rates: Contractor to comply with State of Washington prevailing wage
Docusign Envelope ID: 2BC0D1E6-2FEC-4001-BCD1-795829773D3D
ect Acknowledge
RC Zeigler Company
7/21/2024
requirements. Contractor must file an Intent to Pay Prevailing Wage at the beginning ofthe project
and at the beginning of each calendar year and an Affidavit of Wages Paid at the end of each
calendar year and at the end of the project with the Washington State Department of Labor and
Industries. *Final payment will be held until Affidavit of Wages Paid is submitted for each
period/calendar year or end of project.
The State of Washington prevailing wage rates applicable for this project, which is located in King County, may
be found at the following website address of the Department of Labor and Industries:
http://www.lni.wa.gov/TradesLicensing/PrevWage/default.asp
http://www.lni.wa.gov/TradesLicensing/PrevWage/WageRates/default.asp
Pursuant to WAC 296-127-011, the applicable effective date for prevailing wage rates paid for the
duration of this contract shall be the date the contract is executed as reflected in the "Effective Date"
identified at the top of the first page of the Agreement.
2.All terms of the Agreement not explicitly modified herein shall remain in full force and effect and
such terms shall apply to Work performed according to this Contract as if fully set forthherein.
3.The City of Renton hereby accepts the foregoing Field Authorization(s} and/or Change Order
Proposal(s}. This formal acceptance constitutes a Change to the contract only when authorizing signature is
affixed. Invoices incorporating this Change Order constitute acceptance by the Contractor as total
reimbursement due in connection with this Change Order.
ACKNOWLEDGEMENTS
7/16/24
Archit ct Acknowledgement Date
Contractor Acknowledgement Date
ELTEC Systems LLC
CITY OF RENTON
By:
Armondo Pavone, Mayor
Date
Attest
Jason A. Seth, City Clerk
ApprovedastoLegalForm
By:
Shane Moloney, City Attorney
Contractor Acknowledgement
7/22/2024
Date
07/31/2024
Approved by Cheryl Beyer via email 7/22/2024