Meter in Sidewalks Retrofit Program
Update 04/12/2023
Project Status Update:
- Total number of MIS (Meters in Sidewalk) = 1,786
- Completed MIS (Meters in Sidewalk) Work Orders = 811
- Meters not in the sidewalk = 119
- Remaining number of MIS (Meters in Sidewalk) = 930
- Total Cost $20,643
- 59 of 130 MIS Routes completed
Feedback:
No meeting took a place, only email correspondence during this time.
Sean:
• Continue making good progress
• Modifying the bracket has almost eliminated non-reporting issues
Sherry:
• Continues working on WO’s and WO revisions
Emina:
• Review of all closed Cityworks work orders
• Data extract, processing, and formatting for GIS update
• MIS Routes and Service Connection layers are up to date
• Kevin: N/A
• Josh: Developed Dashboard with Open/ Closed WO’s