RENTON HENRY MOSES AQUATIC CENTER
MAINTENANCE AND REPAIRS
Addendum # 2
December 13, 2024
NOTICE TO ALL BIDDERS:
Owner: City of Renton Public Works/Facilities
1055 South Grady Way
Renton, WA 98057
Project Manager: Debbie Boodell, Capital Project Coordinator (206) 556-5026
Contact: ARC Architects
Project Manager: Paul Curtis, Principal (503) 407-5552
To All Bidders: Attention is called to the following items effective December 13, 2024, which shall be
added to, deleted from, or changed from the BID DOCUMENTS dated November 4,
2024, thereby incorporating the addendum as part of the CONTRACT DOCUMENTS.
A. GENERAL
QUESTION: Can you clarify if there's any pool related mechanical/equipment work that needs to be
included? I see Pool Equipment/Mechanical/Electrical sections in the Schedule of Values, but I am not
finding any details about it in the construction documents.
ANSWER: The only pool mechanical / equipment work is to ensure a working system at startup.
B. PROJECT MANUAL
1. Section 00 00 03 – Bid Proposal Form, Time For Completion
QUESTION: Project Durations: We need to clarify about the 120 days for the project
completion. I am assuming that is to the point of plastering and filling the pool with
water. We'll need an additional 30 days for the brush & balance process before they can
start using the pool. Can you find out if that is correct? If they want to swim after 120 days,
that is a very short time (especially because during this part of the year, we'll have some
weather impacts).
ANSWER: Given the scope, 120 days to swimming is achievable provided there are
sufficient people to work on the project. The point regarding weather is valid. 30 days is
great. 14 days is acceptable and is required in the project documents.
2 | Page
2. Section 13 11 00 – Swimming Pool General Requirements
QUESTION: In the specification book section 13 11 00 page 8; the pool companies require
a 100% performance bond and need to have constructed in the last 5 years at least 5
commercial designed municipal and public-use swimming pools minimum size 6,000
square feet. Also, a C-53 license is a California type license.
ANSWER: The performance bond and experience are required. The C-53 license is not a
requirement.
B. SUBSTITUTIONS
1. None.
C. DRAWINGS
Architectural Drawings
A. Sheet A2.1.
QUESTION: Keynote 2 shows remove and replace the trench drains in the men's/women's toilet
rooms and the shower areas per plumbing drawings. The plumbing drawing Page P1.0 and P2.0
shows removing and replacing the train drains in the shower areas only.
Please advise if the trench drains get removed per A2.1 areas or per the plumbing drawings.
ANSWER: The trench drains occur in the men’s and women’s toilet rooms and the men’s and
women’s shower areas. All of the trench drains (four total drains) must be removed and replaced.
For bidding purposes, assume a total of 110 linear feet.
D. ATTACHMENTS
1. None.
END OF ADDENDUM #2