HomeMy WebLinkAboutEX_44_I-405 BRT - BT105 SRTC Project History 10.15.24I-405 BRT
BT105 SRTC Project History
Pre-2016
• ST/City coordination on what is included in Sound Transit 3 Plan (ST3).
2016
• ST3 approved by voters, which included the South Renton Transit Center as part of the new
Stride Bus Rapid Transit (BRT) program. 2018/2019
• Level 1/Level 2 alternatives evaluation via conceptual design Interagency group workshops with
the City, WSDOT, ST, and KCM. Workshops evaluated 10+ conceptual designs/site schemes.
2020
• ST/City coordination on 10% conceptual engineering plans.
• SEPA Determination of Non-Significance (DNS) issued in September 2020.
2021
• ST participation in City-convened Stakeholder Workgroup Meetings for Rainier/Grady Junction
TOD Subarea Plan.
2022/2023
• ST/City coordination on 30% preliminary engineering plans.
• Started monthly ST/City coordination meetings to collaborate on a variety of design topics
related to the revised potential future parking garage location and design refinements for 60%
and 90% engineering plans in May 2022.
2024
• SEPA Addendum issued to cover surface parking and minor design updates to the transit center
and roadway improvements in June 2024.
• CUP and associated land use applications submitted to City in June 2024.