No preview available
HomeMy WebLinkAboutChange Order - 2510/17/2024 10/26/2024 CAG-22-163, CO #25-24 Approved by Cheryl Beyer via email 10/18/2024 Attest:__________________________________ City Clerk, Jason A. Seth 12/2/2024 Change Order No. 25 Contract Title: Rainier Ave S. Corridor Improvements – Phase 4 Contract No. CAG-22-163 Page 2 of 56 THE CONTRACT IS MODIFIED AS FOLLOWS: Description of Change: This Change requires the Contractor to remove and abandon existing franchise utility duct banks, gas mains, vaults, and handholes. Proposal Schedule of Prices: DELETE the following bid items from Schedule D: 25-D4 – Remove/Abandon Existing Gas Main, -960 LF @ $27.00 = -$25,920.00 25-D11 – Removal of Structures and Obstructions, -1 LS @ $65,245.00 = - $65,245.00 ADD the following bid items to Schedule D: 25-D62 – Gravel Borrow Inc. Haul, 3,000 TN @ $24.20 = $72,600.00 25-D71 – Traffic Control for Franchise Utility Infrastructure Removal, 1 LS @ $13,000.00 = $13,000.00 25-D72 – Traffic Control Supervisor for Franchise Utility Infrastructure Removal, 1 LS @ $9,000.00 = $9,000.00 25-D73 – Flagging for Franchise Utility Infrastructure Removal, 750 HR @ $99.00 = $74,250.00 25-D74 – Other Traffic Control Labor for Franchise Utility Infrastructure Removal, 250 HR @ $105.00 = $26,250.00 25-D75 - Franchise Utility Infrastructure Removal, 1 LS @ $1,016,000.00 = $1,016,000.00 Specification and/or Special Provision: DELETE third paragraph of Section 2-02.3(6) SP as follows: Following energization of the new power and telecommunication systems, portions of existing duct banks and conduits that are in conflict with other items of work shall be removed completely and/or sawcut and capped with a solvent weld PVC cap at the limits of interference. Removal and disposal of vaults, handholes, pedestals, pipe segments and capping of ducts to be abandoned shall be considered incidental and included in the Schedule D lump sum contract prices for “Removal of Structures and Obstructions” and no additional payment will be made. Change Order No. 25 Contract Title: Rainier Ave S. Corridor Improvements – Phase 4 Contract No. CAG-22-163 Page 3 of 56 And REPLACE third paragraph of Section 2-02.3(6) SP with the following: Following energization of the new power and telecommunication systems, portions of existing duct banks and conduits that are in conflict with other items of work shall be removed completely and/or sawcut and capped with a solvent weld PVC cap at the limits of interference. See Section 8-35 for Measurement and Payment. Description: None. Materials: None. Construction Requirements: Measurement: 1-10.4 SP is supplemented with the following: No specific unit of measurement shall be applied to the lump sum item “Traffic Control for Franchise Utility Infrastructure Removal.” No specific unit of measurement shall be applied to the lump sum item “Traffic Control Supervisor for Franchise Utility Infrastructure Removal.” “Flagging for Franchise Utility Infrastructure Removal,” per hour. “Other Traffic Control Labor for Franchise Utility Infrastructure Removal,” per hour. 8-35.4 SP is revised as follows: DELETE the second paragraph as follows: No specific unit of measurement shall apply to the lump sum item for “Removal of Structures and Obstruction” as shown on the Plans and specified in Section 2- 02. And REPLACE with the following: No specific unit of measurement shall apply to the lump sum item for “Franchise Utility Infrastructure Removal” as shown on the Plans and specified in Section 2- 02. SP 2-02.3(6) Change Order No. 25 Contract Title: Rainier Ave S. Corridor Improvements – Phase 4 Contract No. CAG-22-163 Page 4 of 56 Payment: 1-10.5 SP is supplemented with the following: “Traffic Control for Franchise Utility Infrastructure Removal,” lump sum. “Traffic Control Supervisor for Franchise Utility Infrastructure Removal,” lump sum. “Flagging for Franchise Utility Infrastructure Removal,” per hour. “Other Traffic Control Labor for Franchise Utility Infrastructure Removal,” per hour. 8-35.5 SP is revised as follows: DELETE the second paragraph as follows: "Removal of Structure and Obstruction", lump sum. (Section 2-02) Payment for the removal of various structures and obstructions will be made at the amount bid per lump sum, which payment will be complete compensation for all labor, materials, tools, equipment, incidentals necessary to complete the work as defined in the specifications and as shown on the contract plans, including but not limited to the removal of existing duct banks, utility vaults, pedestals, and risers, capping and plugging abandoned duct banks, and all other surface obstructions. All costs associated with structure and roadway excavation and backfill of the resultant void with gravel borrow associated with the removal of structure and obstruction shall be considered incidental to and included in the lump sum contract price and no additional payment will be made. The contract bid price above, including all incidental work, shall be full compensation for all labor, material, tools, and equipment necessary to satisfactorily complete the work as described in Section 8-35.3(6) of these Special Provisions. And REPLACE with the following: “Franchise Utility Infrastructure Removal,” lump sum. Payment for Franchise Utility Infrastructure Removals will be made at the bid item amount per lump sum, which payment will be complete compensation for all labor, materials, tools, equipment, incidentals necessary to complete the work as defined in the specifications and as shown on the contract plans, including but not limited to the removal of existing duct banks, gas mains, utility vaults, handholes, capping and plugging abandoned duct banks and gas main, and all other obstructions. Saw cutting, demolition, haul, and disposal of materials to which this Bid item applies shall also be considered incidental. Change Order No. 25 Contract Title: Rainier Ave S. Corridor Improvements – Phase 4 Contract No. CAG-22-163 Page 5 of 56 The contract bid price above, including all incidental work, shall be full compensation for all labor, material, tools, and equipment necessary to satisfactorily complete the work as described in Section 8-35.3(6) of these Special Provisions. Materials Specifications: None. Plans: DELETE Plan Sheets 144, 145, 146, 147, 148, 149, 150, 151, and 162 and REPLACE with attached Plan Sheets 144, 145, 146, 147, 148, 149, 150, 151, and 162. Reason for Change: The franchise utilities requested that the City of Renton perform the removal and abandonment of the existing duct banks, gas mains, vaults, and handholes rather than to remove the existing duct banks, gas mains, vaults, and handholes themselves as required in their respective joint utility trench agreements. Therefore, the City revised the plans to require the Contractor to remove and abandon existing duct banks, gas mains, vaults, and handholes as needed to facilitate the proposed work. Equitable Adjustment: This Change Order does include an equitable adjustment per Section 1- 09.4 of the 2022 WSDOT/APWA Standard Specifications. See attached. Estimated Cost: $1,119,935.00 Extended Overhead: $ 0.00 Force Account Time related damages per 1-09.6.6.d: $ 0.00 Total: $1,119,935.00 * Type dollar amounts in for each of the 1st 3 rows, then right click dollar amount on fourth row and select “update Field”. 25-D71 - Traffic Control for Franchise Utility Infrastructure Removal An independent estimate was prepared for the cost of Traffic Control for Franchise Utility Infrastructure Removal. The Contractor’s quote of $192,297.07 for “Additional LS Traffic Control Items” was rejected and is replaced by the Schedule D bid items herein. The estimated cost of Traffic Control for Franchise Utility Infrastructure Removal is $13,068.00 and has been rounded to an estimated cost of $13,000.00. Change Order No. 25 Contract Title: Rainier Ave S. Corridor Improvements – Phase 4 Contract No. CAG-22-163 Page 6 of 56 25-D72 - Traffic Control Supervisor for Franchise Utility Infrastructure Removal An independent estimate was prepared for the cost of Traffic Control Supervisor for Franchise Utility Infrastructure Removal. The Contractor’s quote of $192,297.07 for “Additional LS Traffic Control Items” was rejected and is replaced by the Schedule D bid items herein. The estimated cost of Traffic Control Supervisor for Franchise Utility Infrastructure Removal is $9,379.36 and has been rounded to an estimated cost of $9,000.00. 25-D73 - Flagging for Franchise Utility Infrastructure Removal An independent estimate was prepared for the cost of Flagging for Franchise Utility Infrastructure Removal. The Contractor’s quote of $192,297.07 for “Additional LS Traffic Control Items” was rejected and is replaced by the Schedule D bid items herein. The estimated cost of Flagging for Franchise Utility Infrastructure Removal is $98.25/HR ($73,687.50 for 750 HR) and has been rounded to an estimated cost of $99.00/HR ($74,250.00 for 750 HR). 25-D74 - Other Traffic Control Labor for Franchise Utility Infrastructure Removal An independent estimate was prepared for the cost of Other Traffic Control Labor for Franchise Utility Infrastructure Removal. The Contractor’s quote of $192,297.07 for “Additional LS Traffic Control Items” was rejected and is replaced by the Schedule D bid items herein. The estimated cost of Other Traffic Control Labor for Franchise Utility Infrastructure Removal is $104.80/HR ($26,200.00 for 250 hours) and has been rounded to an estimated cost of $105.00/HR ($26,250.00 for 250 HR). 25-D75 - Franchise Utility Infrastructure Removal An independent estimate was prepared for the cost of Franchise Utility Infrastructure Removal. The calculated cost of the Franchise Utility Infrastructure Removal is $1,021,793.14, which does not include Traffic Control Items (to be paid under the newly created Schedule D Items herein) or Gravel Borrow Inc. Haul (to be paid under 25-D62). The Contractor’s quote of $1,279,450.10 included the cost of Additional LS Traffic Control Items and Gravel Borrow Inc. Haul. After removing Additional LS Traffic Control Items and Gravel Borrow Inc. Haul from the Contractor’s quote, the lump sum of $1,015,575.89 was accepted and has been rounded to an estimated cost of $1,016,000.00. The total cost of this work is $1,119,935.00 before sales tax, with the sales tax amounting to $113,113.44. This brings the total for the change order, including sales tax, to $1,233,048.44. Extension of Time: The Time for Completion is extended __0__ Working Days. Change Order No. 25 Contract Title: Rainier Ave S. Corridor Improvements – Phase 4 Contract No. CAG-22-163 Page 7 of 56 Affects DBE Work: No. Sections 1-04.4 and 1-04.5 of the 2022 WSDOT/APWA Standard Specifications shall govern this Change Order. The Work of the referenced Contract is modified to include the changes detailed herein. The payment provided for herein shall constitute the complete and final settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all other claims that may be made by the Contractor as a result of this change. To be attached to Change Order: ☒ 1-Estimated Change Order Cost ☒ 2-Plans ☒ 3-Field Directive/Request for Information Response ☒ 4-Change Order Quotation ☐ 5-Project Labor List ☐ 6-Force Account Equipment Rate Request (DOT Form 422-010 EF) ☐ 7-Equitable Adjustment Determination ☐ 8-Additional Working Days Calculation Item No.Quantity Unit Price 25-D62 25-D62 3000 24.20$ CALCULATED TOTAL: 25-D71 25-D71 90 40.50$ 25-D71 90 50.00$ 25-D71 90 29.50$ 25-D71 $10,800.00 0.21$ CALCULATED TOTAL: 25-D72 25-D72 62 85.00$ 25-D72 $5,270.00 0.31$ 25-D72 62 33.00$ 25-D72 $2,046.00 0.21$ CALCULATED TOTAL: 25-D73 25-D73 750 75.00$ 25-D73 $56,250.00 0.31$ CALCULATED TOTAL: 25-D74 25-D74 250 80.00$ 25-D74 $20,000.00 0.31$ CALCULATED TOTAL: 25-D75 45 25-D75 180 127.00$ 25-D75 225 123.00$ 25-D75 253 126.00$ 25-D75 180 106.00$ 25-D75 180 117.00$ 25-D75 $122,490.00 0.31$ 25-D75 180 33.00$ 25-D75 180 113.00$ 25-D75 225 113.00$ 25-D75 225 25.00$ 25-D75 180 25.00$ 25-D75 180 75.00$ 25-D75 253 136.00$ 25-D75 180 40.00$ 25-D75 180 150.00$ 25-D75 $143,870.00 0.21$ 25-D75 11 1,100.00$ 25-D75 $12,100.00 0.21$ CALCULATED TOTAL: Per EA: 25-D75 7 25-D75 14 127.00$ 25-D75 14 123.00$ 25-D75 17 126.00$ 25-D75 14 106.00$ 25-D75 14 117.00$ 25-D75 $8,764.00 0.31$ 25-D75 14 33.00$ 25-D75 21 113.00$ 25-D75 21 113.00$ Equipment - (Foreman Truck) - Pivetta Hours $462.00 Equipment - (Excavator) - Pivetta Hours $2,373.00 Hours $350.00 Labor Markup Cents/Dollar $2,716.84 Equipment - (Excavator) - Pivetta Hours $2,373.00 Labor - (Laborer) - Pivetta Hours $1,484.00 Labor - (Grade Checker) - Pivetta Hours $1,638.00 Labor - (Operator) - Pivetta Hours $1,722.00 Labor - (Operator, Dump Truck) - Pivetta Hours $2,142.00 Remove Existing Handholes Labor - (Foreman) - Pivetta Hours $1,778.00 Services Markup Cents/Dollar $2,541.00 $349,185.60 7,759.68$ Equipment Markup Cents/Dollar $30,212.70 Services (Dump Fees) - Pivetta LOAD $12,100.00 Equipment - (Vac Trailer) - Pivetta Hours $7,200.00 Equipment - (Steel Sheets) - Pivetta Hours $27,000.00 Equipment - (Loader) - Pivetta Hours $13,500.00 Equipment - (Dump Truck) - Pivetta Hours $34,340.00 $5,625.00 Equipment - (Breaker) - Pivetta Hours $4,500.00 Equipment - (Excavator) - Pivetta Hours $20,340.00 Equipment - (Excavator) - Pivetta Hours $25,425.00 Remove Existing Utility Vaults Labor - (Flagger) - Pivetta, 2 Flaggers @ 2 crews @ 0.5 hr per day for 124 days Hours $20,000.00 Labor Markup Cents/Dollar $6,200.00 $72,600.00 $104.80 Gravel Borrow Inc. Haul Gravel Borrow Inc. Haul TN $72,600.00 ESTIMATED HOURLY RATE:$105.00 ESTIMATED TOTAL:$26,250.00 $26,200.00 Traffic Control for Franchise Utility Infrastructure Removal Equipment - (30 Barrels w/lights @ $1.35/barrel/day) - Pivetta DAYS $3,645.00 Equipment Markup Cents/Dollar $2,268.00 Equipment - (50 Candlestick Delineators @ $1.00/candlestick/day) - Pivetta Equipment - (10 Traffic Control Signs w/stands @ $2.95/day/sign) - Pivetta DAYS DAYS $4,500.00 $2,655.00 $9,379.36 $13,000.00 $98.25 ESTIMATED HOURLY RATE:$99.00 Equipment - (TCS Truck) - Pivetta Hours $2,046.00 Equipment Markup Cents/Dollar $429.66 ESTIMATED TOTAL: ESTIMATED TOTAL: $73,687.50 Labor - (Flagger) - Pivetta, 2 Flaggers @ 2 crews @ 1.5 hr per day for 124 Days Hours $56,250.00 Labor Markup Cents/Dollar $17,437.50 $9,000.00 ESTIMATED TOTAL:$74,250.00 Change Order Cost (Equitable Adjustment)Change Order No. 25 Project Name:Rainier Ave S Corridor Improvements - Phase 4 Contractor:Pivetta Brothers Construction, Inc. Description Unit Estimated Cost Contract No:CAG-22-163 Federal Aid No:STPUL-1615(005)By: Shannon Tremper Construction Manager:Perteet Date: 8/02/2024 Independent Cost Estimate Traffic Control Supervisor for Franchise Utility Infrastructure Removal Other Traffic Control Labor for Franchise Utility Infrastructure Removal CALCULATED HOURLY RATE: HOURLY RATE: Flagging for Franchise Utility Infrastructure Removal Labor - (TCS) - Pivetta, 1 TCS @ 1 Crew @ 0.5 hr per day for 124 Days Hours $5,270.00 Labor Markup Cents/Dollar $1,633.70 $13,068.00 Labor - (Laborer) - Pivetta Hours $19,080.00 Labor - (Foreman) - Pivetta Hours $22,860.00 Labor - (Operator) - Pivetta Hours $27,675.00 Labor - (Operator, Dump Truck) - Pivetta Hours $31,815.00 Labor - (Grade Checker) - Pivetta Hours $21,060.00 Labor Markup Cents/Dollar $37,971.90 Equipment - (Foreman Truck) - Pivetta Hours $5,940.00 Equipment - (Breaker) - Pivetta Hours Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 8 of 5656 Item No.Quantity Unit Price Change Order Cost (Equitable Adjustment)Change Order No. 25 Project Name:Rainier Ave S Corridor Improvements - Phase 4 Contractor:Pivetta Brothers Construction, Inc. Description Unit Estimated Cost Contract No:CAG-22-163 Federal Aid No:STPUL-1615(005)By: Shannon Tremper Construction Manager:Perteet Date: 8/02/2024 Independent Cost Estimate25-D75 14 25.00$ 25-D75 14 25.00$ 25-D75 14 75.00$ 25-D75 17 136.00$ 25-D75 14 40.00$ 25-D75 56 150.00$ 25-D75 $18,230.00 0.21$ 25-D75 1 1,100.00$ 25-D75 $1,100.00 0.21$ CALCULATED TOTAL: Per EA: 25-D75 1764 25-D75 189 127.00$ 25-D75 189 123.00$ 25-D75 189 117.00$ 25-D75 343 126.00$ 25-D75 189 106.00$ 25-D75 $132,615.00 0.31$ 25-D75 189 33.00$ 25-D75 189 113.00$ 25-D75 189 113.00$ 25-D75 189 25.00$ 25-D75 189 25.00$ 25-D75 343 90.00$ 25-D75 189 40.00$ 25-D75 343 72.00$ 25-D75 189 150.00$ 25-D75 $149,877.00 0.21$ 25-D75 62 1,100.00$ 25-D75 $68,200.00 0.21$ 25-D75 840 2.50$ 25-D75 $3,050.00 0.12$ CALCULATED TOTAL: Per CY: 25-D75 275 25-D75 30 127.00$ 25-D75 30 123.00$ 25-D75 49 126.00$ 25-D75 30 117.00$ 25-D75 30 106.00$ 25-D75 $20,364.00 0.31$ 25-D75 30 33.00$ 25-D75 30 113.00$ 25-D75 30 113.00$ 25-D75 30 25.00$ 25-D75 30 25.00$ 25-D75 30 75.00$ 25-D75 49 136.00$ 25-D75 30 40.00$ 25-D75 30 150.00$ 25-D75 $23,884.00 0.21$ 25-D75 7 370.00$ 25-D75 $2,590.00 0.21$ 25-D75 140 2.50$ 25-D75 $825.00 0.12$ CALCULATED TOTAL: Per CY: 25-D75 4 25-D75 16 127.00$ 25-D75 16 123.00$ 25-D75 16 126.00$ 25-D75 16 117.00$ 25-D75 16 106.00$ 25-D75 $9,584.00 0.31$ 25-D75 16 33.00$ 25-D75 16 113.00$ 25-D75 16 113.00$ Labor - (Grade Checker) - Pivetta Hours $3,510.00 Labor - (Foreman) - Pivetta Hours $3,810.00 Labor - (Operator) - Pivetta Hours $3,690.00 Equipment - (Foreman Truck) - Pivetta Hours $528.00 Labor - (Grade Checker) - Pivetta Hours $22,113.00 Labor - (Operator, Dump Truck) - Pivetta Hours $43,218.00 Equipment - (Foreman Truck) - Pivetta Hours $6,237.00 Labor - (Laborer) - Pivetta Hours $1,696.00 Labor Markup Cents/Dollar Equipment - (Foreman Truck) - Pivetta Hours Labor - (Operator, Dump Truck) - Pivetta Hours Equipment - (Excavator) - Pivetta Hours $1,808.00 Equipment - (Excavator) - Pivetta Hours $1,808.00 Labor - (Operator, Dump Truck) - Pivetta Hours $2,016.00 Labor - (Grade Checker) - Pivetta Hours $1,872.00 Labor - (Foreman) - Pivetta Hours $2,032.00 Labor - (Operator) - Pivetta Hours $1,968.00 Plug Existing Gas Main EA Subcontractor (Sawcutting)LF $825.00 Services Markup Cents/Dollar $543.90 Subcontractor Markup Cents/Dollar $99.00 $59,535.38 $484.03 Equipment Markup Cents/Dollar $5,015.64 Services (Dump Fee)LOAD $2,590.00 Equipment - (Vac Trailer) - Pivetta Hours $1,200.00 Equipment - (Steel Sheets) - Pivetta Hours $4,500.00 Equipment - (Loader) - Pivetta Hours $2,250.00 Equipment - (Dump Truck) - Pivetta Hours $6,664.00 Equipment - (Breaker) - Pivetta Hours $750.00 Equipment - (Breaker) - Pivetta Hours $750.00 Equipment - (Excavator) - Pivetta Hours $3,390.00 Equipment - (Excavator) - Pivetta Hours $3,390.00 Labor - (Laborer) - Pivetta Hours $3,180.00 Labor Markup Cents/Dollar $6,312.84 $990.00 Remove Existing Gas Main LF Subcontractor (Sawcutting)LF $3,050.00 Services Markup Cents/Dollar $14,322.00 $440,648.82 $421.54 Subcontractor Markup Cents/Dollar $366.00 Equipment Markup Cents/Dollar $31,474.17 Services (Dump Fee)LOAD $68,200.00 Equipment - (Dump Truck) - Pivetta Hours $24,696.00 Equipment - (Steel Sheets) - Pivetta Hours $28,350.00 Equipment - (Loader) - Pivetta Hours $30,870.00 Equipment - (Vac Trailer) - Pivetta Hours $7,560.00 Equipment - (Breaker) - Pivetta Hours $4,725.00 Equipment - (Breaker) - Pivetta Hours $4,725.00 Equipment - (Excavator) - Pivetta Hours $21,357.00 Equipment - (Excavator) - Pivetta Hours $21,357.00 Labor Markup Cents/Dollar $41,110.65 Labor - (Operator) - Pivetta Hours $23,247.00 Labor - (Laborer) - Pivetta Hours $20,034.00 Services (Dump Fees) - Pivetta LOAD $1,100.00 Services Markup Cents/Dollar $231.00 $34,870.14 $4,981.45 Remove Existing JUT LF Labor - (Foreman) - Pivetta Hours $24,003.00 Equipment - (Steel Sheets) - Pivetta Hours $8,400.00 Equipment Markup Cents/Dollar $3,828.30 Equipment - (Dump Truck) - Pivetta Hours $2,312.00 Equipment - (Vac Trailer) - Pivetta Hours $560.00 Equipment - (Breaker) - Pivetta Hours $350.00 Equipment - (Loader) - Pivetta Hours $1,050.00 Equipment - (Breaker) - Pivetta Hours $350.00 $2,971.04 $6,174.00 Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 9 of 5656 Item No.Quantity Unit Price Change Order Cost (Equitable Adjustment)Change Order No. 25 Project Name:Rainier Ave S Corridor Improvements - Phase 4 Contractor:Pivetta Brothers Construction, Inc. Description Unit Estimated Cost Contract No:CAG-22-163 Federal Aid No:STPUL-1615(005)By: Shannon Tremper Construction Manager:Perteet Date: 8/02/2024 Independent Cost Estimate25-D75 16 25.00$ 25-D75 16 25.00$ 25-D75 16 75.00$ 25-D75 16 136.00$ 25-D75 16 150.00$ 25-D75 16 40.00$ 25-D75 $11,360.00 0.21$ 25-D75 4 250.00$ 25-D75 $1,000.00 0.21$ CALCULATED TOTAL: Per EA: 25-D75 16 25-D75 64 127.00$ 25-D75 64 123.00$ 25-D75 64 126.00$ 25-D75 64 117.00$ 25-D75 64 106.00$ 25-D75 $38,336.00 0.31$ 25-D75 64 33.00$ 25-D75 64 113.00$ 25-D75 64 113.00$ 25-D75 64 25.00$ 25-D75 64 25.00$ 25-D75 64 75.00$ 25-D75 64 136.00$ 25-D75 64 150.00$ 25-D75 64 40.00$ 25-D75 $45,440.00 0.21$ 25-D75 16 250.00$ 25-D75 $4,000.00 0.21$ CALCULATED TOTAL: Per EA: 25-D75 1 CALCULATED TOTAL: ESTIMATED TOTAL: 25-D4 -960 $27.00 25-D11 -1 $65,245.00 TOTAL REMOVED FROM SCHEDULE D: 25-D62 3000 $24.20 25-D71 1 $13,000.00 25-D72 1 $9,000.00 25-D73 750 $99.00 25-D74 250 $105.00 25-D75 1 $1,016,000.00 TOTAL ADDED TO SCHEDULE D: Summary of Contractors Quotes: Item Quote Location SL038s2 Total Quoted Added Cost: Plug Existing JUT Conduit EA Materials (Caps, glue, grout) - Pivetta EA $1,000.00 Materials Markup Cents/Dollar $210.00 Equipment - (Steel Sheets) - Pivetta Hours $2,400.00 Equipment - (Vac Trailer) - Pivetta Hours $640.00 Equipment Markup Cents/Dollar $2,385.60 $1,200.00 Equipment - (Dump Truck) - Pivetta Hours Labor - (Grade Checker) - Pivetta Hours $7,488.00 Labor - (Foreman) - Pivetta Hours $8,128.00 Labor - (Operator) - Pivetta Hours $7,872.00 $1,211,100.00 Franchise Utility Infrastructure Removal LS $1,016,000.00 Remove/Abandon Existing Gas Main LF -$25,920.00 Gravel Borrow Inc. Haul TN $72,600.00 -$91,165.00 Item Change - ADD Schedule D Estimated Change Order Cost With Sales Tax $1,233,048.44 Quoted Cost 1,279,450.10$ 1,279,450.10$ Estimated Change Order Cost Without Sales Tax (Schedule D)$1,119,935.00 Estimated Sales Tax Cost (Schedule D)$113,113.44 Materials Markup Cents/Dollar $840.00 $110,042.56 $6,877.66 Equipment Markup Cents/Dollar $9,542.40 Materials (Caps, glue, grout) - Pivetta EA $4,000.00 Equipment - (Steel Sheets) - Pivetta Hours $9,600.00 Equipment - (Vac Trailer) - Pivetta Hours $2,560.00 Equipment - (Loader) - Pivetta Hours $4,800.00 Equipment - (Dump Truck) - Pivetta Hours $8,704.00 Equipment - (Loader) - Pivetta Hours Equipment - (Excavator) - Pivetta Hours $7,232.00 Equipment - (Breaker) - Pivetta Hours $1,600.00 Labor - (Laborer) - Pivetta Hours $6,784.00 Labor Markup Cents/Dollar $11,884.16 Equipment - (Breaker) - Pivetta Hours $1,600.00 Equipment - (Excavator) - Pivetta Hours $7,232.00 Equipment - (Foreman Truck) - Pivetta Hours $2,112.00 Labor - (Operator, Dump Truck) - Pivetta Equipment - (Breaker) - Pivetta Hours $400.00 Equipment - (Breaker) - Pivetta Hours $400.00 Other Traffic Control Labor for Franchise Utility Infrastructure Removal HR $26,250.00 Item Change - REMOVE Schedule D $1,016,000.00 $27,510.64 $6,877.66 $2,176.00 Hours $8,064.00 Franchise Utility Infrastructure Removal Removal of Structures and Obstructions LS -$65,245.00 Traffic Control Supervisor for Franchise Utility Infrastructure Removal LS $9,000.00 Flagging for Franchise Utility Infrastructure Removal HR $74,250.00 Traffic Control for Franchise Utility Infrastructure Removal LS $13,000.00 LS $1,021,793.14 Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 10 of 5656 Item Gravel Borrow Item Price Duration JUT Removal (1,763 LF)1,045 CY $482.32 /CY $45,508.91 $503,895.14 24 Plug Existing JUT Conduits at Start Point 16 EA $7,097.85 /EA $0.00 $113,565.56 8 Remove Existing Vault 45 EA $7,902.44 /EA $20,908.80 $355,609.67 23 Remove Existing Hand Hole 7 EA $4,180.98 /EA $722.77 $29,266.84 2 Gas Main Removal (275 LF)102 CY $550.25 /CY $4,436.67 $56,043.92 3 Plug Existing Gas Main @ Start Point 4 EA $7,192.98 /EA $0.00 $28,771.91 2 Additional LS Traffic Control Items 62 DYS $3,101.57 /DY $192,297.07 Total $71,577.15 $1,279,450.10 62 Remove Gravel Borrow $71,577.15 $1,207,872.96 Remove Traffic Control $192,297.07 $1,015,575.89 QTY Unit Price Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 11 of 56 Project No.: 2022-148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item No.Description Qty UOM Production Rate Manhours Labor Rate Labor Cost Equipment Hours Equipment Rate Equipment Cost Material Unit Cost Material Cost Sucontractor Cost Item Cost 1 2 Remove Existing JUT 1,763 LF 3 Foreman Op 15 - 30 (with Pickup)1,763 LF 0.1067 188.1 $94.96 $17,857.54 188.1 $32.78 $6,164.39 $24,021.93 4 Operator 15 - 30 1,763 LF 0.1067 188.1 $90.96 $17,105.33 $17,105.33 5 Grade Check 1,763 LF 0.1067 188.1 $86.31 $16,230.88 $16,230.88 6 Laborer 1,763 LF 0.1067 188.1 $66.61 $12,526.23 $12,526.23 7 Op Driver 1,763 LF 0.1067 188.1 $95.04 $17,872.59 $17,872.59 8 9 EX-139: JD 85G 1,763 LF 0.1067 188.1 $108.90 $20,479.01 $20,479.01 10 75HB-101: Breaker 1,763 LF 0.1067 188.1 $21.13 $3,973.57 $3,973.57 11 EX-142: 135N 1,763 LF 0.1067 188.1 $122.55 $23,045.94 $23,045.94 12 135HB-101: Breaker 1,763 LF 0.1067 188.1 $29.61 $5,568.26 $5,568.26 13 T-133: International F74 1,763 LF 0.1067 188.1 $72.26 $13,588.73 $13,588.73 14 WL-112: JD 624K 1,763 LF 0.1067 188.1 $89.64 $16,857.10 $16,857.10 15 Vac Trailer 1,763 LF 0.1067 188.1 $37.84 $7,115.94 $7,115.94 16 Steel Plates & Shoring 1,763 LF 0.1067 188.1 $168.40 $31,668.18 $31,668.18 17 18 Material Handling 24 DY 4.0000 96.0 $90.96 $8,732.16 96.0 $89.64 $8,605.44 $17,337.60 19 Trucking and Disposal - Debris & Soils 1,045 CY $92.94 $97,099.43 $97,099.43 20 21 Sawcutting 840 LF $4,536.00 $4,536.00 22 23 JUT Gravel Borrow 1,881 Tons $24.20 $45,508.91 $45,508.91 24 25 Incidental Overtime 1,036 MH 1.000 1036.266667 $31.00 $32,124.27 $32,124.27 26 $122,449.01 $137,066.55 $142,608.34 $4,536.00 $406,659.90 31%21%21%12%-- $37,959.19 $28,783.98 $29,947.75 $544.32 $97,235.24 $160,408.20 $165,850.53 $172,556.09 $5,080.32 $503,895.14 COST WITHOUT GRAVEL BORROW $458,386.23 CY Price $482.32 CY WITHOUT GRAVEL BORROW $438.76 Work Days Required 24 Notes: Sawcutting at 4 Crossings at 70 LF Each and 2nd Street Crossing at 140' Change Order Pricing Total Cost Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. Utilities will be required to cut any wires encountered (in conduit or direct buried). PCO: Description: Lineal Foot Pricing for JUT Removal 007 FD #56 JUT Removal Element Cost Allowable Markup Markup Cost Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 12 of 56 Project No.: 2022-148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item No.Description Qty UOM Production Rate Manhours Labor Rate Labor Cost Equipment Hours Equipment Rate Equipment Cost Material Unit Cost Material Cost Sucontractor Cost Item Cost 1 2 Remove Existing JUT 16 EA 3 Foreman Op 15 - 30 (with Pickup)16 EA 4.0000 64.0 $94.96 $6,077.44 64.0 $32.78 $2,097.92 $8,175.36 4 Operator 15 - 30 16 EA 4.0000 64.0 $90.96 $5,821.44 $5,821.44 5 Grade Check 16 EA 4.0000 64.0 $86.31 $5,523.84 $5,523.84 6 Laborer 16 EA 4.0000 64.0 $66.61 $4,263.04 $4,263.04 7 Op Driver 16 EA 4.0000 64.0 $95.04 $6,082.56 $6,082.56 8 10 EX-139: JD 85G 16 EA 4.0000 64.0 $108.90 $6,969.60 $6,969.60 11 75HB-101: Breaker 16 EA 4.0000 64.0 $21.13 $1,352.32 $1,352.32 12 EX-142: 135N 16 EA 4.0000 64.0 $122.55 $7,843.20 $7,843.20 13 135HB-101: Breaker 16 EA 4.0000 64.0 $29.61 $1,895.04 $1,895.04 14 T-133: International F74 16 EA 4.0000 64.0 $72.26 $4,624.64 $4,624.64 15 WL-112: JD 624K 16 EA 4.0000 64.0 $89.64 $5,736.96 $5,736.96 16 Vac Trailer 16 EA 4.0000 64.0 $37.84 $2,421.76 $2,421.76 17 Steel Plates & Shoring 16 EA 4.0000 64.0 $168.40 $10,777.60 $10,777.60 18 19 Material Handling 8 DY 4.0000 32.0 $90.96 $2,910.72 32.0 $89.64 $2,868.48 $5,779.20 20 Materials 16 EA $140.00 $2,240.00 $2,240.00 21 22 Incidental Overtime 352 MH 1.000 352 $31.00 $10,912.00 $10,912.00 23 24 25 $41,591.04 $46,587.52 $2,240.00 $0.00 $90,418.56 31%21%21%12%-- $12,893.22 $9,783.38 $470.40 $0.00 $23,147.00 $54,484.26 $56,370.90 $2,710.40 $0.00 $113,565.56 Price Per Each $7,097.85 Work Days Required 8 Notes: PVC Conduit to be capped with PVC Caps or expansion plugs Allowable Markup Markup Cost Total Cost Assuming 4 conduit plugs between 2" and 6" in size at each location. Work to be done in conjunction with JUT Removal. Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. Element Cost Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Per Each Unit Price for JUT Plug/Abandon Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 13 of 56 Project No.: 2022-148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item No.Description Qty UOM Production Rate Manhours Labor Rate Labor Cost Equipment Hours Equipment Rate Equipment Cost Material Unit Cost Material Cost Sucontractor Cost Item Cost 1 2 Remove Existing JUT 45 EA 3 Foreman Op 15 - 30 (with Pickup)45 EA 4.0000 180.0 $94.96 $17,092.80 180.0 $32.78 $5,900.40 $22,993.20 4 Operator 15 - 30 45 EA 4.0000 180.0 $90.96 $16,372.80 $16,372.80 5 Grade Check 45 EA 4.0000 180.0 $86.31 $15,535.80 $15,535.80 6 Laborer 45 EA 4.0000 180.0 $66.61 $11,989.80 $11,989.80 7 Op Driver 45 EA 4.0000 180.0 $95.04 $17,107.20 $17,107.20 8 9 EX-139: JD 85G 45 EA 4.0000 180.0 $108.90 $19,602.00 $19,602.00 10 75HB-101: Breaker 45 EA 4.0000 180.0 $21.13 $3,803.40 $3,803.40 11 EX-142: 135N 45 EA 4.0000 180.0 $122.55 $22,059.00 $22,059.00 12 135HB-101: Breaker 45 EA 4.0000 180.0 $29.61 $5,329.80 $5,329.80 13 T-133: International F74 45 EA 4.0000 180.0 $72.26 $13,006.80 $13,006.80 14 WL-112: JD 624K 45 EA 4.0000 180.0 $89.64 $16,135.20 $16,135.20 15 Vac Trailer 45 EA 4.0000 180.0 $37.84 $6,811.20 $6,811.20 16 Steel Plates & Shoring 45 EA 4.0000 180.0 $168.40 $30,312.00 $30,312.00 17 18 Material Handling 23 DY 4.0000 92.0 $90.96 $8,368.32 92.0 $89.64 $8,246.88 $16,615.20 19 Trucking and Disposal 160.0 CY $92.94 $14,870.59 $14,870.59 20 21 JUT Gravel Borrow - Import 864 Tons $24.20 $20,908.80 $20,908.80 22 22 Incidental Overtime 992 MH 1.000 992 $31.00 $30,752.00 $30,752.00 24 $117,218.72 $131,206.68 $35,779.39 $0.00 $284,204.79 31%21%21%12%-- $36,337.80 $27,553.40 $7,513.67 $0.00 $71,404.88 $153,556.52 $158,760.08 $43,293.06 $0.00 $355,609.67 COST WITHOUT GRAVEL BORROW $334,700.87 Price Per Each $7,902.44 CY WITHOUT GRAVEL BORROW $7,437.80 Work Days Required 23 Notes: Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. PVC Conduit to be capped with PVC Caps or expansion plugs Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Per Each Unit Price for JUT Vault Removal Element Cost Worked to be done in conjunction with JUT Removal and Plug/Abandon Conduit. Allowable Markup Markup Cost Total Cost 12 PSE Vaults, 17 Century Link Vaults, and 16 Comcast Vaults Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 14 of 56 Project No.: 2022-148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item No.Description Qty UOM Production Rate Manhours Labor Rate Labor Cost Equipment Hours Equipment Rate Equipment Cost Material Unit Cost Material Cost Sucontractor Cost Item Cost 1 2 Remove Existing JUT 7 EA 3 Foreman Op 15 - 30 (with Pickup)7 EA 2.0000 14.0 $94.96 $1,329.44 14.0 $32.78 $458.92 $1,788.36 4 Operator 15 - 30 7 EA 2.0000 14.0 $90.96 $1,273.44 $1,273.44 5 Grade Check 7 EA 2.0000 14.0 $86.31 $1,208.34 $1,208.34 6 Laborer 7 EA 2.0000 14.0 $66.61 $932.54 $932.54 7 Op Driver 7 EA 2.0000 14.0 $95.04 $1,330.56 $1,330.56 8 9 P-147: Shop Truck 7 EA 2.0000 14.0 $32.78 $458.92 $458.92 10 EX-139: JD 85G 7 EA 2.0000 14.0 $108.90 $1,524.60 $1,524.60 11 75HB-101: Breaker 7 EA 2.0000 14.0 $21.13 $295.82 $295.82 12 EX-142: 135N 7 EA 2.0000 14.0 $122.55 $1,715.70 $1,715.70 13 135HB-101: Breaker 7 EA 2.0000 14.0 $29.61 $414.54 $414.54 14 T-133: International F74 7 EA 2.0000 14.0 $72.26 $1,011.64 $1,011.64 15 WL-112: JD 624K 7 EA 2.0000 14.0 $89.64 $1,254.96 $1,254.96 16 Vac Trailer 7 EA 2.0000 14.0 $37.84 $529.76 $529.76 17 Steel Plates & Shoring 7 EA 4.0000 28.0 $168.40 $4,715.20 $4,715.20 18 19 Material Handling 2 DY 4.0000 8.0 $90.96 $727.68 8.0 $89.64 $717.12 $1,444.80 20 Trucking and Disposal 4.1 CY $92.94 $385.53 $385.53 21 22 JUT Gravel Borrow - Import 30 Tons $24.20 $722.77 $722.77 23 22 Incidental Overtime 78 MH 1.000 78 $31.00 $2,418.00 $2,418.00 25 $9,220.00 $13,097.18 $1,108.31 $0.00 $23,425.49 31%21%21%12%-- $2,858.20 $2,750.41 $232.74 $0.00 $5,841.35 $12,078.20 $15,847.59 $1,341.05 $0.00 $29,266.84 COST WITHOUT GRAVEL BORROW $28,544.07 Price Per Each $4,180.98 CY WITHOUT GRAVEL BORROW $4,077.72 Work Days Required 2 Notes: PVC Conduit to be capped with PVC Caps or expansion plugs Allowable Markup Markup Cost Total Cost Any handhole larger than 4' x 4' will be considered a vault. Worked to be done in conjunction with JUT Removal and Plug/Abandon Conduit. Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. Element Cost Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Per Each Unit Price for JUT Hand Hole Removal Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 15 of 56 Project No.: 2022-148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item No.Description Qty UOM Production Rate Manhours Labor Rate Labor Cost Equipment Hours Equipment Rate Equipment Cost Material Unit Cost Material Cost Sucontractor Cost Item Cost 1 2 Remove Existing JUT 275 LF 3 Foreman Op 15 - 30 (with Pickup)275 LF 0.0800 22.0 $94.96 $2,089.12 22.0 $32.78 $721.16 $2,810.28 4 Operator 15 - 30 275 LF 0.0800 22.0 $90.96 $2,001.12 $2,001.12 5 Grade Check 275 LF 0.0800 22.0 $86.31 $1,898.82 $1,898.82 6 Laborer 275 LF 0.0800 22.0 $66.61 $1,465.42 $1,465.42 7 Op Driver 275 LF 0.0800 22.0 $95.04 $2,090.88 $2,090.88 8 10 EX-139: JD 85G 275 LF 0.0800 22.0 $108.90 $2,395.80 $2,395.80 11 75HB-101: Breaker 275 LF 0.0800 22.0 $21.13 $464.86 $464.86 12 EX-142: 135N 275 LF 0.0800 22.0 $122.55 $2,696.10 $2,696.10 13 135HB-101: Breaker 275 LF 0.0800 22.0 $29.61 $651.42 $651.42 14 T-133: International F74 275 LF 0.0800 22.0 $72.26 $1,589.72 $1,589.72 15 WL-112: JD 624K 275 LF 0.0800 22.0 $89.64 $1,972.08 $1,972.08 16 Vac Trailer 275 LF 0.0800 22.0 $37.84 $832.48 $832.48 17 Steel Plates & Shoring 275 LF 0.0800 22.0 $168.40 $3,704.80 $3,704.80 18 19 Material Handling 3 DY 4.0000 12.0 $90.96 $1,091.52 12.0 $89.64 $1,075.68 $2,167.20 20 Trucking and Disposal 102 CY $92.94 $9,466.23 $9,466.23 21 21 Sawcutting 140 LF $756.00 $756.00 23 24 JUT Gravel Borrow 183 Tons $24.20 $4,436.67 $4,436.67 22 Incidental Overtime 122 MH 1.000 122 $31.00 $3,782.00 $3,782.00 25 $14,418.88 $16,104.10 $13,902.90 $756.00 $45,181.88 31%21%21%12%-- $4,469.85 $3,381.86 $2,919.61 $90.72 $10,862.04 $18,888.73 $19,485.96 $16,822.51 $846.72 $56,043.92 COST WITHOUT GRAVEL BORROW $51,607.25 CY Price $550.25 CY WITHOUT GRAVEL BORROW $506.69 Work Days Required 3 Notes: Allowable Markup Markup Cost Total Cost Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. 1 Crossing at 70 LF for PSE Gas Element Cost Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Lineal Foot Pricing for Gas Main Removal Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 16 of 56 Project No.: 2022-148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item No.Description Qty UOM Production Rate Manhours Labor Rate Labor Cost Equipment Hours Equipment Rate Equipment Cost Material Unit Cost Material Cost Sucontractor Cost Item Cost 1 2 Plug/Cap Existing Main 4 EA 3 Foreman Op 15 - 30 (with Pickup)4 EA 4.0000 16.0 $94.96 $1,519.36 16.0 $32.78 $524.48 $2,043.84 4 Operator 15 - 30 4 EA 4.0000 16.0 $90.96 $1,455.36 $1,455.36 5 Grade Check 4 EA 4.0000 16.0 $86.31 $1,380.96 $1,380.96 6 Laborer 4 EA 4.0000 16.0 $66.61 $1,065.76 $1,065.76 7 Op Driver 4 EA 4.0000 16.0 $95.04 $1,520.64 $1,520.64 8 9 P-147: Shop Truck 4 EA 4.0000 16.0 $32.78 $524.48 $524.48 10 EX-139: JD 85G 4 EA 4.0000 16.0 $108.90 $1,742.40 $1,742.40 11 75HB-101: Breaker 4 EA 4.0000 16.0 $21.13 $338.08 $338.08 12 EX-142: 135N 4 EA 4.0000 16.0 $122.55 $1,960.80 $1,960.80 13 135HB-101: Breaker 4 EA 4.0000 16.0 $29.61 $473.76 $473.76 14 T-133: International F74 4 EA 4.0000 16.0 $72.26 $1,156.16 $1,156.16 15 WL-112: JD 624K 4 EA 4.0000 16.0 $89.64 $1,434.24 $1,434.24 16 Steel Plates & Shoring 4 EA 4.0000 16.0 $168.40 $2,694.40 $2,694.40 17 18 Vac Trailer 4 EA 4.0000 16.0 $37.84 $605.44 $605.44 19 20 Material Handling 2 DY 4.0000 8.0 $90.96 $727.68 8.0 $89.64 $717.12 $1,444.80 21 Materials 10 EA $35.00 $350.00 $350.00 22 22 Incidental Overtime 88 MH 1.000 88 $31.00 $2,728.00 $2,728.00 24 25 $10,397.76 $12,171.36 $350.00 $0.00 $22,919.12 31%21%21%12%-- $3,223.31 $2,555.99 $73.50 $0.00 $5,852.79 $13,621.07 $14,727.35 $423.50 $0.00 $28,771.91 Price Per Each $7,192.98 Work Days Required 2 Notes: HDPE pipes to be plugged with expansion plugs or cement grout. Allowable Markup Markup Cost Total Cost Assuming 1 Cap/Plug between 2" and 4" at each location. Initial cuts of existing Gas Main to be done by others. Work to be done in conjunction with Gas Main Removal. Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. Element Cost Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Per Each Unit Price for Gas Plug/Abandon Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 17 of 56 Project No.: 2022-148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item No.Description Qty UOM Production Rate Manhours Labor Rate Labor Cost Equipment Hours Equipment Rate Equipment Cost Material Unit Cost Material Cost Sucontractor Cost Item Cost 1 2 Pay Item A10 - Temporary Traffic Control Devices 62 DYS 3 Incidental Equipment 62 DYS 8.0000 496.00 $17.25 $8,556.00 $8,556.00 4 5 Pay Item A13 - TCS 62 DYS 6 Traffic Control Supervisor 62 DYS 8.0000 496.0 $65.74 $32,607.04 496.00 $32.78 $16,258.88 $48,865.92 7 8 22 Incidental Overtime - TCS 496 MH 1.000 496 $24.00 $11,904.00 $11,904.00 10 Incidental Overtime - Flaggers 3,968 MH 1.0000 3968 $20.00 $79,360.00 $79,360.00 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 $123,871.04 $24,814.88 $0.00 $0.00 $148,685.92 31%21%21%12%-- $38,400.02 $5,211.12 $0.00 $0.00 $43,611.15 $162,271.06 $30,026.00 $0.00 $0.00 $192,297.07 Notes: Allowable Markup Markup Cost Total Cost Element Cost Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Additional Traffic Control Removal of Existing Vaults and Duct Banks - Estimated Change Order Cost Change Order #25, Page 18 of 56 FIELD DIRECTIVE Project Name Federal Aid #Contract No.Date Field Directive Description Field Directive No. Contractor Project Engineer (or Representative) Date Jordan Howe Rainier Ave S Corridor Improvements - Phase 4 (S 3rd ST to NW 3rd PL) 801 2nd Avenue, Suite 302, Seattle, WA 98104 | P 206.436.0515 1/8/2024 Pivetta Brothers Construction Removal of Existing Vaults and Duct Banks 056 STPUL-1615(005) CAG-22-163 1/8/2024 The following is documentation of an oral order given by the Engineer per WSDOT Specification 1-04.4. The Contractor shall prepare a cost proposal to remove the existing franchise utility vaults and duct banks after the new joint utility trench system is active as indicated on the attached sheets 144, 145, 146, 147, 148, 149, 150, 151, and 162. The required vault removals are shown onthe added tables on each sheet. The required duct bank removals are shown with blue hatching. Removal of Existing Vaults and Duct Banks - Field Directive #56 Change Order #25, Page 19 of 5656 RAINIER AVE S SW S U N S E T B L V D S 3 R D S T O'REILLY AUTO PARTSFIRESTONE SHELL 7-ELEVEN HERTZ/LYFT WALGREENS HE R T Z / L Y F T SA F E W A Y CORRESPONDING SHEETS FRANCHISE UTILITY STRUCTURE SCHEDULE GENERAL NOTES CONSTRUCTION NOTES CONSTRUCTION NOTES FRANCHISE UTILITY STRUCTURE SCHEDULE (REMOVALS) PLAN NUMBER BY APP.REVISION DESCRIPTION DRAWN BY: DESIGN BY: CHECK BY: PROJ MGR: FILE:BY:DATE: APPROVED FOR CONSTRUCTION DATE DRAWING NO. PROJECT NO. FED AID NO. DATE: SHEET NO.OF SURVEYED: 14087A-JUT01.dwg BID DOCUMENT Public Works Department CITY OF RENTON R EGIST E R E D N O T G N I HSAWFOETAT S ER N E P R F O E NNALIO E S IGS 47649 KA R I N A P . FRA N A D A Tacoma Wenatchee KPG.com Seattle 3131 Elliott Avenue, Suite 400 Seattle, WA 98121 206.286.1640 7 -13 -2022 JOINT UTILITY TRENCH PLAN STA 11+00 TO STA 15+00 144 14087A JULY 2022 285144 RAINIER AVE S CORRIDOR IMPROVEMENTS - PHASE 4 (S 3RD ST TO NW 3RD PL) KPG JF KPF KPF DPY STP(UL) -1615(005) FWD #26 - PSE JUT REVISIONS DPY KPF 6/27/2023 FWD #XX - EXIST JUT/GAS REMOVALS DPY KPF 9/20/2023 Removal of Existing Vaults and Duct Banks - Plans Change Order #25, Page 20 of 56 RAINIER AVE S WALGREENS MIDAS SANSONINA HERTZ/LYFT WENDY'S TACO TIME SAFEWAY CORRESPONDING SHEETS FRANCHISE UTILITY STRUCTURE SCHEDULE GENERAL NOTES CONSTRUCTION NOTES CONSTRUCTION NOTES FRANCHISE UTILITY STRUCTURE SCHEDULE (REMOVALS) NUMBER BY APP.REVISION DESCRIPTION DRAWN BY: DESIGN BY: CHECK BY: PROJ MGR: FILE:BY:DATE: APPROVED FOR CONSTRUCTION DATE DRAWING NO. PROJECT NO. FED AID NO. DATE: SHEET NO.OF SURVEYED: 14087A-JUT01.dwg BID DOCUMENT Public Works Department CITY OF RENTON R EGIST E R E D N O T G N I HSAWFOETAT S ER N E P R F O E NNALIO E S IGS 47649 KA R I N A P . FRA N A D A Tacoma Wenatchee KPG.com Seattle 3131 Elliott Avenue, Suite 400 Seattle, WA 98121 206.286.1640 7 -13 -2022 JF KPG (S 3RD ST TO NW 3RD PL) RAINIER AVE S CORRIDOR IMPROVEMENTS - PHASE 4 145 285 JULY 2022 14087A 145 STA 15+00 TO STA 18+25 JOINT UTILITY TRENCH PLAN PLAN DPY KPF KPF STP(UL) -1615(005) FWD #13 - COMCAST JUT REVISIONS DPY KPF 5/9/2023 FWD #26 - PSE JUT REVISIONS DPY KPF 6/27/2023 FWD #30 - PSE JUT SECTIONS 1 DPY KPF 7/7/2023 DPY KPF 9/20/2023FWD #XX - EXIST JUT/GAS REMOVALS DPY KPF 9/29/2023FWD #46 - SERVICE CONNECTIONS HIGHLIGHTING KEY EXIST JUT STRUCTURE REMOVALS EXIST GAS MAIN REMOVE/ABANDON EXIST JUT TRENCH REMOV/ABANDON REMOVE Removal of Existing Vaults and Duct Banks - Plans Change Order #25, Page 21 of 56 RAINIER AVE S S 2 N D S T BIG ISLAND POKE SOUTH LAKE EUROPEAN AUTOZONE TACO TIME VACANT BUDDY'S HOME FURNISHING RENTON VETERINARY HOSPITAL GRAVITY SPORTS METRO PCS CORRESPONDING SHEETS FRANCHISE UTILITY STRUCTURE SCHEDULE FRANCHISE UTILITY STRUCTURE SCHEDULE GENERAL NOTES CONSTRUCTION NOTES CONSTRUCTION NOTES FRANCHISE UTILITY STRUCTURE SCHEDULE (REMOVALS) FRANCHISE UTILITY STRUCTURE SCHEDULE (REMOVALS) NUMBER BY APP.REVISION DESCRIPTION DRAWN BY: DESIGN BY: CHECK BY: PROJ MGR: FILE:BY:DATE: APPROVED FOR CONSTRUCTION DATE DRAWING NO. PROJECT NO. FED AID NO. DATE: SHEET NO.OF SURVEYED: 14087A-JUT01.dwg BID DOCUMENT Public Works Department CITY OF RENTON R EGIST E R E D N O T G N I HSAWFOETAT S ER N E P R F O E NNALIO E S IGS 47649 KA R I N A P . FRA N A D A Tacoma Wenatchee KPG.com Seattle 3131 Elliott Avenue, Suite 400 Seattle, WA 98121 206.286.1640 7 -13 -2022 JF KPG (S 3RD ST TO NW 3RD PL) RAINIER AVE S CORRIDOR IMPROVEMENTS - PHASE 4 146 285 JULY 2022 14087A 146 STA 18+25 TO STA 22+50 JOINT UTILITY TRENCH PLAN PLAN DPY KPF KPF STP(UL) -1615(005) FWD #13 - COMCAST JUT REVISIONS DPY KPF 5/9/2023 FWD #17 - LUMEN JUT REVISIONS DPY KPF 5/26/2023 FWD #26 - PSE JUT REVISIONS DPY KPF 6/27/2023 FWD #30 - PSE JUT SECTIONS 1 DPY KPF 7/7/2023 FWD #31 - PSE JUT SECTIONS 2 DPY KPF 7/12/2023 DPY KPF 9/20/2023 FWD #45 - PSE CONDUIT REVISION DPY KPF 9/20/2023 FWD #XX- EXIST JUT/GAS REMOVALS FWD #46 - SERVICE CONNECTIONS DPY KPF 9/29/2023 Removal of Existing Vaults and Duct Banks - Plans Change Order #25, Page 22 of 56 SW V I C T O R I A S T HAY E S P L S W RAINIER AVE S WATSON SECURITY WEST WIND MOTEL ROYAL ORCHID FORMULA 1 FAST LUBE TOMMY'S CAFE BROWN BEAR CAR WASH HARDI E A V E S CORRESPONDING SHEETS FRANCHISE UTILITY STRUCTURE SCHEDULE GENERAL NOTES CONSTRUCTION NOTES CONSTRUCTION NOTES FRANCHISE UTILITY STRUCTURE SCHEDULE (REMOVALS) NUMBER BY APP.REVISION DESCRIPTION DRAWN BY: DESIGN BY: CHECK BY: PROJ MGR: FILE:BY:DATE: APPROVED FOR CONSTRUCTION DATE DRAWING NO. PROJECT NO. FED AID NO. DATE: SHEET NO.OF SURVEYED: 14087A-JUT01.dwg BID DOCUMENT Public Works Department CITY OF RENTON R EGIST E R E D N O T G N I HSAWFOETAT S ER N E P R F O E NNALIO E S IGS 47649 KA R I N A P . FRA N A D A Tacoma Wenatchee KPG.com Seattle 3131 Elliott Avenue, Suite 400 Seattle, WA 98121 206.286.1640 7 -13 -2022 JF KPG (S 3RD ST TO NW 3RD PL) RAINIER AVE S CORRIDOR IMPROVEMENTS - PHASE 4 147 285 JULY 2022 14087A 147 STA 22+50 TO STA 27+00 JOINT UTILITY TRENCH PLAN PLAN DPY KPF KPF STP(UL) -1615(005) FWD #13 - COMCAST JUT REVISIONS DPY KPF 5/9/2023 FWD #17 - LUMEN JUT REVISIONS DPY KPF 5/30/2023 FWD #26 - PSE JUT REVISIONS DPY KPF 6/27/2023 FWD #31 - PSE JUT SECTIONS 2 DPY KPF 7/12/2023 FWD #XX- EXIST JUT/GAS REMOVALS DPY KPF 9/20/2023 FWD #46 - SERVICE CONNECTIONS DPY KPF 9/29/2023 FWD #45 - PSE CONDUIT REVISION DPY KPF 10/2/2023 Removal of Existing Vaults and Duct Banks - Plans Change Order #25, Page 23 of 56 BROWN BEAR RAINIER AVE S S T O B I N S T BROWN BEAR CAR WASH CHEVRON MCDONALD'S STARBUCKS CORRESPONDING SHEETSFRANCHISE UTILITY STRUCTURE SCHEDULE GENERAL NOTES CONSTRUCTION NOTES CONSTRUCTION NOTES FRANCHISE UTILITY STRUCTURE SCHEDULE (REMOVALS) NUMBER BY APP.REVISION DESCRIPTION DRAWN BY: DESIGN BY: CHECK BY: PROJ MGR: FILE:BY:DATE: APPROVED FOR CONSTRUCTION DATE DRAWING NO. PROJECT NO. FED AID NO. DATE: SHEET NO.OF SURVEYED: 14087A-JUT02.dwg BID DOCUMENT Public Works Department CITY OF RENTON R EGIST E R E D N O T G N I HSAWFOETAT S ER N E P R F O E NNALIO E S IGS 47649 KA R I N A P . FRA N A D A Tacoma Wenatchee KPG.com Seattle 3131 Elliott Avenue, Suite 400 Seattle, WA 98121 206.286.1640 7 -13 -2022 PLAN JOINT UTILITY TRENCH PLAN STA 27+00 TO STA 31+00 148 14087A JULY 2022 285148 RAINIER AVE S CORRIDOR IMPROVEMENTS - PHASE 4 (S 3RD ST TO NW 3RD PL) KPG JF KPF KPF DPY STP(UL) -1615(005) FWD #13 - COMCAST JUT REVISIONS DPY KPF 5/9/2023 DPY KPF 9/20/2023FWD #XX - EXIST JUT/GAS REMOVALS DPY KPF 9/29/2023FWD #46 - SERVICE CONNECTIONS Removal of Existing Vaults and Duct Banks - Plans Change Order #25, Page 24 of 56 R E N T O N A V E N U E E X T RAINIER AVE N AI R P O R T W A Y BANNER BANK MCDONALD'S ARCO AM/PM RENTON LAUNDRY RAINIER AVE S CORRESPONDING SHEETS FRANCHISE UTILITY STRUCTURE SCHEDULE GENERAL NOTES CONSTRUCTION NOTES CONSTRUCTION NOTES FRANCHISE UTILITY STRUCTURE SCHEDULE (REMOVALS) NUMBER BY APP.REVISION DESCRIPTION DRAWN BY: DESIGN BY: CHECK BY: PROJ MGR: FILE:BY:DATE: APPROVED FOR CONSTRUCTION DATE DRAWING NO. PROJECT NO. FED AID NO. DATE: SHEET NO.OF SURVEYED: 14087A-JUT02.dwg BID DOCUMENT Public Works Department CITY OF RENTON R EGIST E R E D N O T G N I HSAWFOETAT S ER N E P R F O E NNALIO E S IGS 47649 KA R I N A P . FRA N A D A Tacoma Wenatchee KPG.com Seattle 3131 Elliott Avenue, Suite 400 Seattle, WA 98121 206.286.1640 7 -13 -2022 PLAN JF KPG (S 3RD ST TO NW 3RD PL) RAINIER AVE S CORRIDOR IMPROVEMENTS - PHASE 4 149 285 JULY 2022 14087A 149 STA 31+00 TO STA 35+50 JOINT UTILITY TRENCH PLAN DPY KPF KPF STP(UL) -1615(005) FWD #13 - COMCAST JUT REVISIONS DPY KPF 5/9/2023 FWD #26 - PSE JUT REVISIONS DPY KPF 6/27/2023 DPY KPF 9/20/2023FWD #XX - EXIST JUT/GAS REMOVALS Removal of Existing Vaults and Duct Banks - Plans Change Order #25, Page 25 of 56 N E L S O N P L N W RAINIER AVE N MATHEWSON'S AUTOMOTIVE PRECISION MOTORS CORRESPONDING SHEETSFRANCHISE UTILITY STRUCTURE SCHEDULE GENERAL NOTES CONSTRUCTION NOTES CONSTRUCTION NOTES FRANCHISE UTILITY STRUCTURE SCHEDULE (REMOVALS) NUMBER BY APP.REVISION DESCRIPTION DRAWN BY: DESIGN BY: CHECK BY: PROJ MGR: FILE:BY:DATE: APPROVED FOR CONSTRUCTION DATE DRAWING NO. PROJECT NO. FED AID NO. DATE: SHEET NO.OF SURVEYED: 14087A-JUT02.dwg BID DOCUMENT Public Works Department CITY OF RENTON R EGIST E R E D N O T G N I HSAWFOETAT S ER N E P R F O E NNALIO E S IGS 47649 KA R I N A P . FRA N A D A Tacoma Wenatchee KPG.com Seattle 3131 Elliott Avenue, Suite 400 Seattle, WA 98121 206.286.1640 7 -13 -2022 PLAN JF KPG (S 3RD ST TO NW 3RD PL) RAINIER AVE S CORRIDOR IMPROVEMENTS - PHASE 4 150 285 JULY 2022 14087A 150 STA 35+50 TO STA 39+00 JOINT UTILITY TRENCH PLAN DPY KPF KPF STP(UL) -1615(005) FWD #13 - COMCAST JUT REVISIONS DPY KPF 5/9/2023 FWD #26 - PSE JUT REVISIONS DPY KPF 6/27/2023 FWD #31 - PSE JUT SECTIONS 2 DPY KPF 7/12/2023 DPY KPF 9/20/2023FWD #XX - EXIST JUT/GAS REMOVALS Removal of Existing Vaults and Duct Banks - Plans Change Order #25, Page 26 of 56 RAINIER AVE N NW 3 R D P L VACANT GERBER COLLISION & GLASS ADVANCE AUTO TUNE N E L S O N P L N W CORRESPONDING SHEETSFRANCHISE UTILITY STRUCTURE SCHEDULE GENERAL NOTES CONSTRUCTION NOTES CONSTRUCTION NOTES FRANCHISE UTILITY STRUCTURE SCHEDULE (REMOVALS) NUMBER BY APP.REVISION DESCRIPTION DRAWN BY: DESIGN BY: CHECK BY: PROJ MGR: FILE:BY:DATE: APPROVED FOR CONSTRUCTION DATE DRAWING NO. PROJECT NO. FED AID NO. DATE: SHEET NO.OF SURVEYED: 14087A-JUT02.dwg BID DOCUMENT Public Works Department CITY OF RENTON R EGIST E R E D N O T G N I HSAWFOETAT S ER N E P R F O E NNALIO E S IGS 47649 KA R I N A P . FRA N A D A Tacoma Wenatchee KPG.com Seattle 3131 Elliott Avenue, Suite 400 Seattle, WA 98121 206.286.1640 7 -13 -2022 PLAN JF KPG (S 3RD ST TO NW 3RD PL) RAINIER AVE S CORRIDOR IMPROVEMENTS - PHASE 4 151 285 JULY 2022 14087A 151 STA 39+00 TO STA 43+50 JOINT UTILITY TRENCH PLAN DPY KPF KPF STP(UL) -1615(005) FWD #13 - COMCAST JUT REVISIONS DPY KPF 5/9/2023 FWD #26 - PSE JUT REVISIONS DPY KPF 6/27/2023 FWD #31 - PSE JUT SECTIONS 2 DPY KPF 7/12/2023 DPY KPF 9/20/2023FWD #XX - EXIST JUT/GAS REMOVALS Removal of Existing Vaults and Duct Banks - Plans Change Order #25, Page 27 of 56 TYPICAL JOINT UTILITY TRENCH TRANSITION TYPICAL JOINT UTILITY TRENCH SECTIONS GENERAL JOINT UTILITY TRENCH NOTES SECONDARY ELECTRICAL NOTES TYPICAL JUT SECTION 1 TYPICAL JUT SECTION 2 TYPICAL JUT SECTION 3 TYPICAL JUT SECTION 4 JOINT UTILITY TRENCH LEGEND JOINT UTILITY TRENCH LEGEND (CONTINUED) NUMBER BY APP.REVISION DESCRIPTION DRAWN BY: DESIGN BY: CHECK BY: PROJ MGR: FILE:BY:DATE: APPROVED FOR CONSTRUCTION DATE DRAWING NO. PROJECT NO. FED AID NO. DATE: SHEET NO.OF SURVEYED: 14087A-JUTDET.dwg BID DOCUMENT Public Works Department CITY OF RENTON R EGIST E R E D N O T G N I HSAWFOETAT S ER N E P R F O E NNALIO E S IGS 47649 KA R I N A P . FRA N A D A Tacoma Wenatchee KPG.com Seattle 3131 Elliott Avenue, Suite 400 Seattle, WA 98121 206.286.1640 7 -13 -2022 162 14087A JULY 2022 285162 KPG JF KPF KPF DPY (S 3RD ST TO NW 3RD PL) RAINIER AVE S CORRIDOR IMPROVEMENTS - PHASE 4 JOINT UTILITY TRENCH DETAILS STP(UL) -1615(005) FWD #31 - PSE JUT SECTIONS 2 DPY KPF 7/12/2023 FWD #43 - TYP JUT SECTION REVISION DPY KPF 9/15/2023 DPY KPF 9/20/2023FWD #XX - EXIST JUT/GAS REMOVALS Removal of Existing Vaults and Duct Banks - Plans Change Order #25, Page 28 of 56 Serial Letter: 038s2 April 2, 2024 To: Michelle Faltaous City of Renton 1055 South Grady Way Renton, Washington 98057 Reference Project: CAG-22-163, Rainier Ave S Corridor Improvements – Phase 4 Project Subject: PCO-007 FD-56 JUT Removal Mrs. Michelle Faltaous: As discussed with the City’s Project team, Pivetta Brothers Construction, Inc (Pivetta) has revised our pricing to remove and abandon the existing Joint Utility Trench (JUT) and gas main as identified in Field Directive #56 (FD-56). This pricing is summarized as follows: Item QTY Unit Price Item Price Dura�on JUT Removal (1,763 LF) 1,045 CY $469.14 /CY $490,128.70 24 Plug Exis�ng JUT Conduits at Start Point 16 EA $7,097.85 /EA $113,565.56 8 Remove Exis�ng Vault 45 EA $7,902.44 /EA $355,609.67 23 Remove Exis�ng Hand Hole 7 EA $4,180.98 /EA $29,266.84 2 Gas Main Removal (275 LF) 102 CY $537.07 /CY $54,701.83 3 Plug Exis�ng Gas Main @ Start Point 4 EA $7,192.98 /EA $28,771.91 2 Addi�onal LS Traffic Control Items 62 DYS $3,101.57 /DY $192,297.07 Total $1,264,341.57 62 This pricing does not include items covered by existing pay items such as CSBC, temporary pavements, or flagging but does include the gravel borrow backfill. Plugging/Capping Existing JUT Conduits and Gas Main To more accurately price the effort needed to cap/plug of the existing JUT conduits, Pivetta has identified 16 different locations (4 conduits per location) where we will start removing the JUT. At each of these locations, Pivetta will perform the following steps: 1. Excavate by hand or with a vacuum trailer to expose the conduit, 2. Window each conduit to confirm there are no wires (utility will need to remove all wires prior to the start of the JUT removal), 3. Cut conduit and cap section being abandoned, and 4. Start removing JUT as needed with excavator and pipe crew. Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 29 of 56 A similar approach to the JUT conduits has been applied to capping the existing gas main. The only exception is that Puget Sound Energy (PSE) will be required to cut the existing gas main since Pivetta has no way of safely confirming the line has been properly abandoned. Disposal of Debris A significant amount of debris is expected to be mixed in with the soil as we remove the existing JUT. This debris will include the conduit and piping, constant density fill (CDF), and small construction debris under 8-inches in size. As such, the disposal costs for this material have been calculated based on current project costs. This includes 2.5 hours for trucks to round trip to Franklin Ridge at an average rate of $200 per hour. It also includes the current disposal fee of $,1080 for a truck and trailer. A lower disposal fee could be calculated but this would require us to slow our production of the JUT removal and segregate the debris from the soil being exported. Our initial rough estimates showed this approach to be more costly. Additional Traffic Control Pay items A10 Temporary Traffic Control Devices and A13 Traffic Control Supervisor are both lump sum items. Each of these pay items is materially affected by this change since we are adding work and operations to the project. The costs for the Temporary Traffic Control Devices is estimated at $17.25 per hour to cover the wear and tear on our equipment as well as any incidental rentals or miscellaneous purchases such as signage. Pay item A13 Traffic Control Supervisor (TCS) is calculated using the actual wages paid to our TCS and the company pickup truck they’re assigned. Mitigating Project Schedule Impacts Pivetta has updated the project schedule using the dates provided by the utilities, along with the durations for the JUT removal based on 40 hours per week. As shown in the attached schedule, 2024-03-29 Rainier Ave Schedule Update Rev. 1, this change is adding 32 Working Days to the project (beyond what has been agreed to with CO-19) and placing project completion on 1/5/2026. To mitigate this impact, Pivetta is proposing to remove the JUT as the new sewer and storm work is being constructed. To maintain the project schedule, Pivetta will be required to work overtime and we have added this cost for the JUT removal. Our mitigation schedule 2024-03-29 Rainier Ave Schedule Update – JUT Mitigation Rev. 1, maintains the 654 Working Days allowed with CO-19, and Pivetta will work the necessary overtime to achieve this date using 5 – 10 Hour work shifts as our work week. The expectation is that the City will only charge 5 Working Days for the week and not as identified in Special Provision section 1-08.0(2). Due to the complexity of measuring quantities for this effort, Pivetta is requesting this change order be executed as a lump sum amount. This will place additional risk on Pivetta, with both quantity and production, but it will simplify the payment process to determine who is responsible for an element of work. Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 30 of 56 Please feel free to contact me at (206) 914-2723, if you have any questions or concerns. Respectfully, Bill Adams Sr. Project Manager w/ Attachments: Cc: Detailed Pricing Rev. 2 2024-03-29 Rainier Ave Schedule Update Rev. 1 2023-03-29 Rainier Ave Schedule Update – JUT Mitigation Rev. 1 Jordan Howe, Perteet Shannon Tremper, Perteet Russell Owen, Pivetta Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 31 of 56 Project No.: 2022‐148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item  No.Description Qty UOM Production  Rate Manhours Labor Rate Labor Cost Equipment  Hours Equipment  Rate Equipment  Cost Material Unit  Cost Material Cost Sucontractor Cost Item Cost 1 2 Remove Existing JUT 1,763 LF 3 Foreman Op 15 ‐ 30 (with Pickup) 1,763 LF 0.1067 188.1 $94.96 $17,857.54 188.1 $32.78 $6,164.39 $24,021.93 4 Operator 15 ‐ 30 1,763 LF 0.1067 188.1 $90.96 $17,105.33 $17,105.33 5 Grade Check 1,763 LF 0.1067 188.1 $86.31 $16,230.88 $16,230.88 6 Laborer 1,763 LF 0.1067 188.1 $66.61 $12,526.23 $12,526.23 7Op Driver 1,763 LF 0.1067 188.1 $95.04 $17,872.59 $17,872.59 8 9EX‐139: JD 85G 1,763 LF 0.1067 188.1 $108.90 $20,479.01 $20,479.01 10 75HB‐101: Breaker 1,763 LF 0.1067 188.1 $21.13 $3,973.57 $3,973.57 11 EX‐142: 135N 1,763 LF 0.1067 188.1 $122.55 $23,045.94 $23,045.94 12 135HB‐101: Breaker 1,763 LF 0.1067 188.1 $29.61 $5,568.26 $5,568.26 13 T‐133: International F74 1,763 LF 0.1067 188.1 $72.26 $13,588.73 $13,588.73 14 WL‐112: JD 624K 1,763 LF 0.1067 188.1 $89.64 $16,857.10 $16,857.10 15 Vac Trailer 1,763 LF 0.1067 188.1 $37.84 $7,115.94 $7,115.94 16 Steel Plates & Shoring 1,763 LF 0.1067 188.1 $168.40 $31,668.18 $31,668.18 17 18 Material Handling 24 DY 4.0000 96.0 $90.96 $8,732.16 96.0 $89.64 $8,605.44 $17,337.60 19 Trucking and Disposal ‐ Debris & Soils 1,045 CY $92.94 $97,099.43 $97,099.43 20 21 Sawcutting 840 LF $4,536.00 $4,536.00 22 23 JUT Gravel Borrow 1,410 Tons $24.20 $34,131.68 $34,131.68 24 25 Incidental Overtime 1,036 MH 1.000 1036.266667 $31.00 $32,124.27 $32,124.27 26 $122,449.01 $137,066.55 $131,231.11 $4,536.00 $395,282.67 31% 21% 21% 12%‐‐ $37,959.19 $28,783.98 $27,558.53 $544.32 $94,846.02 $160,408.20 $165,850.53 $158,789.65 $5,080.32 $490,128.70 CY Price $469.14 Work Days Required 24 Notes: Sawcutting at 4 Crossings at 70 LF Each and 2nd Street Crossing at 140' Change Order Pricing Total Cost Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. Utilities will be required to cut any wires encountered (in conduit or direct buried). PCO: Description: Lineal Foot Pricing for JUT Removal 007 FD #56 JUT Removal Element Cost Allowable Markup Markup Cost Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 32 of 56 Project No.: 2022‐148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item  No.Description Qty UOM Production  Rate Manhours Labor Rate Labor Cost Equipment  Hours Equipment  Rate Equipment  Cost Material Unit  Cost Material Cost Sucontractor Cost Item Cost 1 2 Remove Existing JUT 16 EA 3 Foreman Op 15 ‐ 30 (with Pickup) 16 EA 4.0000 64.0 $94.96 $6,077.44 64.0 $32.78 $2,097.92 $8,175.36 4 Operator 15 ‐ 30 16 EA 4.0000 64.0 $90.96 $5,821.44 $5,821.44 5 Grade Check 16 EA 4.0000 64.0 $86.31 $5,523.84 $5,523.84 6 Laborer 16 EA 4.0000 64.0 $66.61 $4,263.04 $4,263.04 7Op Driver 16 EA 4.0000 64.0 $95.04 $6,082.56 $6,082.56 8 10 EX‐139: JD 85G 16 EA 4.0000 64.0 $108.90 $6,969.60 $6,969.60 11 75HB‐101: Breaker 16 EA 4.0000 64.0 $21.13 $1,352.32 $1,352.32 12 EX‐142: 135N 16 EA 4.0000 64.0 $122.55 $7,843.20 $7,843.20 13 135HB‐101: Breaker 16 EA 4.0000 64.0 $29.61 $1,895.04 $1,895.04 14 T‐133: International F74 16 EA 4.0000 64.0 $72.26 $4,624.64 $4,624.64 15 WL‐112: JD 624K 16 EA 4.0000 64.0 $89.64 $5,736.96 $5,736.96 16 Vac Trailer 16 EA 4.0000 64.0 $37.84 $2,421.76 $2,421.76 17 Steel Plates & Shoring 16 EA 4.0000 64.0 $168.40 $10,777.60 $10,777.60 18 19 Material Handling 8 DY 4.0000 32.0 $90.96 $2,910.72 32.0 $89.64 $2,868.48 $5,779.20 20 Materials 16 EA $140.00 $2,240.00 $2,240.00 21 22 Incidental Overtime 352 MH 1.000 352 $31.00 $10,912.00 $10,912.00 23 24 25 $41,591.04 $46,587.52 $2,240.00 $0.00 $90,418.56 31% 21% 21% 12%‐‐ $12,893.22 $9,783.38 $470.40 $0.00 $23,147.00 $54,484.26 $56,370.90 $2,710.40 $0.00 $113,565.56 Price Per Each $7,097.85 Work Days Required 8 Notes: PVC Conduit to be capped with PVC Caps or expansion plugs Allowable Markup Markup Cost Total Cost Assuming 4 conduit plugs between 2" and 6" in size at each location. Work to be done in conjunction with JUT Removal. Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. Element Cost Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Per Each Unit Price for JUT Plug/Abandon Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 33 of 56 Project No.: 2022‐148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item  No.Description Qty UOM Production  Rate Manhours Labor Rate Labor Cost Equipment  Hours Equipment  Rate Equipment  Cost Material Unit  Cost Material Cost Sucontractor Cost Item Cost 1 2 Remove Existing JUT 45 EA 3 Foreman Op 15 ‐ 30 (with Pickup) 45 EA 4.0000 180.0 $94.96 $17,092.80 180.0 $32.78 $5,900.40 $22,993.20 4 Operator 15 ‐ 30 45 EA 4.0000 180.0 $90.96 $16,372.80 $16,372.80 5 Grade Check 45 EA 4.0000 180.0 $86.31 $15,535.80 $15,535.80 6 Laborer 45 EA 4.0000 180.0 $66.61 $11,989.80 $11,989.80 7Op Driver 45 EA 4.0000 180.0 $95.04 $17,107.20 $17,107.20 8 9EX‐139: JD 85G 45 EA 4.0000 180.0 $108.90 $19,602.00 $19,602.00 10 75HB‐101: Breaker 45 EA 4.0000 180.0 $21.13 $3,803.40 $3,803.40 11 EX‐142: 135N 45 EA 4.0000 180.0 $122.55 $22,059.00 $22,059.00 12 135HB‐101: Breaker 45 EA 4.0000 180.0 $29.61 $5,329.80 $5,329.80 13 T‐133: International F74 45 EA 4.0000 180.0 $72.26 $13,006.80 $13,006.80 14 WL‐112: JD 624K 45 EA 4.0000 180.0 $89.64 $16,135.20 $16,135.20 15 Vac Trailer 45 EA 4.0000 180.0 $37.84 $6,811.20 $6,811.20 16 Steel Plates & Shoring 45 EA 4.0000 180.0 $168.40 $30,312.00 $30,312.00 17 18 Material Handling 23 DY 4.0000 92.0 $90.96 $8,368.32 92.0 $89.64 $8,246.88 $16,615.20 19 Trucking and Disposal 160.0 CY $92.94 $14,870.59 $14,870.59 20 21 JUT Gravel Borrow ‐ Import 864 Tons $24.20 $20,908.80 $20,908.80 22 22 Incidental Overtime 992 MH 1.000 992 $31.00 $30,752.00 $30,752.00 24 $117,218.72 $131,206.68 $35,779.39 $0.00 $284,204.79 31% 21% 21% 12%‐‐ $36,337.80 $27,553.40 $7,513.67 $0.00 $71,404.88 $153,556.52 $158,760.08 $43,293.06 $0.00 $355,609.67 Price Per Each $7,902.44 Work Days Required 23 Notes: Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. PVC Conduit to be capped with PVC Caps or expansion plugs Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Per Each Unit Price for JUT Vault Removal Element Cost Worked to be done in conjunction with JUT Removal and Plug/Abandon Conduit. Allowable Markup Markup Cost Total Cost 12 PSE Vaults, 17 Century Link Vaults, and 16 Comcast Vaults Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 34 of 56 Project No.: 2022‐148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item  No.Description Qty UOM Production  Rate Manhours Labor Rate Labor Cost Equipment  Hours Equipment  Rate Equipment  Cost Material Unit  Cost Material Cost Sucontractor Cost Item Cost 1 2 Remove Existing JUT 7 EA 3 Foreman Op 15 ‐ 30 (with Pickup) 7 EA 2.0000 14.0 $94.96 $1,329.44 14.0 $32.78 $458.92 $1,788.36 4 Operator 15 ‐ 30 7 EA 2.0000 14.0 $90.96 $1,273.44 $1,273.44 5 Grade Check 7 EA 2.0000 14.0 $86.31 $1,208.34 $1,208.34 6 Laborer 7 EA 2.0000 14.0 $66.61 $932.54 $932.54 7Op Driver 7 EA 2.0000 14.0 $95.04 $1,330.56 $1,330.56 8 9P‐147: Shop Truck 7 EA 2.0000 14.0 $32.78 $458.92 $458.92 10 EX‐139: JD 85G 7 EA 2.0000 14.0 $108.90 $1,524.60 $1,524.60 11 75HB‐101: Breaker 7 EA 2.0000 14.0 $21.13 $295.82 $295.82 12 EX‐142: 135N 7 EA 2.0000 14.0 $122.55 $1,715.70 $1,715.70 13 135HB‐101: Breaker 7 EA 2.0000 14.0 $29.61 $414.54 $414.54 14 T‐133: International F74 7 EA 2.0000 14.0 $72.26 $1,011.64 $1,011.64 15 WL‐112: JD 624K 7 EA 2.0000 14.0 $89.64 $1,254.96 $1,254.96 16 Vac Trailer 7 EA 2.0000 14.0 $37.84 $529.76 $529.76 17 Steel Plates & Shoring 7 EA 4.0000 28.0 $168.40 $4,715.20 $4,715.20 18 19 Material Handling 2 DY 4.0000 8.0 $90.96 $727.68 8.0 $89.64 $717.12 $1,444.80 20 Trucking and Disposal 4.1 CY $92.94 $385.53 $385.53 21 22 JUT Gravel Borrow ‐ Import 30 Tons $24.20 $722.77 $722.77 23 22 Incidental Overtime 78 MH 1.000 78 $31.00 $2,418.00 $2,418.00 25 $9,220.00 $13,097.18 $1,108.31 $0.00 $23,425.49 31% 21% 21% 12%‐‐ $2,858.20 $2,750.41 $232.74 $0.00 $5,841.35 $12,078.20 $15,847.59 $1,341.05 $0.00 $29,266.84 Price Per Each $4,180.98 Work Days Required 2 Notes: PVC Conduit to be capped with PVC Caps or expansion plugs Allowable Markup Markup Cost Total Cost Any handhole larger than 4' x 4' will be considered a vault. Worked to be done in conjunction with JUT Removal and Plug/Abandon Conduit. Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. Element Cost Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Per Each Unit Price for JUT Hand Hole Removal Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 35 of 56 Project No.: 2022‐148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item  No.Description Qty UOM Production  Rate Manhours Labor Rate Labor Cost Equipment  Hours Equipment  Rate Equipment  Cost Material Unit  Cost Material Cost Sucontractor Cost Item Cost 1 2 Remove Existing JUT 275 LF 3 Foreman Op 15 ‐ 30 (with Pickup) 275 LF 0.0800 22.0 $94.96 $2,089.12 22.0 $32.78 $721.16 $2,810.28 4 Operator 15 ‐ 30 275 LF 0.0800 22.0 $90.96 $2,001.12 $2,001.12 5 Grade Check 275 LF 0.0800 22.0 $86.31 $1,898.82 $1,898.82 6 Laborer 275 LF 0.0800 22.0 $66.61 $1,465.42 $1,465.42 7Op Driver 275 LF 0.0800 22.0 $95.04 $2,090.88 $2,090.88 8 10 EX‐139: JD 85G 275 LF 0.0800 22.0 $108.90 $2,395.80 $2,395.80 11 75HB‐101: Breaker 275 LF 0.0800 22.0 $21.13 $464.86 $464.86 12 EX‐142: 135N 275 LF 0.0800 22.0 $122.55 $2,696.10 $2,696.10 13 135HB‐101: Breaker 275 LF 0.0800 22.0 $29.61 $651.42 $651.42 14 T‐133: International F74 275 LF 0.0800 22.0 $72.26 $1,589.72 $1,589.72 15 WL‐112: JD 624K 275 LF 0.0800 22.0 $89.64 $1,972.08 $1,972.08 16 Vac Trailer 275 LF 0.0800 22.0 $37.84 $832.48 $832.48 17 Steel Plates & Shoring 275 LF 0.0800 22.0 $168.40 $3,704.80 $3,704.80 18 19 Material Handling 3 DY 4.0000 12.0 $90.96 $1,091.52 12.0 $89.64 $1,075.68 $2,167.20 20 Trucking and Disposal 102 CY $92.94 $9,466.23 $9,466.23 21 21 Sawcutting 140 LF $756.00 $756.00 23 24 JUT Gravel Borrow 138 Tons $24.20 $3,327.50 $3,327.50 22 Incidental Overtime 122 MH 1.000 122 $31.00 $3,782.00 $3,782.00 25 $14,418.88 $16,104.10 $12,793.73 $756.00 $44,072.71 31% 21% 21% 12%‐‐ $4,469.85 $3,381.86 $2,686.68 $90.72 $10,629.12 $18,888.73 $19,485.96 $15,480.41 $846.72 $54,701.83 CY Price $537.07 Work Days Required 3 Notes: Allowable Markup Markup Cost Total Cost Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. 1 Crossing at 70 LF for PSE Gas Element Cost Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Lineal Foot Pricing for Gas Main Removal Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 36 of 56 Project No.: 2022‐148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item  No.Description Qty UOM Production  Rate Manhours Labor Rate Labor Cost Equipment  Hours Equipment  Rate Equipment  Cost Material Unit  Cost Material Cost Sucontractor Cost Item Cost 1 2 Plug/Cap Existing Main 4 EA 3 Foreman Op 15 ‐ 30 (with Pickup) 4 EA 4.0000 16.0 $94.96 $1,519.36 16.0 $32.78 $524.48 $2,043.84 4 Operator 15 ‐ 30 4 EA 4.0000 16.0 $90.96 $1,455.36 $1,455.36 5 Grade Check 4 EA 4.0000 16.0 $86.31 $1,380.96 $1,380.96 6 Laborer 4 EA 4.0000 16.0 $66.61 $1,065.76 $1,065.76 7Op Driver 4 EA 4.0000 16.0 $95.04 $1,520.64 $1,520.64 8 9P‐147: Shop Truck 4 EA 4.0000 16.0 $32.78 $524.48 $524.48 10 EX‐139: JD 85G 4 EA 4.0000 16.0 $108.90 $1,742.40 $1,742.40 11 75HB‐101: Breaker 4 EA 4.0000 16.0 $21.13 $338.08 $338.08 12 EX‐142: 135N 4 EA 4.0000 16.0 $122.55 $1,960.80 $1,960.80 13 135HB‐101: Breaker 4 EA 4.0000 16.0 $29.61 $473.76 $473.76 14 T‐133: International F74 4 EA 4.0000 16.0 $72.26 $1,156.16 $1,156.16 15 WL‐112: JD 624K 4 EA 4.0000 16.0 $89.64 $1,434.24 $1,434.24 16 Steel Plates & Shoring 4 EA 4.0000 16.0 $168.40 $2,694.40 $2,694.40 17 18 Vac Trailer 4 EA 4.0000 16.0 $37.84 $605.44 $605.44 19 20 Material Handling 2 DY 4.0000 8.0 $90.96 $727.68 8.0 $89.64 $717.12 $1,444.80 21 Materials 10 EA $35.00 $350.00 $350.00 22 22 Incidental Overtime 88 MH 1.000 88 $31.00 $2,728.00 $2,728.00 24 25 $10,397.76 $12,171.36 $350.00 $0.00 $22,919.12 31% 21% 21% 12%‐‐ $3,223.31 $2,555.99 $73.50 $0.00 $5,852.79 $13,621.07 $14,727.35 $423.50 $0.00 $28,771.91 Price Per Each $7,192.98 Work Days Required 2 Notes: HDPE pipes to be plugged with expansion plugs or cement grout. Allowable Markup Markup Cost Total Cost Assuming 1 Cap/Plug between 2" and 4" at each location. Initial cuts of existing Gas Main to be done by others. Work to be done in conjunction with Gas Main Removal. Items such as CSBC, Temp Patching, Flagging to be paid under existing Bid Items. Element Cost Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Per Each Unit Price for Gas Plug/Abandon Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 37 of 56 Project No.: 2022‐148 Project Name: Rainier Ave S Phase 4 Date:2/5/2024 Item  No.Description Qty UOM Production  Rate Manhours Labor Rate Labor Cost Equipment  Hours Equipment  Rate Equipment  Cost Material Unit  Cost Material Cost Sucontractor Cost Item Cost 1 2 Pay Item A10 ‐ Temporary Traffic Control Devices 62 DYS 3 Incidental Equipment 62 DYS 8.0000 496.00 $17.25 $8,556.00 $8,556.00 4 5 Pay Item A13 ‐ TCS 62 DYS 6 Traffic Control Supervisor 62 DYS 8.0000 496.0 $65.74 $32,607.04 496.00 $32.78 $16,258.88 $48,865.92 7 8 22 Incidental Overtime ‐ TCS 496 MH 1.000 496 $24.00 $11,904.00 $11,904.00 10 Incidental Overtime ‐ Flaggers 3,968 MH 1.0000 3968 $20.00 $79,360.00 $79,360.00 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 $123,871.04 $24,814.88 $0.00 $0.00 $148,685.92 31% 21% 21% 12%‐‐ $38,400.02 $5,211.12 $0.00 $0.00 $43,611.15 $162,271.06 $30,026.00 $0.00 $0.00 $192,297.07 Notes: Allowable Markup Markup Cost Total Cost Element Cost Change Order Pricing PCO: 007 FD #56 JUT Removal Description: Additional Traffic Control Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 38 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 0 Rainier Ave Phase 4 Project Schedule 772 d?0 d?0 d?Wed 11/2/22 NA Wed 11/2/22 Mon 1/5/26 Wed 11/2/22 Mon 1/5/26 1 2 Bid Opening Date 1 d 0 d 0 d Wed 11/2/22 Wed 11/2/22 Wed 11/2/22 Wed 11/2/22 Wed 11/2/22 Wed 11/2/22 Project Overview 3 Award Date (w/in 45 calendar days after opening bids)1.13 d 0 d 0 d Tue 12/13/22 Tue 12/13/22 Tue 12/13/22 Tue 12/13/22 Tue 12/13/22 Tue 12/13/22 2FS+45 d Project Overview 4 Contract Execution Date 1 d 0 d 0 d Thu 12/22/22 Thu 12/22/22 Thu 12/22/22 Thu 12/22/22 Thu 12/22/22 Thu 12/22/22 3 Project Overview 5 Notice to Proceed Date 1 d 0 d 0 d Mon 3/13/23 Mon 3/13/23 Mon 3/13/23 Mon 3/13/23 Mon 3/13/23 Mon 3/13/23 3,20FS+8 d Project Overview 6 Substantial Completion Date 0 d 0 d 0 d NA NA Mon 1/5/26 Mon 1/5/26 Mon 1/5/26 Mon 1/5/26 536,540,324,354,472,288,471,539 Project Overview 7 Physical Completion Date 0 d 0 d 0 d NA NA Mon 1/5/26 Mon 1/5/26 Mon 1/5/26 Mon 1/5/26 5,6 Project Overview 8 Contractual Physical Completion Date (500 working days)0 d 186 d 186 d NA NA Wed 4/2/25 Wed 4/2/25 Mon 1/5/26 Mon 1/5/26 5FS+500 d Project Overview 9 10 Preconstruction 164 d 0 d 0 d Sun 2/12/23 Fri 10/6/23 Sun 2/12/23 Fri 10/6/23 Sun 2/12/23 Fri 10/6/23 4 11 Submit Contractor's Health and Safety Plan 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 4 Pivetta - Administration 12 Prepare/Submit Confined Space Entry Program 5 d 0 d 0 d Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 5 Pivetta - Administration 13 Prepare/Submit Shoring and Excavation Plan 3 d 0 d 0 d Wed 2/15/23 Fri 2/17/23 Wed 2/15/23 Fri 2/17/23 Wed 2/15/23 Fri 2/17/23 4 Pivetta - Administration 14 Prepare/Submit Breakdown of Lump Sum Bid Items 5 d 0 d 0 d Sun 2/12/23 Fri 2/17/23 Sun 2/12/23 Fri 2/17/23 Sun 2/12/23 Fri 2/17/23 4 Pivetta - Administration 15 Prepare/Submit Preliminary QPL/RAM for Jobsite Materials 5 d 0 d 0 d Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 4 Pivetta - Administration 16 Prepare/Submit Preliminary Schedule of Working Drawing Submittals 5 d 0 d 0 d Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 4 Pivetta - Administration 17 Submit Work Hour Variance to CoR 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 4 Pivetta - Administration 18 Prepare/Submit Type 2 Working Drawings for Field Office 1 d 0 d 0 d Thu 3/2/23 Thu 3/2/23 Thu 3/2/23 Thu 3/2/23 Thu 3/2/23 Thu 3/2/23 4 Pivetta - Administration 19 Submit Preliminary Type B Schedule 1 d 0 d 0 d Tue 2/21/23 Tue 2/21/23 Tue 2/21/23 Tue 2/21/23 Tue 2/21/23 Tue 2/21/23 4 Pivetta - Administration 20 Attend Preconstruction Conference 1 d 0 d 0 d Wed 2/22/23 Wed 2/22/23 Wed 2/22/23 Wed 2/22/23 Wed 2/22/23 Wed 2/22/23 4FS+49 d,11,14,15,16,17,18,19 City of Renton 21 22 Submit Final Type B Progress Schedule 1 d 0 d 0 d Mon 3/20/23 Mon 3/20/23 Mon 3/20/23 Mon 3/20/23 Mon 3/20/23 Mon 3/20/23 20 Pivetta - Administration 23 Prepare/Submit Project Specific Traffic Control Plan 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 4 Pivetta - Administration 24 Prepare/Submit Confined Space Program Plan 5 d 0 d 0 d Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Pivetta - Administration 25 Submit/Fabricate Sample Project Identification Signs to CoR 5 d 0 d 0 d Mon 2/20/23 Mon 2/27/23 Mon 2/20/23 Mon 2/27/23 Mon 2/20/23 Mon 2/27/23 4 Pivetta - Administration 26 Prepare/Submit Dewatering Plan (Waiting on RFI-007 submitted 2/20/2023)5 d 0 d 0 d Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 4 Pivetta - Administration 27 Prepare/Submit Contaminated Soil and GW Handling and Mgmt Plan 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 4 Pivetta - Administration 28 Request JUT Structures and Conduit 1 d 0 d 0 d Wed 3/8/23 Wed 3/8/23 Wed 3/8/23 Wed 3/8/23 Wed 3/8/23 Wed 3/8/23 20 Pivetta - Administration 29 Utility Preconstruction Meeting 1 d 0 d 0 d Thu 3/16/23 Thu 3/16/23 Thu 3/16/23 Thu 3/16/23 Thu 3/16/23 Thu 3/16/23 5FS+2 d City of Renton 30 31 Setup/Install Temporary Field Offices 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 20 Pivetta 32 Complete Project Existing Conditions Survey 4 d 0 d 0 d Mon 3/13/23 Fri 3/17/23 Mon 3/13/23 Fri 3/17/23 Mon 3/13/23 Fri 3/17/23 5 Pivetta - Administration 33 Control and Staking 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 5 North Peak 34 35 Rainier Ave. S. - Construction Duration 687 d?0 d?0 d?Mon 3/13/23 NA Mon 3/13/23 Mon 1/5/26 Mon 3/13/23 Mon 1/5/26 5,13 36 Mobilization 107 d 0 d 0 d Mon 3/13/23 Fri 8/11/23 Mon 3/13/23 Fri 8/11/23 Mon 3/13/23 Fri 8/11/23 37 CCTV and Flush Sewer Lines 0 d 0 d 0 d Tue 8/1/23 Tue 8/1/23 Tue 8/1/23 Tue 8/1/23 Tue 8/1/23 Tue 8/1/23 5,12 Insituform 38 Fence Removal and Reinstallation 5 d 0 d 0 d Tue 8/1/23 Mon 8/7/23 Tue 8/1/23 Mon 8/7/23 Tue 8/1/23 Mon 8/7/23 33SS Pivetta 39 Sewer Manhole Delivery 39 d 0 d 0 d Fri 6/16/23 Fri 8/11/23 Fri 6/16/23 Fri 8/11/23 Fri 6/16/23 Fri 8/11/23 5 Pivetta - Administration 40 41 Potholing 42 d 0 d 0 d Mon 3/13/23 Tue 5/9/23 Mon 3/13/23 Tue 5/9/23 Mon 3/13/23 Tue 5/9/23 42 Pothole South Rainer Ave - STA 15+25 to 25+00 17 d 0 d 0 d Mon 3/13/23 Wed 4/5/23 Mon 3/13/23 Wed 4/5/23 Mon 3/13/23 Wed 4/5/23 5,23 43 Pothole North Rainier Ave - STA 25+00 to 42+85 24 d 0 d 0 d Wed 4/5/23 Tue 5/9/23 Wed 4/5/23 Tue 5/9/23 Wed 4/5/23 Tue 5/9/23 42 44 Pothole Side Streets 0 d 0 d 0 d Thu 5/4/23 Thu 5/4/23 Thu 5/4/23 Thu 5/4/23 Thu 5/4/23 Thu 5/4/23 43 45 46 Stage 1 (West)493 d?183 d?183 d?Tue 3/28/23 NA Tue 3/28/23 Mon 4/7/25 Tue 3/28/23 Mon 1/5/26 5 47 Site Prep - Sta 13+93.10 to 40+80.29 133.25 d 0 d 0 d Tue 3/28/23 Fri 10/6/23 Tue 3/28/23 Fri 10/6/23 Tue 3/28/23 Fri 10/6/23 48 Install Project Identification and Business Owner Signs 1 d 0 d 0 d Tue 3/28/23 Tue 3/28/23 Tue 3/28/23 Tue 3/28/23 Tue 3/28/23 Tue 3/28/23 4 Pivetta 49 Install High Visibility Fence/Inspection by CoR 1 d 0 d 0 d Wed 3/29/23 Wed 3/29/23 Wed 3/29/23 Wed 3/29/23 Wed 3/29/23 Wed 3/29/23 4 Pivetta 50 Install TESC- Stage 1 28 d 0 d 0 d Wed 3/29/23 Fri 5/5/23 Wed 3/29/23 Fri 5/5/23 Wed 3/29/23 Fri 5/5/23 4 Pivetta 51 Clear & Grub - Stage 1 (Work Progressing as Needed with Other Activities)2.25 d 0 d 0 d Mon 4/24/23 Wed 6/21/23 Mon 4/24/23 Wed 6/21/23 Mon 4/24/23 Wed 6/21/23 50 Pivetta 52 Complete Removals 5 d 0 d 0 d Mon 4/24/23 Fri 10/6/23 Mon 4/24/23 Fri 10/6/23 Mon 4/24/23 Fri 10/6/23 51 Pivetta 53 Relocate Bus Shelter - Sta 27+45.48 3 d 0 d 0 d Mon 4/24/23 Wed 4/26/23 Mon 4/24/23 Wed 4/26/23 Mon 4/24/23 Wed 4/26/23 5 Pivetta 54 Temporary Channelization and Signalization - Sta 13+95 to 43+63.00 14 d 0 d 0 d Wed 4/5/23 Mon 4/24/23 Wed 4/5/23 Mon 4/24/23 Wed 4/5/23 Mon 4/24/23 55 Portable Temporary Signal System (SW Sunset/S 3rd St.) (2nd St.) (Airport Way/Renton Ave)6 d 0 d 0 d Wed 4/5/23 Wed 4/12/23 Wed 4/5/23 Wed 4/12/23 Wed 4/5/23 Wed 4/12/23 56 Pull Wire to Tie In Temp Signal 2 d 0 d 0 d Wed 4/5/23 Thu 4/6/23 Wed 4/5/23 Thu 4/6/23 Wed 4/5/23 Thu 4/6/23 48 Golden Gate 57 Video Detection Camera Installation 1 d 0 d 0 d Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 56SS+2 d Golden Gate 58 Install Portable Signal System 1 d 0 d 0 d Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 57 Golden Gate 59 Adjust and Modify Signals 1 d 0 d 0 d Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 58 Golden Gate 60 Temporary Channelization - Sta 13+95 to 43+63.00 9 d 0 d 0 d Wed 4/12/23 Mon 4/24/23 Wed 4/12/23 Mon 4/24/23 Wed 4/12/23 Mon 4/24/23 61 Install Stage 1 Construction Channelization and Striping - South of Airport Way 0 d 0 d 0 d Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 57,59,58,56,53,48FF SPM 1/5 1/5 4/2 2/20 2/20 2/20 2/20 2/20 2/20 8/1 5/4 4/12 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 1 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 39 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 62 Install Stage 1 Construction Channelization and Striping - North of Airport Way 1 d 0 d 0 d Mon 4/24/23 Mon 4/24/23 Mon 4/24/23 Mon 4/24/23 Mon 4/24/23 Mon 4/24/23 61 SPM 63 Joint Utility Trench - Sta 15+25 to 42+85 242 d?0 d?0 d?Tue 3/28/23 Fri 3/29/24 Tue 3/28/23 Fri 3/29/24 Tue 3/28/23 Fri 3/29/24 64 JUT - Walgreens to Sansonia (Sections A, EE, AA) - Sta 15+25 to Sta 18+40 87 d 0 d 0 d Tue 3/28/23 Mon 7/31/23 Tue 3/28/23 Mon 7/31/23 Tue 3/28/23 Mon 7/31/23 65 Receive Vaults and Conduits from Utilities 10 d 0 d 0 d Tue 3/28/23 Mon 6/5/23 Tue 3/28/23 Mon 6/5/23 Tue 3/28/23 Mon 6/5/23 5,28 Utilities 66 Install Vaults 3.5 d 0 d 0 d Thu 5/11/23 Wed 6/7/23 Thu 5/11/23 Wed 6/7/23 Thu 5/11/23 Wed 6/7/23 65,74,42 Pivetta - JUT 67 Install Conduits 34 d 0 d 0 d Mon 6/12/23 Mon 7/31/23 Mon 6/12/23 Mon 7/31/23 Mon 6/12/23 Mon 7/31/23 66 Pivetta - JUT/Golden Gate/PSE - Gas 68 JUT - Night/Stage 2 - Hertz/Lyft to Taco Time - Sta 14+21.6 to 18+40 104 d 0 d 0 d Tue 3/28/23 Wed 8/23/23 Tue 3/28/23 Wed 8/23/23 Tue 3/28/23 Wed 8/23/23 69 Receive Vaults and Conduits from Utilities 6 d 0 d 0 d Tue 3/28/23 Tue 5/30/23 Tue 3/28/23 Tue 5/30/23 Tue 3/28/23 Tue 5/30/23 28 Utilities 70 Install Vaults 2 d 0 d 0 d Mon 7/31/23 Tue 8/1/23 Mon 7/31/23 Tue 8/1/23 Mon 7/31/23 Tue 8/1/23 69 71 Install Conduits 8 d 0 d 0 d Mon 8/14/23 Wed 8/23/23 Mon 8/14/23 Wed 8/23/23 Mon 8/14/23 Wed 8/23/23 75,70 Pivetta - JUT/Golden Gate/PSE - Gas 72 JUT - Night/Crossing - Watson Sec to Taco Time, Across 2nd St., Vacant to Metro PCS - Sta 18+40 to 20+10 108 d 0 d 0 d Tue 3/28/23 Tue 8/29/23 Tue 3/28/23 Tue 8/29/23 Tue 3/28/23 Tue 8/29/23 73 Receive Vaults and Conduits from Utilities 10 d 0 d 0 d Tue 3/28/23 Mon 6/5/23 Tue 3/28/23 Mon 6/5/23 Tue 3/28/23 Mon 6/5/23 28 Utilities 74 Install Vaults 12 d 0 d 0 d Tue 6/20/23 Fri 7/7/23 Tue 6/20/23 Fri 7/7/23 Tue 6/20/23 Fri 7/7/23 73,42 Pivetta - JUT 75 Install Conduits 21 d 0 d 0 d Tue 8/1/23 Tue 8/29/23 Tue 8/1/23 Tue 8/29/23 Tue 8/1/23 Tue 8/29/23 73,74,67 Pivetta - JUT/Golden Gate/PSE - Gas 76 JUT - Night/Stage 2 - Vacant to Formula 1 Fast Lube - Sta 20+10 to 25+20 114 d 0 d 0 d Tue 3/28/23 Thu 9/7/23 Tue 3/28/23 Thu 9/7/23 Tue 3/28/23 Thu 9/7/23 77 Remove/Relocate Bus Shelter - Sta 24+59.90 4 d 0 d 0 d Mon 6/12/23 Thu 6/15/23 Mon 6/12/23 Thu 6/15/23 Mon 6/12/23 Thu 6/15/23 5 Pivetta - JUT 78 Receive Vaults and Conduits from Utilities 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 79 Install Vaults 4 d 0 d 0 d Wed 8/30/23 Tue 9/5/23 Wed 8/30/23 Tue 9/5/23 Wed 8/30/23 Tue 9/5/23 78,77,70 80 Install Conduits 6 d 0 d 0 d Wed 8/30/23 Thu 9/7/23 Wed 8/30/23 Thu 9/7/23 Wed 8/30/23 Thu 9/7/23 79 Pivetta - JUT/Golden Gate/PSE - Gas 81 JUT - Big Island Poke to Watson Security (Sections B, C, F, D, R, K, M, JJ, DD, LL, E, G, H, Z) - Sta 19+00 to 24+80 153 d 0 d 0 d Tue 3/28/23 Fri 11/3/23 Tue 3/28/23 Fri 11/3/23 Tue 3/28/23 Fri 11/3/23 82 Receive Vaults and Conduits from Utilities 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 83 Install Vaults (J07 Installed Last with RFI-072)0 d 0 d 0 d Mon 5/15/23 Mon 7/17/23 Mon 5/15/23 Mon 7/17/23 Mon 5/15/23 Mon 7/17/23 82,65,79 Pivetta - JUT 84 Install Conduits 38 d 0 d 0 d Mon 9/11/23 Fri 11/3/23 Mon 9/11/23 Fri 11/3/23 Mon 9/11/23 Fri 11/3/23 85 Install Conduits 23 d 0 d 0 d Mon 9/11/23 Fri 11/3/23 Mon 9/11/23 Fri 11/3/23 Mon 9/11/23 Fri 11/3/23 82,83,298,67,71,80 Pivetta - JUT/Golden Gate/PSE - Gas 86 Contaminated Soils at STA 21+50 9 d 0 d 0 d Thu 9/28/23 Tue 10/10/23 Thu 9/28/23 Tue 10/10/23 Thu 9/28/23 Tue 10/10/23 85SS 87 JUT - Night/Power Crossting - Sta 23+80 3 d 0 d 0 d Mon 10/2/23 Wed 10/4/23 Mon 10/2/23 Wed 10/4/23 Mon 10/2/23 Wed 10/4/23 88 Install Conduits (Deleted Per FD)3 d 0 d 0 d Mon 10/2/23 Wed 10/4/23 Mon 10/2/23 Wed 10/4/23 Mon 10/2/23 Wed 10/4/23 Pivetta - JUT/Golden Gate/PSE - Gas 89 JUT - Victoria Street (CO-09)8 d 0 d 0 d Mon 11/20/23 Fri 12/1/23 Mon 11/20/23 Fri 12/1/23 Mon 11/20/23 Fri 12/1/23 90 Install Conduits 8 d 0 d 0 d Mon 11/20/23 Fri 12/1/23 Mon 11/20/23 Fri 12/1/23 Mon 11/20/23 Fri 12/1/23 95 91 JUT - Watson Security to Renton Ave. Ext (NO PSE Gas) - Sta 24+80 to 31+90 186 d?0 d?0 d?Tue 3/28/23 Fri 1/5/24 Tue 3/28/23 Fri 1/5/24 Tue 3/28/23 Fri 1/5/24 92 Receive Vaults and Conduits from Utilities 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 93 Install Vaults 12 d 0 d 0 d Tue 5/23/23 Tue 10/17/23 Tue 5/23/23 Tue 10/17/23 Tue 5/23/23 Tue 10/17/23 92,83,43 Pivetta - JUT 94 Install Conduits 9 d?0 d?0 d?Mon 11/6/23 Fri 1/5/24 Mon 11/6/23 Fri 11/17/23 Mon 11/6/23 Fri 1/5/24 93 Pivetta - JUT/Golden Gate/PSE - Gas 95 Watson Security to Hayes 4 d 0 d 0 d Mon 11/6/23 Fri 11/17/23 Mon 11/6/23 Fri 11/17/23 Mon 11/6/23 Fri 11/17/23 85 96 Hayes to Renton Ave 4 d 0 d 0 d Mon 12/4/23 Fri 1/5/24 Mon 12/4/23 Fri 1/5/24 Mon 12/4/23 Fri 1/5/24 95,90 97 Contaminated Soil @ STA 28+75 2 d 0 d 0 d Tue 12/12/23 Wed 12/13/23 Tue 12/12/23 Wed 12/13/23 Tue 12/12/23 Wed 12/13/23 96SS 98 JUT - Night/Power Crossing - Tobin St, Sta 28+75 and 30+28 4 d 0 d 0 d Wed 1/24/24 Mon 1/29/24 Wed 1/24/24 Mon 1/29/24 Wed 1/24/24 Mon 1/29/24 99 Install Conduits 4 d 0 d 0 d Wed 1/24/24 Mon 1/29/24 Wed 1/24/24 Mon 1/29/24 Wed 1/24/24 Mon 1/29/24 94,96,103 Pivetta - JUT/Golden Gate/PSE - Gas 100 JUT - Night/Crossing Renton Ave Ext - Sta 31+90 to 33+00 194 d 0 d 0 d Tue 3/28/23 Tue 1/23/24 Tue 3/28/23 Tue 1/23/24 Tue 3/28/23 Tue 1/23/24 101 Receive Vaults and Conduits from Utilities 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 102 Install Vaults 4 d 0 d 0 d Mon 10/2/23 Thu 10/5/23 Mon 10/2/23 Thu 10/5/23 Mon 10/2/23 Thu 10/5/23 101,62 Pivetta - JUT 103 Install Conduits 7 d 0 d 0 d Mon 1/8/24 Tue 1/23/24 Mon 1/8/24 Tue 1/23/24 Mon 1/8/24 Tue 1/23/24 101,102,96 Pivetta - JUT/Golden Gate/PSE - Gas 104 JUT - Arco to Gerber Collision- Section P, U, V, W (No PSE Gas) - Sta 33+00 to 42+85 242 d 0 d 0 d Tue 3/28/23 Fri 3/29/24 Tue 3/28/23 Fri 3/29/24 Tue 3/28/23 Fri 3/29/24 105 Receive Vaults and Conduits from Utilities 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 106 Install Vaults 17 d 0 d 0 d Wed 10/18/23 Fri 1/5/24 Wed 10/18/23 Fri 1/5/24 Wed 10/18/23 Fri 1/5/24 93,105,38 Pivetta - JUT 107 Install Conduits 25 d 0 d 0 d Wed 2/14/24 Fri 3/29/24 Wed 2/14/24 Fri 3/29/24 Wed 2/14/24 Fri 3/29/24 105,106,111 Pivetta - JUT/Golden Gate/PSE - Gas 108 JUT - Night/Crossings - Sta 33+77, 36+17, 40+43 206 d 0 d 0 d Tue 3/28/23 Thu 2/8/24 Tue 3/28/23 Thu 2/8/24 Tue 3/28/23 Thu 2/8/24 109 Receive Vaults and Conduits from Utility Owner 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 110 Install Vaults 1 d 0 d 0 d Wed 10/18/23 Wed 10/18/23 Wed 10/18/23 Wed 10/18/23 Wed 10/18/23 Wed 10/18/23 106SS,102,109 Pivetta - JUT 111 Install Conduit 8 d 0 d 0 d Tue 1/30/24 Thu 2/8/24 Tue 1/30/24 Thu 2/8/24 Tue 1/30/24 Thu 2/8/24 110,99 Pivetta - JUT/Golden Gate/PSE - Gas 112 JUT - Utility Owner Work, Removals, Grounding/Bonding 15+25 to 42+85 198 d 63 d 63 d Mon 10/2/23 NA Mon 10/2/23 Wed 7/31/24 Mon 10/2/23 Tue 10/29/24 113 Lumen/CenturyLink to Begin Work South of Victoria Street 0 d 0 d 0 d Tue 1/23/24 Tue 1/23/24 Tue 1/23/24 Tue 1/23/24 Tue 1/23/24 Tue 1/23/24 94 114 PSE Gas - Install 1-6" Gas Line & Connections to Main JUT across Rainier (Ends at HH/II in SW Victoria)28 d 0 d 0 d Mon 10/2/23 Thu 1/4/24 Mon 10/2/23 Thu 1/4/24 Mon 10/2/23 Thu 1/4/24 67SS PSE - Gas 115 Relocate Gas Line on Airport Way to Avoid Storm Drain 4 d 0 d 0 d Mon 1/8/24 Thu 1/11/24 Mon 1/8/24 Thu 1/11/24 Mon 1/8/24 Thu 1/11/24 116 Rem/Abandon Existing PSE Gas Main 60 d 113 d 113 d Mon 10/2/23 NA Mon 10/2/23 Fri 5/17/24 Mon 10/2/23 Tue 10/29/24 114SS PSE - Gas 117 PSE - Pull Wire (Power and Fiber) and Complete Connections 32 d 0 d 0 d NA NA Mon 4/1/24 Tue 5/14/24 Mon 4/1/24 Thu 10/3/24 110,107 Utilities 118 CO-21 Golden Gate Complete Business Connections - Execute CO and Order Materials 10 d 110 d 0 d NA NA Mon 4/1/24 Fri 4/12/24 Fri 9/6/24 Thu 9/19/24 107 119 CO-21 Golden Gate Complete Business Connections - Install 10 d 110 d 110 d NA NA Mon 4/15/24 Fri 4/26/24 Fri 9/20/24 Thu 10/3/24 118 120 PSE - Install Transformers - V02A, V0X, V15A, V16A 30 d 30 d 30 d NA NA Mon 4/1/24 Fri 5/10/24 Mon 5/13/24 Tue 6/25/24 107 PSE - Electric 121 Complete PSE Swap Overs 30 d 0 d 0 d NA NA Mon 4/1/24 Fri 5/10/24 Mon 4/1/24 Fri 5/10/24 107 122 PSE Pole Removal and Installation - S. Tobin St. - Sta 501+51.37 (moved from JUT to conversion)2 d 98 d 98 d NA NA Mon 5/13/24 Tue 5/14/24 Wed 10/2/24 Thu 10/3/24 121 PSE - Electric 123 Lumen/Centurylink - Pull Wire and Complete Connections Project Wide 54 d 0 d 0 d NA NA Mon 4/1/24 Fri 6/14/24 Mon 4/1/24 Tue 6/25/24 117SS,110,113,107 Centurylink 7/17 1/23 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 2 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 40 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 124 Complete Lumen Connections Tobin South 30 d 0 d 0 d NA NA Mon 4/1/24 Fri 5/10/24 Mon 4/1/24 Fri 5/10/24 107 125 Complete Lumen Connections Tobin North 24 d 6 d 0 d NA NA Mon 5/13/24 Fri 6/14/24 Tue 5/21/24 Tue 6/25/24 124 126 Comcast - Pull Wire and Complete Connections 30 d 0 d 0 d NA NA Mon 4/1/24 Fri 5/10/24 Mon 4/1/24 Fri 5/10/24 123SS,110,107 Comcast 127 Remove Existing Vaults, Pedestals, and Risers 55 d 0 d 0 d NA NA Mon 5/13/24 Wed 7/31/24 Mon 5/13/24 Thu 8/8/24 120SS,123SS,126SS Utilities 128 CO-24 Remove Existing JUT Tobin South 32 d 0 d 0 d NA NA Mon 5/13/24 Thu 6/27/24 Mon 5/13/24 Thu 6/27/24 124,121,126 129 CO-24 Remove Existing JUT Tobin North 31 d 6 d 6 d NA NA Mon 6/17/24 Wed 7/31/24 Wed 6/26/24 Thu 8/8/24 125 130 5G Small Cell Network Conduit System - Sta 14+65 to 41+55 23 d 0 d 0 d Mon 10/2/23 Wed 11/1/23 Mon 10/2/23 Wed 11/1/23 Mon 10/2/23 Wed 11/1/23 131 Trench and Conduit 21 d 0 d 0 d Mon 10/2/23 Mon 10/30/23 Mon 10/2/23 Mon 10/30/23 Mon 10/2/23 Mon 10/30/23 67SS,107 Golden Gate 132 Boxes 2 d 0 d 0 d Tue 10/31/23 Wed 11/1/23 Tue 10/31/23 Wed 11/1/23 Tue 10/31/23 Wed 11/1/23 131 Golden Gate 133 Water Line/Night - Sta 14+02 to 42+14.5 491 d 183 d 183 d Thu 3/30/23 NA Thu 3/30/23 Mon 4/7/25 Thu 3/30/23 Mon 1/5/26 134 Stage 1 Bypass, Cut and Cap 116 d 0 d 0 d Mon 4/17/23 Mon 10/2/23 Mon 4/17/23 Mon 10/2/23 Mon 4/17/23 Mon 10/2/23 135 Cut and Cap Existing Waterline - Sta 15+55 4 d 0 d 0 d Mon 4/17/23 Thu 4/20/23 Mon 4/17/23 Thu 4/20/23 Mon 4/17/23 Thu 4/20/23 42 Pivetta - Water/City of Renton Water 136 Cut and Cap Existing Waterline - Taco Time to Buddy's Home Furnishings - Sta 18+20 to 21+00 0 d 0 d 0 d Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 135,42 Pivetta - Water/City of Renton Water 137 Cut and Cap Existing Waterline - SW Victoria - Sta 25+00 (Deleted - Work Not Required)1 d 0 d 0 d Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Pivetta - Water/City of Renton Water 138 Cut and Cap Waterline - S. Tobin St. - Sta 28+60 (Deleted - Work Not Required)1 d 0 d 0 d Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Pivetta - Water/City of Renton Water 139 Water Line - Stage 1 - Sta 14+02.2 to 42+06.9 Rainier Ave, Sta 30+74.5 to 602+87.44 Airport Way 125 d 0 d 0 d Tue 5/2/23 Mon 10/30/23 Tue 5/2/23 Mon 10/30/23 Tue 5/2/23 Mon 10/30/23 140 Install Water Line and Appurtenances 28 d 0 d 0 d Tue 5/2/23 Mon 10/30/23 Tue 5/2/23 Mon 10/30/23 Tue 5/2/23 Mon 10/30/23 62,136 Pivetta - Water 141 FRPCS Concrete DMB (Deleted - Work Occurring with Water Line Install)15 d 0 d 0 d Mon 10/2/23 Fri 10/20/23 Mon 10/2/23 Fri 10/20/23 Mon 10/2/23 Fri 10/20/23 Pivetta - Water 142 Pressure Testing, Polypig, Disinfect Water Line 88 d 0 d 0 d Wed 6/21/23 Tue 10/24/23 Wed 6/21/23 Tue 10/24/23 Wed 6/21/23 Tue 10/24/23 140 Pivetta - Water 143 Install Water Line Services and Meters 0 d 0 d 0 d Thu 6/1/23 Thu 6/1/23 Thu 6/1/23 Thu 6/1/23 Thu 6/1/23 Thu 6/1/23 142 Pivetta - Water 144 Install Hydrants 8 d 0 d 0 d Thu 6/1/23 Wed 10/11/23 Thu 6/1/23 Wed 10/11/23 Thu 6/1/23 Wed 10/11/23 143 Pivetta - Water 145 Abandon/Remove Existing Water Line 2 d 0 d 0 d Thu 10/12/23 Fri 10/13/23 Thu 10/12/23 Fri 10/13/23 Thu 10/12/23 Fri 10/13/23 144 Pivetta - Water 146 Water Line - Crossing - Taco Time to S. 2nd St. - Sta 18+49.0 & 18+49.0 to 19+31.9 219 d 0 d 0 d Thu 3/30/23 Thu 2/29/24 Thu 3/30/23 Thu 2/29/24 Thu 3/30/23 Thu 2/29/24 147 Install Water Line and Appurtenances 2 d 0 d 0 d Thu 5/11/23 Tue 5/23/23 Thu 5/11/23 Tue 5/23/23 Thu 5/11/23 Tue 5/23/23 140SS+5 d Pivetta - Water 148 Cathodic Protection Submittal (Submittal #81, RAM 055)0 d 0 d 0 d Thu 3/30/23 Thu 3/30/23 Thu 3/30/23 Thu 3/30/23 Thu 3/30/23 Thu 3/30/23 149 Test Station Changes (PCO-019 for RFI-70 and RFI-085 Changes)10 d 0 d 0 d Thu 7/13/23 Fri 10/13/23 Thu 7/13/23 Fri 10/13/23 Thu 7/13/23 Fri 10/13/23 150 Procure Cathodic Protection 13 d 0 d 0 d Mon 10/16/23 Wed 11/1/23 Mon 10/16/23 Wed 11/1/23 Mon 10/16/23 Wed 11/1/23 148,149 151 Install Cathodic Protection over SPU Lines 4 d 0 d 0 d Mon 2/26/24 Thu 2/29/24 Mon 2/26/24 Thu 2/29/24 Mon 2/26/24 Thu 2/29/24 147,150 Pivetta - Water 152 Stage 2, Bypass, Cut and Cap 125 d 0 d 0 d Mon 4/17/23 Fri 10/13/23 Mon 4/17/23 Fri 10/13/23 Mon 4/17/23 Fri 10/13/23 153 Install Water Bypass - Hertz/Lyft to Wendy's - Sta 15+55 to 16+40 (Performed with Stage 1)0 d 0 d 0 d Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 143,147,145 Pivetta - Water 154 Install Water Bypass - Taco Time - Sta 18+25 to 18+50 (Deleted - Work Not Required)1 d 0 d 0 d Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Pivetta - Water 155 Install Water Bypass - Buddy's Home Furnishing to Royal Orchid - Sta 21+00 to 24+80 5 d 0 d 0 d Thu 10/5/23 Wed 10/11/23 Thu 10/5/23 Wed 10/11/23 Thu 10/5/23 Wed 10/11/23 143 Pivetta - Water 156 Cut and Cap - Chevron to S. Tobin Crossing - Sta 28+75 (Not Required)1 d 0 d 0 d Thu 10/12/23 Thu 10/12/23 Thu 10/12/23 Thu 10/12/23 Thu 10/12/23 Thu 10/12/23 155 Pivetta - Water 157 Cut and Cap Existing Water Line - McDonalds to Arco - Sta 30+60 to 34+10 (Not Required)1 d 0 d 0 d Fri 10/13/23 Fri 10/13/23 Fri 10/13/23 Fri 10/13/23 Fri 10/13/23 Fri 10/13/23 156 Pivetta - Water 158 Water Line - Stage 2 - S. 3rd St. - Sta 203+40 to NW 3rd Pl - Sta 699+16.40 77 d 0 d 0 d Mon 10/16/23 Thu 2/22/24 Mon 10/16/23 Thu 2/22/24 Mon 10/16/23 Thu 2/22/24 159 Install Water Line and Appurtenances 28.87 d 0 d 0 d Mon 10/16/23 Wed 1/24/24 Mon 10/16/23 Wed 1/24/24 Mon 10/16/23 Wed 1/24/24 157,153 Pivetta - Water 160 FRPCS Concrete DMB 47 d 0 d 0 d Thu 11/2/23 Wed 1/24/24 Thu 11/2/23 Wed 1/24/24 Thu 11/2/23 Wed 1/24/24 159 Pivetta - Water 161 Install Polypig Station 46 d 0 d 0 d Thu 11/2/23 Wed 1/24/24 Thu 11/2/23 Wed 1/24/24 Thu 11/2/23 Wed 1/24/24 160 Pivetta - Water 162 Pressure Testing, Polypig, Disinfect Water Line 21 d 0 d 0 d Wed 1/17/24 Thu 2/22/24 Wed 1/17/24 Thu 2/22/24 Wed 1/17/24 Thu 2/22/24 161 Pivetta - Water 163 Install Water Line Services and Meters 0 d 0 d 0 d Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 162 Pivetta - Water 164 Install Hydrants 0 d 0 d 0 d Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 163 Pivetta - Water 165 Abandon/Remove Existing Water Line 30 d 0 d 0 d Mon 10/16/23 Thu 11/30/23 Mon 10/16/23 Thu 11/30/23 Mon 10/16/23 Thu 11/30/23 164 Pivetta - Water 166 Stage 3 Bypass, Cut and Cap 3 d 431 d 431 d NA NA Mon 4/1/24 Wed 4/3/24 Thu 1/1/26 Mon 1/5/26 167 Cut and Cap - Formula 1 Fast Lube to S. Tobin St. - Sta 25+65 to 28+65 (DELETED)3 d 431 d 431 d NA NA Mon 4/1/24 Wed 4/3/24 Thu 1/1/26 Mon 1/5/26 Pivetta - Water/City of Renton Water 168 Water Line - Stage 3 - S. Tobin St. - Sta 28+58.6 to 28+61.6 (Performing with Stage 2)63 d 0 d 0 d Mon 11/6/23 Thu 2/22/24 Mon 11/6/23 Thu 2/22/24 Mon 11/6/23 Thu 2/22/24 169 Install Water Line and Appurtenances 4 d 0 d 0 d Mon 11/6/23 Thu 11/9/23 Mon 11/6/23 Thu 11/9/23 Mon 11/6/23 Thu 11/9/23 44 Pivetta - Water 170 Pressure Testing, Polypig, Disinfect Water Line 22 d 0 d 0 d Wed 1/17/24 Thu 2/22/24 Wed 1/17/24 Thu 2/22/24 Wed 1/17/24 Thu 2/22/24 169 Pivetta - Water 171 Install Water Line Services and Meters 4 d 0 d 0 d Mon 1/8/24 Wed 1/24/24 Mon 1/8/24 Wed 1/24/24 Mon 1/8/24 Wed 1/24/24 170 Pivetta - Water 172 Install Hydrants 0 d 0 d 0 d Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 171 Pivetta - Water 173 Abandon/Remove Existing Water Line and Bypass 30 d 0 d 0 d Tue 1/9/24 Thu 2/22/24 Tue 1/9/24 Thu 2/22/24 Tue 1/9/24 Thu 2/22/24 172 Pivetta - Water 174 Install Hydrants in Conflict 182 d 69 d 69 d NA NA Wed 7/10/24 Mon 4/7/25 Mon 1/27/25 Wed 7/16/25 175 Hydrant at Walgreens (STA 16+54) - Sewer Conflict (RFI078)1 d 132 d 49 d NA NA Wed 7/10/24 Wed 7/10/24 Mon 1/27/25 Mon 1/27/25 185 176 Hydrant at NE corner of Rainier & S 2nd St - Reinstall (RFI139) - after JUT removal 1 d 234 d 233 d NA NA Thu 8/1/24 Thu 8/1/24 Wed 7/16/25 Wed 7/16/25 127 177 Blow Off at Gene Meyer (STA 20+25) - JUT/Storm Conflict/Sequence 1 d 100 d 17 d NA NA Fri 8/23/24 Fri 8/23/24 Mon 1/27/25 Mon 1/27/25 127,208 178 Hydrant at Autozone (STA 21+73) - JUT Conflict 1 d 116 d 33 d NA NA Thu 8/1/24 Thu 8/1/24 Mon 1/27/25 Mon 1/27/25 127 179 Hydrant at Watson (STA 24+24) - JUT Conflict 1 d 116 d 33 d NA NA Thu 8/1/24 Thu 8/1/24 Mon 1/27/25 Mon 1/27/25 127 180 Hydrant at Tommy's Café (STA 26+27.5) - adjust length after stg 1 chan 1 d 69 d 68 d NA NA Mon 4/7/25 Mon 4/7/25 Wed 7/16/25 Wed 7/16/25 374 181 Sewer - Sta 15+49.20 to 42+77.80 163 d 83 d 83 d Tue 1/30/24 NA Tue 1/30/24 Wed 9/18/24 Tue 1/30/24 Mon 1/27/25 182 L035 - PCO033 Sewer Bypass (sent 1/30/24) - Response/Resolution 0 d 62 d 62 d Tue 1/30/24 NA Tue 1/30/24 Mon 4/1/24 Tue 1/30/24 Fri 6/28/24 183 Sewer - Night (Walgreens to Sansonina) - Sta 15+49.20 to 18+26.81 7 d 0 d 0 d NA NA Fri 6/28/24 Tue 7/9/24 Fri 6/28/24 Tue 7/9/24 184 Remove/Replace Manholes and Install Sewer 5 d 0 d 0 d NA NA Fri 6/28/24 Fri 7/5/24 Fri 6/28/24 Fri 7/5/24 145,39,107,182,128 Pivetta - Sewer 185 Install New Side Sewer 2 d 0 d 0 d NA NA Mon 7/8/24 Tue 7/9/24 Mon 7/8/24 Tue 7/9/24 184 Pivetta - Sewer 4/17 6/1 3/30 4/17 1/8 1/8 1/8 4/1 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 3 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 41 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 186 Sewer (Big Island Poke to Hayes Pl SW) - Sta 19+63.58 to 25+43.57 5 d 0 d 0 d NA NA Wed 7/10/24 Tue 7/16/24 Wed 7/10/24 Tue 7/16/24 187 Remove/Replace Manholes 5 d 0 d 0 d NA NA Wed 7/10/24 Tue 7/16/24 Wed 7/10/24 Tue 7/16/24 185 Pivetta - Sewer 188 S. 2nd St. - Sta 19+64.16 3 d 0 d 0 d NA NA Wed 7/17/24 Fri 7/19/24 Wed 7/17/24 Fri 7/19/24 189 Install Sewer and Manholes 3 d 0 d 0 d NA NA Wed 7/17/24 Fri 7/19/24 Wed 7/17/24 Fri 7/19/24 187 Pivetta - Sewer 190 Sewer (Chevron to Advance Auto Tune) - Sta 28+55.98 to 42+77.80 10 d 0 d 0 d NA NA Mon 7/22/24 Fri 8/2/24 Mon 7/22/24 Fri 8/2/24 191 Remove/Replace/Install Manholes 7 d 0 d 0 d NA NA Mon 7/22/24 Tue 7/30/24 Mon 7/22/24 Tue 7/30/24 189 Pivetta - Sewer 192 Install Sewer 3 d 0 d 0 d NA NA Wed 7/31/24 Fri 8/2/24 Wed 7/31/24 Fri 8/2/24 191 Pivetta - Sewer 193 Sewer - Night/Side Street - SW Victoria - Sta 24+91.19 1 d 0 d 0 d NA NA Mon 8/5/24 Mon 8/5/24 Mon 8/5/24 Mon 8/5/24 194 Remove/Replace Manholes 1 d 0 d 0 d NA NA Mon 8/5/24 Mon 8/5/24 Mon 8/5/24 Mon 8/5/24 192 Pivetta - Sewer 195 Sewer - Night/Side Street - Hayes Pl SW - Sta 25+43.57 1 d 0 d 0 d NA NA Tue 8/6/24 Tue 8/6/24 Tue 8/6/24 Tue 8/6/24 196 Remove/Replace/Install Manholes 1 d 0 d 0 d NA NA Tue 8/6/24 Tue 8/6/24 Tue 8/6/24 Tue 8/6/24 194 Pivetta - Sewer 197 Sewer - Night/Renton Ave Ext - Sta 32+81.14 to 31+60.06 2 d 0 d 0 d NA NA Wed 8/7/24 Thu 8/8/24 Wed 8/7/24 Thu 8/8/24 198 Remove/Replace/Install Manholes 1 d 0 d 0 d NA NA Wed 8/7/24 Wed 8/7/24 Wed 8/7/24 Wed 8/7/24 196 Pivetta - Sewer 199 Install Sewer 1 d 0 d 0 d NA NA Thu 8/8/24 Thu 8/8/24 Thu 8/8/24 Thu 8/8/24 198 Pivetta - Sewer 200 Install CIPP Lining 28 d 83 d 83 d NA NA Fri 8/9/24 Wed 9/18/24 Tue 12/10/24 Mon 1/27/25 199 201 Install CIPP Lining (Big Island Poke to Hayes Pl SW) - Sta 19+63.58 to 25+43.57 4 d 83 d 0 d NA NA Fri 8/9/24 Wed 8/14/24 Tue 12/10/24 Fri 12/13/24 37,198 Insituform 202 Install CIPP Lining (Chevron to Advance Auto Tune) - Sta 28+55.98 to 42+77.80 9 d 83 d 0 d NA NA Thu 8/15/24 Tue 8/27/24 Mon 12/16/24 Fri 1/3/25 201,191 Insituform 203 Install CIPP Lining (SW Victoria) - Sta 24+91.19 5 d 83 d 0 d NA NA Wed 8/28/24 Wed 9/4/24 Mon 1/6/25 Fri 1/10/25 202,194 Insituform 204 Install CIPP Lining (Hayes Pl SW) - Sta 25+43.57 5 d 83 d 0 d NA NA Thu 9/5/24 Wed 9/11/24 Mon 1/13/25 Fri 1/17/25 203,196 Insituform 205 Install CIPP Lining (Renton Ave Ext) - Sta 32+81.14 to 31+60.06 5 d 83 d 0 d NA NA Thu 9/12/24 Wed 9/18/24 Tue 1/21/25 Mon 1/27/25 198,204 Insituform 206 Storm Drainage - Sta 15+11.89 to 41+02.35 57 d 0 d 0 d NA NA Fri 8/9/24 Tue 10/29/24 Fri 8/9/24 Mon 1/5/26 207 Storm Drainage (Walgreens to Sansonina) - Sta 15+11.89 to 17+63.75 12 d 0 d 0 d NA NA Fri 8/9/24 Mon 8/26/24 Fri 8/9/24 Mon 8/26/24 208 Install Drainage and Catch Basins 10 d 0 d 0 d NA NA Fri 8/9/24 Thu 8/22/24 Fri 8/9/24 Thu 8/22/24 199,127 Pivetta - Storm 209 Storm Drainage - Night/Crossing - Sta 16+05.52 2 d 0 d 0 d NA NA Fri 8/23/24 Mon 8/26/24 Fri 8/23/24 Mon 8/26/24 210 Install Drainage and Catch Basins 2 d 0 d 0 d NA NA Fri 8/23/24 Mon 8/26/24 Fri 8/23/24 Mon 8/26/24 208 Pivetta - Storm 211 Storm Drainage (Big Island Poke to Watson Security) - Sta 18+54.92 to 23+32.67 24 d 0 d 0 d NA NA Tue 8/27/24 Mon 9/30/24 Tue 8/27/24 Mon 1/5/26 212 Install Drainage and Catch Basins 13 d 0 d 0 d NA NA Tue 8/27/24 Fri 9/13/24 Tue 8/27/24 Fri 9/13/24 210 Pivetta - Storm 213 Storm Drainage - S. 2nd St. - Night/Crossings, Stage 2 and 3 Work - Sta 19+07.53 to 22+07.86 11 d 0 d 0 d NA NA Mon 9/16/24 Mon 9/30/24 Mon 9/16/24 Mon 1/5/26 214 Install Drainage and Catch Basins 10 d 0 d 0 d NA NA Mon 9/16/24 Fri 9/27/24 Mon 9/16/24 Fri 9/27/24 210,212 Pivetta - Storm 215 Install Filterra Unit 1 d 307 d 307 d NA NA Mon 9/30/24 Mon 9/30/24 Mon 1/5/26 Mon 1/5/26 214 Pivetta - Storm 216 Storm Drainage - SW Victoria St. to Brown Bear Car Wash- Night/Crossing - Sta 24+70.79 to 26+65.08 8 d 0 d 0 d NA NA Mon 9/30/24 Wed 10/9/24 Mon 9/30/24 Wed 10/9/24 217 Install Drainage and Catch Basins 8 d 0 d 0 d NA NA Mon 9/30/24 Wed 10/9/24 Mon 9/30/24 Wed 10/9/24 214,127 Pivetta - Storm 218 Storm Drainage Brown Bear to Renton Laundry - Sta 26+65.08 to 35+53.35 29 d 14 d 14 d NA NA Mon 9/16/24 Thu 10/24/24 Fri 10/4/24 Wed 11/5/25 219 Install Drainage and Catch Basins 11 d 14 d 0 d NA NA Mon 9/16/24 Mon 9/30/24 Fri 10/4/24 Fri 10/18/24 212,114,117,120,123,126 Pivetta - Storm 220 Install Filterra Units 3 d 269 d 0 d NA NA Tue 10/1/24 Thu 10/3/24 Mon 11/3/25 Wed 11/5/25 219 Pivetta - Storm 221 Storm Drainage - Renton Ave Ext - Night/Crossing - Sta 31+39.02 to 33+02.08 11 d 0 d 0 d NA NA Thu 10/10/24 Thu 10/24/24 Thu 10/10/24 Thu 10/24/24 222 Install Drainage and Catch Basins 11 d 0 d 0 d NA NA Thu 10/10/24 Thu 10/24/24 Thu 10/10/24 Thu 10/24/24 217,114,117,120,123,126 Pivetta - Storm 223 Storm Drainage Mathewson's Automotive to Judo Boxing - Sta 37+84.90 to 41+02.35 4 d 14 d 14 d NA NA Tue 10/1/24 Fri 10/4/24 Mon 10/21/24 Thu 10/24/24 224 Install Drainage and Catch Basins 4 d 14 d 14 d NA NA Tue 10/1/24 Fri 10/4/24 Mon 10/21/24 Thu 10/24/24 219 Pivetta - Storm 225 Storm Drainage - NW 3rd Pl - Night/Crossing - Sta 40+68.75 to 41+02.35 3 d 0 d 0 d NA NA Fri 10/25/24 Tue 10/29/24 Fri 10/25/24 Tue 10/29/24 226 Install Drainage and Catch Basins 3 d 0 d 0 d NA NA Fri 10/25/24 Tue 10/29/24 Fri 10/25/24 Tue 10/29/24 224,222,132 Pivetta - Storm 227 Decorative Illumination System - Sta 14+89 to 41+55 199 d 0 d 0 d NA NA Mon 4/1/24 Wed 1/22/25 Wed 7/31/24 Wed 1/22/25 228 Below Grade 42 d 84 d 84 d NA NA Mon 4/1/24 Wed 5/29/24 Wed 7/31/24 Tue 10/29/24 229 Trench and Conduit 23 d 84 d 0 d NA NA Mon 4/1/24 Wed 5/1/24 Wed 7/31/24 Fri 8/30/24 Golden Gate 230 Foundations 24 d 106 d 0 d NA NA Mon 4/1/24 Thu 5/2/24 Fri 8/30/24 Thu 10/3/24 61,229SS Golden Gate 231 Junction Boxes 18 d 106 d 0 d NA NA Fri 5/3/24 Wed 5/29/24 Fri 10/4/24 Tue 10/29/24 230,110 Golden Gate 232 Service Installation 10 d 130 d 130 d NA NA Fri 5/17/24 Fri 5/31/24 Fri 11/22/24 Mon 12/9/24 231SS+10 d Golden Gate/PSE - Electric 233 Above Ground 194 d 0 d 0 d NA NA Mon 4/8/24 Wed 1/22/25 Tue 10/8/24 Wed 1/22/25 234 Install Lighting Wiring 20 d 0 d 0 d NA NA Tue 12/10/24 Tue 1/14/25 Tue 12/10/24 Tue 1/14/25 231,232,345 Golden Gate 235 Set Poles 62 d 127 d 127 d NA NA Mon 4/8/24 Fri 7/5/24 Tue 10/8/24 Tue 1/14/25 230SS+5 d Golden Gate 236 Test and Turn On 2 d 0 d 0 d NA NA Wed 1/15/25 Thu 1/16/25 Wed 1/15/25 Thu 1/16/25 235,234 Golden Gate 237 Remove and Salvage Old Poles&Wiring 3 d 0 d 0 d NA NA Fri 1/17/25 Wed 1/22/25 Fri 1/17/25 Wed 1/22/25 236 Golden Gate 238 Signalization - Sta 14+10 to 40+40 224 d 84 d 84 d NA NA Thu 5/2/24 Tue 4/1/25 Tue 9/3/24 Mon 1/5/26 239 Traffic Signal Rainier & SW Sunset - Sta 14+10 189 d 0 d 0 d NA NA Thu 5/2/24 Mon 2/10/25 Tue 9/3/24 Mon 2/10/25 240 Below Grade 8 d 84 d 84 d NA NA Thu 5/2/24 Mon 5/13/24 Tue 9/3/24 Mon 1/27/25 241 Conduit Underground 5 d 84 d 0 d NA NA Thu 5/2/24 Wed 5/8/24 Tue 9/3/24 Mon 9/9/24 229 Golden Gate 242 Foundations - before C&G 3 d 175 d 0 d NA NA Fri 5/3/24 Tue 5/7/24 Thu 1/23/25 Mon 1/27/25 230 Golden Gate 243 Road Crossings 3 d 84 d 0 d NA NA Thu 5/9/24 Mon 5/13/24 Tue 9/10/24 Thu 9/12/24 241 Golden Gate 244 Service Installation 1 d 0 d 0 d NA NA Mon 1/27/25 Mon 1/27/25 Mon 1/27/25 Mon 1/27/25 246 Golden Gate/PSE - Electric 245 Above Ground 13 d 0 d 0 d NA NA Thu 1/23/25 Mon 2/10/25 Thu 1/23/25 Mon 2/10/25 246 Install Boxes - after C&G/Sidewalks 2 d 0 d 0 d NA NA Thu 1/23/25 Fri 1/24/25 Thu 1/23/25 Fri 1/24/25 243,237 Golden Gate 247 Pull Cable 2 d 0 d 0 d NA NA Tue 1/28/25 Wed 1/29/25 Tue 1/28/25 Wed 1/29/25 244 Golden Gate H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 4 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 42 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 248 Build Traffic Signal System 8 d 0 d 0 d NA NA Thu 1/30/25 Mon 2/10/25 Thu 1/30/25 Mon 2/10/25 247,242 Golden Gate 249 Traffic Signal Rainier & 2nd Street 195 d 0 d 0 d NA NA Wed 5/8/24 Tue 2/25/25 Fri 9/13/24 Tue 2/25/25 250 Below Grade 14 d 88 d 88 d NA NA Wed 5/8/24 Tue 5/28/24 Fri 9/13/24 Wed 2/12/25 251 Foundations 3 d 184 d 0 d NA NA Wed 5/8/24 Fri 5/10/24 Mon 2/10/25 Wed 2/12/25 242 Golden Gate 252 Conduit Underground 5 d 84 d 0 d NA NA Tue 5/14/24 Mon 5/20/24 Fri 9/13/24 Thu 9/19/24 243 Golden Gate 253 Road Crossings 3 d 84 d 0 d NA NA Tue 5/21/24 Thu 5/23/24 Fri 9/20/24 Tue 9/24/24 252 Golden Gate 254 Install Boxes 2 d 84 d 0 d NA NA Fri 5/24/24 Tue 5/28/24 Wed 9/25/24 Thu 9/26/24 253 Golden Gate 255 Service Installation 1 d 170 d 170 d NA NA Wed 5/29/24 Wed 5/29/24 Mon 2/10/25 Mon 2/10/25 254 Golden Gate/PSE - Electric 256 Above Ground 10 d 0 d 0 d NA NA Tue 2/11/25 Tue 2/25/25 Tue 2/11/25 Tue 2/25/25 257 Pull Cable 2 d 0 d 0 d NA NA Tue 2/11/25 Wed 2/12/25 Tue 2/11/25 Wed 2/12/25 248,255 Golden Gate 258 Build Traffic Signal System 8 d 0 d 0 d NA NA Thu 2/13/25 Tue 2/25/25 Thu 2/13/25 Tue 2/25/25 257 Golden Gate 259 Pedestrian Signal Rainier& SW Victoria 211 d 95 d 95 d NA NA Mon 5/13/24 Mon 3/24/25 Fri 9/27/24 Fri 12/19/25 260 Below Grade 15 d 95 d 95 d NA NA Mon 5/13/24 Mon 6/3/24 Fri 9/27/24 Thu 2/13/25 261 Foundations 1 d 184 d 0 d NA NA Mon 5/13/24 Mon 5/13/24 Thu 2/13/25 Thu 2/13/25 251 Golden Gate 262 Conduit Underground 2 d 84 d 0 d NA NA Wed 5/29/24 Thu 5/30/24 Fri 9/27/24 Mon 9/30/24 254 Golden Gate 263 Road Crossings 1 d 84 d 0 d NA NA Fri 5/31/24 Fri 5/31/24 Tue 10/1/24 Tue 10/1/24 262 Golden Gate 264 Install Boxes 1 d 84 d 0 d NA NA Mon 6/3/24 Mon 6/3/24 Wed 10/2/24 Wed 10/2/24 263 Golden Gate 265 Service Installation 1 d 376 d 189 d NA NA Tue 6/4/24 Tue 6/4/24 Thu 12/11/25 Thu 12/11/25 264 Golden Gate/PSE - Electric 266 Above Ground 6 d 187 d 187 d NA NA Mon 3/17/25 Mon 3/24/25 Fri 12/12/25 Fri 12/19/25 267 Pull cable 2 d 187 d 0 d NA NA Mon 3/17/25 Tue 3/18/25 Fri 12/12/25 Mon 12/15/25 258,265,278 Golden Gate 268 Build Traffic Signal System 4 d 187 d 0 d NA NA Wed 3/19/25 Mon 3/24/25 Tue 12/16/25 Fri 12/19/25 267,251 Golden Gate 269 Traffic Signal Rainier& Renton Ave Ext 204 d 0 d 0 d NA NA Tue 5/14/24 Fri 3/14/25 Thu 10/3/24 Fri 3/14/25 270 Below Grade 27 d 98 d 98 d NA NA Tue 5/14/24 Fri 6/21/24 Thu 10/3/24 Fri 2/28/25 271 Foundations 10 d 184 d 0 d NA NA Tue 5/14/24 Tue 5/28/24 Fri 2/14/25 Fri 2/28/25 261 Golden Gate 272 Conduit Underground 8 d 84 d 0 d NA NA Tue 6/4/24 Thu 6/13/24 Thu 10/3/24 Mon 10/14/24 264 Golden Gate 273 Road Crossings 3 d 84 d 0 d NA NA Fri 6/14/24 Tue 6/18/24 Tue 10/15/24 Thu 10/17/24 272 Golden Gate 274 Install Boxes 2 d 84 d 0 d NA NA Thu 6/20/24 Fri 6/21/24 Fri 10/18/24 Mon 10/21/24 273 Golden Gate 275 Service Installation 1 d 163 d 163 d NA NA Mon 6/24/24 Mon 6/24/24 Tue 2/25/25 Tue 2/25/25 274 Golden Gate/PSE - Electric 276 Above Ground 13 d 0 d 0 d NA NA Wed 2/26/25 Fri 3/14/25 Wed 2/26/25 Fri 3/14/25 277 Pull Cable 3 d 0 d 0 d NA NA Wed 2/26/25 Fri 2/28/25 Wed 2/26/25 Fri 2/28/25 275,258 Golden Gate 278 Build Traffic Signal System 10 d 0 d 0 d NA NA Mon 3/3/25 Fri 3/14/25 Mon 3/3/25 Fri 3/14/25 277,261,271 Golden Gate 279 Pedestrian Signal Rainier& 3rd Pl 206 d 101 d 101 d NA NA Wed 5/29/24 Tue 4/1/25 Tue 10/22/24 Mon 1/5/26 280 Below Grade 23 d 101 d 101 d NA NA Wed 5/29/24 Mon 7/1/24 Tue 10/22/24 Mon 12/22/25 281 Foundations 1 d 387 d 200 d NA NA Wed 5/29/24 Wed 5/29/24 Mon 12/22/25 Mon 12/22/25 271 Golden Gate 282 Conduit Underground 3 d 84 d 0 d NA NA Mon 6/24/24 Wed 6/26/24 Tue 10/22/24 Thu 10/24/24 274 Golden Gate 283 Road Crossings 2 d 84 d 0 d NA NA Thu 6/27/24 Fri 6/28/24 Fri 10/25/24 Mon 10/28/24 282 Golden Gate 284 Install Boxes 1 d 84 d 0 d NA NA Mon 7/1/24 Mon 7/1/24 Tue 10/29/24 Tue 10/29/24 283 Golden Gate 285 Service Installation 1 d 363 d 176 d NA NA Tue 7/2/24 Tue 7/2/24 Fri 12/19/25 Fri 12/19/25 284 Golden Gate/PSE - Electric 286 Above Ground 6 d 187 d 187 d NA NA Tue 3/25/25 Tue 4/1/25 Mon 12/22/25 Mon 1/5/26 287 Pull Cable 1 d 187 d 0 d NA NA Tue 3/25/25 Tue 3/25/25 Mon 12/22/25 Mon 12/22/25 285,268 Golden Gate 288 Build Traffic Signal System 5 d 187 d 187 d NA NA Wed 3/26/25 Tue 4/1/25 Tue 12/23/25 Mon 1/5/26 281,287 Golden Gate 289 Walls - Sta 15+50.95 to 799+17.37 263 d 284 d 284 d Mon 10/2/23 NA Mon 10/2/23 Thu 10/31/24 Mon 10/2/23 Mon 1/5/26 290 Wall 1 - Modular Block FW - Sta 15+50.95 to 16+21.24 (Wall Sta 0+00 to 1+18)25 d 123 d 123 d NA NA Mon 4/8/24 Fri 5/10/24 Wed 10/2/24 Thu 1/1/26 291 Constuct Modular Block Fill Wall - Wall 1 15 d 123 d 0 d NA NA Mon 4/8/24 Fri 4/26/24 Wed 10/2/24 Tue 10/22/24 230SS+5 d Key West 292 FRPCS Thickened Edge Sidewalk 5 d 402 d 0 d NA NA Mon 4/29/24 Fri 5/3/24 Fri 12/12/25 Thu 12/18/25 291 WCCI 293 Install Pedestrian Railing 5 d 402 d 16 d NA NA Mon 5/6/24 Fri 5/10/24 Fri 12/19/25 Thu 1/1/26 292 WCCI 294 Wall 2 - Modular Block FW - Sta 17+08.50 to 17+23.95 (Wall Sta 0+00 to 0+59)10 d 123 d 123 d NA NA Mon 4/29/24 Fri 5/10/24 Wed 10/23/24 Mon 1/5/26 295 Construct Modular Block Fill Wall - Wall 2 5 d 123 d 0 d NA NA Mon 4/29/24 Fri 5/3/24 Wed 10/23/24 Tue 10/29/24 291 Key West 296 FRPCS Thickened Edge Sidewalk 5 d 404 d 404 d NA NA Mon 5/6/24 Fri 5/10/24 Tue 12/23/25 Mon 1/5/26 295,292SS WCCI 297 Wall 5 - CCFW & CIP Fill Wall - Sta 399+50.72 to 399+39.01 (Wall Sta 0+00 to 0+35)161 d 386 d 386 d Mon 10/2/23 NA Mon 10/2/23 Thu 6/6/24 Mon 10/2/23 Mon 1/5/26 298 Demolish Existing Wall 5 - Sta 0+10 to 0+21.70 2 d 0 d 0 d Mon 10/2/23 Tue 10/3/23 Mon 10/2/23 Tue 10/3/23 Mon 10/2/23 Tue 10/3/23 83 Pivetta 299 Construct CIP Fill Wall - Wall 5 15 d 107 d 0 d NA NA Tue 4/23/24 Mon 5/13/24 Wed 9/25/24 Tue 10/15/24 230SS+16 d,298 WCCI 300 Construct Cement Concrete Fill Wall - Wall 5 10 d 107 d 0 d NA NA Tue 5/14/24 Tue 5/28/24 Wed 10/16/24 Tue 10/29/24 230,299 WCCI 301 Construct WSDOT Std 4"Thick Gutter - Wall 5 5 d 386 d 0 d NA NA Wed 5/29/24 Tue 6/4/24 Fri 12/19/25 Thu 1/1/26 300 WCCI 302 Install Pedestrian Railing - Sta 0+10 to 0+35 - Wall 5 2 d 386 d 386 d NA NA Wed 6/5/24 Thu 6/6/24 Fri 1/2/26 Mon 1/5/26 293,301 WCCI 303 Wall 6 - Rock Wall - Sta 799+42.45 to 799+17.37 (Wall Sta 0+00 to 0+19.29)5 d 143 d 143 d NA NA Mon 4/1/24 Fri 4/5/24 Wed 10/23/24 Tue 10/29/24 304 Excavate/Construct/Backfill Rock Wall - Wall 6 5 d 143 d 143 d NA NA Mon 4/1/24 Fri 4/5/24 Wed 10/23/24 Tue 10/29/24 94 Pivetta - Earthwork 305 Gateway Wall A - Sta 33+59.15 to 599+37.00 20 d 269 d 269 d NA NA Fri 10/4/24 Thu 10/31/24 Thu 11/6/25 Mon 12/8/25 306 Construct Gateway Wall A - Renton Ave. Ext.15 d 269 d 0 d NA NA Fri 10/4/24 Thu 10/24/24 Thu 11/6/25 Mon 12/1/25 220,299 WCCI 307 Install Decorative Cutouts and Skate Deterrent Gateway Wall A - Renton Ave. Ext. 5 d 269 d 266 d NA NA Fri 10/25/24 Thu 10/31/24 Tue 12/2/25 Mon 12/8/25 306 WCCI 308 Curb and Gutter - Sta 14+30.99 to 42+80.28 38 d 83 d 83 d NA NA Thu 9/19/24 Tue 11/12/24 Tue 1/28/25 Mon 1/5/26 309 Curb and Gutter - Walgreens to Big Island Poke - Sta 14+30.99 to 19+12.69 2 d 83 d 83 d NA NA Thu 9/19/24 Fri 9/20/24 Tue 1/28/25 Mon 1/5/26 205,284 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 5 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 43 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 310 Grade/Prep Base/Place CSBC 1 d 83 d 0 d NA NA Thu 9/19/24 Thu 9/19/24 Tue 1/28/25 Tue 1/28/25 208,242,165,52,107,175,177,178,179 Pivetta - Earthwork 311 Form and Pour Curb and Gutter 1 d 313 d 313 d NA NA Fri 9/20/24 Fri 9/20/24 Mon 1/5/26 Mon 1/5/26 310 WCCI 312 Curb and Gutter - Big Island Poke to SW Victoria St - Sta 19+12.69 to 24+80 4 d 83 d 83 d NA NA Fri 9/20/24 Wed 9/25/24 Wed 1/29/25 Mon 1/5/26 313 Grade/Prep Base/Place CSBC 2 d 83 d 0 d NA NA Fri 9/20/24 Mon 9/23/24 Wed 1/29/25 Thu 1/30/25 310 Pivetta - Earthwork 314 Form and Pour Curb and Gutter 2 d 310 d 310 d NA NA Tue 9/24/24 Wed 9/25/24 Fri 1/2/26 Mon 1/5/26 313 WCCI 315 Curb and Gutter - SW Victoria St. to Renton Ave Ext. - Sta 25+00 to 31+64.76 17 d 83 d 83 d NA NA Tue 9/24/24 Wed 10/16/24 Fri 1/31/25 Mon 1/5/26 316 Grade/Prep Base/Place CSBC 3 d 83 d 0 d NA NA Tue 9/24/24 Thu 9/26/24 Fri 1/31/25 Tue 2/4/25 212,313 Pivetta - Earthwork 317 Form and Pour Curb and Gutter 3 d 83 d 0 d NA NA Fri 9/27/24 Tue 10/1/24 Wed 2/5/25 Fri 2/7/25 316 WCCI 318 Bus Shelter - Sta 27+45.48 11 d 295 d 295 d NA NA Wed 10/2/24 Wed 10/16/24 Mon 12/15/25 Mon 1/5/26 319 FRPCS Bus Shelter Footings 10 d 295 d 0 d NA NA Wed 10/2/24 Tue 10/15/24 Mon 12/15/25 Fri 1/2/26 317 WCCI 320 Install Bus Shelter 1 d 295 d 295 d NA NA Wed 10/16/24 Wed 10/16/24 Mon 1/5/26 Mon 1/5/26 319 Pivetta 321 Curb and Gutter - Renton Ave. Ext to End - Sta 32+56.87 to 42+80.28 5 d 61 d 61 d NA NA Wed 10/30/24 Tue 11/5/24 Thu 2/6/25 Mon 1/5/26 322 Grade/Prep Base/Place CSBC 2 d 61 d 0 d NA NA Wed 10/30/24 Thu 10/31/24 Thu 2/6/25 Fri 2/7/25 226,316 Pivetta - Earthwork 323 Form and Pour Curb and Gutter 2 d 61 d 0 d NA NA Fri 11/1/24 Mon 11/4/24 Mon 2/10/25 Tue 2/11/25 322,317 WCCI 324 Install Curb Mounted Delineator Posts - Renton Ave. Ext.1 d 281 d 281 d NA NA Tue 11/5/24 Tue 11/5/24 Mon 1/5/26 Mon 1/5/26 323 SPM 325 Islands - Sta 32+90 to 33+30 5 d 61 d 61 d NA NA Tue 11/5/24 Tue 11/12/24 Wed 2/12/25 Wed 2/19/25 326 Grade/Place CSBC/Place Island 2 - Renton Ave Ext. 5 d 61 d 0 d NA NA Tue 11/5/24 Tue 11/12/24 Wed 2/12/25 Wed 2/19/25 323,199 Pivetta - Earthwork 327 Sidewalk - 14+30.99 to 42+80.28 36 d 0 d 0 d NA NA Wed 10/30/24 Mon 12/23/24 Wed 10/30/24 Tue 10/21/25 328 Sidewalk Walgreens to Big Island Poke - Sta 14+30.99 to 19+12.69 8 d 0 d 0 d NA NA Wed 10/30/24 Fri 11/8/24 Wed 10/30/24 Tue 10/21/25 329 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 3 d 0 d 0 d NA NA Wed 10/30/24 Fri 11/1/24 Wed 10/30/24 Fri 11/1/24 116,231,127,173,226,274,284,291,295,300,304Pivetta - Earthwork 330 FRPCS - Sidewalk and Driveway Approaches 3 d 2 d 0 d NA NA Mon 11/4/24 Wed 11/6/24 Wed 11/6/24 Fri 11/8/24 329 WCCI 331 Grade/Form/Pour - Curb Ramps/Install DWS - 2nd St. - Sta 19+64.04 2 d 232 d 23 d NA NA Thu 11/7/24 Fri 11/8/24 Mon 10/20/25 Tue 10/21/25 330 WCCI 332 Sidewalk Big Island Poke to SW Victoria St. - Sta 19+12.69 to 24+80 15 d 0 d 0 d NA NA Mon 11/4/24 Mon 11/25/24 Mon 11/4/24 Tue 10/21/25 333 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 5 d 0 d 0 d NA NA Mon 11/4/24 Fri 11/8/24 Mon 11/4/24 Fri 11/8/24 329 Pivetta - Earthwork 334 FRPCS - Sidewalk and Driveway Approaches 5 d 0 d 0 d NA NA Tue 11/12/24 Mon 11/18/24 Tue 11/12/24 Mon 11/18/24 333,330 WCCI 335 Grade/Form/Pour - Curb Ramps/Install DWS - 2nd St. - Sta 20+08 5 d 222 d 13 d NA NA Tue 11/19/24 Mon 11/25/24 Wed 10/15/25 Tue 10/21/25 334 WCCI 336 Grade/Form/Pour - Curb Ramps/Install DWS - Rainier/SW Victoria St. - Sta 24+44 2 d 225 d 16 d NA NA Tue 11/19/24 Wed 11/20/24 Mon 10/20/25 Tue 10/21/25 334 WCCI 337 Sidewalk - SW Victoria St. to Renton Ave Ext. - Sta 25+00 to 31+64.76 13 d 2 d 2 d NA NA Tue 11/12/24 Mon 12/2/24 Thu 11/14/24 Tue 10/21/25 338 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 3 d 2 d 0 d NA NA Tue 11/12/24 Thu 11/14/24 Thu 11/14/24 Mon 11/18/24 333 Pivetta - Earthwork 339 FRPCS - Sidewalk and Driveway Approaches 3 d 0 d 0 d NA NA Tue 11/19/24 Thu 11/21/24 Tue 11/19/24 Thu 11/21/24 338,334 WCCI 340 Grade/Form/Pour - Curb Ramps/Install DWS - Rainier/SW Victoria St. - Sta 25+39.73 2 d 222 d 13 d NA NA Fri 11/22/24 Mon 11/25/24 Mon 10/20/25 Tue 10/21/25 339 WCCI 341 Grade/Form/Pour - Curb Ramps/Install DWS - Midblock Crosswalk - Sta 25+47.49 5 d 0 d 0 d NA NA Fri 11/22/24 Mon 12/2/24 Fri 11/22/24 Mon 12/2/24 339 WCCI 342 Grade/Form/Pour - Curb Ramps/Install DWS - Renton Ave. Ext. - Sta 31+40.67 2 d 222 d 13 d NA NA Fri 11/22/24 Mon 11/25/24 Mon 10/20/25 Tue 10/21/25 339 WCCI 343 Sidewalk - Renton Ave. Ext to End - Sta 32+30 to 42+80.28 17 d 5 d 5 d NA NA Fri 11/15/24 Wed 12/11/24 Fri 11/22/24 Tue 10/21/25 344 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 5 d 5 d 0 d NA NA Fri 11/15/24 Thu 11/21/24 Fri 11/22/24 Mon 12/2/24 338 Pivetta - Earthwork 345 FRPCS - Sidewalk and Driveway Approaches 5 d 0 d 0 d NA NA Tue 12/3/24 Mon 12/9/24 Tue 12/3/24 Mon 12/9/24 339,341,344 WCCI 346 Grade/Form/Pour - Curb Ramps/Install DWS - Renton Ave. Ext. - Sta 32+30 2 d 212 d 3 d NA NA Tue 12/10/24 Wed 12/11/24 Mon 10/20/25 Tue 10/21/25 345 WCCI 347 Grade/Form/Pour - Curb Ramps/Install DWS - Renton Ave Ext. - Sta 32+71.52 to 33+97.39 2 d 212 d 3 d NA NA Tue 12/10/24 Wed 12/11/24 Mon 10/20/25 Tue 10/21/25 345 WCCI 348 Grade/Form/Pour - Curb Ramps/Install DWS - NW 3rd Pl - Sta 40+32.69 to 41+26.24 2 d 212 d 3 d NA NA Tue 12/10/24 Wed 12/11/24 Mon 10/20/25 Tue 10/21/25 345 WCCI 349 Concrete Switchback - Sta 37+14.35 to 37+34.20 20 d 190 d 190 d NA NA Fri 11/22/24 Mon 12/23/24 Thu 9/4/25 Wed 10/1/25 350 Excavate/Place 4" Compacted CSBC 10 d 190 d 0 d NA NA Fri 11/22/24 Mon 12/9/24 Thu 9/4/25 Wed 9/17/25 344 Pivetta - Earthwork 351 FRPCS Cement Concrete Switchback, Ramp, Stairs 10 d 190 d 0 d NA NA Tue 12/10/24 Mon 12/23/24 Thu 9/18/25 Wed 10/1/25 350 WCCI 352 Urban Design Features 45 d 190 d 190 d NA NA Tue 12/24/24 Thu 3/6/25 Thu 10/2/25 Mon 12/8/25 353 Fabricate Handrails 40 d 190 d 0 d NA NA Tue 12/24/24 Thu 2/27/25 Thu 10/2/25 Mon 12/1/25 351 Pivetta 354 Install Handrails and Fencing 5 d 190 d 187 d NA NA Fri 2/28/25 Thu 3/6/25 Tue 12/2/25 Mon 12/8/25 351,353 Pivetta 355 Roadway - Sta 13+95 to 42+80.28 27 d 61 d 61 d NA NA Wed 11/13/24 Mon 12/23/24 Thu 2/20/25 Tue 10/28/25 356 HMA 27 d 61 d 61 d NA NA Wed 11/13/24 Mon 12/23/24 Thu 2/20/25 Tue 10/28/25 357 HMA - Southbound Rainier & Renton Ave Ext - Sta 13+95 to 42+80 27 d 61 d 61 d NA NA Wed 11/13/24 Mon 12/23/24 Thu 2/20/25 Tue 10/28/25 358 Grind Pavement 5 d 61 d 0 d NA NA Wed 11/13/24 Tue 11/19/24 Thu 2/20/25 Wed 2/26/25 185,323,326 Becker Blacktop 359 Grade Base/Place Geotextile & CSBC 10 d 61 d 0 d NA NA Fri 11/15/24 Mon 12/2/24 Mon 2/24/25 Fri 3/7/25 358SS+2 d Pivetta - Earthwork 360 Prep T Cuts 10 d 72 d 11 d NA NA Tue 11/19/24 Wed 12/4/24 Thu 3/13/25 Wed 3/26/25 359SS+2 d Pivetta - Earthwork 361 Place 8" HMA CL 1/2" PG 70-22 - New HMA Section/Trench Patch - Southbound Rainier Ave, Side Streets 5 d 61 d 0 d NA NA Tue 12/10/24 Mon 12/16/24 Mon 3/17/25 Fri 3/21/25 360SS+2 d,365 Icon 362 Grade/Place CSBC/Place 4" HMA - Driveways 5 d 209 d 171 d NA NA Tue 12/17/24 Mon 12/23/24 Wed 10/22/25 Tue 10/28/25 361,345,331,335,336,340,341,342,346,347,348Icon 363 Concrete Panel Approaches (Rainier and 2nd St.) - Sta 18+57.89 to 18+92.89 12 d 61 d 61 d NA NA Wed 11/20/24 Mon 12/9/24 Thu 2/27/25 Fri 3/14/25 364 Grade/Compact Subsurface and Place 2" CSBC - SB Rainier Ave. S. 2 d 61 d 0 d NA NA Wed 11/20/24 Thu 11/21/24 Thu 2/27/25 Fri 2/28/25 359SS+3 d Pivetta - Earthwork 365 Install 10" Concrete Panels - SB Rainier Ave. S.10 d 61 d 0 d NA NA Fri 11/22/24 Mon 12/9/24 Mon 3/3/25 Fri 3/14/25 364 WCCI 366 367 Stage 2 (East)151 d 0 d 0 d NA NA Mon 3/17/25 Fri 10/17/25 Mon 3/17/25 Mon 12/8/25 278 368 Temporary Channelization and Signalization 12+12.5 to 43+63 5 d 0 d 0 d NA NA Mon 3/17/25 Fri 3/21/25 Mon 3/17/25 Fri 3/21/25 369 Install Construction Channelization, Striping, Warning Signs - Shift Traffic to West Side of Rainier Ave.5 d 0 d 0 d NA NA Mon 3/17/25 Fri 3/21/25 Mon 3/17/25 Fri 3/21/25 236,237,361SS,278 SPM 370 Adjust and Modify Signals 5 d 0 d 0 d NA NA Mon 3/17/25 Fri 3/21/25 Mon 3/17/25 Fri 3/21/25 369SS,278 Golden Gate 371 Site Prep - Sta 12+12.5 to 42+07.42 10 d 69 d 69 d NA NA Mon 3/24/25 Fri 4/4/25 Tue 7/1/25 Tue 7/15/25 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 6 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 44 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 372 Clear & Grub - Stage 2 5 d 69 d 0 d NA NA Mon 3/24/25 Fri 3/28/25 Tue 7/1/25 Tue 7/8/25 369,370 Pivetta - Earthwork 373 Relocate Cable Railing and Posts 5 d 69 d 0 d NA NA Mon 3/24/25 Fri 3/28/25 Tue 7/1/25 Tue 7/8/25 372SS Pivetta - Earthwork 374 Complete Removals 5 d 69 d 0 d NA NA Mon 3/31/25 Fri 4/4/25 Wed 7/9/25 Tue 7/15/25 372,373 Pivetta - Earthwork 375 Sewer - Sta 25+02.65 to 28+55.98 9 d 0 d 0 d NA NA Mon 3/24/25 Thu 4/3/25 Mon 3/24/25 Thu 4/3/25 376 Sewer - Royal Orchid/Formula 1 Fast Lube to S. Tobin St. - Sta 25+02.65 to 28+48.03 8 d 0 d 0 d NA NA Mon 3/24/25 Wed 4/2/25 Mon 3/24/25 Wed 4/2/25 377 Install New 8" Sewer and Manhole 6 d 0 d 0 d NA NA Mon 3/24/25 Mon 3/31/25 Mon 3/24/25 Mon 3/31/25 369,370 Pivetta - Sewer 378 Install New Side Sewers 2 d 0 d 0 d NA NA Tue 4/1/25 Wed 4/2/25 Tue 4/1/25 Wed 4/2/25 377 Pivetta - Sewer 379 S. Tobin St. - Night/Crossing Sta 28+48.03 to 28+55.98 1 d 0 d 0 d NA NA Thu 4/3/25 Thu 4/3/25 Thu 4/3/25 Thu 4/3/25 380 Install 12" Sewer 1 d 0 d 0 d NA NA Thu 4/3/25 Thu 4/3/25 Thu 4/3/25 Thu 4/3/25 377,378 Pivetta - Sewer 381 Storm Drainage - Sta 203+50 (S. 3rd) to 41+72.60 (Rainier)66 d 0 d 0 d NA NA Fri 4/4/25 Wed 7/9/25 Fri 4/4/25 Wed 7/9/25 382 S. 3rd Street to Taco Time - Sta 203+50 to 200+79.67 (S. 3rd) & 13+50 to 17+63.44 (Rainier) 19 d 0 d 0 d NA NA Fri 4/4/25 Wed 4/30/25 Fri 4/4/25 Wed 4/30/25 383 Install Drainage and Catch Basins 16 d 0 d 0 d NA NA Fri 4/4/25 Fri 4/25/25 Fri 4/4/25 Fri 4/25/25 380 Pivetta - Sewer 384 Install Filterra Units 3 d 0 d 0 d NA NA Mon 4/28/25 Wed 4/30/25 Mon 4/28/25 Wed 4/30/25 383 Pivetta - Sewer 385 Storm Drainage - Night/Crossing - Sta 14+25.73 2 d 0 d 0 d NA NA Thu 5/1/25 Fri 5/2/25 Thu 5/1/25 Fri 5/2/25 386 Install Drainage and Catch Basin 2 d 0 d 0 d NA NA Thu 5/1/25 Fri 5/2/25 Thu 5/1/25 Fri 5/2/25 384 Pivetta - Sewer 387 Royal Orchid to N of Airport Way - Sta 24+83.45 to 34+19.81 18 d 0 d 0 d NA NA Mon 5/5/25 Thu 5/29/25 Mon 5/5/25 Thu 5/29/25 388 Install Drainage and Catch Basins 15 d 0 d 0 d NA NA Mon 5/5/25 Fri 5/23/25 Mon 5/5/25 Fri 5/23/25 386 Pivetta - Sewer 389 Install Filterra Units 3 d 0 d 0 d NA NA Tue 5/27/25 Thu 5/29/25 Tue 5/27/25 Thu 5/29/25 388 Pivetta - Sewer 390 Storm Drainage - Night/Crossing - Sta 30+78.93 3 d 0 d 0 d NA NA Fri 5/30/25 Tue 6/3/25 Fri 5/30/25 Tue 6/3/25 391 Install Drainage and Catch Basin 2 d 0 d 0 d NA NA Fri 5/30/25 Mon 6/2/25 Fri 5/30/25 Mon 6/2/25 389 Pivetta - Sewer 392 Install Filterra Unit 1 d 0 d 0 d NA NA Tue 6/3/25 Tue 6/3/25 Tue 6/3/25 Tue 6/3/25 391 Pivetta - Sewer 393 Airport Way - Sta 33+17.81 to 601+64.04 6 d 0 d 0 d NA NA Wed 6/4/25 Wed 6/11/25 Wed 6/4/25 Wed 6/11/25 394 Install Drainage and Catch Basins 5 d 0 d 0 d NA NA Wed 6/4/25 Tue 6/10/25 Wed 6/4/25 Tue 6/10/25 392 Pivetta - Sewer 395 Install Filterra Units 1 d 0 d 0 d NA NA Wed 6/11/25 Wed 6/11/25 Wed 6/11/25 Wed 6/11/25 394 Pivetta - Sewer 396 N of Airport Way to S. of Nelson Pl. - Sta 36+15.83 to 38+57.60 - Night/Partial Stage 3 7 d 0 d 0 d NA NA Thu 6/12/25 Mon 6/23/25 Thu 6/12/25 Mon 6/23/25 397 Install Drainage and Catch Basins 6 d 0 d 0 d NA NA Thu 6/12/25 Fri 6/20/25 Thu 6/12/25 Fri 6/20/25 395 Pivetta - Sewer 398 Install Filterra Units 1 d 0 d 0 d NA NA Mon 6/23/25 Mon 6/23/25 Mon 6/23/25 Mon 6/23/25 397 Pivetta - Sewer 399 S. of Nelson Pl to End - Sta 37+91.23 to 41+72.60 11 d 0 d 0 d NA NA Tue 6/24/25 Wed 7/9/25 Tue 6/24/25 Wed 7/9/25 400 Install Drainage and Catch Basins 8 d 0 d 0 d NA NA Tue 6/24/25 Thu 7/3/25 Tue 6/24/25 Thu 7/3/25 398 Pivetta - Sewer 401 Install Filterra Units 3 d 0 d 0 d NA NA Mon 7/7/25 Wed 7/9/25 Mon 7/7/25 Wed 7/9/25 400 Pivetta - Sewer 402 Illumination - Sta 204+60 to 201+25, 133+50 to 42+08 146 d 0 d 0 d NA NA Mon 3/24/25 Fri 10/17/25 Wed 5/21/25 Fri 10/17/25 403 Decorative Illumination System 146 d 0 d 0 d NA NA Mon 3/24/25 Fri 10/17/25 Wed 5/21/25 Fri 10/17/25 404 Below Ground 33 d 42 d 42 d NA NA Mon 3/24/25 Wed 5/7/25 Wed 5/21/25 Wed 7/9/25 405 Trench and Conduit 23 d 42 d 0 d NA NA Mon 3/24/25 Wed 4/23/25 Wed 5/21/25 Tue 6/24/25 369 Golden Gate 406 Foundations 24 d 42 d 0 d NA NA Mon 3/24/25 Thu 4/24/25 Wed 5/21/25 Wed 6/25/25 405SS Golden Gate 407 Junction Boxes 9 d 42 d 0 d NA NA Fri 4/25/25 Wed 5/7/25 Thu 6/26/25 Wed 7/9/25 406 Golden Gate 408 Above Ground 56 d 0 d 0 d NA NA Thu 7/31/25 Fri 10/17/25 Thu 7/31/25 Fri 10/17/25 409 Set Poles 31 d 0 d 0 d NA NA Thu 7/31/25 Fri 9/12/25 Thu 7/31/25 Fri 9/12/25 406,436 Golden Gate 410 Install Lighting Wiring 20 d 0 d 0 d NA NA Mon 9/15/25 Fri 10/10/25 Mon 9/15/25 Fri 10/10/25 407,409 Golden Gate 411 Test and Turn On 2 d 0 d 0 d NA NA Mon 10/13/25 Tue 10/14/25 Mon 10/13/25 Tue 10/14/25 409,410 Golden Gate 412 Remove and Salvage Old Poles&Wiring 3 d 0 d 0 d NA NA Wed 10/15/25 Fri 10/17/25 Wed 10/15/25 Fri 10/17/25 411 Golden Gate 413 Walls - Sta 18+53.50 to 33+39.60 25 d 68 d 68 d NA NA Thu 5/8/25 Thu 6/12/25 Fri 8/15/25 Mon 12/8/25 414 Wall 3 - CCFW and Modular Block Wall - Sta 300+54.06 to 301+10.11 15 d 68 d 68 d NA NA Thu 5/8/25 Thu 5/29/25 Fri 8/15/25 Fri 9/5/25 415 Construct Concrete Fill Wall - Sta 17+53.50 to 18+48.48 5 d 68 d 0 d NA NA Thu 5/8/25 Wed 5/14/25 Fri 8/15/25 Thu 8/21/25 407,369 WCCI 416 Construct Modular Block Wall - Sta 300+54.05 to 301+10.11 10 d 68 d 0 d NA NA Thu 5/15/25 Thu 5/29/25 Fri 8/22/25 Fri 9/5/25 415 Key West 417 Wall 4 - Modular Block Wall - Sta 21+11.76 to 21+59.62 5 d 68 d 68 d NA NA Fri 5/30/25 Thu 6/5/25 Mon 9/8/25 Fri 9/12/25 418 Construct Modular Block Wall - Sta 21+11.76 to 21+59.62 5 d 68 d 30 d NA NA Fri 5/30/25 Thu 6/5/25 Mon 9/8/25 Fri 9/12/25 416 Key West 419 Gateway Wall B - Sta 33+39.60 to 600+57.12 20 d 68 d 68 d NA NA Thu 5/15/25 Thu 6/12/25 Fri 8/22/25 Mon 12/8/25 420 Construct Gateway Wall B 15 d 68 d 0 d NA NA Thu 5/15/25 Thu 6/5/25 Fri 8/22/25 Fri 9/12/25 415 WCCI 421 Install Decorative Cutouts and Skate Deterrent - Gateway Wall B 5 d 121 d 118 d NA NA Fri 6/6/25 Thu 6/12/25 Tue 12/2/25 Mon 12/8/25 420 WCCI 422 Curb and Gutter - Sta 204+63.59 to 42+07.42 17 d 0 d 0 d NA NA Thu 7/10/25 Fri 8/1/25 Thu 7/10/25 Mon 9/29/25 423 Curb and Gutter - S. 3rd St. to S. 2nd St. - Sta 204+63.59 to 301+09.32 8 d 0 d 0 d NA NA Thu 7/10/25 Mon 7/21/25 Thu 7/10/25 Mon 7/21/25 424 Grade/Prep Base/Place CSBC 4 d 0 d 0 d NA NA Thu 7/10/25 Tue 7/15/25 Thu 7/10/25 Tue 7/15/25 401,173,378,380,407 Pivetta - Earthwork 425 Form and Pour Curb and Gutter 4 d 0 d 0 d NA NA Wed 7/16/25 Mon 7/21/25 Wed 7/16/25 Mon 7/21/25 424 WCCI 426 Curb and Gutter - S. 2nd St. to S. Tobin St. - Sta 19+57.82 to 28+61.93 6 d 0 d 0 d NA NA Wed 7/16/25 Wed 7/23/25 Thu 7/17/25 Wed 7/23/25 427 Grade/Prep Base/Place CSBC 2 d 1 d 0 d NA NA Wed 7/16/25 Thu 7/17/25 Thu 7/17/25 Fri 7/18/25 424,180,176 Pivetta - Earthwork 428 Form and Pour Curb and Gutter 2 d 0 d 0 d NA NA Tue 7/22/25 Wed 7/23/25 Tue 7/22/25 Wed 7/23/25 425,427 WCCI 429 Curb and Gutter - S. Tobin St. to Airport Way - Sta 28+61.93 to 604+36.35 11 d 1 d 1 d NA NA Fri 7/18/25 Fri 8/1/25 Mon 7/21/25 Mon 9/29/25 430 Grade/Prep Base/Place CSBC 2 d 1 d 0 d NA NA Fri 7/18/25 Mon 7/21/25 Mon 7/21/25 Tue 7/22/25 427,122 Pivetta - Earthwork 431 Form and Pour Curb and Gutter 2 d 0 d 0 d NA NA Thu 7/24/25 Fri 7/25/25 Thu 7/24/25 Fri 7/25/25 430,428 WCCI 432 Islands - Sta 31+86.30 to 601+03.49 5 d 40 d 40 d NA NA Mon 7/28/25 Fri 8/1/25 Tue 9/23/25 Mon 9/29/25 433 Grade/Place CSBC/Place Island 1 - Airport Way 5 d 40 d 0 d NA NA Mon 7/28/25 Fri 8/1/25 Tue 9/23/25 Mon 9/29/25 431 Pivetta - Earthwork H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 7 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 45 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 434 Curb and Gutter - Airport Way to End - Sta 603+57.87 to 42+07.42 7 d 0 d 0 d NA NA Tue 7/22/25 Wed 7/30/25 Wed 7/23/25 Wed 7/30/25 435 Grade/Prep Base/Place CSBC 3 d 1 d 1 d NA NA Tue 7/22/25 Thu 7/24/25 Wed 7/23/25 Fri 7/25/25 430 Pivetta - Earthwork 436 Form and Pour Curb and Gutter 3 d 0 d 0 d NA NA Mon 7/28/25 Wed 7/30/25 Mon 7/28/25 Wed 7/30/25 431,435 WCCI 437 Sidewalk - Sta 204+63.59 to 42+07.42 37 d 38 d 38 d NA NA Tue 7/22/25 Thu 9/11/25 Mon 9/15/25 Mon 12/8/25 438 Sidewalk - S. 3rd St. to S. 2nd St. - Sta 204+63.59 to 301+09.32 17 d 38 d 38 d NA NA Tue 7/22/25 Wed 8/13/25 Mon 9/15/25 Tue 10/14/25 439 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 5 d 38 d 0 d NA NA Tue 7/22/25 Mon 7/28/25 Mon 9/15/25 Fri 9/19/25 151,425,374,415,416,418,420,470 Pivetta - Earthwork 440 FRPCS - Sidewalk and Driveway Approaches 8 d 38 d 0 d NA NA Thu 7/31/25 Mon 8/11/25 Wed 9/24/25 Fri 10/3/25 439SS+2 d,436 WCCI 441 Grade/Form/Pour - Curb Ramps/Install DWS - S. 3rd St. - Sta 12+12.51 to 201+45.07 2 d 43 d 5 d NA NA Tue 8/12/25 Wed 8/13/25 Mon 10/13/25 Tue 10/14/25 440 WCCI 442 Grade/Form/Pour - Curb Ramps/Install DWS - S. 3rd St. - Sta 200+78.57 to 14+00.41 2 d 43 d 5 d NA NA Tue 8/12/25 Wed 8/13/25 Mon 10/13/25 Tue 10/14/25 440 WCCI 443 Grade/Form/Pour - Curb Ramps/Install DWS - S. 2nd St. - Sta 18+48.51 to 19+08.79 2 d 43 d 5 d NA NA Tue 8/12/25 Wed 8/13/25 Mon 10/13/25 Tue 10/14/25 440 WCCI 444 Sidewalk - S. 2nd St. to S. Tobin St. - Sta 19+57.82 to 28+61.93 17 d 38 d 38 d NA NA Tue 7/29/25 Wed 8/20/25 Mon 9/22/25 Mon 12/8/25 445 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 5 d 38 d 0 d NA NA Tue 7/29/25 Mon 8/4/25 Mon 9/22/25 Fri 9/26/25 439 Pivetta - Earthwork 446 FRPCS - Sidewalk and Driveway Approaches 5 d 38 d 0 d NA NA Tue 8/12/25 Mon 8/18/25 Mon 10/6/25 Fri 10/10/25 445,440,451 WCCI 447 Grade/Form/Pour - Curb Ramps/Install DWS - S. 2nd St. - Sta 19+55.68 to 20+08.13 2 d 38 d 0 d NA NA Tue 8/19/25 Wed 8/20/25 Mon 10/13/25 Tue 10/14/25 446 WCCI 448 Grade/Form/Pour - Curb Ramps/Install DWS - Midblock Crosswalk - Sta 25+40.51 to 25+47.25 2 d 38 d 0 d NA NA Tue 8/19/25 Wed 8/20/25 Mon 10/13/25 Tue 10/14/25 446 WCCI 449 Grade/Form/Pour - Curb Ramps/Install DWS - S. Tobin St. - Sta 27+93.39 to 500+74.79 2 d 38 d 0 d NA NA Tue 8/19/25 Wed 8/20/25 Mon 10/13/25 Tue 10/14/25 446 WCCI 450 Bus Shelter - Sta 24+59.90 6 d 38 d 38 d NA NA Tue 8/5/25 Tue 8/12/25 Mon 9/29/25 Mon 12/8/25 451 FRPCS Bus Shelter Footings 5 d 38 d 0 d NA NA Tue 8/5/25 Mon 8/11/25 Mon 9/29/25 Fri 10/3/25 445 WCCI 452 Install Bus Shelter 1 d 80 d 77 d NA NA Tue 8/12/25 Tue 8/12/25 Mon 12/8/25 Mon 12/8/25 451 Pivetta 453 Sidewalk - S. Tobin St. to Airport Way 5 d 39 d 39 d NA NA Tue 8/5/25 Mon 8/11/25 Tue 9/30/25 Wed 10/8/25 454 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 4 d 39 d 0 d NA NA Tue 8/5/25 Fri 8/8/25 Tue 9/30/25 Fri 10/3/25 445 Pivetta - Earthwork 455 FRPCS - Sidewalk and Driveway Approaches 4 d 41 d 2 d NA NA Wed 8/6/25 Mon 8/11/25 Fri 10/3/25 Wed 10/8/25 454SS+1 d WCCI 456 Shared Use Path - Airport Way to Sta 38+80 27 d 39 d 39 d NA NA Tue 8/5/25 Thu 9/11/25 Tue 9/30/25 Mon 12/8/25 457 Grade/Prep Base/Place CSBC - Shared Use Path 5 d 39 d 0 d NA NA Tue 8/5/25 Mon 8/11/25 Tue 9/30/25 Mon 10/6/25 454SS Pivetta - Earthwork 458 Place HMA - Shared Use Path 5 d 62 d 59 d NA NA Tue 9/2/25 Mon 9/8/25 Tue 12/2/25 Mon 12/8/25 457,479,461 WCCI 459 Concrete Switchback - Sta 35+36.63 to 35+68.13 23 d 59 d 59 d NA NA Mon 8/11/25 Thu 9/11/25 Thu 11/6/25 Mon 12/8/25 460 Excavate/Place 4" Compacted CSBC 5 d 62 d 0 d NA NA Mon 8/11/25 Fri 8/15/25 Thu 11/6/25 Thu 11/13/25 454 Pivetta - Earthwork 461 FRPCS Cement Concrete Switchback, Ramp, Stairs 10 d 62 d 0 d NA NA Mon 8/18/25 Fri 8/29/25 Fri 11/14/25 Mon 12/1/25 460 WCCI 462 Install Handrails and Fencing 5 d 59 d 56 d NA NA Fri 9/5/25 Thu 9/11/25 Tue 12/2/25 Mon 12/8/25 461,473 WCCI 463 Sidewalk - Airport Way to End - 603+57.87 to 42+07.42 6 d 39 d 39 d NA NA Tue 8/12/25 Tue 8/19/25 Tue 10/7/25 Tue 10/14/25 464 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 2 d 39 d 0 d NA NA Tue 8/12/25 Wed 8/13/25 Tue 10/7/25 Wed 10/8/25 457 Pivetta - Earthwork 465 FRPCS - Sidewalk and Driveway Approaches 2 d 39 d 0 d NA NA Thu 8/14/25 Fri 8/15/25 Thu 10/9/25 Fri 10/10/25 455,464 WCCI 466 Grade/Form/Pour - Curb Ramps/Install DWS - S. Tobin St. - Sta 500+87.95 to 500+39.28 2 d 39 d 1 d NA NA Mon 8/18/25 Tue 8/19/25 Mon 10/13/25 Tue 10/14/25 465 WCCI 467 Grade/Form/Pour - Curb Ramps/Install DWS - Airport Way - Sta 31+31.67 to 32+15.90 2 d 39 d 1 d NA NA Mon 8/18/25 Tue 8/19/25 Mon 10/13/25 Tue 10/14/25 465 WCCI 468 Grade/Form/Pour - Curb Ramps/Install DWS - Airport Way - Sta 33+20.23 to 33+65.12 2 d 39 d 0 d NA NA Mon 8/18/25 Tue 8/19/25 Mon 10/13/25 Tue 10/14/25 465 WCCI 469 Urban Design Features 105 d 59 d 59 d NA NA Mon 4/7/25 Thu 9/4/25 Thu 9/11/25 Mon 12/1/25 470 Drill Foundations for Decorative Trellis 2 d 109 d 71 d NA NA Mon 4/7/25 Tue 4/8/25 Thu 9/11/25 Fri 9/12/25 374 Pivetta 471 Install Trellis 5 d 59 d 0 d NA NA Wed 8/20/25 Tue 8/26/25 Thu 11/13/25 Wed 11/19/25 468 Pivetta 472 Install Trash Receptacles and Benches 1 d 59 d 0 d NA NA Wed 8/27/25 Wed 8/27/25 Thu 11/20/25 Thu 11/20/25 468,471 Pivetta 473 Install Fence 5 d 59 d 0 d NA NA Thu 8/28/25 Thu 9/4/25 Fri 11/21/25 Mon 12/1/25 468,472 Pivetta 474 Roadway - Sta 12+12.5 to 43+63 23 d 40 d 40 d NA NA Mon 8/4/25 Thu 9/4/25 Tue 9/30/25 Mon 12/8/25 475 HMA - Northbound Rainier & Airport Way - Sta 12+12.5 to 43+63 23 d 38 d 38 d NA NA Mon 8/4/25 Thu 9/4/25 Tue 9/30/25 Tue 10/28/25 476 Grind Pavement 5 d 40 d 0 d NA NA Mon 8/4/25 Fri 8/8/25 Tue 9/30/25 Mon 10/6/25 436,433 Becker Blacktop 477 Grade Base/Place Geotextile & CSBC 10 d 40 d 0 d NA NA Wed 8/6/25 Tue 8/19/25 Thu 10/2/25 Wed 10/15/25 165,173,476SS+2 d Pivetta - Earthwork 478 Prep T Cuts 10 d 40 d 0 d NA NA Fri 8/8/25 Thu 8/21/25 Mon 10/6/25 Fri 10/17/25 477SS+2 d Pivetta - Earthwork 479 Place 8" HMA CL 1/2" PG 70-22 - New HMA Section/Trench Patch - Southbound Rainier Ave, Side Streets 5 d 40 d 0 d NA NA Tue 8/12/25 Mon 8/18/25 Wed 10/8/25 Tue 10/14/25 478SS+2 d Icon 480 Grade/Place CSBC/Place 4" HMA - Driveways 10 d 38 d 0 d NA NA Thu 8/21/25 Thu 9/4/25 Wed 10/15/25 Tue 10/28/25 479,441,442,443,447,448,449,466,467,468Icon 481 Concrete Panel Approaches (Rainier and 2nd St.) - Sta 18+57.89 to 18+92.89 7 d 42 d 42 d NA NA Mon 8/11/25 Tue 8/19/25 Thu 10/9/25 Fri 10/17/25 482 Grade/Compact Subsurface and Place 2" CSBC - SB Rainier Ave. S. 2 d 42 d 0 d NA NA Mon 8/11/25 Tue 8/12/25 Thu 10/9/25 Fri 10/10/25 477SS+3 d,151 Pivetta - Earthwork 483 Install 10" Concrete Panels - SB Rainier Ave. S.5 d 42 d 42 d NA NA Wed 8/13/25 Tue 8/19/25 Mon 10/13/25 Fri 10/17/25 482 WCCI 484 Dual Faced Slope Mountable Curb - Airport Way - Sta 600+90 to 603+45 7 d 69 d 69 d NA NA Tue 8/19/25 Wed 8/27/25 Wed 11/26/25 Mon 12/8/25 485 S. 3rd St. - Sta to 200+62 to 201+55 5 d 69 d 69 d NA NA Tue 8/19/25 Mon 8/25/25 Wed 11/26/25 Fri 12/5/25 486 FRPCS - Dual Faced Sloped Mountable Traffic Curb - S. 3rd St. 4 d 69 d 0 d NA NA Tue 8/19/25 Fri 8/22/25 Wed 11/26/25 Wed 12/3/25 479 SPM 487 Install Curb Mounted Delineator Posts - S. 3rd St. 1 d 70 d 1 d NA NA Mon 8/25/25 Mon 8/25/25 Fri 12/5/25 Fri 12/5/25 486 SPM 488 Airport Way - Sta 600+90 to 603+45 3 d 69 d 69 d NA NA Mon 8/25/25 Wed 8/27/25 Thu 12/4/25 Mon 12/8/25 489 FRPCS - Dual Faced Sloped Mountable Traffic Curb - Airport Way 2 d 69 d 0 d NA NA Mon 8/25/25 Tue 8/26/25 Thu 12/4/25 Fri 12/5/25 486 SPM 490 Install Curb Mounted Delineator Posts - Airport Way 1 d 69 d 69 d NA NA Wed 8/27/25 Wed 8/27/25 Mon 12/8/25 Mon 12/8/25 489,487 SPM 491 492 Stage 3 (Median)48 d 0 d 0 d NA NA Mon 10/20/25 Mon 1/5/26 Mon 10/20/25 Mon 1/5/26 493 Temporary Channelization and Signalization - 14+05 to 40+15 2 d 0 d 0 d NA NA Mon 10/20/25 Tue 10/21/25 Mon 10/20/25 Tue 10/21/25 494 Install Const. Channelization & Shift Traffic to Outside Lanes - Rainier Ave S. 2 d 0 d 0 d NA NA Mon 10/20/25 Tue 10/21/25 Mon 10/20/25 Tue 10/21/25 412,483,479 Pivetta 495 Adjust Signal Heads and Cameras 2 d 0 d 0 d NA NA Mon 10/20/25 Tue 10/21/25 Mon 10/20/25 Tue 10/21/25 494SS Golden Gate H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 8 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 46 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 496 Site Prep - Sta 14+05 to 40+15 5 d 0 d 0 d NA NA Wed 10/22/25 Tue 10/28/25 Wed 10/22/25 Tue 10/28/25 497 Sawcut and Remove Pavement in Median 5 d 0 d 0 d NA NA Wed 10/22/25 Tue 10/28/25 Wed 10/22/25 Tue 10/28/25 494,495 Pivetta 498 Roadway - Sta 14+05 to 40+40 31 d 0 d 0 d NA NA Wed 10/29/25 Mon 12/15/25 Wed 10/29/25 Mon 12/15/25 499 Median 1 - Sta 14+05 to 18+44.96 20 d 0 d 0 d NA NA Wed 10/29/25 Wed 11/26/25 Wed 10/29/25 Wed 12/3/25 500 Grade Base/Place CSBC/FRPCS Median 1 Curb 5 d 0 d 0 d NA NA Wed 10/29/25 Tue 11/4/25 Wed 10/29/25 Tue 11/4/25 497,539SS Pivetta - Earthwork 501 Install River Rock Treatment 5 d 3 d 0 d NA NA Wed 11/5/25 Wed 11/12/25 Mon 11/10/25 Mon 11/17/25 500 WCCI 502 Install Bioretention Planter Area 5 d 3 d 0 d NA NA Thu 11/13/25 Wed 11/19/25 Tue 11/18/25 Mon 11/24/25 501 Coria 503 Install Plants 5 d 3 d 0 d NA NA Thu 11/20/25 Wed 11/26/25 Tue 11/25/25 Wed 12/3/25 502 Pivetta 504 Adjust Monument Case and Cover to FG 1 d 11 d 11 d NA NA Wed 11/5/25 Wed 11/5/25 Fri 11/21/25 Fri 11/21/25 500 Pivetta 505 Median 2 - Sta 19+65 7 d 0 d 0 d NA NA Wed 11/5/25 Fri 11/14/25 Wed 11/5/25 Fri 11/21/25 506 Grade Base/Place CSBC/FRPCS Median Curb 2 3 d 0 d 0 d NA NA Wed 11/5/25 Fri 11/7/25 Wed 11/5/25 Fri 11/7/25 500 Pivetta - Earthwork 507 Install River Rock Treatment 2 d 5 d 1 d NA NA Thu 11/13/25 Fri 11/14/25 Thu 11/20/25 Fri 11/21/25 506,501 WCCI 508 Median 3 - Sta 23+40 to 25+50 15 d 0 d 0 d NA NA Mon 11/10/25 Wed 12/3/25 Mon 11/10/25 Mon 12/8/25 509 Grade Base/Place CSBC/FRPCS Median Curb 3 3 d 0 d 0 d NA NA Mon 11/10/25 Thu 11/13/25 Mon 11/10/25 Thu 11/13/25 506,539SS Pivetta - Earthwork 510 Install Midblock Crosswalk and DWS 2 d 4 d 0 d NA NA Fri 11/14/25 Mon 11/17/25 Thu 11/20/25 Fri 11/21/25 509 WCCI 511 Install River Rock Treatment 3 d 4 d 0 d NA NA Tue 11/18/25 Thu 11/20/25 Mon 11/24/25 Wed 11/26/25 507,510 WCCI 512 Install Bioretention Planter Area 3 d 4 d 1 d NA NA Fri 11/21/25 Tue 11/25/25 Mon 12/1/25 Wed 12/3/25 511 Coria 513 Install Plants 3 d 3 d 0 d NA NA Mon 12/1/25 Wed 12/3/25 Thu 12/4/25 Mon 12/8/25 503,512 Coria 514 Install Root Barrier 3 d 3 d 0 d NA NA Mon 12/1/25 Wed 12/3/25 Thu 12/4/25 Mon 12/8/25 513SS Coria 515 Median 4 - Sta 25+50 to 31+65.38 6 d 0 d 0 d NA NA Mon 11/10/25 Tue 11/18/25 Mon 11/10/25 Wed 11/19/25 516 Grade Base/Place CSBC/FRPCS Median Curb 4 3 d 0 d 0 d NA NA Mon 11/10/25 Thu 11/13/25 Mon 11/10/25 Thu 11/13/25 509SS,539SS Piveta - Earthwork 517 Install River Rock Treatment 3 d 1 d 0 d NA NA Fri 11/14/25 Tue 11/18/25 Mon 11/17/25 Wed 11/19/25 516 WCCI 518 Median 5 - Sta 38+39.71 to 40+12.21 5 d 0 d 0 d NA NA Fri 11/14/25 Thu 11/20/25 Fri 11/14/25 Fri 11/21/25 519 Grade Base/Place CSBC/FRPCS Median Curb 5 3 d 0 d 0 d NA NA Fri 11/14/25 Tue 11/18/25 Fri 11/14/25 Tue 11/18/25 516 Piveta - Earthwork 520 Install River Rock Treatment 2 d 1 d 1 d NA NA Wed 11/19/25 Thu 11/20/25 Thu 11/20/25 Fri 11/21/25 517,519 WCCI 521 Traffic Mounted Curb - Sta 20+25 to 23+40, 33+50 to 38+39.71 6 d 0 d 0 d NA NA Fri 11/14/25 Fri 11/21/25 Fri 11/14/25 Fri 11/21/25 522 Install Traffic Mounted Curb North of S. 2nd Street to Median 3 3 d 0 d 0 d NA NA Fri 11/14/25 Tue 11/18/25 Fri 11/14/25 Tue 11/18/25 509 SPM 523 Install Traffic Mounted Curb North of Airport Way to Median 5 3 d 0 d 0 d NA NA Wed 11/19/25 Fri 11/21/25 Wed 11/19/25 Fri 11/21/25 522,519 SPM 524 HMA Paving - Sta 14+05 to 42+10 14 d 0 d 0 d NA NA Mon 11/24/25 Mon 12/15/25 Mon 11/24/25 Mon 12/15/25 525 Grade Base/Place Geotextile & CSBC - New HMA Southbound Rainier 5 d 0 d 0 d NA NA Mon 11/24/25 Tue 12/2/25 Mon 11/24/25 Tue 12/2/25 523,504,520 Pivetta - Earthwork 526 Place HMA to Curb - Southbound Rainier 2 d 10 d 10 d NA NA Wed 11/26/25 Mon 12/1/25 Fri 12/12/25 Mon 12/15/25 525SS+2 d Icon 527 Grade Base/Place Geotextile & CSBC - New HMA Section Northbound Rainier 5 d 0 d 0 d NA NA Wed 12/3/25 Tue 12/9/25 Wed 12/3/25 Tue 12/9/25 525 Pivetta - Earthwork 528 Place HMA to Curb - Northbound Rainier 2 d 0 d 0 d NA NA Fri 12/5/25 Mon 12/8/25 Fri 12/5/25 Mon 12/8/25 527SS+2 d Icon 529 Place 4" Fiber Reinforced Asphalt Concrete (FRAC) - Project Wide 5 d 0 d 0 d NA NA Tue 12/9/25 Mon 12/15/25 Tue 12/9/25 Mon 12/15/25 361,479,490,528 Icon 530 Final Channelization and Striping 10 d 0 d 0 d NA NA Tue 12/16/25 Mon 1/5/26 Tue 12/16/25 Mon 1/5/26 531 Channelization and Striping - Southbound Rainier Ave - Sta 12+70.9 to 42+87.1 5 d 0 d 0 d NA NA Tue 12/16/25 Mon 12/22/25 Tue 12/16/25 Mon 12/22/25 532 Install Striping, Arrows, Blue Hydrant Markers 2 d 0 d 0 d NA NA Tue 12/16/25 Wed 12/17/25 Tue 12/16/25 Wed 12/17/25 526,529 SPM 533 Install Signs 5 d 0 d 0 d NA NA Tue 12/16/25 Mon 12/22/25 Tue 12/16/25 Mon 12/22/25 532SS Pivetta 534 Channelization and Striping - Northbound Rainier Ave - Sta 12+70.9 to 42+80.29 8 d 0 d 0 d NA NA Thu 12/18/25 Mon 1/5/26 Tue 12/23/25 Mon 1/5/26 535 Install Striping, Arrows, Blue Hydrant Markers 2 d 3 d 3 d NA NA Thu 12/18/25 Fri 12/19/25 Tue 12/23/25 Wed 12/24/25 532,528 SPM 536 Install Signs 5 d 0 d 0 d NA NA Tue 12/23/25 Mon 1/5/26 Tue 12/23/25 Mon 1/5/26 533,535SS Pivetta 537 538 Landscaping and Irrigation 76 d 3 d 3 d NA NA Fri 9/5/25 Wed 12/24/25 Wed 10/29/25 Mon 1/5/26 539 Install Irrigation 15 d 38 d 38 d NA NA Fri 9/5/25 Thu 9/25/25 Wed 10/29/25 Wed 11/19/25 362,480 Coria 540 Install Landscaping 15 d 3 d 3 d NA NA Thu 12/4/25 Wed 12/24/25 Tue 12/9/25 Mon 1/5/26 514,539,362,480,401,421,452,472,307,304,354,458,471,462Coria H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 9 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 47 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 0 Rainier Ave Phase 4 Project Schedule 740 d?0 d?0 d?Wed 11/2/22 NA Wed 11/2/22 Mon 11/10/25 Wed 11/2/22 Mon 11/10/25 1 2 Bid Opening Date 1 d 0 d 0 d Wed 11/2/22 Wed 11/2/22 Wed 11/2/22 Wed 11/2/22 Wed 11/2/22 Wed 11/2/22 Project Overview 3 Award Date (w/in 45 calendar days after opening bids)1.13 d 0 d 0 d Tue 12/13/22 Tue 12/13/22 Tue 12/13/22 Tue 12/13/22 Tue 12/13/22 Tue 12/13/22 2FS+45 d Project Overview 4 Contract Execution Date 1 d 0 d 0 d Thu 12/22/22 Thu 12/22/22 Thu 12/22/22 Thu 12/22/22 Thu 12/22/22 Thu 12/22/22 3 Project Overview 5 Notice to Proceed Date 1 d 0 d 0 d Mon 3/13/23 Mon 3/13/23 Mon 3/13/23 Mon 3/13/23 Mon 3/13/23 Mon 3/13/23 3,20FS+8 d Project Overview 6 Substantial Completion Date 0 d 0 d 0 d NA NA Mon 11/10/25 Mon 11/10/25 Mon 11/10/25 Mon 11/10/25 536,540,324,354,472,288,471,539 Project Overview 7 Physical Completion Date 0 d 0 d 0 d NA NA Mon 11/10/25 Mon 11/10/25 Mon 11/10/25 Mon 11/10/25 5,6 Project Overview 8 Contractual Physical Completion Date (500 working days)0 d 154 d 154 d NA NA Wed 4/2/25 Wed 4/2/25 Mon 11/10/25 Mon 11/10/25 5FS+500 d Project Overview 9 10 Preconstruction 164 d 0 d 0 d Sun 2/12/23 Fri 10/6/23 Sun 2/12/23 Fri 10/6/23 Sun 2/12/23 Fri 10/6/23 4 11 Submit Contractor's Health and Safety Plan 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 4 Pivetta - Administration 12 Prepare/Submit Confined Space Entry Program 5 d 0 d 0 d Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 5 Pivetta - Administration 13 Prepare/Submit Shoring and Excavation Plan 3 d 0 d 0 d Wed 2/15/23 Fri 2/17/23 Wed 2/15/23 Fri 2/17/23 Wed 2/15/23 Fri 2/17/23 4 Pivetta - Administration 14 Prepare/Submit Breakdown of Lump Sum Bid Items 5 d 0 d 0 d Sun 2/12/23 Fri 2/17/23 Sun 2/12/23 Fri 2/17/23 Sun 2/12/23 Fri 2/17/23 4 Pivetta - Administration 15 Prepare/Submit Preliminary QPL/RAM for Jobsite Materials 5 d 0 d 0 d Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 4 Pivetta - Administration 16 Prepare/Submit Preliminary Schedule of Working Drawing Submittals 5 d 0 d 0 d Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 4 Pivetta - Administration 17 Submit Work Hour Variance to CoR 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 4 Pivetta - Administration 18 Prepare/Submit Type 2 Working Drawings for Field Office 1 d 0 d 0 d Thu 3/2/23 Thu 3/2/23 Thu 3/2/23 Thu 3/2/23 Thu 3/2/23 Thu 3/2/23 4 Pivetta - Administration 19 Submit Preliminary Type B Schedule 1 d 0 d 0 d Tue 2/21/23 Tue 2/21/23 Tue 2/21/23 Tue 2/21/23 Tue 2/21/23 Tue 2/21/23 4 Pivetta - Administration 20 Attend Preconstruction Conference 1 d 0 d 0 d Wed 2/22/23 Wed 2/22/23 Wed 2/22/23 Wed 2/22/23 Wed 2/22/23 Wed 2/22/23 4FS+49 d,11,14,15,16,17,18,19 City of Renton 21 22 Submit Final Type B Progress Schedule 1 d 0 d 0 d Mon 3/20/23 Mon 3/20/23 Mon 3/20/23 Mon 3/20/23 Mon 3/20/23 Mon 3/20/23 20 Pivetta - Administration 23 Prepare/Submit Project Specific Traffic Control Plan 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 4 Pivetta - Administration 24 Prepare/Submit Confined Space Program Plan 5 d 0 d 0 d Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Pivetta - Administration 25 Submit/Fabricate Sample Project Identification Signs to CoR 5 d 0 d 0 d Mon 2/20/23 Mon 2/27/23 Mon 2/20/23 Mon 2/27/23 Mon 2/20/23 Mon 2/27/23 4 Pivetta - Administration 26 Prepare/Submit Dewatering Plan (Waiting on RFI-007 submitted 2/20/2023)5 d 0 d 0 d Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 Mon 10/2/23 Fri 10/6/23 4 Pivetta - Administration 27 Prepare/Submit Contaminated Soil and GW Handling and Mgmt Plan 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 4 Pivetta - Administration 28 Request JUT Structures and Conduit 1 d 0 d 0 d Wed 3/8/23 Wed 3/8/23 Wed 3/8/23 Wed 3/8/23 Wed 3/8/23 Wed 3/8/23 20 Pivetta - Administration 29 Utility Preconstruction Meeting 1 d 0 d 0 d Thu 3/16/23 Thu 3/16/23 Thu 3/16/23 Thu 3/16/23 Thu 3/16/23 Thu 3/16/23 5FS+2 d City of Renton 30 31 Setup/Install Temporary Field Offices 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 20 Pivetta 32 Complete Project Existing Conditions Survey 4 d 0 d 0 d Mon 3/13/23 Fri 3/17/23 Mon 3/13/23 Fri 3/17/23 Mon 3/13/23 Fri 3/17/23 5 Pivetta - Administration 33 Control and Staking 0 d 0 d 0 d Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 Mon 2/20/23 5 North Peak 34 35 Rainier Ave. S. - Construction Duration 655 d?0 d?0 d?Mon 3/13/23 NA Mon 3/13/23 Mon 11/10/25 Mon 3/13/23 Mon 11/10/25 5,13 36 Mobilization 107 d 0 d 0 d Mon 3/13/23 Fri 8/11/23 Mon 3/13/23 Fri 8/11/23 Mon 3/13/23 Fri 8/11/23 37 CCTV and Flush Sewer Lines 0 d 0 d 0 d Tue 8/1/23 Tue 8/1/23 Tue 8/1/23 Tue 8/1/23 Tue 8/1/23 Tue 8/1/23 5,12 Insituform 38 Fence Removal and Reinstallation 5 d 0 d 0 d Tue 8/1/23 Mon 8/7/23 Tue 8/1/23 Mon 8/7/23 Tue 8/1/23 Mon 8/7/23 33SS Pivetta 39 Sewer Manhole Delivery 39 d 0 d 0 d Fri 6/16/23 Fri 8/11/23 Fri 6/16/23 Fri 8/11/23 Fri 6/16/23 Fri 8/11/23 5 Pivetta - Administration 40 41 Potholing 42 d 0 d 0 d Mon 3/13/23 Tue 5/9/23 Mon 3/13/23 Tue 5/9/23 Mon 3/13/23 Tue 5/9/23 42 Pothole South Rainer Ave - STA 15+25 to 25+00 17 d 0 d 0 d Mon 3/13/23 Wed 4/5/23 Mon 3/13/23 Wed 4/5/23 Mon 3/13/23 Wed 4/5/23 5,23 43 Pothole North Rainier Ave - STA 25+00 to 42+85 24 d 0 d 0 d Wed 4/5/23 Tue 5/9/23 Wed 4/5/23 Tue 5/9/23 Wed 4/5/23 Tue 5/9/23 42 44 Pothole Side Streets 0 d 0 d 0 d Thu 5/4/23 Thu 5/4/23 Thu 5/4/23 Thu 5/4/23 Thu 5/4/23 Thu 5/4/23 43 45 46 Stage 1 (West)461 d?183 d?183 d?Tue 3/28/23 NA Tue 3/28/23 Thu 2/20/25 Tue 3/28/23 Mon 11/10/25 5 47 Site Prep - Sta 13+93.10 to 40+80.29 133.25 d 0 d 0 d Tue 3/28/23 Fri 10/6/23 Tue 3/28/23 Fri 10/6/23 Tue 3/28/23 Fri 10/6/23 48 Install Project Identification and Business Owner Signs 1 d 0 d 0 d Tue 3/28/23 Tue 3/28/23 Tue 3/28/23 Tue 3/28/23 Tue 3/28/23 Tue 3/28/23 4 Pivetta 49 Install High Visibility Fence/Inspection by CoR 1 d 0 d 0 d Wed 3/29/23 Wed 3/29/23 Wed 3/29/23 Wed 3/29/23 Wed 3/29/23 Wed 3/29/23 4 Pivetta 50 Install TESC- Stage 1 28 d 0 d 0 d Wed 3/29/23 Fri 5/5/23 Wed 3/29/23 Fri 5/5/23 Wed 3/29/23 Fri 5/5/23 4 Pivetta 51 Clear & Grub - Stage 1 (Work Progressing as Needed with Other Activities)2.25 d 0 d 0 d Mon 4/24/23 Wed 6/21/23 Mon 4/24/23 Wed 6/21/23 Mon 4/24/23 Wed 6/21/23 50 Pivetta 52 Complete Removals 5 d 0 d 0 d Mon 4/24/23 Fri 10/6/23 Mon 4/24/23 Fri 10/6/23 Mon 4/24/23 Fri 10/6/23 51 Pivetta 53 Relocate Bus Shelter - Sta 27+45.48 3 d 0 d 0 d Mon 4/24/23 Wed 4/26/23 Mon 4/24/23 Wed 4/26/23 Mon 4/24/23 Wed 4/26/23 5 Pivetta 54 Temporary Channelization and Signalization - Sta 13+95 to 43+63.00 14 d 0 d 0 d Wed 4/5/23 Mon 4/24/23 Wed 4/5/23 Mon 4/24/23 Wed 4/5/23 Mon 4/24/23 55 Portable Temporary Signal System (SW Sunset/S 3rd St.) (2nd St.) (Airport Way/Renton Ave)6 d 0 d 0 d Wed 4/5/23 Wed 4/12/23 Wed 4/5/23 Wed 4/12/23 Wed 4/5/23 Wed 4/12/23 56 Pull Wire to Tie In Temp Signal 2 d 0 d 0 d Wed 4/5/23 Thu 4/6/23 Wed 4/5/23 Thu 4/6/23 Wed 4/5/23 Thu 4/6/23 48 Golden Gate 57 Video Detection Camera Installation 1 d 0 d 0 d Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 56SS+2 d Golden Gate 58 Install Portable Signal System 1 d 0 d 0 d Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 57 Golden Gate 59 Adjust and Modify Signals 1 d 0 d 0 d Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 58 Golden Gate 60 Temporary Channelization - Sta 13+95 to 43+63.00 9 d 0 d 0 d Wed 4/12/23 Mon 4/24/23 Wed 4/12/23 Mon 4/24/23 Wed 4/12/23 Mon 4/24/23 11/10 11/10 4/2 2/20 2/20 2/20 2/20 2/20 2/20 8/1 5/4 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 2028 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 1 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 48 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 61 Install Stage 1 Construction Channelization and Striping - South of Airport Way 0 d 0 d 0 d Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 Wed 4/12/23 57,59,58,56,53,48FF SPM 62 Install Stage 1 Construction Channelization and Striping - North of Airport Way 1 d 0 d 0 d Mon 4/24/23 Mon 4/24/23 Mon 4/24/23 Mon 4/24/23 Mon 4/24/23 Mon 4/24/23 61 SPM 63 Joint Utility Trench - Sta 15+25 to 42+85 242 d?0 d?0 d?Tue 3/28/23 Fri 3/29/24 Tue 3/28/23 Fri 3/29/24 Tue 3/28/23 Fri 3/29/24 64 JUT - Walgreens to Sansonia (Sections A, EE, AA) - Sta 15+25 to Sta 18+40 87 d 0 d 0 d Tue 3/28/23 Mon 7/31/23 Tue 3/28/23 Mon 7/31/23 Tue 3/28/23 Mon 7/31/23 65 Receive Vaults and Conduits from Utilities 10 d 0 d 0 d Tue 3/28/23 Mon 6/5/23 Tue 3/28/23 Mon 6/5/23 Tue 3/28/23 Mon 6/5/23 5,28 Utilities 66 Install Vaults 3.5 d 0 d 0 d Thu 5/11/23 Wed 6/7/23 Thu 5/11/23 Wed 6/7/23 Thu 5/11/23 Wed 6/7/23 65,74,42 Pivetta - JUT 67 Install Conduits 34 d 0 d 0 d Mon 6/12/23 Mon 7/31/23 Mon 6/12/23 Mon 7/31/23 Mon 6/12/23 Mon 7/31/23 66 Pivetta - JUT/Golden Gate/PSE - Gas 68 JUT - Night/Stage 2 - Hertz/Lyft to Taco Time - Sta 14+21.6 to 18+40 104 d 0 d 0 d Tue 3/28/23 Wed 8/23/23 Tue 3/28/23 Wed 8/23/23 Tue 3/28/23 Wed 8/23/23 69 Receive Vaults and Conduits from Utilities 6 d 0 d 0 d Tue 3/28/23 Tue 5/30/23 Tue 3/28/23 Tue 5/30/23 Tue 3/28/23 Tue 5/30/23 28 Utilities 70 Install Vaults 2 d 0 d 0 d Mon 7/31/23 Tue 8/1/23 Mon 7/31/23 Tue 8/1/23 Mon 7/31/23 Tue 8/1/23 69 71 Install Conduits 8 d 0 d 0 d Mon 8/14/23 Wed 8/23/23 Mon 8/14/23 Wed 8/23/23 Mon 8/14/23 Wed 8/23/23 75,70 Pivetta - JUT/Golden Gate/PSE - Gas 72 JUT - Night/Crossing - Watson Sec to Taco Time, Across 2nd St., Vacant to Metro PCS - Sta 18+40 to 20+10 108 d 0 d 0 d Tue 3/28/23 Tue 8/29/23 Tue 3/28/23 Tue 8/29/23 Tue 3/28/23 Tue 8/29/23 73 Receive Vaults and Conduits from Utilities 10 d 0 d 0 d Tue 3/28/23 Mon 6/5/23 Tue 3/28/23 Mon 6/5/23 Tue 3/28/23 Mon 6/5/23 28 Utilities 74 Install Vaults 12 d 0 d 0 d Tue 6/20/23 Fri 7/7/23 Tue 6/20/23 Fri 7/7/23 Tue 6/20/23 Fri 7/7/23 73,42 Pivetta - JUT 75 Install Conduits 21 d 0 d 0 d Tue 8/1/23 Tue 8/29/23 Tue 8/1/23 Tue 8/29/23 Tue 8/1/23 Tue 8/29/23 73,74,67 Pivetta - JUT/Golden Gate/PSE - Gas 76 JUT - Night/Stage 2 - Vacant to Formula 1 Fast Lube - Sta 20+10 to 25+20 114 d 0 d 0 d Tue 3/28/23 Thu 9/7/23 Tue 3/28/23 Thu 9/7/23 Tue 3/28/23 Thu 9/7/23 77 Remove/Relocate Bus Shelter - Sta 24+59.90 4 d 0 d 0 d Mon 6/12/23 Thu 6/15/23 Mon 6/12/23 Thu 6/15/23 Mon 6/12/23 Thu 6/15/23 5 Pivetta - JUT 78 Receive Vaults and Conduits from Utilities 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 79 Install Vaults 4 d 0 d 0 d Wed 8/30/23 Tue 9/5/23 Wed 8/30/23 Tue 9/5/23 Wed 8/30/23 Tue 9/5/23 78,77,70 80 Install Conduits 6 d 0 d 0 d Wed 8/30/23 Thu 9/7/23 Wed 8/30/23 Thu 9/7/23 Wed 8/30/23 Thu 9/7/23 79 Pivetta - JUT/Golden Gate/PSE - Gas 81 JUT - Big Island Poke to Watson Security (Sections B, C, F, D, R, K, M, JJ, DD, LL, E, G, H, Z) - Sta 19+00 to 24+80 153 d 0 d 0 d Tue 3/28/23 Fri 11/3/23 Tue 3/28/23 Fri 11/3/23 Tue 3/28/23 Fri 11/3/23 82 Receive Vaults and Conduits from Utilities 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 83 Install Vaults (J07 Installed Last with RFI-072)0 d 0 d 0 d Mon 5/15/23 Mon 7/17/23 Mon 5/15/23 Mon 7/17/23 Mon 5/15/23 Mon 7/17/23 82,65,79 Pivetta - JUT 84 Install Conduits 38 d 0 d 0 d Mon 9/11/23 Fri 11/3/23 Mon 9/11/23 Fri 11/3/23 Mon 9/11/23 Fri 11/3/23 85 Install Conduits 23 d 0 d 0 d Mon 9/11/23 Fri 11/3/23 Mon 9/11/23 Fri 11/3/23 Mon 9/11/23 Fri 11/3/23 82,83,298,67,71,80 Pivetta - JUT/Golden Gate/PSE - Gas 86 Contaminated Soils at STA 21+50 9 d 0 d 0 d Thu 9/28/23 Tue 10/10/23 Thu 9/28/23 Tue 10/10/23 Thu 9/28/23 Tue 10/10/23 85SS 87 JUT - Night/Power Crossting - Sta 23+80 3 d 0 d 0 d Mon 10/2/23 Wed 10/4/23 Mon 10/2/23 Wed 10/4/23 Mon 10/2/23 Wed 10/4/23 88 Install Conduits (Deleted Per FD)3 d 0 d 0 d Mon 10/2/23 Wed 10/4/23 Mon 10/2/23 Wed 10/4/23 Mon 10/2/23 Wed 10/4/23 Pivetta - JUT/Golden Gate/PSE - Gas 89 JUT - Victoria Street (CO-09)8 d 0 d 0 d Mon 11/20/23 Fri 12/1/23 Mon 11/20/23 Fri 12/1/23 Mon 11/20/23 Fri 12/1/23 90 Install Conduits 8 d 0 d 0 d Mon 11/20/23 Fri 12/1/23 Mon 11/20/23 Fri 12/1/23 Mon 11/20/23 Fri 12/1/23 95 91 JUT - Watson Security to Renton Ave. Ext (NO PSE Gas) - Sta 24+80 to 31+90 186 d?0 d?0 d?Tue 3/28/23 Fri 1/5/24 Tue 3/28/23 Fri 1/5/24 Tue 3/28/23 Fri 1/5/24 92 Receive Vaults and Conduits from Utilities 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 93 Install Vaults 12 d 0 d 0 d Tue 5/23/23 Tue 10/17/23 Tue 5/23/23 Tue 10/17/23 Tue 5/23/23 Tue 10/17/23 92,83,43 Pivetta - JUT 94 Install Conduits 9 d?0 d?0 d?Mon 11/6/23 Fri 1/5/24 Mon 11/6/23 Fri 11/17/23 Mon 11/6/23 Fri 1/5/24 93 Pivetta - JUT/Golden Gate/PSE - Gas 95 Watson Security to Hayes 4 d 0 d 0 d Mon 11/6/23 Fri 11/17/23 Mon 11/6/23 Fri 11/17/23 Mon 11/6/23 Fri 11/17/23 85 96 Hayes to Renton Ave 4 d 0 d 0 d Mon 12/4/23 Fri 1/5/24 Mon 12/4/23 Fri 1/5/24 Mon 12/4/23 Fri 1/5/24 95,90 97 Contaminated Soil @ STA 28+75 2 d 0 d 0 d Tue 12/12/23 Wed 12/13/23 Tue 12/12/23 Wed 12/13/23 Tue 12/12/23 Wed 12/13/23 96SS 98 JUT - Night/Power Crossing - Tobin St, Sta 28+75 and 30+28 4 d 0 d 0 d Wed 1/24/24 Mon 1/29/24 Wed 1/24/24 Mon 1/29/24 Wed 1/24/24 Mon 1/29/24 99 Install Conduits 4 d 0 d 0 d Wed 1/24/24 Mon 1/29/24 Wed 1/24/24 Mon 1/29/24 Wed 1/24/24 Mon 1/29/24 94,96,103 Pivetta - JUT/Golden Gate/PSE - Gas 100 JUT - Night/Crossing Renton Ave Ext - Sta 31+90 to 33+00 194 d 0 d 0 d Tue 3/28/23 Tue 1/23/24 Tue 3/28/23 Tue 1/23/24 Tue 3/28/23 Tue 1/23/24 101 Receive Vaults and Conduits from Utilities 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 102 Install Vaults 4 d 0 d 0 d Mon 10/2/23 Thu 10/5/23 Mon 10/2/23 Thu 10/5/23 Mon 10/2/23 Thu 10/5/23 101,62 Pivetta - JUT 103 Install Conduits 7 d 0 d 0 d Mon 1/8/24 Tue 1/23/24 Mon 1/8/24 Tue 1/23/24 Mon 1/8/24 Tue 1/23/24 101,102,96 Pivetta - JUT/Golden Gate/PSE - Gas 104 JUT - Arco to Gerber Collision- Section P, U, V, W (No PSE Gas) - Sta 33+00 to 42+85 242 d 0 d 0 d Tue 3/28/23 Fri 3/29/24 Tue 3/28/23 Fri 3/29/24 Tue 3/28/23 Fri 3/29/24 105 Receive Vaults and Conduits from Utilities 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 106 Install Vaults 17 d 0 d 0 d Wed 10/18/23 Fri 1/5/24 Wed 10/18/23 Fri 1/5/24 Wed 10/18/23 Fri 1/5/24 93,105,38 Pivetta - JUT 107 Install Conduits 25 d 0 d 0 d Wed 2/14/24 Fri 3/29/24 Wed 2/14/24 Fri 3/29/24 Wed 2/14/24 Fri 3/29/24 105,106,111 Pivetta - JUT/Golden Gate/PSE - Gas 108 JUT - Night/Crossings - Sta 33+77, 36+17, 40+43 206 d 0 d 0 d Tue 3/28/23 Thu 2/8/24 Tue 3/28/23 Thu 2/8/24 Tue 3/28/23 Thu 2/8/24 109 Receive Vaults and Conduits from Utility Owner 1 d 0 d 0 d Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 Tue 3/28/23 Wed 6/21/23 28 Utilities 110 Install Vaults 1 d 0 d 0 d Wed 10/18/23 Wed 10/18/23 Wed 10/18/23 Wed 10/18/23 Wed 10/18/23 Wed 10/18/23 106SS,102,109 Pivetta - JUT 111 Install Conduit 8 d 0 d 0 d Tue 1/30/24 Thu 2/8/24 Tue 1/30/24 Thu 2/8/24 Tue 1/30/24 Thu 2/8/24 110,99 Pivetta - JUT/Golden Gate/PSE - Gas 112 JUT - Utility Owner Work, Removals, Grounding/Bonding 15+25 to 42+85 197 d 32 d 32 d Mon 10/2/23 NA Mon 10/2/23 Tue 7/30/24 Mon 10/2/23 Fri 9/13/24 113 Lumen/CenturyLink to Begin Work South of Victoria Street 0 d 0 d 0 d Tue 1/23/24 Tue 1/23/24 Tue 1/23/24 Tue 1/23/24 Tue 1/23/24 Tue 1/23/24 94 114 PSE Gas - Install 1-6" Gas Line & Connections to Main JUT across Rainier (Ends at HH/II in SW Victoria) 28 d 0 d 0 d Mon 10/2/23 Thu 1/4/24 Mon 10/2/23 Thu 1/4/24 Mon 10/2/23 Thu 1/4/24 67SS PSE - Gas 115 Relocate Gas Line on Airport Way to Avoid Storm Drain 4 d 0 d 0 d Mon 1/8/24 Thu 1/11/24 Mon 1/8/24 Thu 1/11/24 Mon 1/8/24 Thu 1/11/24 116 Rem/Abandon Existing PSE Gas Main 60 d 81 d 81 d Mon 10/2/23 NA Mon 10/2/23 Fri 5/17/24 Mon 10/2/23 Fri 9/13/24 114SS PSE - Gas 117 PSE - Pull Wire (Power and Fiber) and Complete Connections 32 d 0 d 0 d NA NA Mon 4/1/24 Tue 5/14/24 Mon 4/1/24 Mon 8/19/24 110,107 Utilities 118 CO-21 Golden Gate Complete Business Connections - Execute CO and Order Materials 10 d 78 d 0 d NA NA Mon 4/1/24 Fri 4/12/24 Tue 7/23/24 Mon 8/5/24 107 119 CO-21 Golden Gate Complete Business Connections - Install 10 d 78 d 78 d NA NA Mon 4/15/24 Fri 4/26/24 Tue 8/6/24 Mon 8/19/24 118 4/12 7/17 1/23 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 2028 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 2 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 49 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 120 PSE - Install Transformers - V02A, V0X, V15A, V16A 30 d 30 d 30 d NA NA Mon 4/1/24 Fri 5/10/24 Mon 5/13/24 Tue 6/25/24 107 PSE - Electric 121 Complete PSE Swap Overs 30 d 0 d 0 d NA NA Mon 4/1/24 Fri 5/10/24 Mon 4/1/24 Fri 5/10/24 107 122 PSE Pole Removal and Installation - S. Tobin St. - Sta 501+51.37 (moved from JUT to conversion) 2 d 66 d 66 d NA NA Mon 5/13/24 Tue 5/14/24 Fri 8/16/24 Mon 8/19/24 121 PSE - Electric 123 Lumen/Centurylink - Pull Wire and Complete Connections Project Wide 54 d 0 d 0 d NA NA Mon 4/1/24 Fri 6/14/24 Mon 4/1/24 Mon 7/1/24 117SS,110,113,107 Centurylink 124 Complete Lumen Connections Tobin South 30 d 0 d 0 d NA NA Mon 4/1/24 Fri 5/10/24 Mon 4/1/24 Fri 5/10/24 107 125 Complete Lumen Connections Tobin North 24 d 10 d 0 d NA NA Mon 5/13/24 Fri 6/14/24 Tue 5/28/24 Mon 7/1/24 124 126 Comcast - Pull Wire and Complete Connections 30 d 0 d 0 d NA NA Mon 4/1/24 Fri 5/10/24 Mon 4/1/24 Fri 5/10/24 123SS,110,107 Comcast 127 Remove Existing Vaults, Pedestals, and Risers 54 d 0 d 0 d NA NA Mon 5/13/24 Tue 7/30/24 Mon 5/13/24 Tue 8/13/24 120SS,123SS,126SS Utilities 128 CO-24 Remove Existing JUT Tobin South 32 d 0 d 0 d NA NA Mon 5/13/24 Thu 6/27/24 Mon 5/13/24 Thu 6/27/24 124,121,126 129 CO-24 Remove Existing JUT Tobin North 30 d 10 d 10 d NA NA Mon 6/17/24 Tue 7/30/24 Tue 7/2/24 Tue 8/13/24 125 130 5G Small Cell Network Conduit System - Sta 14+65 to 41+55 23 d 0 d 0 d Mon 10/2/23 Wed 11/1/23 Mon 10/2/23 Wed 11/1/23 Mon 10/2/23 Wed 11/1/23 131 Trench and Conduit 21 d 0 d 0 d Mon 10/2/23 Mon 10/30/23 Mon 10/2/23 Mon 10/30/23 Mon 10/2/23 Mon 10/30/23 67SS,107 Golden Gate 132 Boxes 2 d 0 d 0 d Tue 10/31/23 Wed 11/1/23 Tue 10/31/23 Wed 11/1/23 Tue 10/31/23 Wed 11/1/23 131 Golden Gate 133 Water Line/Night - Sta 14+02 to 42+14.5 459 d 183 d 183 d Thu 3/30/23 NA Thu 3/30/23 Thu 2/20/25 Thu 3/30/23 Mon 11/10/25 134 Stage 1 Bypass, Cut and Cap 116 d 0 d 0 d Mon 4/17/23 Mon 10/2/23 Mon 4/17/23 Mon 10/2/23 Mon 4/17/23 Mon 10/2/23 135 Cut and Cap Existing Waterline - Sta 15+55 4 d 0 d 0 d Mon 4/17/23 Thu 4/20/23 Mon 4/17/23 Thu 4/20/23 Mon 4/17/23 Thu 4/20/23 42 Pivetta - Water/City of Renton Water 136 Cut and Cap Existing Waterline - Taco Time to Buddy's Home Furnishings - Sta 18+20 to 21+00 0 d 0 d 0 d Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 135,42 Pivetta - Water/City of Renton Water 137 Cut and Cap Existing Waterline - SW Victoria - Sta 25+00 (Deleted - Work Not Required)1 d 0 d 0 d Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Pivetta - Water/City of Renton Water 138 Cut and Cap Waterline - S. Tobin St. - Sta 28+60 (Deleted - Work Not Required)1 d 0 d 0 d Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Pivetta - Water/City of Renton Water 139 Water Line - Stage 1 - Sta 14+02.2 to 42+06.9 Rainier Ave, Sta 30+74.5 to 602+87.44 Airport Way 125 d 0 d 0 d Tue 5/2/23 Mon 10/30/23 Tue 5/2/23 Mon 10/30/23 Tue 5/2/23 Mon 10/30/23 140 Install Water Line and Appurtenances 28 d 0 d 0 d Tue 5/2/23 Mon 10/30/23 Tue 5/2/23 Mon 10/30/23 Tue 5/2/23 Mon 10/30/23 62,136 Pivetta - Water 141 FRPCS Concrete DMB (Deleted - Work Occurring with Water Line Install)15 d 0 d 0 d Mon 10/2/23 Fri 10/20/23 Mon 10/2/23 Fri 10/20/23 Mon 10/2/23 Fri 10/20/23 Pivetta - Water 142 Pressure Testing, Polypig, Disinfect Water Line 88 d 0 d 0 d Wed 6/21/23 Tue 10/24/23 Wed 6/21/23 Tue 10/24/23 Wed 6/21/23 Tue 10/24/23 140 Pivetta - Water 143 Install Water Line Services and Meters 0 d 0 d 0 d Thu 6/1/23 Thu 6/1/23 Thu 6/1/23 Thu 6/1/23 Thu 6/1/23 Thu 6/1/23 142 Pivetta - Water 144 Install Hydrants 8 d 0 d 0 d Thu 6/1/23 Wed 10/11/23 Thu 6/1/23 Wed 10/11/23 Thu 6/1/23 Wed 10/11/23 143 Pivetta - Water 145 Abandon/Remove Existing Water Line 2 d 0 d 0 d Thu 10/12/23 Fri 10/13/23 Thu 10/12/23 Fri 10/13/23 Thu 10/12/23 Fri 10/13/23 144 Pivetta - Water 146 Water Line - Crossing - Taco Time to S. 2nd St. - Sta 18+49.0 & 18+49.0 to 19+31.9 219 d 0 d 0 d Thu 3/30/23 Thu 2/29/24 Thu 3/30/23 Thu 2/29/24 Thu 3/30/23 Thu 2/29/24 147 Install Water Line and Appurtenances 2 d 0 d 0 d Thu 5/11/23 Tue 5/23/23 Thu 5/11/23 Tue 5/23/23 Thu 5/11/23 Tue 5/23/23 140SS+5 d Pivetta - Water 148 Cathodic Protection Submittal (Submittal #81, RAM 055)0 d 0 d 0 d Thu 3/30/23 Thu 3/30/23 Thu 3/30/23 Thu 3/30/23 Thu 3/30/23 Thu 3/30/23 149 Test Station Changes (PCO-019 for RFI-70 and RFI-085 Changes)10 d 0 d 0 d Thu 7/13/23 Fri 10/13/23 Thu 7/13/23 Fri 10/13/23 Thu 7/13/23 Fri 10/13/23 150 Procure Cathodic Protection 13 d 0 d 0 d Mon 10/16/23 Wed 11/1/23 Mon 10/16/23 Wed 11/1/23 Mon 10/16/23 Wed 11/1/23 148,149 151 Install Cathodic Protection over SPU Lines 4 d 0 d 0 d Mon 2/26/24 Thu 2/29/24 Mon 2/26/24 Thu 2/29/24 Mon 2/26/24 Thu 2/29/24 147,150 Pivetta - Water 152 Stage 2, Bypass, Cut and Cap 125 d 0 d 0 d Mon 4/17/23 Fri 10/13/23 Mon 4/17/23 Fri 10/13/23 Mon 4/17/23 Fri 10/13/23 153 Install Water Bypass - Hertz/Lyft to Wendy's - Sta 15+55 to 16+40 (Performed with Stage 1)0 d 0 d 0 d Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 Mon 4/17/23 143,147,145 Pivetta - Water 154 Install Water Bypass - Taco Time - Sta 18+25 to 18+50 (Deleted - Work Not Required)1 d 0 d 0 d Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Pivetta - Water 155 Install Water Bypass - Buddy's Home Furnishing to Royal Orchid - Sta 21+00 to 24+80 5 d 0 d 0 d Thu 10/5/23 Wed 10/11/23 Thu 10/5/23 Wed 10/11/23 Thu 10/5/23 Wed 10/11/23 143 Pivetta - Water 156 Cut and Cap - Chevron to S. Tobin Crossing - Sta 28+75 (Not Required)1 d 0 d 0 d Thu 10/12/23 Thu 10/12/23 Thu 10/12/23 Thu 10/12/23 Thu 10/12/23 Thu 10/12/23 155 Pivetta - Water 157 Cut and Cap Existing Water Line - McDonalds to Arco - Sta 30+60 to 34+10 (Not Required)1 d 0 d 0 d Fri 10/13/23 Fri 10/13/23 Fri 10/13/23 Fri 10/13/23 Fri 10/13/23 Fri 10/13/23 156 Pivetta - Water 158 Water Line - Stage 2 - S. 3rd St. - Sta 203+40 to NW 3rd Pl - Sta 699+16.40 77 d 0 d 0 d Mon 10/16/23 Thu 2/22/24 Mon 10/16/23 Thu 2/22/24 Mon 10/16/23 Thu 2/22/24 159 Install Water Line and Appurtenances 28.87 d 0 d 0 d Mon 10/16/23 Wed 1/24/24 Mon 10/16/23 Wed 1/24/24 Mon 10/16/23 Wed 1/24/24 157,153 Pivetta - Water 160 FRPCS Concrete DMB 47 d 0 d 0 d Thu 11/2/23 Wed 1/24/24 Thu 11/2/23 Wed 1/24/24 Thu 11/2/23 Wed 1/24/24 159 Pivetta - Water 161 Install Polypig Station 46 d 0 d 0 d Thu 11/2/23 Wed 1/24/24 Thu 11/2/23 Wed 1/24/24 Thu 11/2/23 Wed 1/24/24 160 Pivetta - Water 162 Pressure Testing, Polypig, Disinfect Water Line 21 d 0 d 0 d Wed 1/17/24 Thu 2/22/24 Wed 1/17/24 Thu 2/22/24 Wed 1/17/24 Thu 2/22/24 161 Pivetta - Water 163 Install Water Line Services and Meters 0 d 0 d 0 d Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 162 Pivetta - Water 164 Install Hydrants 0 d 0 d 0 d Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 163 Pivetta - Water 165 Abandon/Remove Existing Water Line 30 d 0 d 0 d Mon 10/16/23 Thu 11/30/23 Mon 10/16/23 Thu 11/30/23 Mon 10/16/23 Thu 11/30/23 164 Pivetta - Water 166 Stage 3 Bypass, Cut and Cap 3 d 399 d 399 d NA NA Mon 4/1/24 Wed 4/3/24 Thu 11/6/25 Mon 11/10/25 167 Cut and Cap - Formula 1 Fast Lube to S. Tobin St. - Sta 25+65 to 28+65 (DELETED)3 d 399 d 399 d NA NA Mon 4/1/24 Wed 4/3/24 Thu 11/6/25 Mon 11/10/25 Pivetta - Water/City of Renton Water 168 Water Line - Stage 3 - S. Tobin St. - Sta 28+58.6 to 28+61.6 (Performing with Stage 2)63 d 0 d 0 d Mon 11/6/23 Thu 2/22/24 Mon 11/6/23 Thu 2/22/24 Mon 11/6/23 Thu 2/22/24 169 Install Water Line and Appurtenances 4 d 0 d 0 d Mon 11/6/23 Thu 11/9/23 Mon 11/6/23 Thu 11/9/23 Mon 11/6/23 Thu 11/9/23 44 Pivetta - Water 170 Pressure Testing, Polypig, Disinfect Water Line 22 d 0 d 0 d Wed 1/17/24 Thu 2/22/24 Wed 1/17/24 Thu 2/22/24 Wed 1/17/24 Thu 2/22/24 169 Pivetta - Water 171 Install Water Line Services and Meters 4 d 0 d 0 d Mon 1/8/24 Wed 1/24/24 Mon 1/8/24 Wed 1/24/24 Mon 1/8/24 Wed 1/24/24 170 Pivetta - Water 172 Install Hydrants 0 d 0 d 0 d Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 Mon 1/8/24 171 Pivetta - Water 173 Abandon/Remove Existing Water Line and Bypass 30 d 0 d 0 d Tue 1/9/24 Thu 2/22/24 Tue 1/9/24 Thu 2/22/24 Tue 1/9/24 Thu 2/22/24 172 Pivetta - Water 174 Install Hydrants in Conflict 168 d 69 d 69 d NA NA Wed 6/12/24 Thu 2/20/25 Tue 12/3/24 Thu 5/29/25 175 Hydrant at Walgreens (STA 16+54) - Sewer Conflict (RFI078)1 d 118 d 48 d NA NA Wed 6/12/24 Wed 6/12/24 Tue 12/3/24 Tue 12/3/24 185 176 Hydrant at NE corner of Rainier & S 2nd St - Reinstall (RFI139) - after JUT removal 1 d 203 d 202 d NA NA Wed 7/31/24 Wed 7/31/24 Thu 5/29/25 Thu 5/29/25 127 177 Blow Off at Gene Meyer (STA 20+25) - JUT/Storm Conflict/Sequence 1 d 85 d 15 d NA NA Wed 7/31/24 Wed 7/31/24 Tue 12/3/24 Tue 12/3/24 127,208 4/17 6/1 3/30 4/17 1/8 1/8 1/8 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 2028 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 3 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 50 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 178 Hydrant at Autozone (STA 21+73) - JUT Conflict 1 d 85 d 15 d NA NA Wed 7/31/24 Wed 7/31/24 Tue 12/3/24 Tue 12/3/24 127 179 Hydrant at Watson (STA 24+24) - JUT Conflict 1 d 85 d 15 d NA NA Wed 7/31/24 Wed 7/31/24 Tue 12/3/24 Tue 12/3/24 127 180 Hydrant at Tommy's Café (STA 26+27.5) - adjust length after stg 1 chan 1 d 69 d 68 d NA NA Thu 2/20/25 Thu 2/20/25 Thu 5/29/25 Thu 5/29/25 374 181 Sewer - Sta 15+49.20 to 42+77.80 117 d 97 d 97 d Tue 1/30/24 NA Tue 1/30/24 Mon 7/15/24 Tue 1/30/24 Tue 12/3/24 182 L035 - PCO033 Sewer Bypass (sent 1/30/24) - Response/Resolution 0 d 44 d 44 d Tue 1/30/24 NA Tue 1/30/24 Mon 4/1/24 Tue 1/30/24 Mon 6/3/24 183 Sewer - Night (Walgreens to Sansonina) - Sta 15+49.20 to 18+26.81 7 d 0 d 0 d NA NA Mon 6/3/24 Tue 6/11/24 Mon 6/3/24 Tue 6/11/24 184 Remove/Replace Manholes and Install Sewer 5 d 0 d 0 d NA NA Mon 6/3/24 Fri 6/7/24 Mon 6/3/24 Fri 6/7/24 145,39,107,182,128SS+14 d Pivetta - Sewer 185 Install New Side Sewer 2 d 0 d 0 d NA NA Mon 6/10/24 Tue 6/11/24 Mon 6/10/24 Tue 6/11/24 184 Pivetta - Sewer 186 Sewer (Big Island Poke to Hayes Pl SW) - Sta 19+63.58 to 25+43.57 5 d 0 d 0 d NA NA Wed 6/12/24 Tue 6/18/24 Wed 6/12/24 Tue 6/18/24 187 Remove/Replace Manholes 5 d 0 d 0 d NA NA Wed 6/12/24 Tue 6/18/24 Wed 6/12/24 Tue 6/18/24 185 Pivetta - Sewer 188 S. 2nd St. - Sta 19+64.16 3 d 0 d 0 d NA NA Thu 6/20/24 Mon 6/24/24 Thu 6/20/24 Mon 6/24/24 189 Install Sewer and Manholes 3 d 0 d 0 d NA NA Thu 6/20/24 Mon 6/24/24 Thu 6/20/24 Mon 6/24/24 187 Pivetta - Sewer 190 Sewer (Chevron to Advance Auto Tune) - Sta 28+55.98 to 42+77.80 10 d 70 d 70 d NA NA Tue 6/25/24 Tue 7/9/24 Thu 10/3/24 Wed 10/16/24 191 Remove/Replace/Install Manholes 7 d 70 d 0 d NA NA Tue 6/25/24 Wed 7/3/24 Thu 10/3/24 Fri 10/11/24 189 Pivetta - Sewer 192 Install Sewer 3 d 70 d 0 d NA NA Fri 7/5/24 Tue 7/9/24 Mon 10/14/24 Wed 10/16/24 191 Pivetta - Sewer 193 Sewer - Night/Side Street - SW Victoria - Sta 24+91.19 1 d 70 d 70 d NA NA Wed 7/10/24 Wed 7/10/24 Thu 10/17/24 Thu 10/17/24 194 Remove/Replace Manholes 1 d 70 d 0 d NA NA Wed 7/10/24 Wed 7/10/24 Thu 10/17/24 Thu 10/17/24 192 Pivetta - Sewer 195 Sewer - Night/Side Street - Hayes Pl SW - Sta 25+43.57 1 d 70 d 70 d NA NA Thu 7/11/24 Thu 7/11/24 Fri 10/18/24 Fri 10/18/24 196 Remove/Replace/Install Manholes 1 d 70 d 0 d NA NA Thu 7/11/24 Thu 7/11/24 Fri 10/18/24 Fri 10/18/24 194 Pivetta - Sewer 197 Sewer - Night/Renton Ave Ext - Sta 32+81.14 to 31+60.06 2 d 70 d 70 d NA NA Fri 7/12/24 Mon 7/15/24 Mon 10/21/24 Tue 12/3/24 198 Remove/Replace/Install Manholes 1 d 70 d 0 d NA NA Fri 7/12/24 Fri 7/12/24 Mon 10/21/24 Mon 10/21/24 196 Pivetta - Sewer 199 Install Sewer 1 d 97 d 27 d NA NA Mon 7/15/24 Mon 7/15/24 Tue 12/3/24 Tue 12/3/24 198 Pivetta - Sewer 200 Install CIPP Lining 28 d 70 d 70 d NA NA Mon 7/15/24 Wed 8/21/24 Tue 10/22/24 Tue 12/3/24 201 Install CIPP Lining (Big Island Poke to Hayes Pl SW) - Sta 19+63.58 to 25+43.57 4 d 70 d 0 d NA NA Mon 7/15/24 Thu 7/18/24 Tue 10/22/24 Fri 10/25/24 37,198 Insituform 202 Install CIPP Lining (Chevron to Advance Auto Tune) - Sta 28+55.98 to 42+77.80 9 d 70 d 0 d NA NA Fri 7/19/24 Wed 7/31/24 Mon 10/28/24 Thu 11/7/24 201,191 Insituform 203 Install CIPP Lining (SW Victoria) - Sta 24+91.19 5 d 70 d 0 d NA NA Thu 8/1/24 Wed 8/7/24 Fri 11/8/24 Fri 11/15/24 202,194 Insituform 204 Install CIPP Lining (Hayes Pl SW) - Sta 25+43.57 5 d 70 d 0 d NA NA Thu 8/8/24 Wed 8/14/24 Mon 11/18/24 Fri 11/22/24 203,196 Insituform 205 Install CIPP Lining (Renton Ave Ext) - Sta 32+81.14 to 31+60.06 5 d 70 d 0 d NA NA Thu 8/15/24 Wed 8/21/24 Mon 11/25/24 Tue 12/3/24 198,204 Insituform 206 Storm Drainage - Sta 15+11.89 to 41+02.35 57 d 0 d 0 d NA NA Tue 6/25/24 Fri 9/13/24 Tue 6/25/24 Mon 11/10/25 207 Storm Drainage (Walgreens to Sansonina) - Sta 15+11.89 to 17+63.75 12 d 0 d 0 d NA NA Tue 6/25/24 Thu 7/11/24 Tue 6/25/24 Thu 7/11/24 208 Install Drainage and Catch Basins 10 d 0 d 0 d NA NA Tue 6/25/24 Tue 7/9/24 Tue 6/25/24 Tue 7/9/24 189 Pivetta - Storm 209 Storm Drainage - Night/Crossing - Sta 16+05.52 2 d 0 d 0 d NA NA Wed 7/10/24 Thu 7/11/24 Wed 7/10/24 Thu 7/11/24 210 Install Drainage and Catch Basins 2 d 0 d 0 d NA NA Wed 7/10/24 Thu 7/11/24 Wed 7/10/24 Thu 7/11/24 208 Pivetta - Storm 211 Storm Drainage (Big Island Poke to Watson Security) - Sta 18+54.92 to 23+32.67 24 d 0 d 0 d NA NA Fri 7/12/24 Wed 8/14/24 Fri 7/12/24 Mon 11/10/25 212 Install Drainage and Catch Basins 13 d 0 d 0 d NA NA Fri 7/12/24 Tue 7/30/24 Fri 7/12/24 Tue 7/30/24 210 Pivetta - Storm 213 Storm Drainage - S. 2nd St. - Night/Crossings, Stage 2 and 3 Work - Sta 19+07.53 to 22+07.86 11 d 0 d 0 d NA NA Wed 7/31/24 Wed 8/14/24 Wed 7/31/24 Mon 11/10/25 214 Install Drainage and Catch Basins 10 d 0 d 0 d NA NA Wed 7/31/24 Tue 8/13/24 Wed 7/31/24 Tue 8/13/24 210,212 Pivetta - Storm 215 Install Filterra Unit 1 d 307 d 307 d NA NA Wed 8/14/24 Wed 8/14/24 Mon 11/10/25 Mon 11/10/25 214 Pivetta - Storm 216 Storm Drainage - SW Victoria St. to Brown Bear Car Wash- Night/Crossing - Sta 24+70.79 to 26+65.08 8 d 0 d 0 d NA NA Wed 8/14/24 Fri 8/23/24 Wed 8/14/24 Fri 8/23/24 217 Install Drainage and Catch Basins 8 d 0 d 0 d NA NA Wed 8/14/24 Fri 8/23/24 Wed 8/14/24 Fri 8/23/24 214,127 Pivetta - Storm 218 Storm Drainage Brown Bear to Renton Laundry - Sta 26+65.08 to 35+53.35 29 d 14 d 14 d NA NA Wed 7/31/24 Tue 9/10/24 Tue 8/20/24 Mon 9/22/25 219 Install Drainage and Catch Basins 11 d 14 d 0 d NA NA Wed 7/31/24 Wed 8/14/24 Tue 8/20/24 Wed 9/4/24 212,114,117,120,123,126 Pivetta - Storm 220 Install Filterra Units 3 d 269 d 0 d NA NA Thu 8/15/24 Mon 8/19/24 Thu 9/18/25 Mon 9/22/25 219 Pivetta - Storm 221 Storm Drainage - Renton Ave Ext - Night/Crossing - Sta 31+39.02 to 33+02.08 11 d 0 d 0 d NA NA Mon 8/26/24 Tue 9/10/24 Mon 8/26/24 Tue 9/10/24 222 Install Drainage and Catch Basins 11 d 0 d 0 d NA NA Mon 8/26/24 Tue 9/10/24 Mon 8/26/24 Tue 9/10/24 217,114,117,120,123,126 Pivetta - Storm 223 Storm Drainage Mathewson's Automotive to Judo Boxing - Sta 37+84.90 to 41+02.35 4 d 14 d 14 d NA NA Thu 8/15/24 Tue 8/20/24 Thu 9/5/24 Tue 9/10/24 224 Install Drainage and Catch Basins 4 d 14 d 14 d NA NA Thu 8/15/24 Tue 8/20/24 Thu 9/5/24 Tue 9/10/24 219 Pivetta - Storm 225 Storm Drainage - NW 3rd Pl - Night/Crossing - Sta 40+68.75 to 41+02.35 3 d 0 d 0 d NA NA Wed 9/11/24 Fri 9/13/24 Wed 9/11/24 Fri 9/13/24 226 Install Drainage and Catch Basins 3 d 0 d 0 d NA NA Wed 9/11/24 Fri 9/13/24 Wed 9/11/24 Fri 9/13/24 224,222,132,129FF Pivetta - Storm 227 Decorative Illumination System - Sta 14+89 to 41+55 167 d 0 d 0 d NA NA Mon 4/1/24 Tue 11/26/24 Thu 6/13/24 Tue 11/26/24 228 Below Grade 42 d 52 d 52 d NA NA Mon 4/1/24 Wed 5/29/24 Thu 6/13/24 Fri 9/13/24 229 Trench and Conduit 23 d 52 d 0 d NA NA Mon 4/1/24 Wed 5/1/24 Thu 6/13/24 Wed 7/17/24 Golden Gate 230 Foundations 24 d 74 d 0 d NA NA Mon 4/1/24 Thu 5/2/24 Wed 7/17/24 Mon 8/19/24 61,229SS Golden Gate 231 Junction Boxes 18 d 74 d 0 d NA NA Fri 5/3/24 Wed 5/29/24 Tue 8/20/24 Fri 9/13/24 230,110 Golden Gate 232 Service Installation 10 d 98 d 98 d NA NA Fri 5/17/24 Fri 5/31/24 Tue 10/8/24 Mon 10/21/24 231SS+10 d Golden Gate/PSE - Electric 233 Above Ground 162 d 0 d 0 d NA NA Mon 4/8/24 Tue 11/26/24 Thu 8/22/24 Tue 11/26/24 234 Install Lighting Wiring 20 d 0 d 0 d NA NA Tue 10/22/24 Tue 11/19/24 Tue 10/22/24 Tue 11/19/24 231,232,345 Golden Gate 235 Set Poles 62 d 95 d 95 d NA NA Mon 4/8/24 Fri 7/5/24 Thu 8/22/24 Tue 11/19/24 230SS+5 d Golden Gate 236 Test and Turn On 2 d 0 d 0 d NA NA Wed 11/20/24 Thu 11/21/24 Wed 11/20/24 Thu 11/21/24 235,234 Golden Gate 237 Remove and Salvage Old Poles&Wiring 3 d 0 d 0 d NA NA Fri 11/22/24 Tue 11/26/24 Fri 11/22/24 Tue 11/26/24 236 Golden Gate 4/1 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 2028 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 4 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 51 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 238 Signalization - Sta 14+10 to 40+40 192 d 52 d 52 d NA NA Thu 5/2/24 Thu 2/13/25 Thu 7/18/24 Mon 11/10/25 239 Traffic Signal Rainier & SW Sunset - Sta 14+10 157 d 0 d 0 d NA NA Thu 5/2/24 Tue 12/17/24 Thu 7/18/24 Tue 12/17/24 240 Below Grade 8 d 52 d 52 d NA NA Thu 5/2/24 Mon 5/13/24 Thu 7/18/24 Tue 12/3/24 241 Conduit Underground 5 d 52 d 0 d NA NA Thu 5/2/24 Wed 5/8/24 Thu 7/18/24 Wed 7/24/24 229 Golden Gate 242 Foundations - before C&G 3 d 143 d 0 d NA NA Fri 5/3/24 Tue 5/7/24 Wed 11/27/24 Tue 12/3/24 230 Golden Gate 243 Road Crossings 3 d 52 d 0 d NA NA Thu 5/9/24 Mon 5/13/24 Thu 7/25/24 Mon 7/29/24 241 Golden Gate 244 Service Installation 1 d 0 d 0 d NA NA Tue 12/3/24 Tue 12/3/24 Tue 12/3/24 Tue 12/3/24 246 Golden Gate/PSE - Electric 245 Above Ground 13 d 0 d 0 d NA NA Wed 11/27/24 Tue 12/17/24 Wed 11/27/24 Tue 12/17/24 246 Install Boxes - after C&G/Sidewalks 2 d 0 d 0 d NA NA Wed 11/27/24 Mon 12/2/24 Wed 11/27/24 Mon 12/2/24 243,237 Golden Gate 247 Pull Cable 2 d 0 d 0 d NA NA Wed 12/4/24 Thu 12/5/24 Wed 12/4/24 Thu 12/5/24 244 Golden Gate 248 Build Traffic Signal System 8 d 0 d 0 d NA NA Fri 12/6/24 Tue 12/17/24 Fri 12/6/24 Tue 12/17/24 247,242 Golden Gate 249 Traffic Signal Rainier & 2nd Street 163 d 0 d 0 d NA NA Wed 5/8/24 Wed 1/8/25 Tue 7/30/24 Wed 1/8/25 250 Below Grade 14 d 56 d 56 d NA NA Wed 5/8/24 Tue 5/28/24 Tue 7/30/24 Thu 12/19/24 251 Foundations 3 d 152 d 0 d NA NA Wed 5/8/24 Fri 5/10/24 Tue 12/17/24 Thu 12/19/24 242 Golden Gate 252 Conduit Underground 5 d 52 d 0 d NA NA Tue 5/14/24 Mon 5/20/24 Tue 7/30/24 Mon 8/5/24 243 Golden Gate 253 Road Crossings 3 d 52 d 0 d NA NA Tue 5/21/24 Thu 5/23/24 Tue 8/6/24 Thu 8/8/24 252 Golden Gate 254 Install Boxes 2 d 52 d 0 d NA NA Fri 5/24/24 Tue 5/28/24 Fri 8/9/24 Mon 8/12/24 253 Golden Gate 255 Service Installation 1 d 138 d 138 d NA NA Wed 5/29/24 Wed 5/29/24 Tue 12/17/24 Tue 12/17/24 254 Golden Gate/PSE - Electric 256 Above Ground 10 d 0 d 0 d NA NA Wed 12/18/24 Wed 1/8/25 Wed 12/18/24 Wed 1/8/25 257 Pull Cable 2 d 0 d 0 d NA NA Wed 12/18/24 Thu 12/19/24 Wed 12/18/24 Thu 12/19/24 248,255 Golden Gate 258 Build Traffic Signal System 8 d 0 d 0 d NA NA Fri 12/20/24 Wed 1/8/25 Fri 12/20/24 Wed 1/8/25 257 Golden Gate 259 Pedestrian Signal Rainier& SW Victoria 179 d 63 d 63 d NA NA Mon 5/13/24 Wed 2/5/25 Tue 8/13/24 Fri 10/31/25 260 Below Grade 15 d 63 d 63 d NA NA Mon 5/13/24 Mon 6/3/24 Tue 8/13/24 Fri 12/20/24 261 Foundations 1 d 152 d 0 d NA NA Mon 5/13/24 Mon 5/13/24 Fri 12/20/24 Fri 12/20/24 251 Golden Gate 262 Conduit Underground 2 d 52 d 0 d NA NA Wed 5/29/24 Thu 5/30/24 Tue 8/13/24 Wed 8/14/24 254 Golden Gate 263 Road Crossings 1 d 52 d 0 d NA NA Fri 5/31/24 Fri 5/31/24 Thu 8/15/24 Thu 8/15/24 262 Golden Gate 264 Install Boxes 1 d 52 d 0 d NA NA Mon 6/3/24 Mon 6/3/24 Fri 8/16/24 Fri 8/16/24 263 Golden Gate 265 Service Installation 1 d 344 d 157 d NA NA Tue 6/4/24 Tue 6/4/24 Thu 10/23/25 Thu 10/23/25 264 Golden Gate/PSE - Electric 266 Above Ground 6 d 187 d 187 d NA NA Wed 1/29/25 Wed 2/5/25 Fri 10/24/25 Fri 10/31/25 267 Pull cable 2 d 187 d 0 d NA NA Wed 1/29/25 Thu 1/30/25 Fri 10/24/25 Mon 10/27/25 258,265,278 Golden Gate 268 Build Traffic Signal System 4 d 187 d 0 d NA NA Fri 1/31/25 Wed 2/5/25 Tue 10/28/25 Fri 10/31/25 267,251 Golden Gate 269 Traffic Signal Rainier& Renton Ave Ext 172 d 0 d 0 d NA NA Tue 5/14/24 Tue 1/28/25 Mon 8/19/24 Tue 1/28/25 270 Below Grade 27 d 66 d 66 d NA NA Tue 5/14/24 Fri 6/21/24 Mon 8/19/24 Mon 1/13/25 271 Foundations 10 d 152 d 0 d NA NA Tue 5/14/24 Tue 5/28/24 Mon 12/23/24 Mon 1/13/25 261 Golden Gate 272 Conduit Underground 8 d 52 d 0 d NA NA Tue 6/4/24 Thu 6/13/24 Mon 8/19/24 Wed 8/28/24 264 Golden Gate 273 Road Crossings 3 d 52 d 0 d NA NA Fri 6/14/24 Tue 6/18/24 Thu 8/29/24 Tue 9/3/24 272 Golden Gate 274 Install Boxes 2 d 52 d 0 d NA NA Thu 6/20/24 Fri 6/21/24 Wed 9/4/24 Thu 9/5/24 273 Golden Gate 275 Service Installation 1 d 131 d 131 d NA NA Mon 6/24/24 Mon 6/24/24 Wed 1/8/25 Wed 1/8/25 274 Golden Gate/PSE - Electric 276 Above Ground 13 d 0 d 0 d NA NA Thu 1/9/25 Tue 1/28/25 Thu 1/9/25 Tue 1/28/25 277 Pull Cable 3 d 0 d 0 d NA NA Thu 1/9/25 Mon 1/13/25 Thu 1/9/25 Mon 1/13/25 275,258 Golden Gate 278 Build Traffic Signal System 10 d 0 d 0 d NA NA Tue 1/14/25 Tue 1/28/25 Tue 1/14/25 Tue 1/28/25 277,261,271 Golden Gate 279 Pedestrian Signal Rainier& 3rd Pl 174 d 69 d 69 d NA NA Wed 5/29/24 Thu 2/13/25 Fri 9/6/24 Mon 11/10/25 280 Below Grade 23 d 69 d 69 d NA NA Wed 5/29/24 Mon 7/1/24 Fri 9/6/24 Mon 11/3/25 281 Foundations 1 d 355 d 168 d NA NA Wed 5/29/24 Wed 5/29/24 Mon 11/3/25 Mon 11/3/25 271 Golden Gate 282 Conduit Underground 3 d 52 d 0 d NA NA Mon 6/24/24 Wed 6/26/24 Fri 9/6/24 Tue 9/10/24 274 Golden Gate 283 Road Crossings 2 d 52 d 0 d NA NA Thu 6/27/24 Fri 6/28/24 Wed 9/11/24 Thu 9/12/24 282 Golden Gate 284 Install Boxes 1 d 52 d 0 d NA NA Mon 7/1/24 Mon 7/1/24 Fri 9/13/24 Fri 9/13/24 283 Golden Gate 285 Service Installation 1 d 331 d 144 d NA NA Tue 7/2/24 Tue 7/2/24 Fri 10/31/25 Fri 10/31/25 284 Golden Gate/PSE - Electric 286 Above Ground 6 d 187 d 187 d NA NA Thu 2/6/25 Thu 2/13/25 Mon 11/3/25 Mon 11/10/25 287 Pull Cable 1 d 187 d 0 d NA NA Thu 2/6/25 Thu 2/6/25 Mon 11/3/25 Mon 11/3/25 285,268 Golden Gate 288 Build Traffic Signal System 5 d 187 d 187 d NA NA Fri 2/7/25 Thu 2/13/25 Tue 11/4/25 Mon 11/10/25 281,287 Golden Gate 289 Walls - Sta 15+50.95 to 799+17.37 231 d 284 d 284 d Mon 10/2/23 NA Mon 10/2/23 Tue 9/17/24 Mon 10/2/23 Mon 11/10/25 290 Wall 1 - Modular Block FW - Sta 15+50.95 to 16+21.24 (Wall Sta 0+00 to 1+18)25 d 91 d 91 d NA NA Mon 4/8/24 Fri 5/10/24 Fri 8/16/24 Thu 11/6/25 291 Constuct Modular Block Fill Wall - Wall 1 15 d 91 d 0 d NA NA Mon 4/8/24 Fri 4/26/24 Fri 8/16/24 Fri 9/6/24 230SS+5 d Key West 292 FRPCS Thickened Edge Sidewalk 5 d 370 d 0 d NA NA Mon 4/29/24 Fri 5/3/24 Fri 10/24/25 Thu 10/30/25 291 WCCI 293 Install Pedestrian Railing 5 d 370 d 16 d NA NA Mon 5/6/24 Fri 5/10/24 Fri 10/31/25 Thu 11/6/25 292 WCCI 294 Wall 2 - Modular Block FW - Sta 17+08.50 to 17+23.95 (Wall Sta 0+00 to 0+59)10 d 91 d 91 d NA NA Mon 4/29/24 Fri 5/10/24 Mon 9/9/24 Mon 11/10/25 295 Construct Modular Block Fill Wall - Wall 2 5 d 91 d 0 d NA NA Mon 4/29/24 Fri 5/3/24 Mon 9/9/24 Fri 9/13/24 291 Key West 296 FRPCS Thickened Edge Sidewalk 5 d 372 d 372 d NA NA Mon 5/6/24 Fri 5/10/24 Tue 11/4/25 Mon 11/10/25 295,292SS WCCI 297 Wall 5 - CCFW & CIP Fill Wall - Sta 399+50.72 to 399+39.01 (Wall Sta 0+00 to 0+35)161 d 354 d 354 d Mon 10/2/23 NA Mon 10/2/23 Thu 6/6/24 Mon 10/2/23 Mon 11/10/25 298 Demolish Existing Wall 5 - Sta 0+10 to 0+21.70 2 d 0 d 0 d Mon 10/2/23 Tue 10/3/23 Mon 10/2/23 Tue 10/3/23 Mon 10/2/23 Tue 10/3/23 83 Pivetta 299 Construct CIP Fill Wall - Wall 5 15 d 75 d 0 d NA NA Tue 4/23/24 Mon 5/13/24 Fri 8/9/24 Thu 8/29/24 230SS+16 d,298 WCCI H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 2028 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 5 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 52 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 300 Construct Cement Concrete Fill Wall - Wall 5 10 d 75 d 0 d NA NA Tue 5/14/24 Tue 5/28/24 Fri 8/30/24 Fri 9/13/24 230,299 WCCI 301 Construct WSDOT Std 4"Thick Gutter - Wall 5 5 d 354 d 0 d NA NA Wed 5/29/24 Tue 6/4/24 Fri 10/31/25 Thu 11/6/25 300 WCCI 302 Install Pedestrian Railing - Sta 0+10 to 0+35 - Wall 5 2 d 354 d 354 d NA NA Wed 6/5/24 Thu 6/6/24 Fri 11/7/25 Mon 11/10/25 293,301 WCCI 303 Wall 6 - Rock Wall - Sta 799+42.45 to 799+17.37 (Wall Sta 0+00 to 0+19.29)5 d 111 d 111 d NA NA Mon 4/1/24 Fri 4/5/24 Mon 9/9/24 Fri 9/13/24 304 Excavate/Construct/Backfill Rock Wall - Wall 6 5 d 111 d 111 d NA NA Mon 4/1/24 Fri 4/5/24 Mon 9/9/24 Fri 9/13/24 94 Pivetta - Earthwork 305 Gateway Wall A - Sta 33+59.15 to 599+37.00 20 d 269 d 269 d NA NA Tue 8/20/24 Tue 9/17/24 Tue 9/23/25 Mon 10/20/25 306 Construct Gateway Wall A - Renton Ave. Ext.15 d 269 d 0 d NA NA Tue 8/20/24 Tue 9/10/24 Tue 9/23/25 Mon 10/13/25 220,299 WCCI 307 Install Decorative Cutouts and Skate Deterrent Gateway Wall A - Renton Ave. Ext. 5 d 269 d 266 d NA NA Wed 9/11/24 Tue 9/17/24 Tue 10/14/25 Mon 10/20/25 306 WCCI 308 Curb and Gutter - Sta 14+30.99 to 42+80.28 25 d 70 d 70 d NA NA Thu 8/22/24 Thu 9/26/24 Wed 12/4/24 Mon 11/10/25 309 Curb and Gutter - Walgreens to Big Island Poke - Sta 14+30.99 to 19+12.69 2 d 70 d 70 d NA NA Thu 8/22/24 Fri 8/23/24 Wed 12/4/24 Mon 11/10/25 205,284 310 Grade/Prep Base/Place CSBC 1 d 70 d 0 d NA NA Thu 8/22/24 Thu 8/22/24 Wed 12/4/24 Wed 12/4/24 208,242,165,52,107,175,177,178,179,199Pivetta - Earthwork 311 Form and Pour Curb and Gutter 1 d 300 d 300 d NA NA Fri 8/23/24 Fri 8/23/24 Mon 11/10/25 Mon 11/10/25 310 WCCI 312 Curb and Gutter - Big Island Poke to SW Victoria St - Sta 19+12.69 to 24+80 4 d 70 d 70 d NA NA Fri 8/23/24 Wed 8/28/24 Thu 12/5/24 Mon 11/10/25 313 Grade/Prep Base/Place CSBC 2 d 70 d 0 d NA NA Fri 8/23/24 Mon 8/26/24 Thu 12/5/24 Fri 12/6/24 310 Pivetta - Earthwork 314 Form and Pour Curb and Gutter 2 d 297 d 297 d NA NA Tue 8/27/24 Wed 8/28/24 Fri 11/7/25 Mon 11/10/25 313 WCCI 315 Curb and Gutter - SW Victoria St. to Renton Ave Ext. - Sta 25+00 to 31+64.76 17 d 70 d 70 d NA NA Tue 8/27/24 Thu 9/19/24 Mon 12/9/24 Mon 11/10/25 316 Grade/Prep Base/Place CSBC 3 d 70 d 0 d NA NA Tue 8/27/24 Thu 8/29/24 Mon 12/9/24 Wed 12/11/24 212,313 Pivetta - Earthwork 317 Form and Pour Curb and Gutter 3 d 70 d 0 d NA NA Fri 8/30/24 Wed 9/4/24 Thu 12/12/24 Mon 12/16/24 316 WCCI 318 Bus Shelter - Sta 27+45.48 11 d 282 d 282 d NA NA Thu 9/5/24 Thu 9/19/24 Mon 10/27/25 Mon 11/10/25 319 FRPCS Bus Shelter Footings 10 d 282 d 0 d NA NA Thu 9/5/24 Wed 9/18/24 Mon 10/27/25 Fri 11/7/25 317 WCCI 320 Install Bus Shelter 1 d 282 d 282 d NA NA Thu 9/19/24 Thu 9/19/24 Mon 11/10/25 Mon 11/10/25 319 Pivetta 321 Curb and Gutter - Renton Ave. Ext to End - Sta 32+56.87 to 42+80.28 5 d 61 d 61 d NA NA Mon 9/16/24 Fri 9/20/24 Fri 12/13/24 Mon 11/10/25 322 Grade/Prep Base/Place CSBC 2 d 61 d 0 d NA NA Mon 9/16/24 Tue 9/17/24 Fri 12/13/24 Mon 12/16/24 226,316 Pivetta - Earthwork 323 Form and Pour Curb and Gutter 2 d 61 d 0 d NA NA Wed 9/18/24 Thu 9/19/24 Tue 12/17/24 Wed 12/18/24 322,317 WCCI 324 Install Curb Mounted Delineator Posts - Renton Ave. Ext.1 d 281 d 281 d NA NA Fri 9/20/24 Fri 9/20/24 Mon 11/10/25 Mon 11/10/25 323 SPM 325 Islands - Sta 32+90 to 33+30 5 d 61 d 61 d NA NA Fri 9/20/24 Thu 9/26/24 Thu 12/19/24 Thu 1/2/25 326 Grade/Place CSBC/Place Island 2 - Renton Ave Ext. 5 d 61 d 0 d NA NA Fri 9/20/24 Thu 9/26/24 Thu 12/19/24 Thu 1/2/25 323,199 Pivetta - Earthwork 327 Sidewalk - 14+30.99 to 42+80.28 36 d 0 d 0 d NA NA Mon 9/16/24 Mon 11/4/24 Mon 9/16/24 Fri 9/5/25 328 Sidewalk Walgreens to Big Island Poke - Sta 14+30.99 to 19+12.69 8 d 0 d 0 d NA NA Mon 9/16/24 Wed 9/25/24 Mon 9/16/24 Fri 9/5/25 329 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 3 d 0 d 0 d NA NA Mon 9/16/24 Wed 9/18/24 Mon 9/16/24 Wed 9/18/24 116,231,127,173,226,274,284,291,295,300,304Pivetta - Earthwork 330 FRPCS - Sidewalk and Driveway Approaches 3 d 2 d 0 d NA NA Thu 9/19/24 Mon 9/23/24 Mon 9/23/24 Wed 9/25/24 329 WCCI 331 Grade/Form/Pour - Curb Ramps/Install DWS - 2nd St. - Sta 19+64.04 2 d 232 d 23 d NA NA Tue 9/24/24 Wed 9/25/24 Thu 9/4/25 Fri 9/5/25 330 WCCI 332 Sidewalk Big Island Poke to SW Victoria St. - Sta 19+12.69 to 24+80 15 d 0 d 0 d NA NA Thu 9/19/24 Wed 10/9/24 Thu 9/19/24 Fri 9/5/25 333 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 5 d 0 d 0 d NA NA Thu 9/19/24 Wed 9/25/24 Thu 9/19/24 Wed 9/25/24 329 Pivetta - Earthwork 334 FRPCS - Sidewalk and Driveway Approaches 5 d 0 d 0 d NA NA Thu 9/26/24 Wed 10/2/24 Thu 9/26/24 Wed 10/2/24 333,330 WCCI 335 Grade/Form/Pour - Curb Ramps/Install DWS - 2nd St. - Sta 20+08 5 d 222 d 13 d NA NA Thu 10/3/24 Wed 10/9/24 Fri 8/29/25 Fri 9/5/25 334 WCCI 336 Grade/Form/Pour - Curb Ramps/Install DWS - Rainier/SW Victoria St. - Sta 24+44 2 d 225 d 16 d NA NA Thu 10/3/24 Fri 10/4/24 Thu 9/4/25 Fri 9/5/25 334 WCCI 337 Sidewalk - SW Victoria St. to Renton Ave Ext. - Sta 25+00 to 31+64.76 13 d 2 d 2 d NA NA Thu 9/26/24 Mon 10/14/24 Mon 9/30/24 Fri 9/5/25 338 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 3 d 2 d 0 d NA NA Thu 9/26/24 Mon 9/30/24 Mon 9/30/24 Wed 10/2/24 333 Pivetta - Earthwork 339 FRPCS - Sidewalk and Driveway Approaches 3 d 0 d 0 d NA NA Thu 10/3/24 Mon 10/7/24 Thu 10/3/24 Mon 10/7/24 338,334 WCCI 340 Grade/Form/Pour - Curb Ramps/Install DWS - Rainier/SW Victoria St. - Sta 25+39.73 2 d 222 d 13 d NA NA Tue 10/8/24 Wed 10/9/24 Thu 9/4/25 Fri 9/5/25 339 WCCI 341 Grade/Form/Pour - Curb Ramps/Install DWS - Midblock Crosswalk - Sta 25+47.49 5 d 0 d 0 d NA NA Tue 10/8/24 Mon 10/14/24 Tue 10/8/24 Mon 10/14/24 339 WCCI 342 Grade/Form/Pour - Curb Ramps/Install DWS - Renton Ave. Ext. - Sta 31+40.67 2 d 222 d 13 d NA NA Tue 10/8/24 Wed 10/9/24 Thu 9/4/25 Fri 9/5/25 339 WCCI 343 Sidewalk - Renton Ave. Ext to End - Sta 32+30 to 42+80.28 17 d 5 d 5 d NA NA Tue 10/1/24 Wed 10/23/24 Tue 10/8/24 Fri 9/5/25 344 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 5 d 5 d 0 d NA NA Tue 10/1/24 Mon 10/7/24 Tue 10/8/24 Mon 10/14/24 338 Pivetta - Earthwork 345 FRPCS - Sidewalk and Driveway Approaches 5 d 0 d 0 d NA NA Tue 10/15/24 Mon 10/21/24 Tue 10/15/24 Mon 10/21/24 339,341,344 WCCI 346 Grade/Form/Pour - Curb Ramps/Install DWS - Renton Ave. Ext. - Sta 32+30 2 d 212 d 3 d NA NA Tue 10/22/24 Wed 10/23/24 Thu 9/4/25 Fri 9/5/25 345 WCCI 347 Grade/Form/Pour - Curb Ramps/Install DWS - Renton Ave Ext. - Sta 32+71.52 to 33+97.39 2 d 212 d 3 d NA NA Tue 10/22/24 Wed 10/23/24 Thu 9/4/25 Fri 9/5/25 345 WCCI 348 Grade/Form/Pour - Curb Ramps/Install DWS - NW 3rd Pl - Sta 40+32.69 to 41+26.24 2 d 212 d 3 d NA NA Tue 10/22/24 Wed 10/23/24 Thu 9/4/25 Fri 9/5/25 345 WCCI 349 Concrete Switchback - Sta 37+14.35 to 37+34.20 20 d 190 d 190 d NA NA Tue 10/8/24 Mon 11/4/24 Mon 7/21/25 Fri 8/15/25 350 Excavate/Place 4" Compacted CSBC 10 d 190 d 0 d NA NA Tue 10/8/24 Mon 10/21/24 Mon 7/21/25 Fri 8/1/25 344 Pivetta - Earthwork 351 FRPCS Cement Concrete Switchback, Ramp, Stairs 10 d 190 d 0 d NA NA Tue 10/22/24 Mon 11/4/24 Mon 8/4/25 Fri 8/15/25 350 WCCI 352 Urban Design Features 45 d 190 d 190 d NA NA Tue 11/5/24 Fri 1/17/25 Mon 8/18/25 Mon 10/20/25 353 Fabricate Handrails 40 d 190 d 0 d NA NA Tue 11/5/24 Fri 1/10/25 Mon 8/18/25 Mon 10/13/25 351 Pivetta 354 Install Handrails and Fencing 5 d 190 d 187 d NA NA Mon 1/13/25 Fri 1/17/25 Tue 10/14/25 Mon 10/20/25 351,353 Pivetta 355 Roadway - Sta 13+95 to 42+80.28 27 d 61 d 61 d NA NA Fri 9/27/24 Mon 11/4/24 Fri 1/3/25 Fri 9/12/25 356 HMA 27 d 61 d 61 d NA NA Fri 9/27/24 Mon 11/4/24 Fri 1/3/25 Fri 9/12/25 357 HMA - Southbound Rainier & Renton Ave Ext - Sta 13+95 to 42+80 27 d 61 d 61 d NA NA Fri 9/27/24 Mon 11/4/24 Fri 1/3/25 Fri 9/12/25 358 Grind Pavement 5 d 61 d 0 d NA NA Fri 9/27/24 Thu 10/3/24 Fri 1/3/25 Thu 1/9/25 185,323,326 Becker Blacktop 359 Grade Base/Place Geotextile & CSBC 10 d 61 d 0 d NA NA Tue 10/1/24 Mon 10/14/24 Tue 1/7/25 Tue 1/21/25 358SS+2 d Pivetta - Earthwork 360 Prep T Cuts 10 d 72 d 11 d NA NA Thu 10/3/24 Wed 10/16/24 Mon 1/27/25 Fri 2/7/25 359SS+2 d Pivetta - Earthwork H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 2028 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 6 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 53 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 361 Place 8" HMA CL 1/2" PG 70-22 - New HMA Section/Trench Patch - Southbound Rainier Ave, Side Streets 5 d 61 d 0 d NA NA Tue 10/22/24 Mon 10/28/24 Wed 1/29/25 Tue 2/4/25 360SS+2 d,365 Icon 362 Grade/Place CSBC/Place 4" HMA - Driveways 5 d 209 d 171 d NA NA Tue 10/29/24 Mon 11/4/24 Mon 9/8/25 Fri 9/12/25 361,345,331,335,336,340,341,342,346,347,348Icon 363 Concrete Panel Approaches (Rainier and 2nd St.) - Sta 18+57.89 to 18+92.89 12 d 61 d 61 d NA NA Fri 10/4/24 Mon 10/21/24 Fri 1/10/25 Tue 1/28/25 364 Grade/Compact Subsurface and Place 2" CSBC - SB Rainier Ave. S. 2 d 61 d 0 d NA NA Fri 10/4/24 Mon 10/7/24 Fri 1/10/25 Mon 1/13/25 359SS+3 d Pivetta - Earthwork 365 Install 10" Concrete Panels - SB Rainier Ave. S.10 d 61 d 0 d NA NA Tue 10/8/24 Mon 10/21/24 Tue 1/14/25 Tue 1/28/25 364 WCCI 366 367 Stage 2 (East)151 d 0 d 0 d NA NA Wed 1/29/25 Wed 9/3/25 Wed 1/29/25 Mon 10/20/25 278 368 Temporary Channelization and Signalization 12+12.5 to 43+63 5 d 0 d 0 d NA NA Wed 1/29/25 Tue 2/4/25 Wed 1/29/25 Tue 2/4/25 369 Install Construction Channelization, Striping, Warning Signs - Shift Traffic to West Side of Rainier Ave. 5 d 0 d 0 d NA NA Wed 1/29/25 Tue 2/4/25 Wed 1/29/25 Tue 2/4/25 236,237,361SS,278 SPM 370 Adjust and Modify Signals 5 d 0 d 0 d NA NA Wed 1/29/25 Tue 2/4/25 Wed 1/29/25 Tue 2/4/25 369SS,278 Golden Gate 371 Site Prep - Sta 12+12.5 to 42+07.42 10 d 69 d 69 d NA NA Wed 2/5/25 Wed 2/19/25 Wed 5/14/25 Wed 5/28/25 372 Clear & Grub - Stage 2 5 d 69 d 0 d NA NA Wed 2/5/25 Tue 2/11/25 Wed 5/14/25 Tue 5/20/25 369,370 Pivetta - Earthwork 373 Relocate Cable Railing and Posts 5 d 69 d 0 d NA NA Wed 2/5/25 Tue 2/11/25 Wed 5/14/25 Tue 5/20/25 372SS Pivetta - Earthwork 374 Complete Removals 5 d 69 d 0 d NA NA Wed 2/12/25 Wed 2/19/25 Wed 5/21/25 Wed 5/28/25 372,373 Pivetta - Earthwork 375 Sewer - Sta 25+02.65 to 28+55.98 9 d 0 d 0 d NA NA Wed 2/5/25 Tue 2/18/25 Wed 2/5/25 Tue 2/18/25 376 Sewer - Royal Orchid/Formula 1 Fast Lube to S. Tobin St. - Sta 25+02.65 to 28+48.03 8 d 0 d 0 d NA NA Wed 2/5/25 Fri 2/14/25 Wed 2/5/25 Fri 2/14/25 377 Install New 8" Sewer and Manhole 6 d 0 d 0 d NA NA Wed 2/5/25 Wed 2/12/25 Wed 2/5/25 Wed 2/12/25 369,370 Pivetta - Sewer 378 Install New Side Sewers 2 d 0 d 0 d NA NA Thu 2/13/25 Fri 2/14/25 Thu 2/13/25 Fri 2/14/25 377 Pivetta - Sewer 379 S. Tobin St. - Night/Crossing Sta 28+48.03 to 28+55.98 1 d 0 d 0 d NA NA Tue 2/18/25 Tue 2/18/25 Tue 2/18/25 Tue 2/18/25 380 Install 12" Sewer 1 d 0 d 0 d NA NA Tue 2/18/25 Tue 2/18/25 Tue 2/18/25 Tue 2/18/25 377,378 Pivetta - Sewer 381 Storm Drainage - Sta 203+50 (S. 3rd) to 41+72.60 (Rainier)66 d 0 d 0 d NA NA Wed 2/19/25 Wed 5/21/25 Wed 2/19/25 Wed 5/21/25 382 S. 3rd Street to Taco Time - Sta 203+50 to 200+79.67 (S. 3rd) & 13+50 to 17+63.44 (Rainier) 19 d 0 d 0 d NA NA Wed 2/19/25 Mon 3/17/25 Wed 2/19/25 Mon 3/17/25 383 Install Drainage and Catch Basins 16 d 0 d 0 d NA NA Wed 2/19/25 Wed 3/12/25 Wed 2/19/25 Wed 3/12/25 380 Pivetta - Sewer 384 Install Filterra Units 3 d 0 d 0 d NA NA Thu 3/13/25 Mon 3/17/25 Thu 3/13/25 Mon 3/17/25 383 Pivetta - Sewer 385 Storm Drainage - Night/Crossing - Sta 14+25.73 2 d 0 d 0 d NA NA Tue 3/18/25 Wed 3/19/25 Tue 3/18/25 Wed 3/19/25 386 Install Drainage and Catch Basin 2 d 0 d 0 d NA NA Tue 3/18/25 Wed 3/19/25 Tue 3/18/25 Wed 3/19/25 384 Pivetta - Sewer 387 Royal Orchid to N of Airport Way - Sta 24+83.45 to 34+19.81 18 d 0 d 0 d NA NA Thu 3/20/25 Mon 4/14/25 Thu 3/20/25 Mon 4/14/25 388 Install Drainage and Catch Basins 15 d 0 d 0 d NA NA Thu 3/20/25 Wed 4/9/25 Thu 3/20/25 Wed 4/9/25 386 Pivetta - Sewer 389 Install Filterra Units 3 d 0 d 0 d NA NA Thu 4/10/25 Mon 4/14/25 Thu 4/10/25 Mon 4/14/25 388 Pivetta - Sewer 390 Storm Drainage - Night/Crossing - Sta 30+78.93 3 d 0 d 0 d NA NA Tue 4/15/25 Thu 4/17/25 Tue 4/15/25 Thu 4/17/25 391 Install Drainage and Catch Basin 2 d 0 d 0 d NA NA Tue 4/15/25 Wed 4/16/25 Tue 4/15/25 Wed 4/16/25 389 Pivetta - Sewer 392 Install Filterra Unit 1 d 0 d 0 d NA NA Thu 4/17/25 Thu 4/17/25 Thu 4/17/25 Thu 4/17/25 391 Pivetta - Sewer 393 Airport Way - Sta 33+17.81 to 601+64.04 6 d 0 d 0 d NA NA Fri 4/18/25 Fri 4/25/25 Fri 4/18/25 Fri 4/25/25 394 Install Drainage and Catch Basins 5 d 0 d 0 d NA NA Fri 4/18/25 Thu 4/24/25 Fri 4/18/25 Thu 4/24/25 392 Pivetta - Sewer 395 Install Filterra Units 1 d 0 d 0 d NA NA Fri 4/25/25 Fri 4/25/25 Fri 4/25/25 Fri 4/25/25 394 Pivetta - Sewer 396 N of Airport Way to S. of Nelson Pl. - Sta 36+15.83 to 38+57.60 - Night/Partial Stage 3 7 d 0 d 0 d NA NA Mon 4/28/25 Tue 5/6/25 Mon 4/28/25 Tue 5/6/25 397 Install Drainage and Catch Basins 6 d 0 d 0 d NA NA Mon 4/28/25 Mon 5/5/25 Mon 4/28/25 Mon 5/5/25 395 Pivetta - Sewer 398 Install Filterra Units 1 d 0 d 0 d NA NA Tue 5/6/25 Tue 5/6/25 Tue 5/6/25 Tue 5/6/25 397 Pivetta - Sewer 399 S. of Nelson Pl to End - Sta 37+91.23 to 41+72.60 11 d 0 d 0 d NA NA Wed 5/7/25 Wed 5/21/25 Wed 5/7/25 Wed 5/21/25 400 Install Drainage and Catch Basins 8 d 0 d 0 d NA NA Wed 5/7/25 Fri 5/16/25 Wed 5/7/25 Fri 5/16/25 398 Pivetta - Sewer 401 Install Filterra Units 3 d 0 d 0 d NA NA Mon 5/19/25 Wed 5/21/25 Mon 5/19/25 Wed 5/21/25 400 Pivetta - Sewer 402 Illumination - Sta 204+60 to 201+25, 133+50 to 42+08 146 d 0 d 0 d NA NA Wed 2/5/25 Wed 9/3/25 Mon 4/7/25 Wed 9/3/25 403 Decorative Illumination System 146 d 0 d 0 d NA NA Wed 2/5/25 Wed 9/3/25 Mon 4/7/25 Wed 9/3/25 404 Below Ground 33 d 42 d 42 d NA NA Wed 2/5/25 Mon 3/24/25 Mon 4/7/25 Wed 5/21/25 405 Trench and Conduit 23 d 42 d 0 d NA NA Wed 2/5/25 Mon 3/10/25 Mon 4/7/25 Wed 5/7/25 369 Golden Gate 406 Foundations 24 d 42 d 0 d NA NA Wed 2/5/25 Tue 3/11/25 Mon 4/7/25 Thu 5/8/25 405SS Golden Gate 407 Junction Boxes 9 d 42 d 0 d NA NA Wed 3/12/25 Mon 3/24/25 Fri 5/9/25 Wed 5/21/25 406 Golden Gate 408 Above Ground 56 d 0 d 0 d NA NA Fri 6/13/25 Wed 9/3/25 Fri 6/13/25 Wed 9/3/25 409 Set Poles 31 d 0 d 0 d NA NA Fri 6/13/25 Tue 7/29/25 Fri 6/13/25 Tue 7/29/25 406,436 Golden Gate 410 Install Lighting Wiring 20 d 0 d 0 d NA NA Wed 7/30/25 Tue 8/26/25 Wed 7/30/25 Tue 8/26/25 407,409 Golden Gate 411 Test and Turn On 2 d 0 d 0 d NA NA Wed 8/27/25 Thu 8/28/25 Wed 8/27/25 Thu 8/28/25 409,410 Golden Gate 412 Remove and Salvage Old Poles&Wiring 3 d 0 d 0 d NA NA Fri 8/29/25 Wed 9/3/25 Fri 8/29/25 Wed 9/3/25 411 Golden Gate 413 Walls - Sta 18+53.50 to 33+39.60 25 d 68 d 68 d NA NA Tue 3/25/25 Mon 4/28/25 Tue 7/1/25 Mon 10/20/25 414 Wall 3 - CCFW and Modular Block Wall - Sta 300+54.06 to 301+10.11 15 d 68 d 68 d NA NA Tue 3/25/25 Mon 4/14/25 Tue 7/1/25 Tue 7/22/25 415 Construct Concrete Fill Wall - Sta 17+53.50 to 18+48.48 5 d 68 d 0 d NA NA Tue 3/25/25 Mon 3/31/25 Tue 7/1/25 Tue 7/8/25 407,369 WCCI 416 Construct Modular Block Wall - Sta 300+54.05 to 301+10.11 10 d 68 d 0 d NA NA Tue 4/1/25 Mon 4/14/25 Wed 7/9/25 Tue 7/22/25 415 Key West 417 Wall 4 - Modular Block Wall - Sta 21+11.76 to 21+59.62 5 d 68 d 68 d NA NA Tue 4/15/25 Mon 4/21/25 Wed 7/23/25 Tue 7/29/25 418 Construct Modular Block Wall - Sta 21+11.76 to 21+59.62 5 d 68 d 30 d NA NA Tue 4/15/25 Mon 4/21/25 Wed 7/23/25 Tue 7/29/25 416 Key West 419 Gateway Wall B - Sta 33+39.60 to 600+57.12 20 d 68 d 68 d NA NA Tue 4/1/25 Mon 4/28/25 Wed 7/9/25 Mon 10/20/25 420 Construct Gateway Wall B 15 d 68 d 0 d NA NA Tue 4/1/25 Mon 4/21/25 Wed 7/9/25 Tue 7/29/25 415 WCCI H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 2028 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 7 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 54 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 421 Install Decorative Cutouts and Skate Deterrent - Gateway Wall B 5 d 121 d 118 d NA NA Tue 4/22/25 Mon 4/28/25 Tue 10/14/25 Mon 10/20/25 420 WCCI 422 Curb and Gutter - Sta 204+63.59 to 42+07.42 17 d 0 d 0 d NA NA Thu 5/22/25 Mon 6/16/25 Thu 5/22/25 Wed 8/13/25 423 Curb and Gutter - S. 3rd St. to S. 2nd St. - Sta 204+63.59 to 301+09.32 8 d 0 d 0 d NA NA Thu 5/22/25 Tue 6/3/25 Thu 5/22/25 Tue 6/3/25 424 Grade/Prep Base/Place CSBC 4 d 0 d 0 d NA NA Thu 5/22/25 Wed 5/28/25 Thu 5/22/25 Wed 5/28/25 401,173,378,380,407 Pivetta - Earthwork 425 Form and Pour Curb and Gutter 4 d 0 d 0 d NA NA Thu 5/29/25 Tue 6/3/25 Thu 5/29/25 Tue 6/3/25 424 WCCI 426 Curb and Gutter - S. 2nd St. to S. Tobin St. - Sta 19+57.82 to 28+61.93 6 d 0 d 0 d NA NA Thu 5/29/25 Thu 6/5/25 Fri 5/30/25 Thu 6/5/25 427 Grade/Prep Base/Place CSBC 2 d 1 d 0 d NA NA Thu 5/29/25 Fri 5/30/25 Fri 5/30/25 Mon 6/2/25 424,180,176 Pivetta - Earthwork 428 Form and Pour Curb and Gutter 2 d 0 d 0 d NA NA Wed 6/4/25 Thu 6/5/25 Wed 6/4/25 Thu 6/5/25 425,427 WCCI 429 Curb and Gutter - S. Tobin St. to Airport Way - Sta 28+61.93 to 604+36.35 11 d 1 d 1 d NA NA Mon 6/2/25 Mon 6/16/25 Tue 6/3/25 Wed 8/13/25 430 Grade/Prep Base/Place CSBC 2 d 1 d 0 d NA NA Mon 6/2/25 Tue 6/3/25 Tue 6/3/25 Wed 6/4/25 427,122 Pivetta - Earthwork 431 Form and Pour Curb and Gutter 2 d 0 d 0 d NA NA Fri 6/6/25 Mon 6/9/25 Fri 6/6/25 Mon 6/9/25 430,428 WCCI 432 Islands - Sta 31+86.30 to 601+03.49 5 d 40 d 40 d NA NA Tue 6/10/25 Mon 6/16/25 Thu 8/7/25 Wed 8/13/25 433 Grade/Place CSBC/Place Island 1 - Airport Way 5 d 40 d 0 d NA NA Tue 6/10/25 Mon 6/16/25 Thu 8/7/25 Wed 8/13/25 431 Pivetta - Earthwork 434 Curb and Gutter - Airport Way to End - Sta 603+57.87 to 42+07.42 7 d 0 d 0 d NA NA Wed 6/4/25 Thu 6/12/25 Thu 6/5/25 Thu 6/12/25 435 Grade/Prep Base/Place CSBC 3 d 1 d 1 d NA NA Wed 6/4/25 Fri 6/6/25 Thu 6/5/25 Mon 6/9/25 430 Pivetta - Earthwork 436 Form and Pour Curb and Gutter 3 d 0 d 0 d NA NA Tue 6/10/25 Thu 6/12/25 Tue 6/10/25 Thu 6/12/25 431,435 WCCI 437 Sidewalk - Sta 204+63.59 to 42+07.42 37 d 38 d 38 d NA NA Wed 6/4/25 Mon 7/28/25 Wed 7/30/25 Mon 10/20/25 438 Sidewalk - S. 3rd St. to S. 2nd St. - Sta 204+63.59 to 301+09.32 17 d 38 d 38 d NA NA Wed 6/4/25 Fri 6/27/25 Wed 7/30/25 Thu 8/28/25 439 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 5 d 38 d 0 d NA NA Wed 6/4/25 Tue 6/10/25 Wed 7/30/25 Tue 8/5/25 151,425,374,415,416,418,420,470 Pivetta - Earthwork 440 FRPCS - Sidewalk and Driveway Approaches 8 d 38 d 0 d NA NA Fri 6/13/25 Wed 6/25/25 Fri 8/8/25 Tue 8/19/25 439SS+2 d,436 WCCI 441 Grade/Form/Pour - Curb Ramps/Install DWS - S. 3rd St. - Sta 12+12.51 to 201+45.07 2 d 43 d 5 d NA NA Thu 6/26/25 Fri 6/27/25 Wed 8/27/25 Thu 8/28/25 440 WCCI 442 Grade/Form/Pour - Curb Ramps/Install DWS - S. 3rd St. - Sta 200+78.57 to 14+00.41 2 d 43 d 5 d NA NA Thu 6/26/25 Fri 6/27/25 Wed 8/27/25 Thu 8/28/25 440 WCCI 443 Grade/Form/Pour - Curb Ramps/Install DWS - S. 2nd St. - Sta 18+48.51 to 19+08.79 2 d 43 d 5 d NA NA Thu 6/26/25 Fri 6/27/25 Wed 8/27/25 Thu 8/28/25 440 WCCI 444 Sidewalk - S. 2nd St. to S. Tobin St. - Sta 19+57.82 to 28+61.93 17 d 38 d 38 d NA NA Wed 6/11/25 Mon 7/7/25 Wed 8/6/25 Mon 10/20/25 445 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 5 d 38 d 0 d NA NA Wed 6/11/25 Tue 6/17/25 Wed 8/6/25 Tue 8/12/25 439 Pivetta - Earthwork 446 FRPCS - Sidewalk and Driveway Approaches 5 d 38 d 0 d NA NA Thu 6/26/25 Wed 7/2/25 Wed 8/20/25 Tue 8/26/25 445,440,451 WCCI 447 Grade/Form/Pour - Curb Ramps/Install DWS - S. 2nd St. - Sta 19+55.68 to 20+08.13 2 d 38 d 0 d NA NA Thu 7/3/25 Mon 7/7/25 Wed 8/27/25 Thu 8/28/25 446 WCCI 448 Grade/Form/Pour - Curb Ramps/Install DWS - Midblock Crosswalk - Sta 25+40.51 to 25+47.25 2 d 38 d 0 d NA NA Thu 7/3/25 Mon 7/7/25 Wed 8/27/25 Thu 8/28/25 446 WCCI 449 Grade/Form/Pour - Curb Ramps/Install DWS - S. Tobin St. - Sta 27+93.39 to 500+74.79 2 d 38 d 0 d NA NA Thu 7/3/25 Mon 7/7/25 Wed 8/27/25 Thu 8/28/25 446 WCCI 450 Bus Shelter - Sta 24+59.90 6 d 38 d 38 d NA NA Wed 6/18/25 Thu 6/26/25 Wed 8/13/25 Mon 10/20/25 451 FRPCS Bus Shelter Footings 5 d 38 d 0 d NA NA Wed 6/18/25 Wed 6/25/25 Wed 8/13/25 Tue 8/19/25 445 WCCI 452 Install Bus Shelter 1 d 80 d 77 d NA NA Thu 6/26/25 Thu 6/26/25 Mon 10/20/25 Mon 10/20/25 451 Pivetta 453 Sidewalk - S. Tobin St. to Airport Way 5 d 39 d 39 d NA NA Wed 6/18/25 Wed 6/25/25 Thu 8/14/25 Fri 8/22/25 454 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 4 d 39 d 0 d NA NA Wed 6/18/25 Tue 6/24/25 Thu 8/14/25 Tue 8/19/25 445 Pivetta - Earthwork 455 FRPCS - Sidewalk and Driveway Approaches 4 d 41 d 2 d NA NA Fri 6/20/25 Wed 6/25/25 Tue 8/19/25 Fri 8/22/25 454SS+1 d WCCI 456 Shared Use Path - Airport Way to Sta 38+80 27 d 39 d 39 d NA NA Wed 6/18/25 Mon 7/28/25 Thu 8/14/25 Mon 10/20/25 457 Grade/Prep Base/Place CSBC - Shared Use Path 5 d 39 d 0 d NA NA Wed 6/18/25 Wed 6/25/25 Thu 8/14/25 Wed 8/20/25 454SS Pivetta - Earthwork 458 Place HMA - Shared Use Path 5 d 62 d 59 d NA NA Thu 7/17/25 Wed 7/23/25 Tue 10/14/25 Mon 10/20/25 457,479,461 WCCI 459 Concrete Switchback - Sta 35+36.63 to 35+68.13 23 d 59 d 59 d NA NA Wed 6/25/25 Mon 7/28/25 Tue 9/23/25 Mon 10/20/25 460 Excavate/Place 4" Compacted CSBC 5 d 62 d 0 d NA NA Wed 6/25/25 Tue 7/1/25 Tue 9/23/25 Mon 9/29/25 454 Pivetta - Earthwork 461 FRPCS Cement Concrete Switchback, Ramp, Stairs 10 d 62 d 0 d NA NA Wed 7/2/25 Wed 7/16/25 Tue 9/30/25 Mon 10/13/25 460 WCCI 462 Install Handrails and Fencing 5 d 59 d 56 d NA NA Tue 7/22/25 Mon 7/28/25 Tue 10/14/25 Mon 10/20/25 461,473 WCCI 463 Sidewalk - Airport Way to End - 603+57.87 to 42+07.42 6 d 39 d 39 d NA NA Thu 6/26/25 Thu 7/3/25 Thu 8/21/25 Thu 8/28/25 464 Grade/Prep Base/Place CSBC - Sidewalk and Driveway Approaches 2 d 39 d 0 d NA NA Thu 6/26/25 Fri 6/27/25 Thu 8/21/25 Fri 8/22/25 457 Pivetta - Earthwork 465 FRPCS - Sidewalk and Driveway Approaches 2 d 39 d 0 d NA NA Mon 6/30/25 Tue 7/1/25 Mon 8/25/25 Tue 8/26/25 455,464 WCCI 466 Grade/Form/Pour - Curb Ramps/Install DWS - S. Tobin St. - Sta 500+87.95 to 500+39.28 2 d 39 d 1 d NA NA Wed 7/2/25 Thu 7/3/25 Wed 8/27/25 Thu 8/28/25 465 WCCI 467 Grade/Form/Pour - Curb Ramps/Install DWS - Airport Way - Sta 31+31.67 to 32+15.90 2 d 39 d 1 d NA NA Wed 7/2/25 Thu 7/3/25 Wed 8/27/25 Thu 8/28/25 465 WCCI 468 Grade/Form/Pour - Curb Ramps/Install DWS - Airport Way - Sta 33+20.23 to 33+65.12 2 d 39 d 0 d NA NA Wed 7/2/25 Thu 7/3/25 Wed 8/27/25 Thu 8/28/25 465 WCCI 469 Urban Design Features 105 d 59 d 59 d NA NA Thu 2/20/25 Mon 7/21/25 Mon 7/28/25 Mon 10/13/25 470 Drill Foundations for Decorative Trellis 2 d 109 d 71 d NA NA Thu 2/20/25 Fri 2/21/25 Mon 7/28/25 Tue 7/29/25 374 Pivetta 471 Install Trellis 5 d 59 d 0 d NA NA Mon 7/7/25 Fri 7/11/25 Mon 9/29/25 Fri 10/3/25 468 Pivetta 472 Install Trash Receptacles and Benches 1 d 59 d 0 d NA NA Mon 7/14/25 Mon 7/14/25 Mon 10/6/25 Mon 10/6/25 468,471 Pivetta 473 Install Fence 5 d 59 d 0 d NA NA Tue 7/15/25 Mon 7/21/25 Tue 10/7/25 Mon 10/13/25 468,472 Pivetta 474 Roadway - Sta 12+12.5 to 43+63 23 d 40 d 40 d NA NA Tue 6/17/25 Mon 7/21/25 Thu 8/14/25 Mon 10/20/25 475 HMA - Northbound Rainier & Airport Way - Sta 12+12.5 to 43+63 23 d 38 d 38 d NA NA Tue 6/17/25 Mon 7/21/25 Thu 8/14/25 Fri 9/12/25 476 Grind Pavement 5 d 40 d 0 d NA NA Tue 6/17/25 Tue 6/24/25 Thu 8/14/25 Wed 8/20/25 436,433 Becker Blacktop 477 Grade Base/Place Geotextile & CSBC 10 d 40 d 0 d NA NA Fri 6/20/25 Thu 7/3/25 Mon 8/18/25 Fri 8/29/25 165,173,476SS+2 d Pivetta - Earthwork 478 Prep T Cuts 10 d 40 d 0 d NA NA Tue 6/24/25 Tue 7/8/25 Wed 8/20/25 Wed 9/3/25 477SS+2 d Pivetta - Earthwork 479 Place 8" HMA CL 1/2" PG 70-22 - New HMA Section/Trench Patch - Southbound Rainier Ave, Side Streets 5 d 40 d 0 d NA NA Thu 6/26/25 Wed 7/2/25 Fri 8/22/25 Thu 8/28/25 478SS+2 d Icon 480 Grade/Place CSBC/Place 4" HMA - Driveways 10 d 38 d 0 d NA NA Tue 7/8/25 Mon 7/21/25 Fri 8/29/25 Fri 9/12/25 479,441,442,443,447,448,449,466,467,468Icon H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 2028 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 8 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 55 of 56 ID Task Name Duration Total Slack Free Slack Actual Start Actual Finish Early Start Early Finish Late Start Late Finish Predecessors Text2 481 Concrete Panel Approaches (Rainier and 2nd St.) - Sta 18+57.89 to 18+92.89 7 d 42 d 42 d NA NA Wed 6/25/25 Thu 7/3/25 Mon 8/25/25 Wed 9/3/25 482 Grade/Compact Subsurface and Place 2" CSBC - SB Rainier Ave. S. 2 d 42 d 0 d NA NA Wed 6/25/25 Thu 6/26/25 Mon 8/25/25 Tue 8/26/25 477SS+3 d,151 Pivetta - Earthwork 483 Install 10" Concrete Panels - SB Rainier Ave. S.5 d 42 d 42 d NA NA Fri 6/27/25 Thu 7/3/25 Wed 8/27/25 Wed 9/3/25 482 WCCI 484 Dual Faced Slope Mountable Curb - Airport Way - Sta 600+90 to 603+45 7 d 69 d 69 d NA NA Thu 7/3/25 Mon 7/14/25 Fri 10/10/25 Mon 10/20/25 485 S. 3rd St. - Sta to 200+62 to 201+55 5 d 69 d 69 d NA NA Thu 7/3/25 Thu 7/10/25 Fri 10/10/25 Fri 10/17/25 486 FRPCS - Dual Faced Sloped Mountable Traffic Curb - S. 3rd St. 4 d 69 d 0 d NA NA Thu 7/3/25 Wed 7/9/25 Fri 10/10/25 Wed 10/15/25 479 SPM 487 Install Curb Mounted Delineator Posts - S. 3rd St. 1 d 70 d 1 d NA NA Thu 7/10/25 Thu 7/10/25 Fri 10/17/25 Fri 10/17/25 486 SPM 488 Airport Way - Sta 600+90 to 603+45 3 d 69 d 69 d NA NA Thu 7/10/25 Mon 7/14/25 Thu 10/16/25 Mon 10/20/25 489 FRPCS - Dual Faced Sloped Mountable Traffic Curb - Airport Way 2 d 69 d 0 d NA NA Thu 7/10/25 Fri 7/11/25 Thu 10/16/25 Fri 10/17/25 486 SPM 490 Install Curb Mounted Delineator Posts - Airport Way 1 d 69 d 69 d NA NA Mon 7/14/25 Mon 7/14/25 Mon 10/20/25 Mon 10/20/25 489,487 SPM 491 492 Stage 3 (Median)48 d 0 d 0 d NA NA Thu 9/4/25 Mon 11/10/25 Thu 9/4/25 Mon 11/10/25 493 Temporary Channelization and Signalization - 14+05 to 40+15 2 d 0 d 0 d NA NA Thu 9/4/25 Fri 9/5/25 Thu 9/4/25 Fri 9/5/25 494 Install Const. Channelization & Shift Traffic to Outside Lanes - Rainier Ave S. 2 d 0 d 0 d NA NA Thu 9/4/25 Fri 9/5/25 Thu 9/4/25 Fri 9/5/25 412,483,479 Pivetta 495 Adjust Signal Heads and Cameras 2 d 0 d 0 d NA NA Thu 9/4/25 Fri 9/5/25 Thu 9/4/25 Fri 9/5/25 494SS Golden Gate 496 Site Prep - Sta 14+05 to 40+15 5 d 0 d 0 d NA NA Mon 9/8/25 Fri 9/12/25 Mon 9/8/25 Fri 9/12/25 497 Sawcut and Remove Pavement in Median 5 d 0 d 0 d NA NA Mon 9/8/25 Fri 9/12/25 Mon 9/8/25 Fri 9/12/25 494,495 Pivetta 498 Roadway - Sta 14+05 to 40+40 31 d 0 d 0 d NA NA Mon 9/15/25 Mon 10/27/25 Mon 9/15/25 Mon 10/27/25 499 Median 1 - Sta 14+05 to 18+44.96 20 d 0 d 0 d NA NA Mon 9/15/25 Fri 10/10/25 Mon 9/15/25 Wed 10/15/25 500 Grade Base/Place CSBC/FRPCS Median 1 Curb 5 d 0 d 0 d NA NA Mon 9/15/25 Fri 9/19/25 Mon 9/15/25 Fri 9/19/25 497,539SS Pivetta - Earthwork 501 Install River Rock Treatment 5 d 3 d 0 d NA NA Mon 9/22/25 Fri 9/26/25 Thu 9/25/25 Wed 10/1/25 500 WCCI 502 Install Bioretention Planter Area 5 d 3 d 0 d NA NA Mon 9/29/25 Fri 10/3/25 Thu 10/2/25 Wed 10/8/25 501 Coria 503 Install Plants 5 d 3 d 0 d NA NA Mon 10/6/25 Fri 10/10/25 Thu 10/9/25 Wed 10/15/25 502 Pivetta 504 Adjust Monument Case and Cover to FG 1 d 11 d 11 d NA NA Mon 9/22/25 Mon 9/22/25 Tue 10/7/25 Tue 10/7/25 500 Pivetta 505 Median 2 - Sta 19+65 7 d 0 d 0 d NA NA Mon 9/22/25 Tue 9/30/25 Mon 9/22/25 Tue 10/7/25 506 Grade Base/Place CSBC/FRPCS Median Curb 2 3 d 0 d 0 d NA NA Mon 9/22/25 Wed 9/24/25 Mon 9/22/25 Wed 9/24/25 500 Pivetta - Earthwork 507 Install River Rock Treatment 2 d 5 d 1 d NA NA Mon 9/29/25 Tue 9/30/25 Mon 10/6/25 Tue 10/7/25 506,501 WCCI 508 Median 3 - Sta 23+40 to 25+50 15 d 0 d 0 d NA NA Thu 9/25/25 Wed 10/15/25 Thu 9/25/25 Mon 10/20/25 509 Grade Base/Place CSBC/FRPCS Median Curb 3 3 d 0 d 0 d NA NA Thu 9/25/25 Mon 9/29/25 Thu 9/25/25 Mon 9/29/25 506,539SS Pivetta - Earthwork 510 Install Midblock Crosswalk and DWS 2 d 4 d 0 d NA NA Tue 9/30/25 Wed 10/1/25 Mon 10/6/25 Tue 10/7/25 509 WCCI 511 Install River Rock Treatment 3 d 4 d 0 d NA NA Thu 10/2/25 Mon 10/6/25 Wed 10/8/25 Fri 10/10/25 507,510 WCCI 512 Install Bioretention Planter Area 3 d 4 d 1 d NA NA Tue 10/7/25 Thu 10/9/25 Mon 10/13/25 Wed 10/15/25 511 Coria 513 Install Plants 3 d 3 d 0 d NA NA Mon 10/13/25 Wed 10/15/25 Thu 10/16/25 Mon 10/20/25 503,512 Coria 514 Install Root Barrier 3 d 3 d 0 d NA NA Mon 10/13/25 Wed 10/15/25 Thu 10/16/25 Mon 10/20/25 513SS Coria 515 Median 4 - Sta 25+50 to 31+65.38 6 d 0 d 0 d NA NA Thu 9/25/25 Thu 10/2/25 Thu 9/25/25 Fri 10/3/25 516 Grade Base/Place CSBC/FRPCS Median Curb 4 3 d 0 d 0 d NA NA Thu 9/25/25 Mon 9/29/25 Thu 9/25/25 Mon 9/29/25 509SS,539SS Piveta - Earthwork 517 Install River Rock Treatment 3 d 1 d 0 d NA NA Tue 9/30/25 Thu 10/2/25 Wed 10/1/25 Fri 10/3/25 516 WCCI 518 Median 5 - Sta 38+39.71 to 40+12.21 5 d 0 d 0 d NA NA Tue 9/30/25 Mon 10/6/25 Tue 9/30/25 Tue 10/7/25 519 Grade Base/Place CSBC/FRPCS Median Curb 5 3 d 0 d 0 d NA NA Tue 9/30/25 Thu 10/2/25 Tue 9/30/25 Thu 10/2/25 516 Piveta - Earthwork 520 Install River Rock Treatment 2 d 1 d 1 d NA NA Fri 10/3/25 Mon 10/6/25 Mon 10/6/25 Tue 10/7/25 517,519 WCCI 521 Traffic Mounted Curb - Sta 20+25 to 23+40, 33+50 to 38+39.71 6 d 0 d 0 d NA NA Tue 9/30/25 Tue 10/7/25 Tue 9/30/25 Tue 10/7/25 522 Install Traffic Mounted Curb North of S. 2nd Street to Median 3 3 d 0 d 0 d NA NA Tue 9/30/25 Thu 10/2/25 Tue 9/30/25 Thu 10/2/25 509 SPM 523 Install Traffic Mounted Curb North of Airport Way to Median 5 3 d 0 d 0 d NA NA Fri 10/3/25 Tue 10/7/25 Fri 10/3/25 Tue 10/7/25 522,519 SPM 524 HMA Paving - Sta 14+05 to 42+10 14 d 0 d 0 d NA NA Wed 10/8/25 Mon 10/27/25 Wed 10/8/25 Mon 10/27/25 525 Grade Base/Place Geotextile & CSBC - New HMA Southbound Rainier 5 d 0 d 0 d NA NA Wed 10/8/25 Tue 10/14/25 Wed 10/8/25 Tue 10/14/25 523,504,520 Pivetta - Earthwork 526 Place HMA to Curb - Southbound Rainier 2 d 10 d 10 d NA NA Fri 10/10/25 Mon 10/13/25 Fri 10/24/25 Mon 10/27/25 525SS+2 d Icon 527 Grade Base/Place Geotextile & CSBC - New HMA Section Northbound Rainier 5 d 0 d 0 d NA NA Wed 10/15/25 Tue 10/21/25 Wed 10/15/25 Tue 10/21/25 525 Pivetta - Earthwork 528 Place HMA to Curb - Northbound Rainier 2 d 0 d 0 d NA NA Fri 10/17/25 Mon 10/20/25 Fri 10/17/25 Mon 10/20/25 527SS+2 d Icon 529 Place 4" Fiber Reinforced Asphalt Concrete (FRAC) - Project Wide 5 d 0 d 0 d NA NA Tue 10/21/25 Mon 10/27/25 Tue 10/21/25 Mon 10/27/25 361,479,490,528 Icon 530 Final Channelization and Striping 10 d 0 d 0 d NA NA Tue 10/28/25 Mon 11/10/25 Tue 10/28/25 Mon 11/10/25 531 Channelization and Striping - Southbound Rainier Ave - Sta 12+70.9 to 42+87.1 5 d 0 d 0 d NA NA Tue 10/28/25 Mon 11/3/25 Tue 10/28/25 Mon 11/3/25 532 Install Striping, Arrows, Blue Hydrant Markers 2 d 0 d 0 d NA NA Tue 10/28/25 Wed 10/29/25 Tue 10/28/25 Wed 10/29/25 526,529 SPM 533 Install Signs 5 d 0 d 0 d NA NA Tue 10/28/25 Mon 11/3/25 Tue 10/28/25 Mon 11/3/25 532SS Pivetta 534 Channelization and Striping - Northbound Rainier Ave - Sta 12+70.9 to 42+80.29 8 d 0 d 0 d NA NA Thu 10/30/25 Mon 11/10/25 Tue 11/4/25 Mon 11/10/25 535 Install Striping, Arrows, Blue Hydrant Markers 2 d 3 d 3 d NA NA Thu 10/30/25 Fri 10/31/25 Tue 11/4/25 Wed 11/5/25 532,528 SPM 536 Install Signs 5 d 0 d 0 d NA NA Tue 11/4/25 Mon 11/10/25 Tue 11/4/25 Mon 11/10/25 533,535SS Pivetta 537 538 Landscaping and Irrigation 76 d 3 d 3 d NA NA Tue 7/22/25 Wed 11/5/25 Mon 9/15/25 Mon 11/10/25 539 Install Irrigation 15 d 38 d 38 d NA NA Tue 7/22/25 Mon 8/11/25 Mon 9/15/25 Fri 10/3/25 362,480 Coria 540 Install Landscaping 15 d 3 d 3 d NA NA Thu 10/16/25 Wed 11/5/25 Tue 10/21/25 Mon 11/10/25 514,539,362,480,401,421,452,472,307,304,354,458,471,462Coria H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2022 2023 2024 2025 2026 2027 2028 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 9 Project: Rainier Ave S Corridor Improvements - Phase 4 Project City of Renton Project Number: CAG-22-163 Date: Mon 4/1/24 Removal of Existing Vaults and Duct Banks - Change Order Quotation Change Order #25, Page 56 of 56