CAG-22-178 C.O.# 1
PROJECT NAME: 2022-2023 Cedar River Maintenance Dredge Project -Vegetation Management
CONTRACTOR: Applied Ecology, LLC
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the
extra work as outlined below:
BID ITEM NO.
A-02
A-04
NEW
A-08
CONTRACT
AGREEMENT
6_C01 to CAG-22-178.xlsx
Additional Quantities Under This Change Order
Description
Shrubs
Increased total number of shrubs to be installed from 124 to
234.
Invasive Species Control
Increased the total number of invasive species control sweeps
from 8to 12.
2024 Site Walk and Documentation
Added 2024 site walk to show Applied Ecology the areas of work
and added 2024 required documentation denoting when/where
work is completed to be submitted to the City of Renton.
TERM OF AGREEMENT: EXTENSION
Contract expiration date revised from February 29, 2024 to
February 28, 2025.
Total
Unit
Type
EA
EA
LS
N/A
Est.
Qty.
110
4
1
N/A
Unit Price
$28.00
$8,400.00
$10,000.00
N/A
Total
Amount
$3,080.00
$33,600.00
$10,000.00
N/A
$46,680.00
1 of 2
CAG-22-178, CO #1-24
7/17/24
Approved by Cheryl Beyer via email 7/17/2024