Loading...
HomeMy WebLinkAboutM_May_Creek_Ripley_Lane_Schedule_180320_v1ID Task Name Duration Start Finish 1 95% Design Completion 35 days Thu 1/11/18 Thu 3/1/18 2 County Review of 90% Documents 5 days Thu 1/11/18 Wed 1/17/18 3 Otak Construction Document Revision 2 wks Thu 1/18/18 Wed 1/31/18 4 Permitting (City of Renton)4 wks Thu 2/1/18 Wed 2/28/18 5 Parks PM Complete Special Provisions/Validate Drawing Set for Internal QC Review 3 days Thu 2/1/18 Mon 2/5/18 6 Parks Internal QC Review 2 wks Thu 2/8/18 Wed 2/21/18 7 Incorporation of QC Review comments into Contract Documents (Otak and Parks PM) 1 wk Thu 2/22/18 Wed 2/28/18 8 Forward Contract Documents to KC Procurement 0 days Thu 3/1/18 Thu 3/1/18 9 Procurement Phase 45 days Thu 3/1/18 Wed 5/2/18 10 Procurement Agent Review/Parks PM Coordination 2 wks Thu 3/1/18 Wed 3/14/18 11 Advertise Project 3 wks Thu 3/15/18 Wed 4/4/18 12 Pre-Bid Meeting 0 days Wed 3/21/18 Wed 3/21/18 13 Bid Opening 0 days Thu 4/5/18 Thu 4/5/18 14 Award Contract 4 wks Thu 4/5/18 Wed 5/2/18 15 Construction Phase 62 days Thu 5/3/18 Mon 7/30/18 16 NTP 1 - Concrete Deck Panels 0 days Thu 5/3/18 Thu 5/3/18 17 Shop Drawings Prep (Deck Panels)1 wk Thu 5/3/18 Wed 5/9/18 18 Shop Drawings Review (Deck Panels)1 wk Thu 5/10/18 Wed 5/16/18 19 Lead Time for Deck Panels 6 wks Thu 5/17/18 Wed 6/27/18 20 NTP 2 - Construction (on site)0 days Mon 6/18/18 Mon 6/18/18 21 Construction 6 wks Mon 6/18/18 Fri 7/27/18 22 Project Complete (Ripley Lane) Seahawks Training Begins 0 days Sun 7/15/18 Sun 7/15/18 23 Project Complete May Creek 0 days Mon 7/30/18 Mon 7/30/18 3/1 3/21 4/5 5/3 6/18 7/15 7/30 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6 5/13 5/20 5/27 6/3 6/10 6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 December January February March April May June July August Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 1 Project: 18.02.15 May Creek - Rip Date: Thu 2/15/18